WENRA harmonized decommissioning reference levels report - 27 -<br />
Related IAEA safety standards:<br />
Unless otherwise required by the regulatory body, the operator shall establish and maintain decommissioning<br />
plans which are commensurate with the type and status of the facility. The initial decommissioning plan shall be<br />
established in the design phase of the facility (WS-R-2, para 3.13).<br />
When it has been decided to shut down a nuclear facility, the operator shall submit an application for<br />
permission to decommission the facility for approval by the regulatory body, together with the proposed final<br />
decommissioning plan. If it is intended to defer decommissioning, it shall be demonstrated in the final<br />
decommissioning plan that such an option is safe. Furthermore, a line of reasoning shall be provided to show<br />
that no undue burdens are imposed on future generations (WS-R-2, para 6.5).<br />
If final shutdown occurs before a decommissioning plan is prepared, decommissioning of the facility shall not be<br />
started until a satisfactory decommissioning plan has been approved by the regulatory body, unless otherwise<br />
decided by the regulatory body (see para. 6.2) (WS-R-2, para 6.6).<br />
WS-R-2 requirements n°6.5, 6.6 – 3.13