07.05.2013 Views

Case No. 85-11 Page No. 1 of 1 - MAHADISCOM

Case No. 85-11 Page No. 1 of 1 - MAHADISCOM

Case No. 85-11 Page No. 1 of 1 - MAHADISCOM

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

CONSUMER GRIEVANCE REDRESSAL FORUM<br />

MAHARASHTRA STATE ELECTRICITY DISTRIBUTION COMPANY LTD.<br />

NASHIK ZONE<br />

(Established under the section 42 (5) <strong>of</strong> the Electricity Act, 2003)<br />

Phone: 6526484 Office <strong>of</strong> the<br />

Fax: 0253-2591031 Consumer Grievance Redressal Forum<br />

Kharbanda Park, 1 st Floor, Room N. <strong>11</strong>5-<strong>11</strong>8<br />

Dwarka, NASHIK 4220<strong>11</strong><br />

---------------------------------------------------------------------------------------------------------------------------<br />

<strong>No</strong>. / CGRF /Nashik/NUC/N(U-!)Dn./268/C. <strong>No</strong>.<strong>85</strong>-20<strong>11</strong>/ Date:03/04/2012<br />

To.<br />

1) M/s .Mahindra & Mahindra Ltd.<br />

Plot <strong>No</strong>. 89, M.I.D.C.<br />

Satpur Nashik 422007<br />

(Consumer <strong>No</strong>. 049069000702)<br />

(BY R.P.A.D.)<br />

2) <strong>No</strong>dal Officer ,<br />

Maharashtra State Electricity Distribution Com. Ltd.,<br />

Urban Circle <strong>of</strong>fice, Shingada Talav,<br />

Nashik<br />

3) Executive Engineer (U-1)<br />

Maharashtra State Electricity Distribution Com. Ltd.<br />

Kharbanda Park, Division <strong>of</strong>fice<br />

Nashik<br />

DECISION<br />

Date <strong>of</strong> Submission <strong>of</strong> the case : 01/03/2012<br />

Date <strong>of</strong> Decision : 03/04/2012<br />

Appellant<br />

Distribution Licensee<br />

(Respondent)<br />

M/s. Mahindra & Mahindra Ltd., M.I.D.C. Satpur HT Industrial consumer ( hereafter referred as<br />

the Appellant) <strong>of</strong> the Maharashtra State Electricity Distribution Company Ltd. ( hereafter referred as the<br />

Respondent) is charged commercial tariff for some activities in their Industrial Plant. Appellant filed a<br />

complaint regarding this with the Internal Grievance Redressal Committee <strong>of</strong> Maharashtra State Electricity<br />

Distribution Company Ltd. But not satisfied with the decision <strong>of</strong> the Respondent, the consumer has<br />

submitted a representation to the Consumer Grievance Redressal Forum in Schedule “A”. The representation<br />

is registered at Serial <strong>No</strong>.57 <strong>of</strong> 20<strong>11</strong> on 01 /03/2012.<br />

The Forum in its meeting on 06/03/2012, decided to admit this case for hearing on 27/03/2012 at <strong>11</strong>.30<br />

am in the <strong>of</strong>fice <strong>of</strong> the forum . A notice dated 07/03/2012 to that effect was sent to the appellant and the<br />

concerned <strong>of</strong>ficers <strong>of</strong> the Distribution Company. A copy <strong>of</strong> the grievance was also forwarded with this<br />

notice to the <strong>No</strong>dal Officer, MSEDCL, Urban Circle Office Nashik , for submitting para-wise comments to<br />

the Forum on the grievance within 15 days under intimation to the consumer. The copy <strong>of</strong> this notice was also<br />

endorsed to the Chief Engineer, Nashik Zone, the Superintending Engineer, Urban Circle Office Nashik ,<br />

and the Executive Engineer (U-1) ,Nashik .<br />

Shri S. S. Kakade , <strong>No</strong>dal Officer, MSEDCL, Urban Circle Nashik , Shri C. U. Patil , Executive<br />

Engineer , Shri. S. R. Tike, Dy. Executive Engineer represented the Distribution Company during the<br />

hearing. Shri S. S. Shah , Shri, T. N. Agrawal, Shri D.V. Kanse, Shir. S. Rastogi appeared on behalf <strong>of</strong> the<br />

consumer.<br />

<strong>Case</strong> <strong>No</strong>. <strong>85</strong>-<strong>11</strong> <strong>Page</strong> <strong>No</strong>. 1 <strong>of</strong> 1


Consumers Representation:<br />

1. The Appellant is not performing any commercial activity in the plant, but some units are charged under<br />

the tariff <strong>of</strong> commercial head at the rate <strong>of</strong> Rs. 7.95 per unit, in each month. The details <strong>of</strong> the load<br />

connected on two sub-meters are as under.<br />

o Meter SI. <strong>No</strong>. 07100816 : Connected load is 173.5 KW used for sub station lighting,<br />

equipments, control panels etc.<br />

o Meter SI. <strong>No</strong>. MSU 14021 : Connected load is 41.44 KW, mainly related with the lighting<br />

load, AC, PCs etc. required for Plant Vehicle Team (PVT)<br />

Form the above it is clear that the load is not <strong>of</strong> commercial activity. The consumption on these sub<br />

métiers is 1.5 % <strong>of</strong> total consumption.<br />

2. The Appellant had written to the SE, Urban Circle on 25/09/<strong>11</strong> regarding this issue. But as there was<br />

no reply the grievance was submitted to IGRC on 20/12/20<strong>11</strong> . Accordingly decision has been passed<br />

by IGRC vide order <strong>No</strong>. 001243 dated 24/02/2012. They are not satisfied with the decision <strong>of</strong> IGRC<br />

3. Attention is invited to the tariff order (<strong>Case</strong> <strong>No</strong>. <strong>11</strong>1/2009) passed by MERC for the year 2010 which has<br />

made applicable w.e.f. 1 st Sept. 2010. The relevant extract <strong>of</strong> clause <strong>No</strong>. 5.4 Commission Tariff<br />

philosophy in the above order reads as under .<br />

“For instance, within a Factory, there could be canteens, recreation rooms for staff gymnasium, time<br />

<strong>of</strong>fice, crèche for employees’ children, dormitory for workers, guest houses for visiting <strong>of</strong>ficers, etc which<br />

are related to an incidental to the main purpose <strong>of</strong> the factory premises, and are intended for use by the<br />

staff/workers employed within the factory premises, and are not <strong>of</strong>fered on commercial payment basis to<br />

people not employed within the factory premises. The factory cannot function in the absence <strong>of</strong> such.<br />

Ancillary activities, In such cases, the categorization <strong>of</strong> such consumers should be ‘Industrial’ and the<br />

distribution licensee should not install sub-meter or separate meters for such ancillary and incidental<br />

activities, and charge them at commercial or any other rate as has been dome in some cases”<br />

4. From the above it is observed that even facilities like canteen, recreation room, gymnasium, crèche, guest<br />

house etc. provided in the plant are not directly related with part <strong>of</strong> production .All such activities should<br />

be charged under industrial consumption. In contrary to this, the activities like sub-station lighting/<br />

control room, PVT <strong>of</strong>fice etc. are very much essential for the part <strong>of</strong> production, then how such activities<br />

can not be considered as part <strong>of</strong> production for charging under industrial consumption. Although the<br />

word “Sub-Station lighting/ control panel, PVT <strong>of</strong>fice is not mentioned in the order issued by MERC , by<br />

common sense these activates being essential part <strong>of</strong> the production process should have been considered<br />

by IGRC while passing decision.<br />

5. Further it is very surprise to see the conclusion <strong>of</strong> IGRC at point <strong>No</strong>. 3 that MSEDCL’s sub stations are<br />

billed under commercial tariff category. This could be due to reason that MSEDCL’s Sub Stations are<br />

commercial establishments and not registered with the DIC/Industries Dept. As such this point has got<br />

no relevance and can’t be equated with out industrial production activities.<br />

6. Also it is to bring to your notice that in the billing <strong>of</strong> many other large scale industries, no separate<br />

commercial units are billed by MSEDCL some <strong>of</strong> the sample bills <strong>of</strong> Nashik Circle are submitted.<br />

Consumers Demands:<br />

1. Remove the commercial category from our energy bill for both the sub-meters and charge all units<br />

consumptions at industrial tariff only as per the MERC’s order for case <strong>No</strong>. <strong>11</strong>1/2009 .<br />

2. Allow refund <strong>of</strong> tariff difference for excess payment charged from September 2010 onwards<br />

3. The refund amount should be credited along with accrued interest at PLR rate.<br />

4. Compensation <strong>of</strong> Rs. 15,000/- towards man hour, traveling/ incidental expenses incurred by us & also<br />

mental agony.<br />

5. To take appropriate action as per SOP against MSEDCL’s errant <strong>of</strong>ficers for not complying MERC’s<br />

tariff order.<br />

Arguments from the Distribution Company.<br />

The Distribution Company submitted a letter dated 26/03/2012 from the <strong>No</strong>dal Officer, MSEDCL,<br />

Circle Office and other relevant correspondence in this case. Putting forth the arguments on the points raised<br />

in the grievance the representatives <strong>of</strong> the Distribution Company said that:<br />

<strong>Case</strong> <strong>No</strong>. <strong>85</strong>-<strong>11</strong> <strong>Page</strong> <strong>No</strong>. 1 <strong>of</strong> 2


1. Dy. Executive Engineer Satpur has carried out Spot Verification and submitted Spot Verification<br />

Report under letter dated 19/01/2012 bringing out the following points:<br />

There are two lighting meters provided at 132 KV Mahindra & Mahindra Ltd. (PPS Dept.)<br />

Plant-1, Satpur<br />

Meter <strong>No</strong>. 1 :7100816 is utilized at 132 KV M & M Switchyard, Control Room, D.G. Set &<br />

Battery chargers & Lighting <strong>of</strong> area. The connected load found is 186.60 KW and the billing <strong>of</strong><br />

the same is done on average basis <strong>of</strong> 6000 units every month.<br />

Meter <strong>No</strong>. 2: MSU14021 is installed and used for plant vehicle team <strong>of</strong>fice (PVT). Total load is<br />

41.44 KW. This load is utilized for the <strong>of</strong>fice purpose. The bill is issued as per consumption<br />

every month.<br />

2. The IGRC heard the case on 02/02/12. After hearing both the parties the IGRC concluded that :<br />

One sub meter is used for substation lighting , control room and other equipments.<br />

The other sub meter is used for <strong>of</strong>fice<br />

The section 5.4 <strong>of</strong> the said Tariff Order by MERC do not make mention <strong>of</strong> substation or <strong>of</strong>fice.<br />

All <strong>of</strong>fices are applied commercial tariff. Even MSEDCL substations are applied commercial<br />

tariff.<br />

The commercial tariff charged for supply through both the sub meters is correct.<br />

Observations by the Forum:<br />

The Forum records following observations based on the documents submitted and the say <strong>of</strong> the<br />

appellant and the respondent and the prevailing rules and regulations related to the case:<br />

1. The Forum has gone through the contents <strong>of</strong> the para 5.4 <strong>of</strong> the order dated 12 th September 2010 by<br />

the Hon’ble Commission in the <strong>Case</strong> <strong>No</strong>. <strong>11</strong>1 <strong>of</strong> 2009 in the matter <strong>of</strong> MSEDCL’s Petition for Truing Up<br />

for FY 2008-09, Annual Performance Review for FY 2009-10 and Aggregate Revenue Requirement and<br />

Tariff Determination for FY 2010-<strong>11</strong>.<br />

2. It is observed that the Respondent have relied upon the list <strong>of</strong> the items mentioned in the said order and<br />

concluded that since there is no mention <strong>of</strong> the substation or <strong>of</strong>fice in the list, these items could not be<br />

included in the Industrial Tariff. But it should be noted that the list <strong>of</strong> the items is just illustrative and<br />

not exhaustive because the word “etc” has been used to cover more such items. . Any activity carried<br />

out in the factory premises which is incidental and ancillary to the main industrial activity and not<br />

used by outsiders by paying charges is intended to be covered in this list. The activities <strong>of</strong> Switchyard,<br />

Control Room, D.G. Set & battery chargers & Lighting <strong>of</strong> area and plant vehicle team <strong>of</strong>fice in this case<br />

are certainly incidental and ancillary to the main industrial activity <strong>of</strong> the Appellant. The Appellant is<br />

not carrying out these activities on chargeable basis for the outsiders . These are confined for their<br />

captive use only. Hence they can not be termed as commercial according to the Tariff Philosophy as<br />

envisaged by the Hon’ble Commission in the said order dated 12 th September 2010<br />

3. The argument by the Respondent that “Even MSEDCL substations are applied commercial tariff.” is not<br />

correct. Because CE (Commercial) MSEDCL ,Mumbai has issued a Circular no. 143 dated 03/05/20<strong>11</strong><br />

in which it has been clearly instructed that:<br />

“The recorded consumption for all points <strong>of</strong> auxiliary consumption at EHV & MSEDCL sub<br />

stations shall be billed as per Industrial tariff.”<br />

4. The Appellant has also submitted bills <strong>of</strong> 20<strong>11</strong> <strong>of</strong> M/S Raj Rani Steel Casting Pvt. Ltd. , Malegaon<br />

MIDC, Sinnar and M/S Jindal Saw Ltd. , Malegaon MIDC, Sinnar where no separate commercial units<br />

are billed by MSEDCL ,This is anomaly and indiscrimination amongst consumers.<br />

5. In view <strong>of</strong> the observations in the preceding paras , the Forum directs the Respondent to apply industrial<br />

tariff for supply through the sub meters to Switchyard, Control Room, D.G. Set & battery chargers &<br />

Lighting <strong>of</strong> area and plant vehicle team <strong>of</strong>fice w.e.f. 1 st September 2010 and refund the excess amount<br />

recovered to the Appellant with interest at bank rate <strong>of</strong> the Reserve Bank <strong>of</strong> India from the date <strong>of</strong> receipts<br />

<strong>of</strong> the excess amounts till the date <strong>of</strong> refund, as stipulated in section 62(6) <strong>of</strong> the Electricity Act, 2003,<br />

read with Regulation <strong>11</strong>.3 <strong>of</strong> Maharashtra Electricity Regulatory Commission (Terms and Condition <strong>of</strong><br />

Tariff) Regulations, 2005.<br />

6. The Appellant has demanded compensation <strong>of</strong> Rs. 15,000/- towards man hour, traveling/ incidental<br />

expenses incurred and also mental agony. As the MERC regulations do not provide any such<br />

compensation hence denied.<br />

7. In the present case there is an issue <strong>of</strong> the proper interpretation <strong>of</strong> the MERC tariff order. The concerned<br />

<strong>of</strong>ficers <strong>of</strong> the Respondent have applied the tariff as per their understanding and there is no deliberate<br />

intention to harass the consumer. It is not default in service . MERC (Standards <strong>of</strong> Performance <strong>of</strong><br />

Distribution Licensees, Period for Giving Supply and Determination <strong>of</strong> Compensation) Regulations, 2005<br />

<strong>Case</strong> <strong>No</strong>. <strong>85</strong>-<strong>11</strong> <strong>Page</strong> <strong>No</strong>. 1 <strong>of</strong> 3


do not provide any compensation for such case. The demand for compensation under S.O.P. regulations<br />

is also not justified.<br />

ORDER<br />

After considering the grievance submitted by the consumer, comments and arguments by the<br />

Distribution Licensee, all other records available, the following order is passed by the Forum for<br />

implementation:<br />

1. The Respondent should apply industrial tariff for supply through the sub meters to Switchyard,<br />

Control Room, D.G. Set & battery chargers & Lighting <strong>of</strong> area and plant vehicle team <strong>of</strong>fice w.e.f. 1 st<br />

September 2010 and refund the excess amount to the Appellant with interest at bank rate <strong>of</strong> the<br />

Reserve Bank <strong>of</strong> India from the date <strong>of</strong> receipts <strong>of</strong> the excess amounts till the date <strong>of</strong> refund, as<br />

stipulated in section 62(6) <strong>of</strong> the Electricity Act, 2003, read with Regulation <strong>11</strong>.3 <strong>of</strong> Maharashtra<br />

Electricity Regulatory Commission (Terms and Condition <strong>of</strong> Tariff) Regulations, 2005.<br />

2. As per regulation 8.7 <strong>of</strong> <strong>of</strong> the MERC (Consumer Grievance Redressal Forum & Electricity<br />

Ombudsman) Regulations, 2006 , order passed or direction issued by the Forum in this order shall be<br />

implemented by the Distribution Licensee within the time frame stipulated and the concerned <strong>No</strong>dal<br />

Officer shall furnish intimation <strong>of</strong> such compliance to the Forum within one month from the date <strong>of</strong><br />

this order.<br />

3. As per regulation 22 <strong>of</strong> the above mentioned regulations , non-compliance <strong>of</strong> the orders/directions<br />

in this order by the Distribution Licensee in any manner whatsoever shall be deemed to be a<br />

contravention <strong>of</strong> the provisions <strong>of</strong> these Regulations and the Maharashtra Electricity Regulatory<br />

Commission can initiate proceedings suo motu or on a complaint filed by any person to impose<br />

penalty or prosecution proceeding under Sections 142 and 149 <strong>of</strong> the Electricity Act, 2003.<br />

4. If aggrieved by the non-redressal <strong>of</strong> his Grievance by the Forum, the appellant may make a<br />

representation to the Electricity Ombudsman, 606, ‘KESHAVA’, Bandra Kurla Complex, Bandra<br />

(East), Mumbai 400 051 within sixty (60) days from the date <strong>of</strong> this order under regulation 17.2 <strong>of</strong><br />

the MERC (Consumer Grievance Redressal Forum & Electricity Ombudsman) Regulations, 2006.<br />

(Rajan S. Kulkarni )<br />

Member<br />

(Ratan L. Sonule )<br />

Member-Secretary<br />

& Executive Engineer<br />

Consumer Grievance Redressal Forum<br />

Nashik Zone<br />

<strong>Case</strong> <strong>No</strong>. <strong>85</strong>-<strong>11</strong> <strong>Page</strong> <strong>No</strong>. 1 <strong>of</strong> 4<br />

(Suresh P.Wagh)<br />

Chairman<br />

Copy for information and necessary action to:<br />

1. Chief Engineer , Nashik Zone, Maharashtra State Electricity Distribution Company Ltd. ,<br />

Vidyut Bhavan, Nashik Road 422101<br />

2. Chief Engineer (Load Management) , Maharashtra State Electricity Distribution Company Ltd. ,<br />

Head Office , Prakash Gad, Bandra , Mumbai 400051<br />

3. Superintending Engineer, Maharashtra State Electricity Distribution Company Ltd. ,<br />

Nashik Urban Circle <strong>of</strong>fice, Nashik

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!