Chart 14:<br />
The rise and fall of Guaranteed Maximum Price provisions<br />
Two stage procurement<br />
In <strong>2010</strong>, 2.8% of the sample was identified as us<strong>in</strong>g two stage procurement, only a little<br />
down on the 3.4% recorded <strong>in</strong> the 2007 survey and still almost twice as frequent as<br />
experienced <strong>in</strong> 2004 (1.5%). Chart 16 shows the growth of two stage procurement<br />
dur<strong>in</strong>g the 2000’s as the <strong>in</strong>dustry grew and its peak <strong>in</strong> 2007.<br />
Chart 15:<br />
The use of two stage procurement (by contract number)<br />
By value, the pattern of the use of stage procurement is similar if less pronounced:<br />
Page 26