CEO ON-GOING PROJECTS FOR FLOOD CONTROL<br />

Const. of drainage system & footwalk @ Brgy 1 P 275,000<br />

Riprap at Purok Bolinao, Brgy 1 100,000<br />

Improvement of drainage @ Purok Tuna & Bonito, Brgy 1 100,000<br />

Drainage imprvt. & repair of gutter & covered court, Brgy 4 100,000<br />

Continue laying of culvert to open canal & widening<br />

thereafter @ 21 st St., PO Torre Sts. & back of<br />

Redemptorist<br />

100,000<br />

Repair/rehab/clearing & cleaning of drainage & canals at<br />

Puroks Paglaum & Pag-asa, Brgy 17 75,000<br />

Declogging of Mambuloc Creek, Brgy 21 100,000<br />

Footwalk with box culvert @ Purok Acacia 1, Brgy 27 345,000<br />

Riverbank protection wall @ Purok Balonggay, Brgy 28 270,000<br />

Repair/rehab of drainage system, Brgy 36 145,000<br />

Rehab of drainage system along Mabini and San 225,000<br />

Sebastian Sts., Brgy 30<br />

Drainage cleaning/declogging at Puroks St. Joseph, San 50,000<br />

Sebastian & Sto. Niño, Brgy 37<br />

TOTAL P 1,885,000<br />

In addition, 2 new projects totaling P6.4 million are forthcoming.<br />

One is for the construction of a diversion channel from Purok Riverside to<br />

Banago Creek for a project cost of P2 million. This project will also benefit<br />

directly the Sta. Clara Subdivision area. The other, with a project cost of P4.4<br />

million, is to cover the demolition of cracked pavement and replacing it with a<br />

new concrete pavement with drainage declogging in Capitol Shopping,<br />

particularly along sections of Hilado St. from Malaspina to Yakal Ave., sections of<br />

Tindalo Ave. from Hilado to Lopez Jaena St., and sections of Narra Ave. from<br />

Hilado to Lopez Jaena St. We expect this project to diminish the constant<br />

flooding of the area near St. John’s Institute even with mild rains.<br />

In summary therefore, a total of P27.9 million have been spent or<br />

allocated for flood control activities and infrastructures during the year ending<br />

June 30, 2008. This covered the following:<br />

Dredging of Banago Creek and Mandalagan River P 10 million<br />

Construction of river wall protection at Banago<br />

Creek 1.5 million<br />

Construction of foreshore protection at Banago<br />

Creek .350 million<br />

Budget for clean-up of waterways & drainages<br />

by Action Team of Councilor Bobby Rojas 2.5 million<br />

Financial assistance to families affected by<br />

clearing of waterways .372 million