JUBILEE PHASE 1 PROJECT<br />

SUBSEA DEVELOPMENT<br />

OFFSHORE GHANA<br />

Frederic Chauvin<br />

Project Director


JUBILEE PHASE 1 PROJECT<br />

• Ghana in few words<br />

– Capital : Accra<br />

– Population : 24 M ha<br />

– Presidential Republic<br />

– 2010 Gross domestic<br />

product : 18 BUSD<br />

- Resources : gold, cocoa, timber,<br />

bauxite,<br />

manganese


JUBILEE PHASE 1 PROJECT<br />

Jubilee Field<br />

• Situated in Deepwater Tano & West Cape Three Points<br />

blocks 60 km offshore Ghana, West Africa<br />

• Water Depth: 900 m to<br />

1700 m<br />

• FPSO located 130 km<br />

WSW of Takoradi in<br />

water depth 1100 m


JUBILEE PHASE 1 PROJECT<br />

Field Licence Partners<br />

• Tullow (Unit Operator)<br />

• Kosmos Energy<br />

(Technical Operator)<br />

• Anadarko Petroleum<br />

• Ghana National<br />

Petroleum Corporation<br />

• Sabre Oil & Gas<br />

• EO Group


JUBILEE PHASE 1 PROJECT<br />

Field main facts<br />

• Jubilee field discovered in 2007<br />

• Estimated reserves of 500 to<br />

1000 millions barrels of oil<br />

• Significant associated gas<br />

resource ~800 bcf<br />

• High quality light oil - 37.6° API<br />

• Well deliverability potential of over 20,000 bopd<br />

• Phase 1 first oil scheduled for Q4 2010 representing<br />

record time in its category from discovery to delivery


JUBILEE PHASE 1 PROJECT<br />

Phase 1 development<br />

• Turret moored FPSO tanker conversion with 1.8 million bbl<br />

storage and 120,000 bopd production capacity<br />

• 9 flexible risers (4 production, 2 gas injection, 1 gas export<br />

and 2 water injection)<br />

• 17 wells<br />

• 2 riser bases and 8<br />

subsea manifolds<br />

• Rigid infield flowlines<br />

with rigid jumpers<br />

• Controls systems with<br />

2 dynamic umbilicals


JUBILEE PHASE 1 PROJECT<br />

Technip outline scope of work (1/2)<br />

• Design, procurement, fabrication and installation of :<br />

– 27 km of flexible lines with accessories<br />

– 48 km of rigid flowlines with 28 PLETs*<br />

– 42 rigid jumpers**<br />

– 16 suction piles***<br />

*PLET = PipeLine End Termination<br />

**Jumper = short rigid line connecting Xtrees / Manifolds / PLETs<br />

***Suction pile = foundation structure for manifold or riser anchor


JUBILEE PHASE 1 PROJECT<br />

Technip outline scope of work (2/2)<br />

• Installation of free issued equipment :<br />

– 26km of umbilicals<br />

– 158 Flying Leads<br />

– 16 Xmas trees<br />

– 2 riser bases<br />

– 8 manifolds


JUBILEE PHASE 1 PROJECT<br />

Field layout


JUBILEE PHASE 1 PROJECT – PLANNING OVERVIEW<br />

ENGINEERING<br />

Activity<br />

Description<br />

Equipments Design (Pipeline, Piles,<br />

PLETs, Jumpers, Flexible ...)<br />

PROCUREMENT<br />

Flexible Risers<br />

Pipeline (inc. Jumpers)<br />

Well and Flowline JUMPERS<br />

Assembly<br />

OFFSHORE OPERATIONS<br />

Rigid Pipe Installation<br />

Infield Umbilical / Jumpers / XMT<br />

Installation<br />

Flexible & Main Umbilical<br />

Installation<br />

2008 2009 2010<br />

A S O N D J F M A M J J A S O N D J F M A M J J A S O N D


JUBILEE PHASE 1 PROJECT<br />

Project resources (1/3)<br />

• About 200 <strong>project</strong> team<br />

personnel located mainly in<br />

Ghana, France and in the USA<br />

• Up to 600 persons working on<br />

the <strong>project</strong> in peak period<br />

• Technip fabrication sites used<br />

– Le Trait, France, Flexible pipe<br />

factory<br />

– Mobile, USA, Rigid pipe spoolbase<br />

– Dande, Angola, Rigid pipe<br />

Spoolbase<br />

– Pori, Finland yard for PLET and<br />

Pile fabrication<br />

– Sekondi, Ghana, Jumper yard


JUBILEE PHASE 1 PROJECT<br />

Project resources (2/3)<br />

• Vessels used:<br />

TECHNIP<br />

DEEP BLUE<br />

TECHNIP<br />

DEEP PIONEER<br />

OLYMPIC TRITON<br />

VESSEL<br />

Installation scope of<br />

work<br />

Rigid lines, PLETs,<br />

foundation piles,<br />

manifolds and riser<br />

bases<br />

Dynamic umbilicals and<br />

flexible risers<br />

Static umbilicals, rigid<br />

jumpers, survey, Xmas<br />

trees, Flying Leads,<br />

tether piles, SDU,<br />

precommissioning<br />

Mo<br />

28 D<br />

29 M<br />

26 D


JUBILEE PHASE 1 PROJECT<br />

Project resources (3/3)<br />

• Other vessels:<br />

– 8 Heavy Lifts vessels<br />

– 6 cargo vessels<br />

– Precommissioning support vessel<br />

– 2 tugs for FPSO heading control<br />

– 3 supply vessels<br />

– 1 barge<br />

– 1 crew boat


JUBILEE PHASE 1 PROJECT – Fabrication sites


JUBILEE PHASE 1 PROJECT<br />

Key Subsea Development Challenges<br />

1. Fast track development<br />

2. FPSO located above a 2 km wide active<br />

subsea canyon<br />

3. Local fabrication of rigid jumpers<br />

4. Ghana Emerging Oil and Gas Industry and<br />

new country for Technip


JUBILEE PHASE 1 PROJECT – CHALLENGE #1 : FAST TRACK<br />

FEED ongoing while progressing design (Client strategy)<br />

• Split work in 3 packages progressed in parallel:<br />

1. Flexible pipe design/ fabrication<br />

2. Flexible pipe / controls systems installation and local logistics /<br />

fabrication<br />

3. Rigid pipe / jumper design, fabrication and installation<br />

• Adjust <strong>project</strong> organization to accommodate changes<br />

from FEED during design (matrix organisation)<br />

• Take conservative assumptions to progress the design<br />

and extensive use of interface system to control changes<br />

• Collaborative working relationship with the Client


JUBILEE PHASE 1 PROJECT – CHALLENGE #1 : FAST TRACK<br />

Rigid Pipe fabrication in<br />

Germany – March 2009<br />

PLETs Fabrication in<br />

Technip Finland yard –<br />

April 2009<br />

Rigid pipe assembly in Technip spoolbases in USA and Angola – Nov. 2009<br />

Pipe loading<br />

December 2009<br />

-<br />

Pipe installation<br />

January 2010


JUBILEE PHASE 1 PROJECT – CHALLENGE #2<br />

FPSO on top of a 2 km wide active subsea canyon<br />

• All flexible risers configured as pliant waves to avoid<br />

canyon touchdown and provide lateral stability<br />

• Significant quantity of buoyancy modules on each riser to<br />

minimize loading on FPSO turret


JUBILEE PHASE 1 PROJECT – CHALLENGE #3<br />

Local fabrication of rigid jumpers (1/4) - Ghana<br />

• Suitable fabrication site with quay access for supply<br />

vessel had to be set-up (no existing site)<br />

• After evaluation of various sites, Sekondi naval base<br />

was selected as the most suitable site<br />

• Lease with Ghanaian<br />

Navy signed in<br />

September 2009<br />

• Development of<br />

appropriate HSE plan<br />

designed for extensive<br />

utilization of local<br />

workforce


JUBILEE PHASE 1 PROJECT – CHALLENGE #3<br />

Local fabrication of rigid jumpers (2/4)<br />

• Jumper fabrication subcontractor<br />

selected on past references and<br />

local content plan<br />

• Site preparation from September<br />

2009 to January 2010


JUBILEE PHASE 1 PROJECT – CHALLENGE #3<br />

Local fabrication of rigid jumpers (3/4)<br />

• Jumper site in operations for fabrication of 41 jumpers


JUBILEE PHASE 1 PROJECT – CHALLENGE #3<br />

Jumper yard HSE performance (4/4)<br />

• No LTI for the entire duration of the work (450.000 manhours)<br />

Jumper yard – 400,000 man-hours<br />

without LTI Celebration


JUBILEE PHASE 1 PROJECT – CHALLENGE # 4<br />

Ghana Emerging Oil & Gas Industry and<br />

new country for Technip<br />

• Early mobilisation of Country Manager in<br />

Ghana to identify available services in<br />

country and meet with local authorities<br />

• Early visits by engineers to identify vessel<br />

mobilisation sites and potential jumper<br />

assembly yard<br />

• Early definition, with Client support, of the<br />

offshore personnel logistics<br />

• Early audits of hotels in Takoradi area<br />

• Early identification of offices for support<br />

team in Ghana


JUBILEE PHASE 1 PROJECT – CHALLENGE #4<br />

Implementation of local content requirements (1/3)<br />

• Local fabrication of the jumpers<br />

• Local agent for vessel clearance and other in<br />

country services<br />

• Several local structures (Lecture hall, conf room,<br />

quay, Guesthouses, etc..) refurbishments<br />

• Trainings (overseas & in Ghana) – transfer of knowhow,<br />

expertise


JUBILEE PHASE 1 PROJECT – CHALLENGE #4<br />

Implementation of local content requirements (2/3)<br />

• Lecture Hall / HSE induction room – Naval Base<br />

•<br />

• Essikado Yard – 4,000 m 2


JUBILEE PHASE 1 PROJECT – CHALLENGE #4<br />

Implementation of local content requirements (3/3) – Training<br />

• Engineers in Paris & Houston engineering centers<br />

15 trainees to spend 6 months each in Houston or Paris<br />

• HSE Officer in Paris<br />

2 week activities – 1 person<br />

• Welders qualifications<br />

4 weeks activities – 21persons<br />

• Drivers trainings<br />

1 week activities – 12 persons<br />

• GNPC training program<br />

GNPC personnel<br />

Ghanaian engineers during BOSIET<br />

training in USA<br />

Ghanaian engineers during vessel mobilization in<br />

France


JUBILEE PHASE 1 PROJECT<br />

Conclusion<br />

A very large <strong>project</strong> that requires early integration<br />

of tailored responses to the <strong>project</strong> key challenges:<br />

1. Fast track development<br />

2. FPSO located above a 2 km wide active subsea canyon<br />

3. Local fabrication of rigid jumpers<br />

4. Ghana Emerging Oil and Gas Industry and new country<br />

for Technip<br />

Jubilee field – 27 Aug. 10