Case No. 85-11 Page No. 1 of 1 - MAHADISCOM
Case No. 85-11 Page No. 1 of 1 - MAHADISCOM
Case No. 85-11 Page No. 1 of 1 - MAHADISCOM
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
CONSUMER GRIEVANCE REDRESSAL FORUM<br />
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION COMPANY LTD.<br />
NASHIK ZONE<br />
(Established under the section 42 (5) <strong>of</strong> the Electricity Act, 2003)<br />
Phone: 6526484 Office <strong>of</strong> the<br />
Fax: 0253-2591031 Consumer Grievance Redressal Forum<br />
Kharbanda Park, 1 st Floor, Room N. <strong>11</strong>5-<strong>11</strong>8<br />
Dwarka, NASHIK 4220<strong>11</strong><br />
---------------------------------------------------------------------------------------------------------------------------<br />
<strong>No</strong>. / CGRF /Nashik/NUC/N(U-!)Dn./268/C. <strong>No</strong>.<strong>85</strong>-20<strong>11</strong>/ Date:03/04/2012<br />
To.<br />
1) M/s .Mahindra & Mahindra Ltd.<br />
Plot <strong>No</strong>. 89, M.I.D.C.<br />
Satpur Nashik 422007<br />
(Consumer <strong>No</strong>. 049069000702)<br />
(BY R.P.A.D.)<br />
2) <strong>No</strong>dal Officer ,<br />
Maharashtra State Electricity Distribution Com. Ltd.,<br />
Urban Circle <strong>of</strong>fice, Shingada Talav,<br />
Nashik<br />
3) Executive Engineer (U-1)<br />
Maharashtra State Electricity Distribution Com. Ltd.<br />
Kharbanda Park, Division <strong>of</strong>fice<br />
Nashik<br />
DECISION<br />
Date <strong>of</strong> Submission <strong>of</strong> the case : 01/03/2012<br />
Date <strong>of</strong> Decision : 03/04/2012<br />
Appellant<br />
Distribution Licensee<br />
(Respondent)<br />
M/s. Mahindra & Mahindra Ltd., M.I.D.C. Satpur HT Industrial consumer ( hereafter referred as<br />
the Appellant) <strong>of</strong> the Maharashtra State Electricity Distribution Company Ltd. ( hereafter referred as the<br />
Respondent) is charged commercial tariff for some activities in their Industrial Plant. Appellant filed a<br />
complaint regarding this with the Internal Grievance Redressal Committee <strong>of</strong> Maharashtra State Electricity<br />
Distribution Company Ltd. But not satisfied with the decision <strong>of</strong> the Respondent, the consumer has<br />
submitted a representation to the Consumer Grievance Redressal Forum in Schedule “A”. The representation<br />
is registered at Serial <strong>No</strong>.57 <strong>of</strong> 20<strong>11</strong> on 01 /03/2012.<br />
The Forum in its meeting on 06/03/2012, decided to admit this case for hearing on 27/03/2012 at <strong>11</strong>.30<br />
am in the <strong>of</strong>fice <strong>of</strong> the forum . A notice dated 07/03/2012 to that effect was sent to the appellant and the<br />
concerned <strong>of</strong>ficers <strong>of</strong> the Distribution Company. A copy <strong>of</strong> the grievance was also forwarded with this<br />
notice to the <strong>No</strong>dal Officer, MSEDCL, Urban Circle Office Nashik , for submitting para-wise comments to<br />
the Forum on the grievance within 15 days under intimation to the consumer. The copy <strong>of</strong> this notice was also<br />
endorsed to the Chief Engineer, Nashik Zone, the Superintending Engineer, Urban Circle Office Nashik ,<br />
and the Executive Engineer (U-1) ,Nashik .<br />
Shri S. S. Kakade , <strong>No</strong>dal Officer, MSEDCL, Urban Circle Nashik , Shri C. U. Patil , Executive<br />
Engineer , Shri. S. R. Tike, Dy. Executive Engineer represented the Distribution Company during the<br />
hearing. Shri S. S. Shah , Shri, T. N. Agrawal, Shri D.V. Kanse, Shir. S. Rastogi appeared on behalf <strong>of</strong> the<br />
consumer.<br />
<strong>Case</strong> <strong>No</strong>. <strong>85</strong>-<strong>11</strong> <strong>Page</strong> <strong>No</strong>. 1 <strong>of</strong> 1
Consumers Representation:<br />
1. The Appellant is not performing any commercial activity in the plant, but some units are charged under<br />
the tariff <strong>of</strong> commercial head at the rate <strong>of</strong> Rs. 7.95 per unit, in each month. The details <strong>of</strong> the load<br />
connected on two sub-meters are as under.<br />
o Meter SI. <strong>No</strong>. 07100816 : Connected load is 173.5 KW used for sub station lighting,<br />
equipments, control panels etc.<br />
o Meter SI. <strong>No</strong>. MSU 14021 : Connected load is 41.44 KW, mainly related with the lighting<br />
load, AC, PCs etc. required for Plant Vehicle Team (PVT)<br />
Form the above it is clear that the load is not <strong>of</strong> commercial activity. The consumption on these sub<br />
métiers is 1.5 % <strong>of</strong> total consumption.<br />
2. The Appellant had written to the SE, Urban Circle on 25/09/<strong>11</strong> regarding this issue. But as there was<br />
no reply the grievance was submitted to IGRC on 20/12/20<strong>11</strong> . Accordingly decision has been passed<br />
by IGRC vide order <strong>No</strong>. 001243 dated 24/02/2012. They are not satisfied with the decision <strong>of</strong> IGRC<br />
3. Attention is invited to the tariff order (<strong>Case</strong> <strong>No</strong>. <strong>11</strong>1/2009) passed by MERC for the year 2010 which has<br />
made applicable w.e.f. 1 st Sept. 2010. The relevant extract <strong>of</strong> clause <strong>No</strong>. 5.4 Commission Tariff<br />
philosophy in the above order reads as under .<br />
“For instance, within a Factory, there could be canteens, recreation rooms for staff gymnasium, time<br />
<strong>of</strong>fice, crèche for employees’ children, dormitory for workers, guest houses for visiting <strong>of</strong>ficers, etc which<br />
are related to an incidental to the main purpose <strong>of</strong> the factory premises, and are intended for use by the<br />
staff/workers employed within the factory premises, and are not <strong>of</strong>fered on commercial payment basis to<br />
people not employed within the factory premises. The factory cannot function in the absence <strong>of</strong> such.<br />
Ancillary activities, In such cases, the categorization <strong>of</strong> such consumers should be ‘Industrial’ and the<br />
distribution licensee should not install sub-meter or separate meters for such ancillary and incidental<br />
activities, and charge them at commercial or any other rate as has been dome in some cases”<br />
4. From the above it is observed that even facilities like canteen, recreation room, gymnasium, crèche, guest<br />
house etc. provided in the plant are not directly related with part <strong>of</strong> production .All such activities should<br />
be charged under industrial consumption. In contrary to this, the activities like sub-station lighting/<br />
control room, PVT <strong>of</strong>fice etc. are very much essential for the part <strong>of</strong> production, then how such activities<br />
can not be considered as part <strong>of</strong> production for charging under industrial consumption. Although the<br />
word “Sub-Station lighting/ control panel, PVT <strong>of</strong>fice is not mentioned in the order issued by MERC , by<br />
common sense these activates being essential part <strong>of</strong> the production process should have been considered<br />
by IGRC while passing decision.<br />
5. Further it is very surprise to see the conclusion <strong>of</strong> IGRC at point <strong>No</strong>. 3 that MSEDCL’s sub stations are<br />
billed under commercial tariff category. This could be due to reason that MSEDCL’s Sub Stations are<br />
commercial establishments and not registered with the DIC/Industries Dept. As such this point has got<br />
no relevance and can’t be equated with out industrial production activities.<br />
6. Also it is to bring to your notice that in the billing <strong>of</strong> many other large scale industries, no separate<br />
commercial units are billed by MSEDCL some <strong>of</strong> the sample bills <strong>of</strong> Nashik Circle are submitted.<br />
Consumers Demands:<br />
1. Remove the commercial category from our energy bill for both the sub-meters and charge all units<br />
consumptions at industrial tariff only as per the MERC’s order for case <strong>No</strong>. <strong>11</strong>1/2009 .<br />
2. Allow refund <strong>of</strong> tariff difference for excess payment charged from September 2010 onwards<br />
3. The refund amount should be credited along with accrued interest at PLR rate.<br />
4. Compensation <strong>of</strong> Rs. 15,000/- towards man hour, traveling/ incidental expenses incurred by us & also<br />
mental agony.<br />
5. To take appropriate action as per SOP against MSEDCL’s errant <strong>of</strong>ficers for not complying MERC’s<br />
tariff order.<br />
Arguments from the Distribution Company.<br />
The Distribution Company submitted a letter dated 26/03/2012 from the <strong>No</strong>dal Officer, MSEDCL,<br />
Circle Office and other relevant correspondence in this case. Putting forth the arguments on the points raised<br />
in the grievance the representatives <strong>of</strong> the Distribution Company said that:<br />
<strong>Case</strong> <strong>No</strong>. <strong>85</strong>-<strong>11</strong> <strong>Page</strong> <strong>No</strong>. 1 <strong>of</strong> 2
1. Dy. Executive Engineer Satpur has carried out Spot Verification and submitted Spot Verification<br />
Report under letter dated 19/01/2012 bringing out the following points:<br />
There are two lighting meters provided at 132 KV Mahindra & Mahindra Ltd. (PPS Dept.)<br />
Plant-1, Satpur<br />
Meter <strong>No</strong>. 1 :7100816 is utilized at 132 KV M & M Switchyard, Control Room, D.G. Set &<br />
Battery chargers & Lighting <strong>of</strong> area. The connected load found is 186.60 KW and the billing <strong>of</strong><br />
the same is done on average basis <strong>of</strong> 6000 units every month.<br />
Meter <strong>No</strong>. 2: MSU14021 is installed and used for plant vehicle team <strong>of</strong>fice (PVT). Total load is<br />
41.44 KW. This load is utilized for the <strong>of</strong>fice purpose. The bill is issued as per consumption<br />
every month.<br />
2. The IGRC heard the case on 02/02/12. After hearing both the parties the IGRC concluded that :<br />
One sub meter is used for substation lighting , control room and other equipments.<br />
The other sub meter is used for <strong>of</strong>fice<br />
The section 5.4 <strong>of</strong> the said Tariff Order by MERC do not make mention <strong>of</strong> substation or <strong>of</strong>fice.<br />
All <strong>of</strong>fices are applied commercial tariff. Even MSEDCL substations are applied commercial<br />
tariff.<br />
The commercial tariff charged for supply through both the sub meters is correct.<br />
Observations by the Forum:<br />
The Forum records following observations based on the documents submitted and the say <strong>of</strong> the<br />
appellant and the respondent and the prevailing rules and regulations related to the case:<br />
1. The Forum has gone through the contents <strong>of</strong> the para 5.4 <strong>of</strong> the order dated 12 th September 2010 by<br />
the Hon’ble Commission in the <strong>Case</strong> <strong>No</strong>. <strong>11</strong>1 <strong>of</strong> 2009 in the matter <strong>of</strong> MSEDCL’s Petition for Truing Up<br />
for FY 2008-09, Annual Performance Review for FY 2009-10 and Aggregate Revenue Requirement and<br />
Tariff Determination for FY 2010-<strong>11</strong>.<br />
2. It is observed that the Respondent have relied upon the list <strong>of</strong> the items mentioned in the said order and<br />
concluded that since there is no mention <strong>of</strong> the substation or <strong>of</strong>fice in the list, these items could not be<br />
included in the Industrial Tariff. But it should be noted that the list <strong>of</strong> the items is just illustrative and<br />
not exhaustive because the word “etc” has been used to cover more such items. . Any activity carried<br />
out in the factory premises which is incidental and ancillary to the main industrial activity and not<br />
used by outsiders by paying charges is intended to be covered in this list. The activities <strong>of</strong> Switchyard,<br />
Control Room, D.G. Set & battery chargers & Lighting <strong>of</strong> area and plant vehicle team <strong>of</strong>fice in this case<br />
are certainly incidental and ancillary to the main industrial activity <strong>of</strong> the Appellant. The Appellant is<br />
not carrying out these activities on chargeable basis for the outsiders . These are confined for their<br />
captive use only. Hence they can not be termed as commercial according to the Tariff Philosophy as<br />
envisaged by the Hon’ble Commission in the said order dated 12 th September 2010<br />
3. The argument by the Respondent that “Even MSEDCL substations are applied commercial tariff.” is not<br />
correct. Because CE (Commercial) MSEDCL ,Mumbai has issued a Circular no. 143 dated 03/05/20<strong>11</strong><br />
in which it has been clearly instructed that:<br />
“The recorded consumption for all points <strong>of</strong> auxiliary consumption at EHV & MSEDCL sub<br />
stations shall be billed as per Industrial tariff.”<br />
4. The Appellant has also submitted bills <strong>of</strong> 20<strong>11</strong> <strong>of</strong> M/S Raj Rani Steel Casting Pvt. Ltd. , Malegaon<br />
MIDC, Sinnar and M/S Jindal Saw Ltd. , Malegaon MIDC, Sinnar where no separate commercial units<br />
are billed by MSEDCL ,This is anomaly and indiscrimination amongst consumers.<br />
5. In view <strong>of</strong> the observations in the preceding paras , the Forum directs the Respondent to apply industrial<br />
tariff for supply through the sub meters to Switchyard, Control Room, D.G. Set & battery chargers &<br />
Lighting <strong>of</strong> area and plant vehicle team <strong>of</strong>fice w.e.f. 1 st September 2010 and refund the excess amount<br />
recovered to the Appellant with interest at bank rate <strong>of</strong> the Reserve Bank <strong>of</strong> India from the date <strong>of</strong> receipts<br />
<strong>of</strong> the excess amounts till the date <strong>of</strong> refund, as stipulated in section 62(6) <strong>of</strong> the Electricity Act, 2003,<br />
read with Regulation <strong>11</strong>.3 <strong>of</strong> Maharashtra Electricity Regulatory Commission (Terms and Condition <strong>of</strong><br />
Tariff) Regulations, 2005.<br />
6. The Appellant has demanded compensation <strong>of</strong> Rs. 15,000/- towards man hour, traveling/ incidental<br />
expenses incurred and also mental agony. As the MERC regulations do not provide any such<br />
compensation hence denied.<br />
7. In the present case there is an issue <strong>of</strong> the proper interpretation <strong>of</strong> the MERC tariff order. The concerned<br />
<strong>of</strong>ficers <strong>of</strong> the Respondent have applied the tariff as per their understanding and there is no deliberate<br />
intention to harass the consumer. It is not default in service . MERC (Standards <strong>of</strong> Performance <strong>of</strong><br />
Distribution Licensees, Period for Giving Supply and Determination <strong>of</strong> Compensation) Regulations, 2005<br />
<strong>Case</strong> <strong>No</strong>. <strong>85</strong>-<strong>11</strong> <strong>Page</strong> <strong>No</strong>. 1 <strong>of</strong> 3
do not provide any compensation for such case. The demand for compensation under S.O.P. regulations<br />
is also not justified.<br />
ORDER<br />
After considering the grievance submitted by the consumer, comments and arguments by the<br />
Distribution Licensee, all other records available, the following order is passed by the Forum for<br />
implementation:<br />
1. The Respondent should apply industrial tariff for supply through the sub meters to Switchyard,<br />
Control Room, D.G. Set & battery chargers & Lighting <strong>of</strong> area and plant vehicle team <strong>of</strong>fice w.e.f. 1 st<br />
September 2010 and refund the excess amount to the Appellant with interest at bank rate <strong>of</strong> the<br />
Reserve Bank <strong>of</strong> India from the date <strong>of</strong> receipts <strong>of</strong> the excess amounts till the date <strong>of</strong> refund, as<br />
stipulated in section 62(6) <strong>of</strong> the Electricity Act, 2003, read with Regulation <strong>11</strong>.3 <strong>of</strong> Maharashtra<br />
Electricity Regulatory Commission (Terms and Condition <strong>of</strong> Tariff) Regulations, 2005.<br />
2. As per regulation 8.7 <strong>of</strong> <strong>of</strong> the MERC (Consumer Grievance Redressal Forum & Electricity<br />
Ombudsman) Regulations, 2006 , order passed or direction issued by the Forum in this order shall be<br />
implemented by the Distribution Licensee within the time frame stipulated and the concerned <strong>No</strong>dal<br />
Officer shall furnish intimation <strong>of</strong> such compliance to the Forum within one month from the date <strong>of</strong><br />
this order.<br />
3. As per regulation 22 <strong>of</strong> the above mentioned regulations , non-compliance <strong>of</strong> the orders/directions<br />
in this order by the Distribution Licensee in any manner whatsoever shall be deemed to be a<br />
contravention <strong>of</strong> the provisions <strong>of</strong> these Regulations and the Maharashtra Electricity Regulatory<br />
Commission can initiate proceedings suo motu or on a complaint filed by any person to impose<br />
penalty or prosecution proceeding under Sections 142 and 149 <strong>of</strong> the Electricity Act, 2003.<br />
4. If aggrieved by the non-redressal <strong>of</strong> his Grievance by the Forum, the appellant may make a<br />
representation to the Electricity Ombudsman, 606, ‘KESHAVA’, Bandra Kurla Complex, Bandra<br />
(East), Mumbai 400 051 within sixty (60) days from the date <strong>of</strong> this order under regulation 17.2 <strong>of</strong><br />
the MERC (Consumer Grievance Redressal Forum & Electricity Ombudsman) Regulations, 2006.<br />
(Rajan S. Kulkarni )<br />
Member<br />
(Ratan L. Sonule )<br />
Member-Secretary<br />
& Executive Engineer<br />
Consumer Grievance Redressal Forum<br />
Nashik Zone<br />
<strong>Case</strong> <strong>No</strong>. <strong>85</strong>-<strong>11</strong> <strong>Page</strong> <strong>No</strong>. 1 <strong>of</strong> 4<br />
(Suresh P.Wagh)<br />
Chairman<br />
Copy for information and necessary action to:<br />
1. Chief Engineer , Nashik Zone, Maharashtra State Electricity Distribution Company Ltd. ,<br />
Vidyut Bhavan, Nashik Road 422101<br />
2. Chief Engineer (Load Management) , Maharashtra State Electricity Distribution Company Ltd. ,<br />
Head Office , Prakash Gad, Bandra , Mumbai 400051<br />
3. Superintending Engineer, Maharashtra State Electricity Distribution Company Ltd. ,<br />
Nashik Urban Circle <strong>of</strong>fice, Nashik