17.01.2013 Views

Contents 2011 • Issue 02 - Skanska

Contents 2011 • Issue 02 - Skanska

Contents 2011 • Issue 02 - Skanska

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

1.<br />

Collaboration is the name of the game on the Pier 5 Replacement<br />

project at the Norfolk Naval Shipyard in Portsmouth, V.A.<br />

During the project’s bid stage, Civil Senior Estimator Matt Boynton<br />

reached out to Building VDC Director Albert Zulps for help with the<br />

BIM model.<br />

“After the job was awarded, I helped update the model to integrate<br />

the architectural and engineering models and add temporary works,”<br />

Albert explains, “and then Project Engineer Nate Meyers took over<br />

to work out construction sequencing and logistics, and bring the<br />

model into operations.”<br />

“We were able to link the project schedule to create the 4-D<br />

scheduling model,” Nate continues, “which we use to identify<br />

space constraints and equipment conflicts for the barges, rigs<br />

and cranes.”<br />

The project team will continue to use the model to show new<br />

hires the overall approach to the schedule, coordinate work and<br />

compare project schedules.<br />

2.<br />

Two heads are better than one<br />

Communication is key<br />

BIM can serve as a tool to communicate key building elements<br />

that aren’t readily apparent in a normal rendering. Such is the<br />

case as the Oregon team works on the design phase of the Oregon<br />

Sustainability Center in Portland, O.R.<br />

“There are so many elements to make the world’s first mid-rise<br />

Living Building,” says Vice President of Preconstruction Steve Clem.<br />

“For public reviews, we knew we needed to do more than tell the<br />

audience about innovative green methods to get us to net zero.”<br />

BIM was employed to provide visuals of the proposed building’s<br />

solar shading and wastewater and photovoltaic systems.<br />

“BIM really helped us bring average people into the guts of the<br />

design in a simple way,” Steve says. “It probably saved us a lot of<br />

complicated explanations.”<br />

1<br />

Two heads are better than one<br />

3.<br />

On the Croton Water Treatment Plant project in the Bronx, N.Y., BIM<br />

was used to visualize, coordinate and schedule the project.<br />

“We received a 3-D model from the owner, which we used for<br />

sequencing, crane placement and synchronizing our work with other<br />

prime contractors on site. From there, the 3-D model was broken into<br />

smaller parts that corresponded to the activity schedule to create a 4-D<br />

scheduling model to effectively monitor the project schedule,” explains<br />

Project Executive John Crecco.<br />

Once individual items in the model were linked to schedule<br />

activities, video files with time sequenced animations were generated<br />

for each structure within the plant to compare the progress to the<br />

baseline schedule to keep the team on track.<br />

4.<br />

Communication is key 2<br />

Timing is everything<br />

Innovation in mind<br />

Building innovation is the theme at the Hunt Library in Raleigh, N.C.,<br />

where <strong>Skanska</strong> is constructing the signature project on North Carolina<br />

State University Centennial Campus.<br />

The building not only features some of the latest technologies,<br />

like chilled beams and an automated book delivery system, it’s being<br />

built with innovation in mind too. The project team has collaborated<br />

with the design team and the project's subcontractors, using BIM<br />

as a key part of estimating, 4-D scheduling, logistics planning and<br />

coordination/clash detection.<br />

"Perhaps the most unique use of BIM is the material tracking<br />

and supply chain management being done via barcoding on the<br />

curtainwall," says Innovation Intern Josh Vaughan. "The building's<br />

skin is comprised almost entirely of this custom curtainwall, with<br />

each unique panel having to be installed in a certain location, so<br />

the challenge really lends itself to barcoding. We’re able to track<br />

production rates at the fabrication facility as well as installation rates on<br />

site, with the information linked into the model. This has allowed us to<br />

more actively manage the project schedule and sequence other work.”<br />

Real-time strategy<br />

It goes without saying that clash detection is important in a healthcare<br />

facility. Use of BIM went far beyond that for the project team that<br />

recently completed Good Samaritan Hospital in Puyallup, W.A.<br />

“Technology was all over this job from the very beginning,” says<br />

Project Executive Raul Rosales. “We knew if we used these tools<br />

to their full potential, we would not only make our work go more<br />

smoothly, but deliver the client a better building.”<br />

Even from the initial run of the model, it was clear that some of the schedule<br />

sequencing would have to be revised to account for site constraints and dry-in<br />

requirements. The team also kept a live model throughout the project.<br />

“We had real-time drawings and requests for information networked<br />

through the site,” Raul says, “so it only made sense to make sure the<br />

BIM designs were kept in real time as well. Our people need accurate<br />

information at any given time for any task.”<br />

When work began on the Brooklyn Bridge in New York City, <strong>Skanska</strong> Koch<br />

searched for an alternative method of surveying. The complex geometry and<br />

lack of sufficient as-built data made 3-D laser scanning the perfect candidate.<br />

Similar to conventional surveying methods, 3-D laser scans involve<br />

locating an existing structure within a specific coordinate system.<br />

The main difference is that the scans consist of thousands of points<br />

rather than just a few. Also, the data can be obtained from the ground,<br />

which eliminates safety risks associated with tying off and operating<br />

man lifts – risks common to conventional surveying methods.<br />

“The scans help in a lot of other ways too,” says Survey Manager Larry<br />

Guli. “Because they’re computerized, time is saved on coordinating trades<br />

to do surveying, and I can pull up missing data right from my desk rather<br />

than convening the field crew to collect information.”<br />

Surveying isn’t the only aspect of the project reaping the benefits of<br />

3-D laser scanning; it also helps the team erect new parts of the bridge,<br />

create demo procedures and monitor traffic patterns.<br />

Complete outperformance<br />

10 coast to coast coast to coast<br />

11<br />

5.<br />

6.<br />

4<br />

Innovation in mind<br />

Surveying the scene<br />

Real-time strategy 5<br />

Timing is everything 3 Creating an efficient process 8<br />

Sureveying the scene 6<br />

7<br />

7.<br />

BIM strategies were utilized from beginning to end to construct the<br />

Interdisciplinary Science Teaching and Research Facility, located in the<br />

heart of University of South Florida’s Tampa campus.<br />

During preconstruction, material quantities were pulled from the<br />

BIM model to generate project estimates, greatly reducing the amount<br />

of time spent producing estimates.<br />

“By virtually travelling through the model, we were able to quickly<br />

provide the client with project estimates and identify complex construction<br />

areas that would be difficult to detect from traditional 2-D drawings,”<br />

explains Florida's VDC Manager Christina Huber.<br />

From there, the project team created 4-D construction sequences to<br />

visualize complex time scheduling data, linked the 3-D design model to the<br />

construction schedule to create simulations that illustrated the construction<br />

processes in time, coordinated the mechanical, electrical, plumbing and fire<br />

protection systems and produced project safety planning.<br />

“These strategies ensured that the project was delivered under<br />

budget and ahead of schedule,” Christina adds. “In fact, we reduced<br />

the structural schedule by 90 days.”<br />

8.<br />

Complete outperformance<br />

Creating an efficient process<br />

A project utilizing both prefabrication and BIM may sound daunting, but<br />

this hasn’t hindered the team on the Smyth County Community Hospital<br />

project in Marion, V.A. In fact, the team has found a way to merge BIM<br />

and the prefabrication process.<br />

“The operations team brought prefabrication into play for the<br />

overhead utility racks, patient bathroom modules and patient room<br />

headwalls,” explains Project Manager Jeff Elpers. “In order to support this<br />

effort, BIM is used to integrate the prefabrication support systems into<br />

the existing 3-D models.”<br />

Additionally, since the project is design-build, the team used 3-D<br />

coordination in early stages of the design, enabling clashes to be resolved<br />

before the release of construction documents.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!