EXECUTIVE SUMMARY<br />

The proposed 825 MW Muskrat Falls hydro project is located in the Lower Churchill River<br />

Valley in central Labrador.<br />

The project consists of an existing natural feature (the North Spur) and two new<br />

concrete dams . The North Spur would provide a major part of the river impoundment<br />

system (next slide). The current project ,and all alternatives, must use the North Spur.<br />

The ground conditions at the North Spur are very unstable as they include significant<br />

amounts of glacio-marine clay (Quick Clay) that is highly prone to liquefaction and<br />

failure.<br />

A significant landslide took place at the North Spur in 1978 with lesser slides in 1980 and<br />

1981. A series of other major slides have taken place both upriver and downriver from<br />

Muskrat Falls, the latest in 2010.<br />

As of March 1, 2013, Nalcor had not conducted the geotechnical field work and collected<br />

the data necessary to fully assess the North Spur instability problem and design a<br />

suitable, cost effective solution.<br />