CONSTRUCTION NOISE & VIBRATION Page 7 42.6590.R1:CFCD5<br />

QUALITATIVE ASSESSMENT Rev04<br />

330kV ELECTRICITY CABLE<br />

HOLROYD <strong>to</strong> ROOKWOOD ROAD January 2012<br />

occupants of buildings. Table 1 presents a summary of vibration levels (mm/s) for<br />

the assessment of human comfort, derived from AS 2670.2-1990. In terms of<br />

overall ground vibration levels, Appendix C of Assessing Vibration: a technical<br />

guideline recommends criteria for exposure <strong>to</strong> continuous vibration associated<br />

with construction activities, specifically:<br />

Place Day Night<br />

Residence 0.2-0.4mm/s 0.14-0.28mm/s<br />

Offices 0.4-0.8mm/s same<br />

Workshops 0.8-1.6mm/s same<br />

Table 1: Vibration Levels for Assessment of Human Comfort<br />

Vibration Level (mm/s)<br />

Frequency<br />

(Hz)<br />

Continuous Vibration Intermittent Vibration<br />

Day Night Day Night<br />

1 3.2 2.2 95 31<br />

1.25 2.3 1.6 68 22<br />

1.6 1.6 1.1 47 15<br />

2 1.1 0.8 33 11<br />

2.5 0.8 0.6 24 8.0<br />

3.15 0.6 0.4 17 5.8<br />

4 0.4 0.3 19 4.0<br />

5 0.3 0.2 9.5 3.2<br />

6.3 0.3 0.2 7.6 2.5<br />

8 0.2 0.1 6.0 2.0<br />

10 0.2 0.1 6.0 2.0<br />

12.5 0.2 0.1 6.0 2.0<br />

16 0.2 0.1 6.0 2.0<br />

20 0.2 0.1 6.0 2.0<br />

25 0.2 0.1 6.0 2.0<br />

31.5 0.2 0.1 5.4 1.8<br />

40 0.2 0.1 6.0 2.0<br />

50 0.2 0.1 6.0 2.0<br />

63 0.2 0.1 6.0 2.0<br />

80 0.2 0.1 6.0 2.0<br />

PERRAM & PARTNERS ATKINS ACOUSTICS