The Contractor’s responsibilities are to:<br />
1. Design the wall.<br />
2. Comply with material specifications and wall tolerances,<br />
3. Obtain and verify the soil nail load carrying capacity and adhesion values used in design.<br />
4. Install the soil nails and facing in accordance with the finished face requirements and wall<br />
tolerances.<br />
The Inspector’s responsibilities are to:<br />
1. Verify compliance with the specified material properties and requirements.<br />
2. Verify that corrosion protection requirements have been satisfied.<br />
3. Verify that the wall finish face requirements are met.<br />
4. Verify that wall construction tolerance requirements have been satisfied.<br />
5. Observe, verify, and record the results <strong>of</strong> all soil nail tests.<br />
Procedural (Method) Specifications<br />
A procedural specification specifies &l details <strong>of</strong> design and construction, including the soil nail<br />
drilling method, soil nail type and dimensions, corrosion protection system, soil nail installation<br />
method, excavation procedures, and finish wall construction methods. Procedural specifications<br />
are also referred to as “prescriptive” or “closed” specifications. The responsibility <strong>of</strong> the<br />
contractor is to submit material certifications and build the soil nail system in strict accordance<br />
with the plans and specifications.<br />
When a procedural specification is used, the owner (and therefore the inspector), is fully<br />
responsible for the design and performance <strong>of</strong> the soil nail system, as long as the contractor has<br />
installed the nails in accordance with the specification requirements. Furthermore, the inspector<br />
and other personnel involved in the administration <strong>of</strong> the contract are responsible for directing<br />
the contractor’s work if changes are required. The owner assumes all the risk. Procedural<br />
specifications do not usually ensure a better job. Rather, they allow bidding by contractors not<br />
experienced with nail shoring wall work. Use <strong>of</strong> procedural specifications means that the<br />
potential for costly change orders is great.<br />
The procec@-al specification method is not generally recommended for contracting soil nail<br />
svstems.<br />