Support to the Integration of Ukraine in the Trans-European Transport Network TEN-T<br />

4th <strong>Progress</strong> <strong>Report</strong><br />

2. Summary of Project <strong>Progress</strong>, Period 4<br />

This is the forth progress report (<strong>Progress</strong> 4), covering the period 1 st February 2010 to 31 st<br />

July 2010<br />

of the project “Support to the Integration of Ukraine in the Trans-European Transport Network TEN-T”.<br />

The project held a number of meetings throughout the period with the EU Delegation, Ministry of<br />

Transport and Communications (MoTC), executive bodies responsible for each mode of transport, and<br />

international financing institutions (IFIs).<br />

There remain some 18 EU funded projects, including TRACECA, currently operating in Ukraine and in<br />

addition there are many other transport related projects funded by World Bank, USAID and others as<br />

well as support on transport related issues through a Working Group (of which we are a member)<br />

established by an NGO “Foundation for Effective Governance” with the consultancy company<br />

McKinsey. Unfortunately the projects are not coordinated in any way but where possible the TEN-T<br />

meets with their representatives in Ukraine to limit any duplication of effort or conflict of advice. The<br />

TEN-T project has no authority to coordinate or advise any other project, nor would it expect to do so.<br />

Within the evolved strategy plan, Sector Budget Support (SBS) meetings were held by the project<br />

team with representatives of each individual transport subsector as well as MoTC, Roads Research<br />

Institute and EU Delegation concerning the establishment of the Sector Budget Support (SBS)<br />

indicators. The final meeting was held in early July 2010, where the agreement was reached.<br />

There were subsector meetings held with the EU Delegation on aviation following their request to<br />

produce an aviation twinning fiche within the resources of the project, by September 2010.<br />

The appointment of the New Minister of Transport in March 2010 and his later appointments of new<br />

Section Heads and senior managers for Ukravtodor, MoTC rail, Maritime, HR and Aviation etc. caused<br />

delays to the project, while the new appointees established themselves.<br />

Some introductions were facilitated through the MoTC Department of Transport and Communication<br />

System Development and Coordination (DTCSDC) for which we were very grateful, but the dates for<br />

subsequent follow up meetings have yet to be confirmed in some cases.<br />

2.1 Steering Committee and Working Groups<br />

The third meeting of the Steering Committee was delayed from 17th December 2009 to 25th February<br />

2010 to give the members time to review the summary of the Interim <strong>Report</strong>s issued with <strong>Progress</strong><br />

<strong>Report</strong> 3 in January 2010. These were all accepted and the report approved. At the same time a<br />

complete set of the full Interim <strong>Report</strong>s was given to each member on electronic memory sticks but to<br />

date there has been no feedback from any one of the reports, submitted in English and Ukrainian.<br />

The fourth Steering Committee meeting was held on 27 July 2010 which reviewed the progress of the<br />

project and agreed on the activities of the following reporting period. During this Steering Committee<br />

meeting the possible extension of the project contract for one more year was discussed. The<br />

addendum to the contract shall be initiated after the signature of the addendum to the financing<br />

agreement on its extension by the Ministry of Economy. . It was agreed that most of the activities of<br />

the project shall be finalised by the end of 2010, while during the extension period (until the end of<br />

2011) the focus will be on Work Packages 1, 8 and 9 as given in the original ToR with minor<br />

adjustments. The more detailed discussion of the activities during the extension period shall continue<br />

among the Consultant, Beneficiary and EU Delegation the following months.<br />

With the changes in personnel resulting from the reorganisations in the MoTC and transport<br />

subsectors some of the members of the Working Groups established by the project, including some<br />

head of WGs, are no longer in their positions. Notwithstanding, during the period 12 WG meetings<br />

have been held in the aviation (8), road (3), and rail (1). In addition a large number of other, less<br />

formal, meetings have been held to both bring the new personnel on board and discuss specific issues<br />

(e.g. international drivers’ visas, traffic forecasting, road safety and investment projects) were<br />

discussed in smaller groups. A list of all the meetings held in the period is attached as Appendix F.<br />