JUBILEE PHASE 1 PROJECT<br />
SUBSEA DEVELOPMENT<br />
OFFSHORE GHANA<br />
Frederic Chauvin<br />
Project Director
JUBILEE PHASE 1 PROJECT<br />
• Ghana in few words<br />
– Capital : Accra<br />
– Population : 24 M ha<br />
– Presidential Republic<br />
– 2010 Gross domestic<br />
product : 18 BUSD<br />
- Resources : gold, cocoa, timber,<br />
bauxite,<br />
manganese
JUBILEE PHASE 1 PROJECT<br />
Jubilee Field<br />
• Situated in Deepwater Tano & West Cape Three Points<br />
blocks 60 km offshore Ghana, West Africa<br />
• Water Depth: 900 m to<br />
1700 m<br />
• FPSO located 130 km<br />
WSW of Takoradi in<br />
water depth 1100 m
JUBILEE PHASE 1 PROJECT<br />
Field Licence Partners<br />
• Tullow (Unit Operator)<br />
• Kosmos Energy<br />
(Technical Operator)<br />
• Anadarko Petroleum<br />
• Ghana National<br />
Petroleum Corporation<br />
• Sabre Oil & Gas<br />
• EO Group
JUBILEE PHASE 1 PROJECT<br />
Field main facts<br />
• Jubilee field discovered in 2007<br />
• Estimated reserves of 500 to<br />
1000 millions barrels of oil<br />
• Significant associated gas<br />
resource ~800 bcf<br />
• High quality light oil - 37.6° API<br />
• Well deliverability potential of over 20,000 bopd<br />
• Phase 1 first oil scheduled for Q4 2010 representing<br />
record time in its category from discovery to delivery
JUBILEE PHASE 1 PROJECT<br />
Phase 1 development<br />
• Turret moored FPSO tanker conversion with 1.8 million bbl<br />
storage and 120,000 bopd production capacity<br />
• 9 flexible risers (4 production, 2 gas injection, 1 gas export<br />
and 2 water injection)<br />
• 17 wells<br />
• 2 riser bases and 8<br />
subsea manifolds<br />
• Rigid infield flowlines<br />
with rigid jumpers<br />
• Controls systems with<br />
2 dynamic umbilicals
JUBILEE PHASE 1 PROJECT<br />
Technip outline scope of work (1/2)<br />
• Design, procurement, fabrication and installation of :<br />
– 27 km of flexible lines with accessories<br />
– 48 km of rigid flowlines with 28 PLETs*<br />
– 42 rigid jumpers**<br />
– 16 suction piles***<br />
*PLET = PipeLine End Termination<br />
**Jumper = short rigid line connecting Xtrees / Manifolds / PLETs<br />
***Suction pile = foundation structure for manifold or riser anchor
JUBILEE PHASE 1 PROJECT<br />
Technip outline scope of work (2/2)<br />
• Installation of free issued equipment :<br />
– 26km of umbilicals<br />
– 158 Flying Leads<br />
– 16 Xmas trees<br />
– 2 riser bases<br />
– 8 manifolds
JUBILEE PHASE 1 PROJECT<br />
Field layout
JUBILEE PHASE 1 PROJECT – PLANNING OVERVIEW<br />
ENGINEERING<br />
Activity<br />
Description<br />
Equipments Design (Pipeline, Piles,<br />
PLETs, Jumpers, Flexible ...)<br />
PROCUREMENT<br />
Flexible Risers<br />
Pipeline (inc. Jumpers)<br />
Well and Flowline JUMPERS<br />
Assembly<br />
OFFSHORE OPERATIONS<br />
Rigid Pipe Installation<br />
Infield Umbilical / Jumpers / XMT<br />
Installation<br />
Flexible & Main Umbilical<br />
Installation<br />
2008 2009 2010<br />
A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
JUBILEE PHASE 1 PROJECT<br />
Project resources (1/3)<br />
• About 200 <strong>project</strong> team<br />
personnel located mainly in<br />
Ghana, France and in the USA<br />
• Up to 600 persons working on<br />
the <strong>project</strong> in peak period<br />
• Technip fabrication sites used<br />
– Le Trait, France, Flexible pipe<br />
factory<br />
– Mobile, USA, Rigid pipe spoolbase<br />
– Dande, Angola, Rigid pipe<br />
Spoolbase<br />
– Pori, Finland yard for PLET and<br />
Pile fabrication<br />
– Sekondi, Ghana, Jumper yard
JUBILEE PHASE 1 PROJECT<br />
Project resources (2/3)<br />
• Vessels used:<br />
TECHNIP<br />
DEEP BLUE<br />
TECHNIP<br />
DEEP PIONEER<br />
OLYMPIC TRITON<br />
VESSEL<br />
Installation scope of<br />
work<br />
Rigid lines, PLETs,<br />
foundation piles,<br />
manifolds and riser<br />
bases<br />
Dynamic umbilicals and<br />
flexible risers<br />
Static umbilicals, rigid<br />
jumpers, survey, Xmas<br />
trees, Flying Leads,<br />
tether piles, SDU,<br />
precommissioning<br />
Mo<br />
28 D<br />
29 M<br />
26 D
JUBILEE PHASE 1 PROJECT<br />
Project resources (3/3)<br />
• Other vessels:<br />
– 8 Heavy Lifts vessels<br />
– 6 cargo vessels<br />
– Precommissioning support vessel<br />
– 2 tugs for FPSO heading control<br />
– 3 supply vessels<br />
– 1 barge<br />
– 1 crew boat
JUBILEE PHASE 1 PROJECT – Fabrication sites
JUBILEE PHASE 1 PROJECT<br />
Key Subsea Development Challenges<br />
1. Fast track development<br />
2. FPSO located above a 2 km wide active<br />
subsea canyon<br />
3. Local fabrication of rigid jumpers<br />
4. Ghana Emerging Oil and Gas Industry and<br />
new country for Technip
JUBILEE PHASE 1 PROJECT – CHALLENGE #1 : FAST TRACK<br />
FEED ongoing while progressing design (Client strategy)<br />
• Split work in 3 packages progressed in parallel:<br />
1. Flexible pipe design/ fabrication<br />
2. Flexible pipe / controls systems installation and local logistics /<br />
fabrication<br />
3. Rigid pipe / jumper design, fabrication and installation<br />
• Adjust <strong>project</strong> organization to accommodate changes<br />
from FEED during design (matrix organisation)<br />
• Take conservative assumptions to progress the design<br />
and extensive use of interface system to control changes<br />
• Collaborative working relationship with the Client
JUBILEE PHASE 1 PROJECT – CHALLENGE #1 : FAST TRACK<br />
Rigid Pipe fabrication in<br />
Germany – March 2009<br />
PLETs Fabrication in<br />
Technip Finland yard –<br />
April 2009<br />
Rigid pipe assembly in Technip spoolbases in USA and Angola – Nov. 2009<br />
Pipe loading<br />
December 2009<br />
-<br />
Pipe installation<br />
January 2010
JUBILEE PHASE 1 PROJECT – CHALLENGE #2<br />
FPSO on top of a 2 km wide active subsea canyon<br />
• All flexible risers configured as pliant waves to avoid<br />
canyon touchdown and provide lateral stability<br />
• Significant quantity of buoyancy modules on each riser to<br />
minimize loading on FPSO turret
JUBILEE PHASE 1 PROJECT – CHALLENGE #3<br />
Local fabrication of rigid jumpers (1/4) - Ghana<br />
• Suitable fabrication site with quay access for supply<br />
vessel had to be set-up (no existing site)<br />
• After evaluation of various sites, Sekondi naval base<br />
was selected as the most suitable site<br />
• Lease with Ghanaian<br />
Navy signed in<br />
September 2009<br />
• Development of<br />
appropriate HSE plan<br />
designed for extensive<br />
utilization of local<br />
workforce
JUBILEE PHASE 1 PROJECT – CHALLENGE #3<br />
Local fabrication of rigid jumpers (2/4)<br />
• Jumper fabrication subcontractor<br />
selected on past references and<br />
local content plan<br />
• Site preparation from September<br />
2009 to January 2010
JUBILEE PHASE 1 PROJECT – CHALLENGE #3<br />
Local fabrication of rigid jumpers (3/4)<br />
• Jumper site in operations for fabrication of 41 jumpers
JUBILEE PHASE 1 PROJECT – CHALLENGE #3<br />
Jumper yard HSE performance (4/4)<br />
• No LTI for the entire duration of the work (450.000 manhours)<br />
Jumper yard – 400,000 man-hours<br />
without LTI Celebration
JUBILEE PHASE 1 PROJECT – CHALLENGE # 4<br />
Ghana Emerging Oil & Gas Industry and<br />
new country for Technip<br />
• Early mobilisation of Country Manager in<br />
Ghana to identify available services in<br />
country and meet with local authorities<br />
• Early visits by engineers to identify vessel<br />
mobilisation sites and potential jumper<br />
assembly yard<br />
• Early definition, with Client support, of the<br />
offshore personnel logistics<br />
• Early audits of hotels in Takoradi area<br />
• Early identification of offices for support<br />
team in Ghana
JUBILEE PHASE 1 PROJECT – CHALLENGE #4<br />
Implementation of local content requirements (1/3)<br />
• Local fabrication of the jumpers<br />
• Local agent for vessel clearance and other in<br />
country services<br />
• Several local structures (Lecture hall, conf room,<br />
quay, Guesthouses, etc..) refurbishments<br />
• Trainings (overseas & in Ghana) – transfer of knowhow,<br />
expertise
JUBILEE PHASE 1 PROJECT – CHALLENGE #4<br />
Implementation of local content requirements (2/3)<br />
• Lecture Hall / HSE induction room – Naval Base<br />
•<br />
• Essikado Yard – 4,000 m 2
JUBILEE PHASE 1 PROJECT – CHALLENGE #4<br />
Implementation of local content requirements (3/3) – Training<br />
• Engineers in Paris & Houston engineering centers<br />
15 trainees to spend 6 months each in Houston or Paris<br />
• HSE Officer in Paris<br />
2 week activities – 1 person<br />
• Welders qualifications<br />
4 weeks activities – 21persons<br />
• Drivers trainings<br />
1 week activities – 12 persons<br />
• GNPC training program<br />
GNPC personnel<br />
Ghanaian engineers during BOSIET<br />
training in USA<br />
Ghanaian engineers during vessel mobilization in<br />
France
JUBILEE PHASE 1 PROJECT<br />
Conclusion<br />
A very large <strong>project</strong> that requires early integration<br />
of tailored responses to the <strong>project</strong> key challenges:<br />
1. Fast track development<br />
2. FPSO located above a 2 km wide active subsea canyon<br />
3. Local fabrication of rigid jumpers<br />
4. Ghana Emerging Oil and Gas Industry and new country<br />
for Technip<br />