Download - Pfisterer
Download - Pfisterer
Download - Pfisterer
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
BUSINESS<br />
The existing Ruopigen substation had<br />
been in operation since 1965 and has now<br />
been entirely replaced with a gas-insulated<br />
switching unit. With an order amounting<br />
to 1.5 million francs for medium and<br />
high voltage units, PFISTERER IXOSIL was<br />
heavily involved in the rebuild. With a<br />
large part of the order relating to cable<br />
fittings including assembly, unlike a relatively<br />
small portion of the order being for<br />
cables, the order was perfect for IXOSIL.<br />
Another factor was that CONNEX connectors<br />
were built into the GIS system and we<br />
were able to bring a further advantage to<br />
the table compared to our competitors, by<br />
using our own plugs. To top it all we fitted<br />
our IXOSIL outdoor sealing ends onto the<br />
outdoor unit.<br />
Showcase project for both partners<br />
It was clear back in the planning phase<br />
that the Ruopigen substation should be a<br />
showcase for both CKW and IXOSIL. So the<br />
2 / 2009 CONNECT 8<br />
PFISTERER IXOSIL AG: CKW supply station opened<br />
CKW’s Ruopigen substation becomes a showcase<br />
A total of 48 Connex size 5s were installed in 16 SF6 fi elds of which 3 Connex size 5S were not yet connected.<br />
In the last two years the Switzerland based energy company, Centralschweizerischen<br />
Kraftwerke (CKW), has invested over 19 million CHF<br />
in restoring the Ruopigen substation in Littau. Not only did the restoration<br />
reduce it to a quarter of its previous surface area (800 m 2 )<br />
but, by implementing the most technologically advanced network we<br />
could, it should also secure the system‘s high operating safety.<br />
entire team worked rigorously on creating<br />
the best-looking and most practical designs<br />
and fixing solutions for the cable vault.<br />
High quantity, efficiently assembled<br />
From October 2008 to May 2009 two<br />
teams of up to four IXOSIL engineers worked<br />
around 2‘570 hours to install the complete<br />
cable system. We made excellent<br />
progress, due in part to a mild autumn /<br />
early winter and the outdoor unit’s perfectly<br />
built pylon structures. The number<br />
of fittings helped new engineers attach<br />
their parts.<br />
Even our office staff used the opportunity<br />
to take a picture of the work taking<br />
place before their very eyes.<br />
After the high voltage test, Project Manager<br />
Severin Locher handed over a perfectly<br />
running unit to our customer CKW.<br />
The unit was seen by both sides as a great<br />
success and that is clear for all to see.<br />
Petra Arnold<br />
View of the cable vault, fi tted with 5’200 m<br />
630/95 mm 2 , 600m 1000/95 mm 2 and 210 m<br />
240/95 mm 2 Nexan’s XKDCuT cables, 102 m bonding<br />
cables, 420 m fi xing clamps, 147 anchorage clamps and<br />
96 cable ties (photos: CKW/IXOSIL).<br />
123 kV straight joints were used.<br />
Protection from the weather during work.<br />
The outdoor unit’s 45 ESS123-C31 pylons.