12.05.2013 Views

RICS Project Management - PER Sample Submission

RICS Project Management - PER Sample Submission

RICS Project Management - PER Sample Submission

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

<strong>Sample</strong> case study for <strong>Project</strong> management<br />

Note for users: This case study is an example only. There are many approaches you can take to<br />

meet the requirements and you should not rely solely on this sample.<br />

The names and details have been changed.<br />

Competency statement 1<br />

Competency name Programming and planning<br />

Competency reference number T063<br />

Competency level 3<br />

Context for statement (optional)<br />

I have been involved in planning from an early stage in my career having worked in the planning department of<br />

my sponsoring company while working as an undergraduate. I learned the fundamentals of the planning<br />

techniques and also put these into practice during my time with Grinch and Co.<br />

I was trained early on in the use and application of the project management software including Asta<br />

Powerproject, Microsoft <strong>Project</strong> and Pertmaster. In business, I have more often than not utilised the Powerproject<br />

tool for its clear presentation and also because in many instances it is what the client had stipulated as part of<br />

the terms of the contract.<br />

More recently I have been involved with projects where the contractor has used the Prima Vera software<br />

package.<br />

In 300-500 words please complete your statement using the following 3 headings<br />

Knowledge and understanding<br />

I have developed this competency via a number of studies that include the following:<br />

National Diploma in Building Engineering – [learning institution and date removed]<br />

BSc(Hons) Construction <strong>Management</strong> – [learning institution and date removed]<br />

Building Energy Rating Assessor Training – [learning institution and date removed]<br />

Sponsorship and training with Grinch and Co. (1992–1996)<br />

CPD Modules and Company Y Learning Zone. (2009 – present day)<br />

PhD – study commenced.<br />

There are four main questions that need to be answered when preparing a programme:<br />

What needs to be done (and how – with what plant and resource)?<br />

How long will it take?<br />

When will the activity occur?<br />

How much will it cost?<br />

Once all the information is gathered and calculations established, a programme in the form of a bar (Gantt) chart<br />

can be drawn out using a chosen computer software package such as those identified above.<br />

A construction programme will then be established bearing in mind all the key dates including start and finish<br />

time, key milestones with focus on the client interface items, any phasing of works, time and working restrictions,<br />

site access, and storage of materials to be accounted for.


Practical application of knowledge and understanding<br />

Grinch and Co – Planning Engineer<br />

I initially worked with Company X in the tender department – producing programmes using Asta Power<br />

<strong>Project</strong> software on a number of construction projects. This entailed network analysis, critical path identification<br />

and also illustration of programme float.<br />

Barchester Developments – Client <strong>Project</strong> Manager<br />

One of the key aspects of working as the client project manager was to prepare monthly project management<br />

“monitoring” reports. These were the formal way of communicating to the client – in addition to meeting minutes<br />

every second week – of how the project was progressing.<br />

One of our roles was to interrogate a contractor’s programme. The experience gained with Grinch and Co<br />

concerning critical path and float enabled an understanding to ensure the contractor was programming in the<br />

most optimal and efficient sequence – particularly when it came to impacts of design information being attributed<br />

to contractor programme delay.<br />

Cost Report summary detailing the current estimated Final <strong>Project</strong> Cost and how it compared with the Contract<br />

sum.<br />

Reasoned advice (Level 3 where selected)<br />

I recognise that one of the key skills of a project manager is the ability to focus management attention on those<br />

aspects of a problem that most require attention and not waste effort on parts of the project that are insignificant<br />

when compared to the total outcome. When I came to the Dotheboys Hall school project earlier this year, it was<br />

evident to me that significant work was required to address the fire strategy out of which all design deliverables<br />

would be progressed to a conclusion. The client was advised to sanction additional funds for this critical element<br />

of the design.<br />

Last Planner documents are prepared on a weekly basis to co-ordinate the works and inform the team in a<br />

formal manner of the works to be undertaken in the short term – this document is also communicated to the<br />

client for information. This provides a greater visibility to the client pertaining to actual progress on a weekly<br />

basis, and impact on the overall construction programme.<br />

Working as project manager for Goldstone plc on a superstore in a retail park – requiring demolition while leaving<br />

the store operational in part – required detailed input into having the critical elements of the works progressed.<br />

We were able to advise and minimise the disruption in operation to the store.


Case study 1<br />

Context (optional) not included within the word count<br />

<strong>Project</strong>: Upgrade of baggage screening facility<br />

Client: Barry Sheen Airport (BSA) Isle of Man<br />

Value: [removed]<br />

Role: <strong>Project</strong> Manager – design and build contract with NEC 3 Option C form with Target Cost. The role was<br />

project manager for BSA to deliver 19no phases of a new baggage system upgrade to meet new compliance<br />

requirements. The project was undertaken in a live environment.<br />

Introduction<br />

The programme commenced in [date removed] and is due for full completion by [date removed]. The biggest<br />

challenge of this project was the fact that the works were to be carried out in a “live” operational environment.<br />

As project manager, taking over from the previous PM, the learning curve was steep and having not worked<br />

with the NEC form of contract Option C Target Cost previously, this presented further but ultimately interesting<br />

challenges.<br />

The objective of the project was to present upgraded security facility to the baggage system that utilised<br />

significantly less space within the baggage hall and entailed the relocation of baggage handling agents to other<br />

parts of the baggage facility with stakeholder consensus.<br />

Case study – 500-1000 words<br />

2.0 Construction Phasing<br />

The construction programme was established and the first element was to identify the key milestones and<br />

implications of the programme phasing. There were a number of key drivers to this, and milestone dates that<br />

triggered the implementation of contractual Liquidated and Ascertained Damages (LADs) for not achieving<br />

particular dates.<br />

The key aspect of this incorporated establishing the critical path – this identified the key element in this<br />

as being the procurement of the baggage system elements and sign off of design deliverables<br />

applicable thereto.<br />

3.0 Scope of works<br />

As the scope was extensive, for the purpose of illustration I have highlighted only some of the key elements<br />

with elaboration. The procurement of these in a timely manner was essential for the smooth flow and sequence<br />

of operations and objectives of the programme:<br />

Asbestos Identification and Removal<br />

o Engagement and reporting of a specialist consultant for areas in advance of construction<br />

phasing.<br />

Demolition and Clearance<br />

o Identification via the Health and safety plan for asbestos, structural validation and service<br />

isolations in advance of works.


Groundworks<br />

o Substructure concrete – key aspect included identification of make up of ground cover above<br />

service tunnel using CAT facility and pilot holes and core to determine make up that influenced<br />

the concrete design over same to accommodate the 3Tonne baggage security machine<br />

located above.<br />

o Drainage works – solution required to ensure maintenance strategy was improved from current<br />

situation.<br />

Survey works<br />

o Structural – validation required of the existing structure and implication of removal of structure<br />

in a sequence to suit the phasing.<br />

o Mechanical and Electrical – service isolations and capacities identified, future proofing for later<br />

phasing and validation of existing design.<br />

Fire strategy<br />

The fire engineering process was a key element that is highlighted as a result of the brief being<br />

ambiguous. I advised the client we would have to engage the service of a specialist fire engineering<br />

consultant to advise and assist in the progress of a solution to have a design established to meet the<br />

requirements of the Building Control Officer (BCO) requirements.<br />

Surveys and records of the existing building were either outdated, not in existence or inaccurate. In<br />

order to protect the interests of the client business and operations, a clear strategy and plan was<br />

agreed for implementation. This exercise alone entailed detailed 3D modelling and simulation to<br />

identify clash detection of structure and services, i.e. to ensure clear headroom for walkways within the<br />

restricted baggage hall facility.<br />

The process enabled design solutions to be driven out for the remaining design deliverables and the<br />

advice was bought into by the client.<br />

Service isolations<br />

Removal of conveyors<br />

Installation of conveyors<br />

Installation of new security and x-ray machines<br />

Traffic management and re-location<br />

Logistics management and interface with existing operations was critical in terms of management of<br />

traffic routes and flow of baggage dollies and tugs within the busy live airport environment. Access to<br />

the emergency services maintained. Rigid health and safety controls were maintained with the isolation<br />

of the construction site works made clear through demise and physical barriers.<br />

Signage – including re-routing of traffic during relocation of baggage handling operations.<br />

Lighting and HVAC<br />

Cladding<br />

Roller shutter doors<br />

Road surfacing<br />

Decoration<br />

Structural steel<br />

Stairs and walkovers – impact of same on fire escape routes and service / structural interface<br />

Partitions, doors and fit out of offices


Testing and Proving of Systems<br />

o Series of Acceptance tests established<br />

o System integration testing<br />

o Client approval tests<br />

o Confidence trials and training<br />

4.0 Design Deliverables<br />

As part of the agreed contract documentation – Working <strong>Project</strong> Execution Plan (WPEP) – a clear set of design<br />

deliverables were established at the project outset. These entailed having design deliverables being<br />

progressed to scheme design stage and signed off by the key stakeholders within GAL in a timely manner.<br />

Failure to meet the required dates would lead to imposing LADs on to the company as the design and build<br />

contractor.<br />

Summary of objectives leading to detailed design approval:<br />

Controlling change within budget<br />

Co-ordinating elements not in contracts<br />

Presenting detailed proposals for approval<br />

Developing final project plan with programme (and costs if deviation)<br />

Preparation of report with recommendation<br />

In selecting and comparing a design solution to maximise value and meet project brief and planning consent<br />

requirements, the following are some of the key activities that were involved:<br />

Appointment of team resources including specialists, i.e. fire engineering<br />

Health and Safety Plan – development from the CDMC collected data that informed designer risk<br />

assessments<br />

Planning consultations with Building Control Officer<br />

Specialist supply chain engagement and analysis of design to ensure safe, economic and efficient<br />

construction.<br />

Programme studies – to identify key constraints and dependencies, and long lead activities.<br />

Change control – formal process of identifying a need to change the project brief and devaluating the<br />

effects for Client Approval.<br />

Risk <strong>Management</strong><br />

This entailed the ongoing maintenance of a risk register entailing risk analysis and contingency plans<br />

for hazards outside of the direct control of the Client or <strong>Management</strong> team.<br />

The biggest impact was failure to meet a deadline after our Client had committed to a 3rd party airline<br />

that the new line and handling facility would be ready by a certain time.<br />

The Confidence Trial was a mechanism of ensuring for a 7-day period, we would provide standby<br />

operatives and supervisors to “unblock” and rectify any difficulties associated with integration of the<br />

new line into the baggage system.<br />

5.0 <strong>Project</strong> <strong>Management</strong> Controls<br />

The implementation of our management controls were managed through the following:<br />

<strong>Project</strong> Execution Plan (PEP)<br />

Programmes – established at the appropriate level for reporting in accordance with the GAL<br />

requirements, i.e. from level 1 to level 4.


Meetings and workshops held weekly and attended by me as the contractor PM lead:<br />

o Client meetings convened weekly<br />

o Design Team meetings<br />

o Health and Safety meetings<br />

o Last Planner meetings with contractors – weekly and 4-weekly look-ahead / coordination<br />

o Internal company meetings – leadership and teamwork<br />

Client Reports – I was responsible for preparing monthly client reports to include the following:<br />

o Commercial headlines<br />

o Critical issues<br />

o Programme and Progress (P6 Primavera)<br />

o Design<br />

o Contractual Issues (NEC 3 Option C Target Cost)<br />

Early Warning Notices (EWN)<br />

Compensation Event Notification (CEN)<br />

<strong>Project</strong> <strong>Management</strong> Instruction (PMI)<br />

o Risk and Opportunities<br />

o Procurement status<br />

o Health and Safety Reports and Initiatives<br />

Safety First Second Nature (SFSN)<br />

Behavioural <strong>Management</strong> and Observation Studies (BMOS)<br />

Please list the core and optional competencies and mandatory competencies demonstrated in the case study<br />

Core competencies Optional competencies Mandatory competencies<br />

Construction technology and Commercial management of Client care<br />

environmental services<br />

construction<br />

Leadership Communication<br />

Managing people Conduct rules, ethics and<br />

professional practice<br />

Procurement and tendering Conflict avoidance, management<br />

and dispute resolution procedures<br />

Programme and planning Health and safety<br />

Risk management Teamworking

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!