Waterproofing system<br />
The waterproofing system, consisting<br />
of the drainage and protection layer<br />
and the waterproof liner, plays an<br />
important role in the NATM tunnel<br />
design.<br />
The drainage and protection layer<br />
functions as:<br />
• drainage on the outside of the<br />
tunnel<br />
• cushioning layer between rock face<br />
and concrete structure<br />
• protection of the waterproof liner<br />
The waterproof liner offers protection<br />
against leakage.<br />
The waterproofing system must be<br />
continuous and easy to handle and<br />
install.<br />
As during installation and use, the<br />
waterproofing system is exposed to<br />
extreme mechanical, physical,<br />
chemical, and - incidentally -<br />
biological loads, the materials must<br />
be resistant to these loads. They<br />
must also be able to adapt to<br />
irregularities of surfaces on which<br />
they are installed and may <strong>no</strong>t cause<br />
any harm to the environment.<br />
Challenging aspects<br />
The prestigious NEAT project<br />
includes a variety of striking and<br />
challenging aspects.<br />
The long base tunnels will provide a<br />
modern flat-trajectory line, allowing<br />
for substantially longer and heavier<br />
good and passenger trains that travel<br />
twice as fast. The latter trains can<br />
even reach a speed of some 200<br />
km/h.<br />
Such trains can<strong>no</strong>t be used on the<br />
existing Alpine lines, due to the steep<br />
grades and small radii of curvature.<br />
The flat-trajectory involves unusually<br />
deep construction - maximum<br />
overburden is 2,300 m - and high<br />
temperatures, which can reach 45ºC.<br />
The water pressure from strata<br />
overlying the Gotthard base tunnel<br />
has been estimated at as high as 100<br />
bar.<br />
High demands<br />
In view of the exceptional conditions,<br />
the materials to be used for the<br />
construction of the two base tunnels<br />
must meet the most stringent<br />
requirements for a designed service<br />
life of 100 years.<br />
Waterproofing systems, however, are<br />
relatively “young” and have only<br />
available for 30 years. This means<br />
that <strong>no</strong> long-term experience has<br />
been gained with these systems.<br />