PROCEDURES<br />
1 st Cycle – up to Working <strong>Load</strong><br />
25% of working load for each increment<br />
Maintained minimum 2 hours at each increment<br />
Maintained 24 hours at Working <strong>Load</strong>.<br />
Reading is taken at 15 minutes interval<br />
Reading of pile settlement is taken before and<br />
after increment<br />
Unloading at 4 equal stages @ 1 hour interval.