SECTION V: PROPOSAL EVALUATION AND CONTRACT AWARD PROCEDURES<br />
A. Evaluation Procedures<br />
All proposals accepted by the Agency will be reviewed to determine whether they are responsive or non-responsive to the<br />
requisites of this RFP. Proposals that are determined by the agency to be non-responsive will be rejected. The Agency’s<br />
Evaluation Committee will evaluate and rate all remaining proposals based on the Evaluation Criteria prescribed below.<br />
The following two (2) step selection process will be used:<br />
STEP I - Submission of Technical Proposal and establishment of a List of Top Qualified Proposers<br />
Proposers are to submit by the applicable due date and time prescribed in the RFP (See Section I - Timetable), a<br />
Technical Proposal that addresses the information requested in Appendix B - and Form 1.<br />
B. Evaluation Criteria<br />
Evaluation of Technical Proposal<br />
The Evaluation Committee will rate all responsive Technical Proposals pursuant to the following criteria:<br />
A. Project Delivery Related Criteria<br />
A1. Maintenance and protection of Traffic, staging and sequencing of operations 15%<br />
A2. Understanding of scope, DOT’s goals and objectives; required design approvals<br />
and permits; quality assurance and quality control; constructability of proposed<br />
scheme;ability to anticipate problems and provide solutions; and long term<br />
maintenance considerations. 15%<br />
B. Impact and Coordination Related Criteria<br />
B1. Anticipated issues with SIRTOA and plan to address them. Impact of contractor’s<br />
scheme to SIRTOA’s operations and Force Account costs. 8%<br />
B2. Anticipated issues with MTA buses and plan to address them. Impact of<br />
proposed scheme to MTA’s operations. 5%<br />
B3. Impact to and coordination with DOT-Ferries. Impact to parking lot and taxi services 5%<br />
C. Schedule<br />
Ability to support proposed contract and construction duration and ability to support<br />
proposed durations through a coherent and detailed CPM Schedule and through a<br />
demonstration of company resources, personnel, equipment and bonding capability 17%<br />
D. Organizational Chart, Relevant Experience of Firm (Consultant and Contractor) and<br />
Relevant Experience of Key Personnel 15%<br />
E. Safety Record and Specific Safety Concerns for this Project and Plan to Address them 10%<br />
F. Other<br />
F1. Community outreach and ability to address last minute community requests 7%<br />
F2. Environmental and aesthetic considerations 3%<br />
Establishment of a “Short-List” of Best Rated Firms Based on Technical Proposals<br />
Upon completion of the evaluation of the Technical Proposal, proposers will be ranked in descending order of score. A<br />
“short-list” of only those proposers who submit highly relevant and acceptable proposals with better than adequate<br />
understanding of approach and innovativeness in most project areas, which have scored 80% or higher, will be<br />
established. Proposers not included on the “short-list” will not be further considered.<br />
• All proposers will be notified in writing as to whether or not they are included on the “short-list”.<br />
10<br />
100%