Department and chaired by the Honble Chief Minister who is also the<br />

Minister, Planning & Co-ordination.<br />

3. Scheduling of Programme Implementation:<br />

It is proposed that each programme will be implemented over a period<br />

of 3 years, e.g. Phase-I from <strong>2003</strong>-04 to 2005-06, Phase-II from <strong>2004</strong>-05 to<br />

2006-07 and Phase-III from 2005-06 to 2007-08 in the following manner.<br />

Programme Implementation Schedules for<br />

Phase I, Phase-II and Phase III<br />

SL.<br />

No.<br />

Year Phase I Phase II Phase-III<br />

1 <strong>2003</strong>-04 &<br />

<strong>2004</strong>-05<br />

58 % 20% -<br />

2 2005-06 42% 30% 20%<br />

3 2006-07 - 50% 30%<br />

4 2007-08 50%<br />

Total 100% 100% 100%<br />

[ Table 2.6 ]<br />

With a view to ensuring the desired quality of the proposed works,<br />

elaborate Quality Control Modalities have been put in place.<br />

The responsibility for overall supervision and implementation of Special<br />

Connectivity Programme rests with the State Government in Planning & Coordination<br />

Department and the Chief Administrator, KBK. The State Rural<br />

Road Agency and the Special Area Infrastructure Development Authority shall<br />

also supplement the efforts of the State Government.<br />

5. Cost Estimates<br />

The total cost of Special Connectivity Programme has been estimated to<br />

be Rs.3,311.55 crore. This includes Rs.3,131.50 crore for Work Component<br />

and Rs.180.05 crore towards Programme Implementation Support (@5.75% of<br />

the cost of the Work Component) mainly in the form of engagement of<br />

professional consultants to supplement organizational capacities of the State<br />

Rural Development and Works Departments.<br />

Funds to the extent of Rs.700.93 crore are expected to be made available<br />

to the State Government over a period of five years from <strong>2003</strong>-04 to 2007-08<br />

for construction/upgradation of roads including CD/bridge works in KBK<br />

districts from PMGSY and SCA under RLTAP. Additional requirement of<br />

funds is of the order of Rs.2610.62 crore.