ALLU <strong>STABILISATION</strong> SYSTEM<br />
3.4 Principles of ALLU mass stabilisation<br />
There are three different working principles for the ALLU Stabilisation Systems.<br />
Stabilisation in different layers<br />
The method is used when material is solid enough. The binder material is either spread on the<br />
surface or fed directly to the mixing drum while the drum is rotating. While mixing the binder and<br />
soil the PM is also moving the stabilised material towards the excavator. The depth of stabilisation<br />
is not limited by the length of the PM.<br />
Figure: Stabilisation in layers<br />
Stabilisation in blocks<br />
The method is used when the material is very wet (peat, mud or soft clay). The binder is always<br />
fed into the middle of the mixing drums while the drums are rotating and simultaneously moved<br />
vertically.<br />
The depth of the stabilisation is limited<br />
by the length of the PM (2,0 ; 3,0 or 5,0<br />
meters). The total area is usually divided<br />
into 10 to 25 meters square areas<br />
which are marked on the ground with<br />
the sticks and the stabilisation is done<br />
in one sequence. The driver moves the<br />
PM up and down to the required depth<br />
in every area so that the whole volume<br />
is homogenised. The amount of the<br />
binder is also controlled, adjusted and<br />
reported by using the DAC system.<br />
18<br />
Picture: Stabilisation in blocks<br />
Mass stabilisation 2005<br />
Blocks