04.08.2013 Views

chhatru hydro electric project (3x36 =108 mw) - Ministry of Power

chhatru hydro electric project (3x36 =108 mw) - Ministry of Power

chhatru hydro electric project (3x36 =108 mw) - Ministry of Power

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

CHHATRU HYDRO ELECTRIC PROJECT (3X36 <strong>=108</strong> MW)<br />

HIMACHAL PRADESH<br />

1. INTRODUCTION<br />

The Chhatru Hydro<strong>electric</strong> Project located in Lahaul & Spiti district <strong>of</strong><br />

Himachal Pradesh envisages utilization <strong>of</strong> the waters <strong>of</strong> the river Chandra<br />

for power generation on a run <strong>of</strong> river type development, harnessing a<br />

head <strong>of</strong> about 177m.<br />

The <strong>project</strong> with a proposed installation <strong>of</strong> 108 MW (<strong>3x36</strong> MW) would<br />

afford an net annual energy generation <strong>of</strong> 455.72 GWH, in a 90 %<br />

dependable year. The tariff energy from the <strong>project</strong> at present day cost<br />

would be Rs 2.28/unit (levellised) at power house bus bars.<br />

The diversion site is located between Latitude 32 o 18'11" North Longitude<br />

77 o 24'41"East. The barrage site is approachable from Chandigarh by road<br />

being at a distance <strong>of</strong> 410 kms approx. The nearest rail head is located at<br />

Kiratpur and nearest airport is located at Bhunter.<br />

2. SCOPE OF WORKS<br />

The Chhatru HE <strong>project</strong> envisages construction <strong>of</strong> :<br />

a 19m high diversion barrage across river Chhatru to provide a net<br />

live storage <strong>of</strong> 87.50 hacm. with FRL at 3421.00m and MDDL at<br />

3413.50m;<br />

two numbers desanding basins <strong>of</strong> length 381m(L) and size 13m<br />

(W)x19.60m(H) to remove silt particles <strong>of</strong> size 0.20 mm and<br />

above;<br />

a 6.5 km long and 5.10m dia. modified horse shoe shaped head<br />

race tunnel terminating in a surge shaft;<br />

a 91.80m high ,15m dia surge shaft;<br />

350m long, 4.70m dia pressure shaft;<br />

a surface power house having an installation <strong>of</strong> 3 Francis driven<br />

generating units <strong>of</strong> 36 MW each operating under a net head <strong>of</strong> 160<br />

m; and<br />

1150m long tail race tunnel to carry the power house releases back<br />

to the river Chandra.<br />

The power generated from the <strong>project</strong> would be evacuated through. 220<br />

kV double circuit line from Khoskar to 400 KV pooling point at Tandi,<br />

1


eyond which the evacuation will be through 400 KV double circuit net<br />

work to pooling station near Panarsa to feed power to the power grid .<br />

The Salient features <strong>of</strong> the <strong>project</strong> are given at Annex-I and a layout map<br />

at Plate-I<br />

3. HYDROLOGY<br />

The river Chandra drains a catchment area <strong>of</strong> about 1583 Sq. km. at the<br />

proposed barrage site. The discharge data <strong>of</strong> rivder Chandra at diversion<br />

site <strong>of</strong> Chhatru HEP has been derived from June 1973- May 2000 from the<br />

discharge data <strong>of</strong> river Chandra at Ghousal (site Monitored by CWC).<br />

Discharge data <strong>of</strong> river Chandra at Ghousal has been reduced on<br />

catchment area basis at diversion site. For design flood, flood frequency<br />

analysis has been carried out by Gumble Method.The design flood has<br />

been assessed as approx. 1500 cumecs.<br />

4. POWER POTENTIAL STUDIES<br />

The computed inflow series for 27 years viz June 1973 to May, 2000 has<br />

been considered in the assessment <strong>of</strong> a power benefits from the <strong>project</strong>. As<br />

per GOI notification for tariff, the year 1992-93 corresponds to 90%<br />

dependable year. An installation <strong>of</strong> 108 MW comprising 3 generating<br />

units <strong>of</strong> 36 MW each has been proposed. The energy availability from the<br />

<strong>project</strong> in a dependable and an average year has been summarized below:<br />

Particulars<br />

Annual Energy Generation<br />

Dep. Yr. Avr. Yr.<br />

Gross annual Energy Generation (GWH) 455.72 475.80<br />

Annual Load Factor (%) 50.00 52.00<br />

Generation during Lean Flow Season (Dec.-Feb.)<br />

Energy Output (GWH) 41.86<br />

Load Factor (%) 18.00<br />

The design energy at 95 % machine availability in a 90% dependable year<br />

has been worked out at 455.72 GWH.<br />

A net live pondage <strong>of</strong> 75.00 ham. has been provided in the diversion<br />

barrage, which would enable the station to operate as peaking station. The<br />

pondage is equivalent to 280.79 MWH which is sufficient to operate the<br />

station for 3 hours.<br />

2


5. POWER EVACUATION ASPECTS<br />

The power generated from the <strong>project</strong> would be evacuated through. 220<br />

kV, double circuit lines from Khoskar to 400 KV pooling point at Tandi,<br />

beyond which the evacuation will be through 400 KV double circuit net<br />

work to pooling station near Panarsa to feed into the Grid which in turn<br />

connected to National Grid<br />

6. ENVIRONMENTAL ASPECTS<br />

The <strong>project</strong> is located in Lahaul & Spiti valley <strong>of</strong> H.P. Based on<br />

assessment <strong>of</strong> environmental impacts, management plans have to be<br />

formulated for Catchment Area Treatment, compensatory afforestation<br />

and other environmental issues. These issues would be addressed during<br />

investigations for preparation <strong>of</strong> DPR.<br />

7. ESTIMATES OF THE COST<br />

The <strong>project</strong> is estimated to cost Rs. 585.15 crores at power house bus bars<br />

including IDC at Oct., 2003 price level. The preliminary cost estimate <strong>of</strong><br />

the <strong>project</strong> has been prepared as per guidelines <strong>of</strong> CEA / CWC. The break<br />

down <strong>of</strong> the cost estimates is given below:<br />

Civil works : Rs. 386.79 Crores<br />

Electro Mechanical works : Rs. 136.12 Crores<br />

Sub total (Generation) : Rs. 522.91 Crores<br />

Transmission works : Rs. 8.45 Crores<br />

Total Cost : Rs. 531.36 Crores<br />

On Generation works<br />

Interest During Construction : Rs. 62.24 Crores<br />

Total : Rs. 585.15 Crores<br />

8. FINANCIAL ASPECTS<br />

As indicated above, the Chhatru HE <strong>project</strong> with an estimated cost <strong>of</strong> Rs.<br />

585.15 (including IDC <strong>of</strong> Rs.62.24 crores) at power house bus bars with<br />

net energy <strong>of</strong> 455.72 GWH in a 90% dependable year. The <strong>project</strong> is<br />

proposed to be completed in a period <strong>of</strong> 4½ years. The tariff has been<br />

worked out considering a debt-equity ratio <strong>of</strong> 70:30, 16% return on equity,<br />

annual interest rate on loan at 10% .The tariff for first year and levellised<br />

tariff have been work out Rs. 2.89 /kWh & Rs. 2.28/kwh respectively at<br />

power house bus bars.<br />

3


9. CONCLUSIONS<br />

The economy <strong>of</strong> the Himachal Pradesh predominantly depends on<br />

agricultural and allied sectors. The <strong>electric</strong> power being a vital and<br />

essential infrastructure has a significant role to play in economic<br />

upliftment <strong>of</strong> the state. The construction <strong>of</strong> <strong>project</strong> will provided<br />

employment to the local people. The <strong>project</strong> has a distinct advantage <strong>of</strong><br />

being located along a motorable road making it possible to be completed<br />

within four and half year.<br />

4


GENERAL PROJECT FEATURES<br />

5<br />

Annexure-I<br />

LOCATION<br />

State Himachal Pradesh<br />

District Lahaul Spiti<br />

River Chandra river(Chenab Basin)<br />

Barrage site ± 5 km. u/s <strong>of</strong> Chhatru village<br />

<strong>Power</strong> house site ± 3.5 km d/s <strong>of</strong> Chhatru village<br />

on right bank <strong>of</strong> Chandra river<br />

HYDROLOGY<br />

Catchment Area<br />

at diversion site 1583 Sq. km.<br />

Snow catchment 48 Sq. km. above El. 4200m<br />

Probable maximum flood 1500cumecs<br />

Standard <strong>project</strong> flood<br />

Observed maximum flood 828.00 cumsecs<br />

RESERVOIR<br />

Full reservoir (FRL) 3421.00m<br />

Maximum reservoir level (MRL) 3422.00m<br />

Maximum draw down level (MDDL) 3413.50m<br />

Gross storage upto FRL 112.50 Hect-m<br />

Live storage 87.50 Hect-m<br />

Net live storage 70.00 Hect-m<br />

DIVERSION STRUCTURE<br />

Type Barrage<br />

Max. height from R.B.L. 19m<br />

Elevation <strong>of</strong> top <strong>of</strong> dam or bridge ±3424.00m<br />

Average bed level ±3405.00m<br />

SPILLWAY<br />

Design flood 1500cumecs<br />

Type Gated spillways with radial gates<br />

Nos. <strong>of</strong> spillways, Crest elevation 6 Nos. El. 3407.00m<br />

Length <strong>of</strong> gated spillways 5.00m each.


Energy dissipation<br />

Length 98.00m<br />

Down stream bed level ±3403.00m<br />

INTAKE STRUCTURE<br />

Type Surface<br />

Sill level El. 3410.00m<br />

No. & size <strong>of</strong> opening 8 Nos., 5.50mx3.0m<br />

APPROACH TUNNEL<br />

No. 1<br />

Size and type 6.00m dia, Circular concrete Lined<br />

Velocity 3.30m/sec<br />

Length 200m<br />

Design discharge from intake 93.75 cum/sec<br />

DESANDING BASIN<br />

Type Underground, central gutter type<br />

No. <strong>of</strong> basins 2 nos.<br />

Length <strong>of</strong> each basin 381m<br />

Size <strong>of</strong> basins Width13.00m,Depth 19.60m<br />

Minimum particle size to be removed 0.2mm<br />

Flushing tunnel, size 4.00m, D-Shaped<br />

Flushing tunnel, length 1000m<br />

HEAD RACE TUNNEL<br />

No. 1<br />

Size & Shape 5.10m diameter, Modified<br />

Horse shoe shaped Concrete lined<br />

Length 6500 m<br />

Design discharge 75 cumecs<br />

Slope 1 in 120.50 m<br />

Velocity 3.63m/sec<br />

Adit 275m leangth 5m D- shaped<br />

SURGE SHAFT<br />

Type Underground, restricted orifice type<br />

Size 15m dia, 91.80m high<br />

Orifice 2.50m dia<br />

Maximum upsurge level El. 3436.10m<br />

6


Minimum down surge level El. 3396.60m<br />

Bottom level El. 3350.50m<br />

Top level El. 3436.00m<br />

Adit to top <strong>of</strong> surge shaft 4mx6m, D-Shaped<br />

2no. 75m each<br />

PRESSURE SHAFT<br />

Type Underground<br />

Size:<br />

Main 1 No., 4.70m dia,<br />

± 350m long<br />

Branches 3 Nos., 2.70m dia, ± 50m<br />

long each<br />

Velocity 4.32 m/sec.<br />

POWER HOUSE<br />

Type Underground<br />

Installed capacity 108 MW<br />

No. and capacity <strong>of</strong> unit 3 Nos. 36 MW<br />

Size <strong>of</strong> machine hall 67mx15m<br />

Service bay elevation EL 3250m<br />

Type <strong>of</strong> turbine Francis, Vertical axis<br />

Speed <strong>of</strong> turbine 428.60 RPM<br />

Gross Head 177.33 m<br />

Normal tail water level El. 3240.00m<br />

Max. net operating head for<br />

design discharge 182.50m<br />

Minimum net operating head for<br />

design discharge 173.50m<br />

Net operating head for design<br />

discharge 160.00m<br />

Peaking duration 3.00 hrs.<br />

Maximum discharge during peaking hours 75 cumecs.<br />

Firm discharge in 90% dep. Year 11.18 cumecs<br />

TAIL RACE<br />

Size and shape 6.00 m diameter,<br />

D-Shaped concrete lined<br />

Length ± 1150 m<br />

7


SWITCHYARD<br />

Type underground<br />

TRANSMISSION LINE<br />

No. <strong>of</strong> circuits D/C Line<br />

Length <strong>of</strong> each 150Km<br />

Voltage 220.KV<br />

POWER GENERATION<br />

Installed capacity <strong>3x36</strong> MW<br />

Annual energy generation 455.72 MUs<br />

90% dep. Year<br />

8


50 000 MW HYDROELECTRIC INITIATIVE<br />

Government <strong>of</strong> India<br />

<strong>Ministry</strong> <strong>of</strong> <strong>Power</strong><br />

Central Electricity Authority<br />

108 MW CHHATRU<br />

H.E. PROJECT<br />

HIMACHAL PRADESH<br />

Preliminary Feasibility Report<br />

(HYDROLOGY AND POWER POTENTIAL STUDIES)<br />

MARCH ,<br />

22000044<br />

Consultant:<br />

fgekpy izns'k jkT; fctyh cksMZ<br />

Himachal Pradesh State Electricity Board<br />

( H.P.Government Undertaking )


CHAPTER - V<br />

HYDROLOGY<br />

5.1 RIVER CHENAB AND CATCHMENT CHARACTERISTICS.<br />

V -<br />

The river orginates from the snow covered slopes <strong>of</strong> Great Himalayan <strong>of</strong><br />

Pir-Panjal ranges in Lahaul Spiti district and flows in a steep gradient with<br />

a series <strong>of</strong> loopes and bends. The river is formed by the two major<br />

tributaries in the head reaches namely Chandra and Bhaga.The river<br />

Chandra originates from Bara Lachala and is further augmented by<br />

Chandra Tal. The river Bhaga takes <strong>of</strong>f from Suraj Tal in the vicinity <strong>of</strong><br />

Bara Lachala and is further joined by Jhankar and Millang nallahs in the<br />

head reaches. The catchments <strong>of</strong> these two major tributaries have snow<br />

covered peaks at height ranging from ± 3500 m to 5500 m elevation. The<br />

Chandra river and Bhaga river joins at Tandi to form Chandra-Bhaga i.e.<br />

the Chenab. Further downstream <strong>of</strong> confluence, it is joined by other<br />

significant tributaries namely Shansha nallah near Rashil, Thirot nallah at<br />

Thirot, Miyar nallah at Udaipur, Saichu nallah at Dawag, Mahal Nallah at<br />

Killar & Dheda nallah at Lujai d/s <strong>of</strong> Killar. Chenab river drains a<br />

catchments <strong>of</strong> about 7500 Sq. Km. before it crosses in to J&K border.<br />

5.1.1 HYDROMETEOROLOGY OF THE CATCHMENT<br />

This region is a low rainfall area as most <strong>of</strong> the precipitation in the region<br />

is in the form <strong>of</strong> snow. The rainfall takes place during the monsoon months<br />

only and the catchment experiences snowfall during the remaining period<br />

2


V -<br />

<strong>of</strong> the year. There is only one rain gauge station in this region, installed at<br />

Keylong and the rainfall data has not been recorded regularly even at this<br />

station. It is observed that the most <strong>of</strong> the run<strong>of</strong>f in the river results from<br />

the melting <strong>of</strong> snow.<br />

5.2 DISCHARGE DATA AND WATER AVAILABILITY<br />

The discharge data <strong>of</strong> river Chandra at diversion site <strong>of</strong> Chhatru HEP has<br />

been derived from June 1973-May 2000 from the discharge data <strong>of</strong> river<br />

Chandra at Ghousal (site monitored by CWC).<br />

Discharge data <strong>of</strong> river Chandra at Ghousal is given in table 5.1 while the<br />

computed discharge data reduced on catchment area basis at diversion site<br />

is given in Table– 5.2<br />

Based upon ten daily discharge data, a flow duration curve has been<br />

developed. From this curve, it is seen that flow corresponding to 90% &<br />

50% availability works out to 10.41 cumecs & 26.30 cumecs respectively.<br />

The design discharge <strong>of</strong> 75 cumecs is available for 32.15 % <strong>of</strong> the period.<br />

Flow duration curve for lean-season (Dec. to Feb.) has also been<br />

developed . From this curve , it is seen that flow corresponding to 90% &<br />

50% availability works out to 6.96 cumecs & 12.95 cumecs respectively.<br />

5.2.1 CO-RELATION STUDY<br />

W.B. Langbein’s log deviation method has been used to obtain the coefficient<br />

<strong>of</strong> co-relation between discharges <strong>of</strong> river Chandra at Ghousal and<br />

discharges <strong>of</strong> river Bhaga at Tandi.<br />

The Co-relation factors are as follows:<br />

June-July = 0.92<br />

3


Aug.-Sept. = 0.96<br />

Oct.-May = 0.96<br />

These calculations have been shown in Table- 5.3<br />

V -<br />

Similarly coefficient <strong>of</strong> co-relation has been obtained between discharges<br />

<strong>of</strong> river Chenab at Udaipur and the sum <strong>of</strong> discharges <strong>of</strong> river Chandra at<br />

Ghousal & river Bhaga at Tandi.<br />

June-July = 0.94<br />

Aug.-Sept. = 0.96<br />

Oct.-May = 0.88<br />

These calculations have been shown in Table-5.4<br />

From the above co-relation factors it is evident that the discharges <strong>of</strong> river<br />

Chandra at Ghousal & river Bhaga at Tandi including river Chenab at<br />

Udaipur are consistent. Thus the discharges <strong>of</strong> river Chandra at Ghousal<br />

have been approved by CWC and used for carrying out studies which<br />

stands submitted to the CWC and comments are awaited.<br />

5.3 DESIGN FLOOD<br />

The <strong>project</strong> falls in Western Himalayas Zone seven in map <strong>of</strong> India. The<br />

total catchment area <strong>of</strong> river Chenab in India is about 31,047 Sq. Kms. The<br />

catchment is mostly fed by snow. The majority percentage <strong>of</strong> the run<strong>of</strong>f in<br />

the catchment is derived from the snow & glaciers which constitutes a<br />

potential reservoir. Winter precipitation which occurs in the form <strong>of</strong> snow<br />

goes on accumulating till summer. As the summer advances, the<br />

accumulated snow melts and releases water into the stream.<br />

Design Flood has been computed on the basis <strong>of</strong> Flood Estimation report<br />

for Western Himalayas-zone 7 & accordingly <strong>hydro</strong>graphs have been<br />

prepared. The max.. flow due to rain contribution comes out to be 291.59<br />

4


V -<br />

cumecs which has return period <strong>of</strong> 1 in 50 years. The maximum flow for<br />

return period <strong>of</strong> 1 in 100 years is 321.38 cumecs. The snow contribution<br />

has been taken to be 342.09 cumecs ie the maximum discharge <strong>of</strong> flow<br />

during 2 nd week <strong>of</strong> July in flow series at diversion site. Thus the total<br />

design flood works out to be 663.47 cumecs. Flood frequency analysis has<br />

also been carried out by Gumble’s method.<br />

Return period <strong>of</strong> 1 in 1000 years has been considered for computing the<br />

SPF which works out to be 1377.59 cumecs. The designed flood has been<br />

taken as 1500 cumecs. The computations have been shown in Annexure-<br />

V-1.<br />

5.4 SEDIMENTATION ASPECTS<br />

Detailed studies shall be carried out at DPR stage. However 20% <strong>of</strong> the<br />

live storage has been proposed to be kept reserved for silt deposition in the<br />

reservoir.<br />

5


V -<br />

6


PARA DESCRIPTION PAGE<br />

5.1 RIVER CHENAB AND CATCHMENT<br />

CHARACTERISTICS<br />

V -<br />

5.1.1 HYDROMETEOROLOGY OF THE CATCHMENT V-1<br />

5.2 DISCHARGE DATA AND WATER AVAILABILITY V-2<br />

5.2.1 CO-RELATION STUDIES V-2 TO V-3<br />

5.3 DESIGN FLOOD V-3 TO V-4<br />

5.4 SEDIMENTATION ASPECTS V-4<br />

5.5 COMMENTS BY CWC V-4<br />

TABLE – 5.1 TEN DAILY AVERAGE DISCHARGE DATA OF<br />

RIVER CHANDRA AT GHOUSAL<br />

TABLE – 5.2 COMPUTED DISCHARGE DATA AT DIVERSION<br />

SITE<br />

V-1<br />

INFLOWS OF RIVER CHANDRA AT GHOUSAL V-15<br />

INFLOWS OF RIVER BHAGA AT TANDI V-16<br />

TABLE-5.3 CO-RELATION BETWEEN DISCHARGES OF<br />

RIVER CHANDRA AT GHOUSAL & RIVER<br />

BHAGA AT TANDI<br />

INFLOWS OF RIVER CHENAB AT UDAIPUR V-23<br />

INFLOWS OF RIVER BHAGA AT TANDI PLUS<br />

RIVER CHANDRA AT GHOUSAL<br />

TABLE-5.4 CO-RELATION BETWEEN DISCHARGES OF<br />

RIVER CHENAB AT UDAIPUR & THE SUM OF<br />

DISCHARGES OF RIVER CHANDRA AT<br />

GHOUSAL & RIVER BHAGA AT TANDI<br />

7<br />

V-5 TO V-9<br />

V-10 TO V-14<br />

V-17 TO V-22<br />

V-24<br />

V-25 TO V-30<br />

ANNEX.-5 DESIGN FLOOD COMPUTATIONS V-31 TO V-40<br />

PLATE -5.1 FLOW DURATION CURVE (OVER ALL) V-41<br />

PLATE -5.2 FLOW DURATION CURVE (LEAN SEASON) V-42<br />

PLATE -5.3 SYNTHETIC UNIT HYDROGRAPH V-43<br />

PLATE -5.4 DESIGN FLOOD HYDROGRAPH V-44<br />

ANNEXURE-V COMMENTS


1. INTRODUCTION<br />

HIMACHAL PRADESH STATE ELECTRICITY BOARD<br />

EXECUTIVE SUMMARY<br />

As a part <strong>of</strong> an exercise to assess the balance <strong>hydro</strong> potential <strong>of</strong> the country<br />

Central Electricity Authority(CEA ) identified more than 399 Hydro-<strong>electric</strong><br />

Projects with probable installed capacity <strong>of</strong> 1,50,000 MW. After carrying<br />

out ranking studies, 162 <strong>project</strong>s have been identified for preparation <strong>of</strong><br />

Preliminary Feasibility Reports. Chhatru in Chenab basin has been<br />

identified as one <strong>of</strong> these <strong>project</strong>s for preparation <strong>of</strong> PFR by HPSEB so that<br />

it could be taken up for further development during the 10th & 11th Plans.<br />

The identified Chhatru HEP in Lahaul & Spiti valley in HP by CEA<br />

involved construction <strong>of</strong> diversion weir on Chandra river<br />

(32°18’11”Latitude 77°24’41”Longitude) 5 km. upstream <strong>of</strong> village Chhatru<br />

and river Beas and a power house about 3.5 km d/s <strong>of</strong> Chhatru village on<br />

right bank <strong>of</strong> Chandra river (32°20’9”- Latitude 77°20’51” Longitude) with<br />

an installed capacity <strong>of</strong> 108 MW.<br />

A site visit was made to the area by engineers <strong>of</strong> HPSEB and Geologists <strong>of</strong><br />

GSI during January, 2004 for identification /selection <strong>of</strong> suitable site. The<br />

identified/ proposed Chhatru Hydro-<strong>electric</strong> Project is located about 5 km.<br />

u/s <strong>of</strong> village Chhatru (El. ± 3405m). The <strong>project</strong> has been found technoeconomically<br />

feasible. It is located along a motorable road. The diversion<br />

site <strong>of</strong> <strong>project</strong> is also well connected to road, whereas <strong>project</strong> roads have<br />

been proposed to power house and surge shaft. The <strong>project</strong> is about 410<br />

km. approx. from Chandigarh.<br />

2. SCOPE OF THE PROJECT


The <strong>project</strong> comprises a diversion barrage on river Chandra +19m high<br />

above river bed level, an intake arrangement on the right bank, for drawing<br />

discharge <strong>of</strong> 93.75 cumecs, through 6m dia approach tunnel leading to an<br />

underground desilting arrangement comprising two no chambers each<br />

(381mx13mx19.60m), to exclude all particles down to 0.20mm, 5.10m dia,<br />

6500m long modified horse shoe shaped tunnel designed for a discharge <strong>of</strong><br />

75 cumecs, opening into one 15m dia underground restricted orifice type<br />

surge shaft, one pressure shaft <strong>of</strong> 4.70m dia 350m long bifurcating into three<br />

2.70m dia, 50 long each branch pressure shafts feeding three Francis vertical<br />

axis generating units <strong>of</strong> 36 MW each, through a net head <strong>of</strong> 160m in an<br />

underground power house on the right bank <strong>of</strong> Chandra river about 3.50 km.<br />

d/s <strong>of</strong> Chhatru village. The <strong>project</strong> will enable energy generation <strong>of</strong> 455.72<br />

GWH in 90% dependable year at power house bus bars.<br />

3. HYDROLOGY<br />

The river orginates from the snow covered slopes <strong>of</strong> Great Himalayan <strong>of</strong><br />

Pir-Panjal ranges in Lahaul Spiti district and flows in a steep gradient with a<br />

series <strong>of</strong> loopes and bends. The river is formed by the two major tributaries<br />

in the head reaches namely Chandra and Bhaga.The river Chandra originates<br />

from Bara Lachala and is further augmented by Chandra Tal. The river<br />

Bhaga takes <strong>of</strong>f from Suraj Tal in the vicinity <strong>of</strong> Bara Lachala and is further<br />

joined by Jhankar and Millang nallahs in the head reaches. The catchments<br />

<strong>of</strong> these two major tributaries have snow covered peaks at height ranging<br />

from ± 3500 m to 5500 m elevation. The Chandra river and Bhaga river<br />

joins at Tandi to form Chandra-Bhaga i.e. the Chenab. Further downstream<br />

<strong>of</strong> confluence, it is joined by other significant tributaries namely Shansha<br />

nallah near Rashil, Thirot nallah at Thirot, Miyar nallah at Udaipur, Saichu<br />

nallah at Dawag, Mahal Nallah at Killar & Dheda nallah at Lujai d/s <strong>of</strong><br />

Killar. Chenab river drains a catchments <strong>of</strong> about 7500 Sq. Km. before it<br />

crosses in to J&K border.


This region is a low rainfall area as most <strong>of</strong> the precipitation in the region is<br />

in the form <strong>of</strong> snow. The rainfall takes place during the monsoon months<br />

only and the catchment experiences snowfall during the remaining period <strong>of</strong><br />

the year. There is only one rain gauge station in this region, installed at<br />

Keylong and the rainfall data has not been recorded regularly even at this<br />

station. It is observed that the most <strong>of</strong> the run<strong>of</strong>f in the river results from the<br />

melting <strong>of</strong> snow.<br />

The discharge data <strong>of</strong> river Chandra at diversion site <strong>of</strong> Chhatru HEP has<br />

been derived from June 1973-May 2000 from the discharge data <strong>of</strong> river<br />

Chandra at Ghousal (site monitored by CWC). W.B. Langbein’s log<br />

deviation method has been used to obtain the co-efficient <strong>of</strong> co-relation<br />

between discharges <strong>of</strong> river Chandra at Ghousal and discharges <strong>of</strong> river<br />

Bhaga at Tandi.<br />

The design flood works out to be 663.47 cumecs. Flood frequency analysis<br />

has also been carried out by Gumble’s method. The designed flood has been<br />

taken as 1500 cumecs. Similarly coefficient <strong>of</strong> co-relation has been<br />

obtained between discharges <strong>of</strong> river Chenab at Udaipur and the sum <strong>of</strong><br />

discharges <strong>of</strong> river Chandra at Ghousal & river Bhaga at Tandi.<br />

From the above co-relation factors it is evident that the discharges <strong>of</strong> river<br />

Chandra at Ghousal & river Bhaga at Tandi including river Chenab at<br />

Udaipur are consistent. Thus the discharges <strong>of</strong> river Chandra at Ghousal<br />

have been approved by CWC and used for carrying out studies which stands<br />

submitted to the CWC and comments are awaited.<br />

4. POWER POTENTIAL STUDIES<br />

Chhatru Hydro-<strong>electric</strong> Project has been contemplated as a peaking station<br />

to operate in Western part <strong>of</strong> North Regional Grid. Installed capacity <strong>of</strong> the<br />

<strong>project</strong> has been presently kept as 108 MW comprising 3 units <strong>of</strong> 36 MW


each. The <strong>project</strong> will generate 455.72 GWH in 90% dependable year.<br />

Accordingly energy exploitation <strong>of</strong> 62.08% with plant load factor <strong>of</strong> 50% in<br />

90% dependable year will be accomplished.<br />

5. POWER EVACUATION ASPECTS<br />

During the 14 th meeting <strong>of</strong> the Standing Committee on Transmission system<br />

planning <strong>of</strong> Northern Region held on 30.12.02, it has been decided that<br />

PGCIL will construct a Parbati Pooling Point at downstream <strong>of</strong> Parbati-III<br />

HEP which will cater to Allain-Duhangan, Malana-II and other<br />

<strong>project</strong>s/small HEPs <strong>of</strong> Himachal Pradesh. Hence, it is proposed to<br />

evacuate power generated at Chhatru <strong>project</strong> by laying a 15 km. long, 220<br />

KV D/C line from Khoksar to 400 KV pooling point at Tandi.Beyond which<br />

the evacuation will be through 400 KV D/C net work to Pooling point at<br />

Panarsa sub station <strong>of</strong> PGCIL.<br />

6. ENVIRONMENTAL ASPECTS<br />

Environmental Management Plan (EMP) aims at the preservation <strong>of</strong><br />

ecological system by considering certain mitigating measures at the<br />

proposed site. The EMP is required to ensure sustainable development in<br />

the study area <strong>of</strong> 10 km. radius <strong>of</strong> the proposed Chhatru HEP site.<br />

Government regulating agencies like Pollution Control Board working in<br />

the region and more importantly the people living in the area need to extend<br />

their co-operation and contribution in this direction.<br />

It has been evaluated that the study area shall not be affected adversely with<br />

the proposed activity , but is likely to get new economical fillip due to hydel<br />

power generation, not only for the study area but also for the region as<br />

whole.


7. ESTIMATES OF COST<br />

The estimates <strong>of</strong> cost has been prepared on the basis <strong>of</strong> “CEA Guidelines for<br />

rates and cost <strong>of</strong> civil and <strong>electric</strong>al works for Preliminary Feasibility<br />

Reports <strong>of</strong> Hydro-<strong>electric</strong> Projects” received during Oct. 2003.<br />

Accordingly cost <strong>of</strong> <strong>project</strong> works out to be Rs.386.79 crore for civil works,<br />

Rs. 136.12.crore for <strong>electric</strong>al works and Rs. 8.45 crore for transmission<br />

works.<br />

8. FINANCIAL ASPECTS<br />

The financial & economic evaluation has been carried out as per CEA<br />

guide lines considering Interest During Construction (IDC) @ 10% and<br />

interest on working capital @ 9.75%. The life <strong>of</strong> <strong>hydro</strong>-<strong>electric</strong> <strong>project</strong> has<br />

been considered as 35 years. The 455.72 GWH energy units are available<br />

at power house bus bars in 90% dependable year and cost per unit at power<br />

house bus bars works out to Rs. 2.89 per Kwh in the first year <strong>of</strong> operation.<br />

The levelised tariff rate <strong>of</strong> energy works out to be Rs.2.28 per Kwh.<br />

9. CONCLUSION<br />

The economy <strong>of</strong> the Himachal Pradesh is predominantly dependent on<br />

agricultural and allied sectors. The <strong>electric</strong> power being a vital and essential<br />

infrastructure has a significant role to play in economic upliftment <strong>of</strong> the<br />

state. The construction <strong>of</strong> <strong>project</strong> will provide employment to the local<br />

people. The <strong>project</strong> has a distinct advantage <strong>of</strong> being located along a<br />

motorable road making it possible to be completed within four and half<br />

years period.


INDEX<br />

SR.NO. DESCRIPTION PAGE<br />

CHAPTER-I SUMMARY I-1 TO I-6<br />

CHAPTER-II BACKGROUND INFORMATION II-1 TO II-2<br />

CHAPTER-III PROJECT AREA III-1 TO III-2<br />

CHAPTER-IV TOPOGRAPHIC AND GEOTECHNICAL<br />

ASPECTS<br />

IV-1 TO IV-7<br />

CHAPTER-V HYDROLOGY V-1 TO V-52<br />

CHAPTER-VI CONCEPTUAL LAYOUT & PLANNING VI-1 TO VI-35<br />

CHAPTER-VII POWER POTENTIAL STUDIES VII-1 TO VII-45<br />

CHAPTER-VIII POWER EVACUATION VIII-1 TO VIII-10<br />

CHAPTER-IX ENVIRONMENTAL ASPECTS IX-1 TO IX- 22<br />

CHAPTER-X INFRASTRUCTURE X-1 TO X-7<br />

CHAPTER-XI CONSTRUCTION PROGRAMME XI-1 TO XI-7<br />

CHAPTER-XII COST ESTIMATE XII-1 TO XII-34<br />

CHAPTER-XIII ECONOMIC EVALUATION XIII-1 TO XIII-14


PARA DESCRIPTION PAGE<br />

1.0 SUMMARY I-1<br />

1.1 GENERAL PROJECT FEATURES I-4<br />

1.2 STUDIES UNDERTAKEN I-4 TO I-5<br />

1.3 COST ESTIMATE & FINANCIAL ASPECTS I-5 TO I-6<br />

PLATE 1.1 ALTERNATIVE PROPOSAL


1.0 SUMMARY<br />

CHAPTER – I<br />

SUMMARY<br />

The Chhatru Hydro-<strong>electric</strong> Project has been contemplated as a power<br />

generation development on river Chandra in Lahul & Spiti District <strong>of</strong> H.P.<br />

It is an upstream development <strong>of</strong> Proposed Khoksar Hydro-<strong>electric</strong> Project<br />

(90MW) preliminary feasibility report <strong>of</strong> which has been submitted to CEA<br />

recently by HPSEB and is located about 410 km. from Chandigarh. The<br />

<strong>project</strong> envisages utilization <strong>of</strong> river Chandra water through a gross head <strong>of</strong><br />

177.33m for generation <strong>of</strong> 108MW <strong>of</strong> power in a power station.<br />

GENERAL PROJECT FEATURES<br />

LOCATION<br />

State Himachal Pradesh<br />

District Lahaul Spiti<br />

River Chandra river(Chenab Basin)<br />

Barrage site ± 5 km. u/s <strong>of</strong> Chhatru village<br />

<strong>Power</strong> house site ± 3.5 km d/s <strong>of</strong> Chhatru village on right<br />

bank <strong>of</strong> Chandra river


HYDROLOGY<br />

Catchment Area<br />

at diversion site 1583 Sq. km.<br />

Snow catchment 48 Sq. km. above El. 4200m<br />

Probable maximum flood 1500cumecs<br />

Standard <strong>project</strong> flood<br />

Observed maximum flood 828.00 cumsecs<br />

RESERVOIR<br />

Full reservoir (FRL) 3421.00m<br />

Maximum reservoir level (MRL) 3422.00m<br />

Maximum draw down level (MDDL) 3413.50m<br />

Gross storage upto FRL 112.50 Hect-m<br />

Live storage 87.50 Hect-m<br />

Net live storage 70.00 Hect-m<br />

DIVERSION STRUCTURE<br />

Type Barrage<br />

Max. height from R.B.L. 19m<br />

Elevation <strong>of</strong> top <strong>of</strong> dam or bridge ±3424.00m<br />

Average bed level ±3405.00m<br />

SPILLWAY<br />

Design flood 1500cumecs<br />

Type Gated spillways with radial gates<br />

Nos. <strong>of</strong> spillways, Crest elevation 6 Nos. El. 3407.00m<br />

Length <strong>of</strong> gated spillways 5.00m each.<br />

Energy dissipation<br />

Length 98.00m<br />

Down stream bed level ±3403.00m<br />

INTAKE STRUCTURE<br />

Type Surface<br />

Sill level El. 3410.00m<br />

No. & size <strong>of</strong> opening 8 Nos., 5.50mx3.0m<br />

APPROACH TUNNEL<br />

No. 1<br />

Size and type 6.00m dia, Circular concrete Lined<br />

Velocity 3.30m/sec<br />

Length 200m<br />

Design discharge from intake 93.75 cum/sec<br />

DESANDING BASIN<br />

Type Underground, central gutter type<br />

No. <strong>of</strong> basins 2 nos.


Length <strong>of</strong> each basin 381m<br />

Size <strong>of</strong> basins Width13.00m,Depth 19.60m<br />

Minimum particle size to be removed 0.2mm<br />

Flushing tunnel, size 4.00m, D-Shaped<br />

Flushing tunnel, length 1000m<br />

HEAD RACE TUNNEL<br />

No. 1<br />

Size & Shape 5.10m diameter, Modified<br />

Horse shoe shaped Concrete lined<br />

Length 6500 m<br />

Design discharge 75 cumecs<br />

Slope 1 in 120.50 m<br />

Velocity 3.63m/sec<br />

Adit 275m leangth 5m D- shaped<br />

SURGE SHAFT<br />

Type Underground, restricted orifice type<br />

Size 15m dia, 91.80m high<br />

Orifice 2.50m dia<br />

Maximum upsurge level El. 3436.10m<br />

Minimum down surge level El. 3396.60m<br />

Bottom level El. 3350.50m<br />

Top level El. 3436.00m<br />

Adit to top <strong>of</strong> surge shaft 4mx6m, D-Shaped<br />

2no. 75m each<br />

PRESSURE SHAFT<br />

Type Underground<br />

Size:<br />

Main 1 No., 4.70m dia,<br />

± 350m long<br />

Branches 3 Nos., 2.70m dia, ± 50m<br />

long each<br />

Velocity 4.32 m/sec.<br />

POWER HOUSE<br />

Type Underground<br />

Installed capacity 108 MW<br />

No. and capacity <strong>of</strong> unit 3 Nos. 36 MW<br />

Size <strong>of</strong> machine hall 67mx15m<br />

Service bay elevation EL 3250m<br />

Type <strong>of</strong> turbine Francis, Vertical axis


Speed <strong>of</strong> turbine 428.60 RPM<br />

Gross Head 177.33 m<br />

Normal tail water level El. 3240.00m<br />

Max. net operating head for<br />

design discharge 182.50m<br />

Minimum net operating head for<br />

design discharge 173.50m<br />

Net operating head for design<br />

discharge 160.00m<br />

Peaking duration 3.00 hrs.<br />

Maximum discharge during peaking hours 75 cumecs.<br />

Firm discharge in 90% dep. Year 11.18 cumecs<br />

TAIL RACE<br />

Size and shape 6.00 m diameter, D-Shaped<br />

concrete lined<br />

Length ± 1150 m<br />

SWITCHYARD<br />

Type underground<br />

TRANSMISSION LINE<br />

No. <strong>of</strong> circuits D/C Line<br />

Length <strong>of</strong> each 150Km<br />

Voltage 220.KV<br />

POWER GENERATION<br />

Installed capacity <strong>3x36</strong> MW<br />

Annual energy generation 455.72 MUs<br />

90% dep. Year<br />

1.2 STUDIES UNDERTAKEN<br />

The Layout <strong>of</strong> the Chhatru HEP has been finalized keeping in view various<br />

studies undertaken by HPSEB from time to time to conceive a most<br />

economical and viable scheme on Chandra river above the proposed<br />

Khoksar HEP.


Proposal-I<br />

The proposed Chhatru HEP envisages diversion <strong>of</strong> river Chandra about<br />

5km. u/s <strong>of</strong> Chhatru village in Lahaul & Spiti Distt. <strong>of</strong> Himachal Pradesh at<br />

El. 3405m by constructing a diversion Barrage comprising 6 nos. spill bayse<br />

bays each <strong>of</strong> size 5.00mx6.00m with crest El. at 3407m to pass the design<br />

flood <strong>of</strong> 1500 cumecs. The reservoir formed u/s <strong>of</strong> the barrage shall provide<br />

a peaking storage for 3 hrs. The diverted flows will be carried to<br />

underground desilting tank designed to exclude all silt particles down to<br />

0.20 mm size. The inflows will further be carried to surge tank 91.80 high,<br />

15m dia, through 5.10m modified house shoe shaped head race tunnel ±<br />

6.50 km. long . From surge tank, the flow will be carried to underground<br />

power house located on right bank <strong>of</strong> Chandra river through a 4.70m dia.<br />

Pressure shaft bifurcating near the power house to feed 3 nos. vertical axis<br />

generating units <strong>of</strong> 36 MW (108MW) installed capacity each, utilizing a<br />

design discharge <strong>of</strong> 75 cumecs and net head <strong>of</strong> 160 m. Further the water<br />

shall be discharge to Chandra river through underground tail race ± 1150m<br />

long and 6.00m dia D-shaped tunnel.<br />

Proposal-II<br />

About 600m d/s <strong>of</strong> the Proposal-I the diversion barrage has been proposed,<br />

where river terrace <strong>of</strong> about 200m width is available as proposed in GSI<br />

report. The proposal envisages the diversion at El. ± 3397m, to pass a<br />

design flood <strong>of</strong> 1500 cumecs. The diverted flow will be further carried to<br />

underground desilting tank, designed to exclude all silt particles down to<br />

0.20mm size. The inflow will further be carried to surge tank 91.80 high,<br />

15m dia, through 5.10m modified horse shoe shaped head race tunnel<br />

±6.00km. The flow will be carried to under ground power house to feed 3<br />

nos. generating units each <strong>of</strong> 33 MW (99MW) installed capacity each,<br />

utilizing a design discharge <strong>of</strong> 75 cumecs and net head <strong>of</strong> 151m. The HRT


after Chhatru nallah, surge shaft, pressure shaft, power house and tail race<br />

are the same <strong>of</strong> as Proposal-I.<br />

The proposal has been rejected on the fact that the installed capacity <strong>of</strong> the<br />

<strong>project</strong> has been reduced from 108 MW to 99 MW and there is always threat<br />

<strong>of</strong> Hamta glacier to damage the diversion structure <strong>of</strong> the <strong>project</strong>.<br />

The alternative proposals are shown in Plate-1.1.<br />

1.3 COST ESTIMATE & FINANCIAL ASPECTS<br />

COST ESTIMATE<br />

Capital cost <strong>of</strong> the <strong>project</strong> (At Price level Oct.2003):<br />

Civil works Rs. 386.79 Crore<br />

Electrical works<br />

(P-Production) Rs. 136.12Crore<br />

Cost <strong>of</strong> generation Rs. 522.91 Crore<br />

T-Transmission Rs. 8.45 Crore<br />

Total Rs 531.36 Crore<br />

Capital cost <strong>of</strong> Generation Rs. 585.15 Crore<br />

(Including IDC Rs. 62.24Crore)<br />

Loan 70% Rs. 409.60Crore<br />

Equity 30% Rs. 175.54Crore<br />

FINANCIAL ASPECTS<br />

Cost <strong>of</strong> generation per MW <strong>of</strong><br />

Installed capacity Rs. 4.84Crore<br />

Levelized tariff at PH<br />

Bus bars in 90% dep. Year<br />

Rs. 2.28/Kwh


Energy available in 90% dep. Year<br />

at power house bus bars<br />

455.72GWH


PARA DESCRIPTION PAGE<br />

2.0 BACK GROUND INFORMATION II-1<br />

2.1 GENERAL INFORMATION II-1<br />

2.2 POWER SCENARIOS & EXISTING<br />

INSTALLATIONS<br />

2.2.1 POWER ABSORPTION IN NORTH REGION II-1<br />

2.2.2 POWER LOAD DEVELOPMENT II-1 TO II-2<br />

2.3 NECESSITY OF THE PROJECTS AND<br />

RELATED ASPECTS<br />

PLATE 2.1 MASTER PLAN OF BEAS BASIN<br />

II-1<br />

II-2


CHAPTER – II<br />

BACKGROUND INFORMATION<br />

2.0 BACKGROUND INFORMTION<br />

2.1 GENERAL INFORMATION<br />

Hydel potential <strong>of</strong> Chenab basin in H.P. has been identified as 3155.30 MW<br />

as indicated in Plate –2.1 for this basin. The hydel <strong>project</strong>s under operation<br />

are Sisu (0.10 MW),Biling(0.20 Mw), Shansha(0.20 MW), Killar (0.30<br />

MW) and Thirot (4.50 MW) in this basin. The proposed <strong>project</strong>s as per<br />

CEA ranking study are Chhatru (108 MW), Khoksar (90 MW), Gondhala<br />

(144 Mw), Bardang(114 MW) and Sach-Khas (70 MW) in addition to<br />

Tunsha(150 MW), Rashil(150 MW), Palam(60 MW), Tingal(81 MW),<br />

Miyar(90 MW), Seli(600 MW), Dugli(360 MW), Sagpari(210 Mw) and<br />

Dugar (360 <strong>mw</strong>). The investigation <strong>of</strong> Gyspa (240 MW) is already under<br />

investigation.<br />

2.2 POWER SCENARIOS & EXISTING INSTALLATIONS<br />

2.2.1 POWER ABSORPTION IN NORTHERN REGION<br />

2.2.2 POWER LOAD DEVELOPMENT<br />

The Northern Region comprises the states <strong>of</strong> Himachal, Haryana, Punjab,<br />

Rajashtan, Jammu & Kashmir, Uttar Pradesh and Union territory <strong>of</strong> Delhi<br />

and Chandigarh. The Northern Regional <strong>Power</strong> Grid comprises the power<br />

system controlled by the Electricity Boards <strong>of</strong> above states/Union territories<br />

and Bhakhra Beas Management Board.<br />

The <strong>Power</strong> system in this region is now operating in an inter-connected and<br />

co-ordinated manner. Even in co-ordinated operation <strong>of</strong> existing <strong>hydro</strong>,<br />

nuclear and thermal power stations, including benefits from the ongoing


<strong>project</strong>s and as well from the new schemes cleared by CEA, the Northern<br />

region is expected to face severe power deficits in the 10 th Five Year Plan.<br />

2.3 NECESSITY OF THE PROJECT AND RELATED ASPECTS<br />

From the growth <strong>of</strong> peak demand and anticipated installed generation<br />

capacity on the basis <strong>of</strong> schemes proposed for benefits under<br />

construction/consideration during 9 th and early 10 th Five Year Plan period it<br />

is observed that power supply position in the Northern region would become<br />

all the more acute from the start <strong>of</strong> 10 th Five Year Plan and power region<br />

shortages would have to be faced unless additional schemes are taken up<br />

immediately and implemented to derive timely benefits. The most<br />

important source <strong>of</strong> power development in the Northern region is its<br />

abundant <strong>hydro</strong> resources located in Himachal Pradesh, Uttar Pradesh and<br />

Jammu & Kashmir. Priority would have to be given to the development <strong>of</strong><br />

these untapped resources because <strong>of</strong> the following distinguishing features <strong>of</strong><br />

the <strong>hydro</strong> stations.<br />

i) They estimate the most economic source <strong>of</strong> power development.<br />

ii) They provide the cheapest source <strong>of</strong> peaking capacity.<br />

iii) They enable improvement in the utilization <strong>of</strong> thermal/nuclear power<br />

stations in the region.<br />

iv) They provide much needed operation & flexibility to the system.<br />

Thus there is an urgent need <strong>of</strong> rapid <strong>hydro</strong> potential exploitation for<br />

providing additional generation capacity in the Northern region. Among the<br />

various sites, available for <strong>hydro</strong> development, Gharopa Hydro-<strong>electric</strong><br />

Project is considered very attractive from point <strong>of</strong> view <strong>of</strong> deriving benefits<br />

during 11 th Five Year Plan. The <strong>project</strong> is located on NH-21 and all the<br />

sites are well connected with NH-21. The existing communication facilities<br />

will be <strong>of</strong> considerable utility in cutting down the pre-construction time.


PARA DESCRIPTION PAGE<br />

3.0 PROJECT AREA III-1<br />

3.1 DESCRIPTION OF PROJECT INCLUDING<br />

RIVER SYSTEM<br />

III-1<br />

3.2 SOCIO ECONOMIC AND OTHER ASPECTS III-2


CHAPTER – III<br />

PROEJCT AREA<br />

3.0 PROJECT AREA<br />

3.1 DESCRIPTION OF PROJECT INCLUDING RIVER SYSTEM<br />

Himachal Pradesh has the unique distinction <strong>of</strong> providing water both to the<br />

Indus and Ganges basins. The major river systems <strong>of</strong> the region are<br />

Chander Bhaga or Chenab , the Ravi, the Satluj and the Yamuna. These<br />

perennial rivers are both snow and rain fed and are protected by fairly<br />

extensive cover <strong>of</strong> natural vegetation.<br />

River Chandra originates from the snow covered slopes <strong>of</strong> Great Himalayan<br />

<strong>of</strong> Pir Panjal ranges in Lahaul Spiti Distt. flows in a steep gradient. The<br />

river is formed by the two major tributaries namely Chandra & Bhaga.<br />

This <strong>project</strong> comprises a diversion barrage on river Chandra, ± 19m high<br />

above river bed level near village Chhatru, an intake arrangement on the<br />

right bank for drawing discharge <strong>of</strong> 93.75 cumecs through two approach<br />

tunnels leading to an underground desilting arrangement to exclude all silt<br />

particles down to 0.2mm, 5.10m dia, 6500m long modified horse show<br />

shaped tunnel designed for a discharge <strong>of</strong> ± 75 cumecs opening into one<br />

15m dia, underground restricted orifice type surge shaft, one pressure shaft<br />

<strong>of</strong> 4.70m dia 350m long bifurcating into three 2.70m dia, 50m long each<br />

branch pressure shafts, feeding three Francis vertical axis generating units <strong>of</strong><br />

36 MW each through a net head <strong>of</strong> 160m in an underground power house<br />

on the right bank <strong>of</strong> Chandra river. The <strong>project</strong> will enable energy<br />

generation <strong>of</strong> 455.72 GWH in 90% dependable year <strong>of</strong> flows.


3.2 SOCIO-ECONOMIC AND OTHER ASPECTS<br />

The economy <strong>of</strong> the Himachal Pradesh is predominantly dependent on<br />

agricultural and allied sectors. The per capital income <strong>of</strong> Himachal Pradesh<br />

in 1997-98 was Rs. 8747 as compared to Rs. 10400 at the national level.<br />

The <strong>electric</strong> power being a vital and essential infrastructure has a significant<br />

role to play in economic upliftment <strong>of</strong> the state. The construction <strong>of</strong> <strong>project</strong><br />

will provide employment to the local people. When completed it will be<br />

another step towards realization <strong>of</strong> the dreams <strong>of</strong> the state and exploiting its<br />

power potential for heralding an era <strong>of</strong> progress and prosperity for not only<br />

<strong>of</strong> Himachal Pradesh but for the entire northern region.


PARA DESCRIPTION PAGE<br />

4.0 GEOLOGY IV-1<br />

4.1 INTRODUCTION IV-1<br />

4.2 REGIONAL GEOLOGY IV-1 TO IV-3<br />

4.3 STRUCTURE & TECTONICS IV-4 TO IV-5<br />

4.4 SEISMO TECTONICS AND SEISMICITY IV-5 TO IV-6<br />

4.5 GEO-TECHNICAL APPPRAISAL IV-6 TO V-7<br />

4.6 REFERENCES IV-7<br />

PLATE- 4.1 GEOLOGICAL MAP


CHAPTER – IV<br />

TOPOGRAPHIC & GEO-TECHNICAL<br />

ASPECTS<br />

The geo-technical studies <strong>of</strong> <strong>project</strong> area have been got carried out from GSI<br />

during Jan. 2004 which is appended in below;<br />

4.0 GEOLOGY OF AREA AROUND CHHATRU HYDROELECTRIC<br />

PROJECT, CHENAB BASIN, LAHAUL AND SPITI DISTRICT,<br />

HIMACHAL PRADESH.<br />

4.1 INTRODUCTION<br />

The Central Electricity Authority in an effort to assess the balance<br />

<strong>hydro</strong><strong>electric</strong> potential in the country have identified 1,50,000 MW <strong>of</strong><br />

balance <strong>hydro</strong><strong>electric</strong> potential which can be harnessed through 399<br />

proposed schemes. After carrying out ranking studies, the CEA have<br />

selected a few schemes in Chandra valley <strong>of</strong> which Chhatru is one that is<br />

being taken up in the first phase for preparation <strong>of</strong> Pre Feasibility Reports.<br />

The proposed Chhatru Hydro<strong>electric</strong> Project is located on Chandra river,<br />

upstream <strong>of</strong> its confluence with Bhaga river and upstream <strong>of</strong> the village<br />

Chhatru in Lahaul and Spiti district <strong>of</strong> Himachal Pradesh.<br />

The proposed scheme is a run <strong>of</strong> river scheme that envisages construction <strong>of</strong><br />

a diversion dam/ weir across the river Chandra, 5 Km upstream <strong>of</strong> the<br />

village Chhatru (32 0 18’00” N: 77 0 28’ 00” E; 52 H/7), a water conductor<br />

system comprising 12 km long head race tunnel and a powerhouse on the<br />

right bank <strong>of</strong> Chandra River, about 3.5 km upstream <strong>of</strong> Chhatru bridge<br />

(32 0 19’00” N: 77 0 27’00” E; 52 H/7) with probable installed capacity <strong>of</strong> 140<br />

MW.<br />

4.2 REGIONAL GEOLOGY<br />

The area where <strong>project</strong> is located forms a part <strong>of</strong> Great Himalayan Range<br />

and constitutes both northern and southern slopes <strong>of</strong> Chandra Valley. The<br />

altitude in the area, varies between 2750m and 6020m. The terrain in upper<br />

reaches <strong>of</strong> tributaries shows typical glacial landscape characterized by<br />

rugged towering peaks, cirque glaciers and moraine deposits. Chandra river<br />

forms the main drainage <strong>of</strong> the area. It is joined by a number <strong>of</strong> tributaries<br />

on its either bank. These are mostly snow/ glacier fed. These tributaries


show sub-dendritic to trellis pattern. The higher reaches <strong>of</strong> slopes on either<br />

side <strong>of</strong> Chandra river have a number <strong>of</strong> glaciers which form the perennial<br />

source <strong>of</strong> discharge in tributaries. There are several conspicuous moraines<br />

that are well developed towards left bank. There are a number <strong>of</strong> water falls<br />

in the area <strong>of</strong> which the one at Sissu village and that about 4 km upstream <strong>of</strong><br />

Sissu Nala are prominent ones. The presence <strong>of</strong> abundant waterfalls in the<br />

area, besides glacier fed discharge is attributable to thick-bedded nature <strong>of</strong><br />

rocks and flat disposition <strong>of</strong> beds. Besides drainage, the lakes are a common<br />

feature in glacial terrain. The lower Chandra valley is characterized by the<br />

river terraces that are being used for habitation and cultivation by local<br />

inhabitants. Although three levels <strong>of</strong> terraces have been identified in Sissu<br />

area, only one prominent terrace has been identified in Chhatru and Khoksar<br />

areas. These terraces are very thick and extend up to 3225 m elevation in<br />

lower reaches i.e. near Sissu and Retil villages.<br />

The valley slopes in the area are characterised by the stretches <strong>of</strong> unusually<br />

abundant debris. These could have been due to the fractured or weathered<br />

rocks transported in abundance by snow, avalanches and landslides to the<br />

lower elevations on the banks <strong>of</strong> the river.<br />

The area around the proposed <strong>project</strong>s exposes the rocks belonging to<br />

Rohtang Group <strong>of</strong> Pre-Cambrian age (Prashara & Kumbkarni, 1986-87).<br />

But same has been named as Lahul Group by Prashra (1992). At higher<br />

elevations, it is succeeded by the rocks belonging to Haimanta Group in the<br />

east and those belonging to Vaikrita Group extending from Chandra area in<br />

west.<br />

The Pre-Cambrian stratigraphic succession in the area given by Prashra at El<br />

(1986-87) and Prashra (1992) is given below:-<br />

GROUP FORMATIO<br />

N<br />

Haimanta<br />

Kunzum La<br />

Batal<br />

Chola Thach<br />

LITHOLOGY AGE<br />

Greenish grey siltstone, shale &<br />

dolomite<br />

Quartzite, phyllite, carbonaceous and<br />

pyritous<br />

( It also includes Manjir and Katarigali<br />

Formations)<br />

Garnetiferous schist and quartzite<br />

Proterozoic


Lahaul or Rohtang<br />

Gneissic Group<br />

Gufa<br />

Damphung<br />

Kulti<br />

Granite gneiss, migmatite and meta<br />

sediments<br />

Matamorphites with subordinate gneiss<br />

and migmatite<br />

Granite gneiss, migmatites with high<br />

grade metamorphites<br />

According to Prashra (1992), the rocks <strong>of</strong> Lahaul Group are divisible into<br />

two lithological units i.e. Rohtang Gneissic Complex and Chola Thach<br />

Formation. While the Rohtang Geneissic Complex is predominantly made<br />

up <strong>of</strong> gneisses, granites and migmatites with subordinate metasediments, the<br />

latter represents primarily metasedimentary sequence. The Rohtang Gneissic<br />

Complex has further been subdivided into different formations namely<br />

Kulti, Damphung and Gufa.<br />

Kulti is the oldest Formation and is exposed between Khoksar and Chhota<br />

Dara in the valley <strong>of</strong> Chandra river, the area in which the <strong>project</strong> is located.<br />

It comprises mostly migmatite and granite gneisses which from about 80%<br />

<strong>of</strong> lithology. Schists and quartzites form intercalations within gneisses and<br />

migmatites. The individual gneiss bands are thin (0.25m to 1. 0m) and these<br />

attain thickness up to 5.0m between Kulti and Chhatru on left bank <strong>of</strong><br />

Chandra River. Quartzite is generally light grey, fine grained and micaceous<br />

and with increase in mica content it grades into mica- schist.<br />

The rocks belonging to Damphung Formation/ Member conformably overly<br />

the rocks <strong>of</strong> Kulti Formation. These are well exposed on both the slopes <strong>of</strong><br />

Chandra Valley upstream <strong>of</strong> Khoksar- Damphung area. These comprise<br />

mica schist, micaceous quartzite and quartz schist. This schist is commonly<br />

kyanite, staurolite, garnet and occasionally sillimanite bearing on the eastern<br />

slopes <strong>of</strong> Chhatru Nala. Grey to dark grey-banded quartzite appears at same<br />

stratigraphic level as <strong>of</strong> Damphung Formation indicating that these two are<br />

facies variant <strong>of</strong> each other. The rocks <strong>of</strong> Damphung Formation pass into<br />

those <strong>of</strong> Gufa Formation. Lithologically these resemble the rocks belonging<br />

to Kulti Member and comprises predominantly granitic and migmatitic<br />

gneisses besides subordinate schist and quartzite.<br />

The rocks belonging to Chola Thach Formation represent the sedimentary<br />

sequence in Lahaul or Rohtang Group and overlie the rocks <strong>of</strong> Gufa<br />

Formation with gradational contact. This Formation is exposed in low-lying<br />

stretches around Sissu and Teling areas. It consists <strong>of</strong> grey fine-grained<br />

quartzite, quartz schist and mica schist that are partly garnetiferous.<br />

Proterozoic


Haimanta Group <strong>of</strong> rocks has been divided into Batal and Kunzum- La<br />

Formations. In the southeastern part <strong>of</strong> the Lahaul i.e. in the valley <strong>of</strong><br />

Chenab or Chandra-Bhaga, the Batal Formation <strong>of</strong> this group is regarded to<br />

be represented by Manjir and Katarigali Formations <strong>of</strong> Vaikrita Group in<br />

Chamba area. Here Rapa & Gadhoke (1984) mapped two formations i.e.<br />

Bagotu and Dunai which were regarded equivalents <strong>of</strong> Manjir and Salooni<br />

Formations <strong>of</strong> Chamba area. Subsequently unfossiliferous part <strong>of</strong> Salooni<br />

Formation was renamed as Bharmour Formation and correlated it with<br />

Katarigali Formation <strong>of</strong> Jammu & Kashmir. These formations have not been<br />

defined in the rest <strong>of</strong> Lahaul area except that the pelites underlying the<br />

Tandi Group were correlated with Salooni and conglomerate exposed at<br />

Chobia and Trilokinath with Manjir Formation by Raina and Prashara<br />

(1973).<br />

Manjir Formation conformably overlies the Chamba Formation which is<br />

considered extension <strong>of</strong> the Batal Formation <strong>of</strong> Lahaul. It is characterized by<br />

diamictite, shale, slate and quartzite. The frame work <strong>of</strong> clasts is constituted<br />

<strong>of</strong> quartzite, vein quartz, phyllite, slate, limestone and granite. The clasts <strong>of</strong><br />

pelitic rocks show considerable stretching and diamictite facies at places<br />

change into grit and quartz wacke.<br />

The rocks belonging to Katarigali Formation conformably overlie those <strong>of</strong><br />

Manjir Formation. These are mainly composed <strong>of</strong> quartzite, slate & phyllite.<br />

The area encompassing the <strong>project</strong> exposes the rocks belonging to Katarigali<br />

Formation<br />

4.3 STRUCTURE AND TECTONICS<br />

Tectonically, the present area forms part <strong>of</strong> Central Axial Zone <strong>of</strong><br />

Himalayas. The structural elements <strong>of</strong> the area can be grouped in two i.e.<br />

non-diastrophic and diastrophic structures. The non-diastrophic structures<br />

include colour and compositional banding, current bedding in the quartzites<br />

<strong>of</strong> Manjir and Katarigali Formations etc. The diastrophic structures include<br />

schistosity, crenulation cleavage, fracture cleavage, joints etc. Schistosity is<br />

most penetrative planar structure in the area and has general NW-SE trend<br />

with shallow dips (10 o -25 o ). It is developed parallel to axial plane <strong>of</strong> first<br />

folds and is parallel to sub parallel to bedding. Crenulation cleavage has<br />

developed parallel to axial plane <strong>of</strong> second phase folds. It has folded<br />

bedding as well as schistosity. General trend <strong>of</strong> this structural plane is NW-<br />

SE with 15 o -30 o dips towards NE. Fracture cleavage is represented by<br />

fractures developed parallel to the axial plane <strong>of</strong> third phase folds. It’s trend<br />

varies from NNE-SSW to NNW-SSE and dips sub-vertically to vertically.<br />

Broadly there are three prominent sets <strong>of</strong> joints having NNE-SSW, E-W and<br />

NNW-SSE to N-S trends and have steep to very steep dips.


Three phases <strong>of</strong> folding are identifiable in the area. The folds belonging to<br />

first phase (F1) are rarely preserved. These are invariably tight in nature and<br />

have NW-SE trend in general. The mesoscopic folds belonging to second<br />

phase (F2) are most common folds in the area. These are open to tight and<br />

upright to recumbent. These are coaxial with folds <strong>of</strong> F1 phase and have<br />

NW-SE general trend with 5 o -10 o plunge towards NW. The third phase folds<br />

(F3) are represented by open warps. These are transverse to F1 and F2 folds<br />

and have a general low plunge towards N to NE. The rocks <strong>of</strong> this area are<br />

disposed in the form <strong>of</strong> a regional anticline, the axes <strong>of</strong> which coincides<br />

with the Chandra river. This anticline is represented by a broad upright warp<br />

with large crestal area. It shows 5 o -10 o plunge towards NW exposing the<br />

younger formations towards downstream.<br />

4.4 SEISMOTECTONICS AND SEISMICITY<br />

Seismotectonically, the area encompassing the proposed <strong>project</strong> is located in<br />

Central Himalayas on the western margin <strong>of</strong> Shimla Seismic Block <strong>of</strong><br />

Narula (1999). The Shimla Seismic Block is bound by Sunder Nagar Fault<br />

in west and Kaurik Fault in east. As per Seismotectonic Atlas <strong>of</strong> India and<br />

its environs (Narula et al., 2000), the litho tectonic packets <strong>of</strong> Himalayan<br />

Orogenic Belt in the region are poorly metamorphosed litho units <strong>of</strong><br />

Tethyan Unit, high and low grade assemblages <strong>of</strong> Central crystalline and<br />

Lesser Himalayan Belt along with granitoids and basic volcanics. The<br />

southern fringe <strong>of</strong> Himalayan belt is occupied by the cover rocks <strong>of</strong> frontal<br />

belt.<br />

Within Himalayan Belt, the northern most conspicuous structural element is<br />

the Main Himalayan Thrust (MCT). From Manali towards east up to eastern<br />

syntaxes through out the entire Himalayas, this is considered as most<br />

important tectonic surface. However, it is not clearly discernible northwest<br />

<strong>of</strong> Manali. Further south, within the lesser Himalayas, the most important<br />

tectonic surface is Vaikrita Thrust (VT). The Lesser Himalayan Belt is<br />

separated from the Frontal Belt by the Main Boundary Thrust (MBT).<br />

Further south, the southern limit <strong>of</strong> the Frontal Belt is marked by the Main<br />

Frontal Thrust (MFT) that has its surface manifestations at a few places only<br />

within MBT and MFT, the belt is traversed by several subsidiary thrusts that<br />

have considerable spatial extent.<br />

In addition to the structural discontinuities sub-parallel to regional trend,<br />

there are a number <strong>of</strong> faults and lineaments transverse to this fold-thrust<br />

belt. The Sunder Nagar Fault located in the <strong>project</strong> area is a dextral<br />

transverse structure that extends from Higher Himalayas to Frontal Belt.<br />

The Ropar Fault (Tear ?) is postulated to be continuation <strong>of</strong> Sunder Nagar<br />

Fault. Another fault similar to above has been identified in south east <strong>of</strong><br />

Chandigarh. All these transverse faults including Yamuna Tear located<br />

further southeast exhibit neo-tectonic activity.


A total <strong>of</strong> about 80 seismic events having magnitude >4.0 have been<br />

recorded in the Himalayan Belt in the area. Out <strong>of</strong> these 17 events had<br />

magnitude >5 and were mostly confined to the depths less than 40 km. The<br />

events having magnitude >4 and >5 are predominant in the area. Seismic<br />

activity is concentrated mainly in the Himalayan Belt, particularly in NW<br />

sector around Chamba- Kangra in adjoining Kangra Seismic Block. Out <strong>of</strong><br />

the 17 events having magnitude >5, 14 events are located in this zone. In<br />

this region <strong>of</strong> Himalayas, 4 events having magnitude >6 were recorded and<br />

three out <strong>of</strong> these including the Great Kangra earthquake <strong>of</strong> 1905 are located<br />

along MBT and one event on the surface trace <strong>of</strong> Sunder Nagar Fault. Six<br />

earthquakes from the area have caused considerable damage and these<br />

include Kangra Earthquake <strong>of</strong> 4 th April 1905 (Ms=8.0); Chamba<br />

Earthquake <strong>of</strong> 22 nd June, 1945 (Ms=6.5.); Dharamshala earthquake <strong>of</strong> 14 th<br />

June, 1978 and 26th April, 1986 and Chamba Earthquake <strong>of</strong> 24 th March,<br />

1995 . Keeping in view the seismic status and seismotectonic setup in view,<br />

the area has been kept on the margins <strong>of</strong> Zones V and IV as per Map <strong>of</strong><br />

India showing Seismic Zones (IS: 1893 (Part-I):2002). Therefore it is<br />

suggested that suitable seismic coefficient be specifically evolved for the<br />

area and incorporated in the design <strong>of</strong> the appurtenant structures <strong>of</strong> the<br />

<strong>project</strong>s.<br />

4.5 GEOTECHNICAL APPRAISAL<br />

The site was visited on 24.8.2003 along with Shri A.K. Gupta, Director<br />

Planning, HPSEB, Sundernagar and other HPSEB <strong>of</strong>ficers. The proposed<br />

Chhatru Hydro<strong>electric</strong> Project is located in the upper reaches <strong>of</strong> Chandra<br />

Valley where both terrain and climate are hostile. The valley flanks are<br />

dotted with recent and sub-recent avalanches which have accumulated as<br />

talus cones which go upto 100 m above river bed at places. The proposed<br />

dam site is located about 5 km upstream <strong>of</strong> Chhatru. The river Chenab<br />

flows towards west. The area exposes granitic gneiss belonging to Rohtang<br />

Gneissic Group. The rocks are folded into an anticline and river flows along<br />

this anticlinal axis. The river bed is about 100 m wide. The talus cones<br />

extend on abutments upto about 100 m above river bed. This site does not<br />

appear to be suitable for dam as bed rock is expected to be deep both in the<br />

river bed and on the abutments. The abutments are covered with boulders<br />

upto 5 m in size. It is suggested that temporary diversion structure founded<br />

on permeable strata be considered here. Similarly, the site for locating<br />

intake structure for HRT in bed rock is not available at least up to 2 km on<br />

both sides from the site <strong>of</strong> diversion structure. Therefore the tunnel<br />

alignment in the initial reaches has to be explored for delineating the bed<br />

rock so that proper intake structure is constructed. Upto the point where<br />

adequate rock cover is available over the tunnel the same will have to be<br />

designed as structural tunnel with false portal. The desilting arrangement<br />

has to be designed underground due to topographic and climatic constraints.


About 600 m downstream <strong>of</strong> the proposed site, the ridge between two<br />

hanging glaciers can be utilized for temporary diversion structure. The<br />

diversion structure could be located in the ridge upstream <strong>of</strong> Hamta Glacier.<br />

However, the behavior <strong>of</strong> glacier has to be investigated at this site. About<br />

200 m wide terrace is available for transferring discharge to right abutment<br />

where bed rock is exposed right from terrace. The intake structure can be<br />

located in bed rock. The 8 km long HRT will encounter granitic gneiss.<br />

These are foliated and jointed. The foliation trends NW-SE and dips about<br />

25 o -30 o towards NE. The HRT will be crossing Chhatru Nala. It is<br />

suggested that HRT be aligned in such a way that adequate rock cover is<br />

available over the structure. The possibility <strong>of</strong> locating an intermediate<br />

construction adit in Chhatru Nala may be looked into.<br />

The proposed powerhouse with 100 MW installed capacity is located on<br />

right bank <strong>of</strong> Chenab about 2.5 km downstream <strong>of</strong> Chhatru Bridge. The<br />

proposed site is located between two nalas which have debris cones at their<br />

mouth. The site has thin debris fans comprising boulders up to about 50 m<br />

above riverbed. Above it, the granite gneiss is exposed on steep slope upto<br />

200 m above riverbed. The rock is jointed. The site is suitable for an<br />

underground powerhouse. There is also possibility <strong>of</strong> locating the<br />

switchyard on left bank <strong>of</strong> the river on a terrace where sufficient space is<br />

available. Otherwise the same may be kept underground.<br />

4.6 REFRENCES<br />

Narula, P.L., (1991) Seismotectonic evaluation <strong>of</strong> NW Himalaya, Rec. Geo.<br />

Surv. Ind., 127(8), 14949.<br />

Narula, P.L., Acharayya, S.K. and Banerjee, J. (2000) Seismotectonic Atlas<br />

<strong>of</strong> India and its environs. Pub. Geol. Surv. Ind.<br />

Prashara, K.C., Des Raj and Kumbkarni, S. (1986- 87). Geology <strong>of</strong> Parts <strong>of</strong><br />

Chandra Valley, Lahaul and Spiti district, Himachal Pradesh, Unpubl. G S I<br />

Report for F S: 1986-87<br />

Prashara, K.C. (1992) Final Report on Geology <strong>of</strong> Lahaul and Spiti District,<br />

Himachal Pradesh., Unpublished GSI Compilation<br />

Raina, V. K. and Prashara, K. C., (1973). Geological Mapping in Parts <strong>of</strong><br />

Pangi Valley, Chamba and Lahaul Spiti districts, Himachal Pradesh,<br />

Unpublished GSI Report for F. S. 1971- 72 .<br />

Rapa, D.A. and Gadhoke, S.K. (1983). Geology <strong>of</strong> Parts <strong>of</strong> Chamba district,<br />

Himachal Pradesh, Unpub. GSI Report for F.S. 1982- 83


PARA DESCRIPTION PAGE<br />

5.1 RIVER CHANNEL AND CATCHMENT<br />

CHARACTERISTICS<br />

5.1.1 HYDROMETEOROLOGY OF THE CATCHMENT V-1<br />

5.2 DISCHARGE DATA AND WATER AVAILABILITY V-2<br />

5.2.1 CO-RELATION STUDY V-2 TO V-3<br />

5.3 DESIGN FLOOD V-3 TO V-4<br />

5.4 SEDIMENTATION ASPECTS V-4<br />

TABLE-5.1 TEN DAILY AVERAGE DISCHARGE DATA OF<br />

RIVER CHANDRA AT GHOUSAS FROM JUNE 1973<br />

TO MAY 2000<br />

TABLE-5.2 TEN DAILY AVERAGE DISCHARGE DATA<br />

DIVERSION SITE<br />

TABLE-5.3 INFLOW OF RIVER CHANDRA AT GHOUSAL &<br />

INFLOW OF RIVER BHAGA AT TANDI<br />

TABLE-V-5.3(1)<br />

TO 5.3(6)<br />

REGRESSION ANALYSIS BETWEEN DISCHARGES<br />

OF TANDI & GHOUSAL<br />

TABLE- 5.4 INFLOWS OF RIVER CHANDRA AT UDAIPUR &<br />

INFLOWS OF RIVER BHAGA AT TANDI PLUS<br />

RIVER CHANDRA AT GHOUSAL<br />

TABLE- 5.4(1)<br />

TO 5.4 (6)<br />

REGRESSION ANALYSIS BETWEEN DISCHARGES<br />

OF TANDI PLUS GHOUSAL AND UDAIPUR<br />

V-1<br />

V-5- TO V-9<br />

V-10 TO V-14<br />

V-15<br />

V-16<br />

V-17 TO V-22<br />

V-23<br />

V-24<br />

PLATE –5.1 FLOW DURATION CURVE (OVER ALL) V-31<br />

PLATE-5.2 FLOW DURATION CURVE (LEAN PERIOD) V-32<br />

V-25 TO V-30<br />

ANNEXURE-V-1 ESTIMATE OF DESIGN FLOOD V-33 TO V-45<br />

ANNEXURE-V-2 COMMENTS RAISED BY CEA/CWC ON<br />

HYDROLOGY<br />

ANNEXURE-V-3 REPLY TO THE COMMENTS ON HYDROLOGY V-52<br />

V-46 TO V-51


CHAPTER – V<br />

HYDROLOGY<br />

5.1 RIVER CHENAB AND CATCHMENT CHARACTERISTICS.<br />

The river orginates from the snow covered slopes <strong>of</strong> Great Himalayan <strong>of</strong><br />

Pir-Panjal ranges in Lahaul Spiti district and flows in a steep gradient with a<br />

series <strong>of</strong> loopes and bends. The river is formed by the two major tributaries<br />

in the head reaches namely Chandra and Bhaga.The river Chandra originates<br />

from Bara Lachala and is further augmented by Chandra Tal. The river<br />

Bhaga takes <strong>of</strong>f from Suraj Tal in the vicinity <strong>of</strong> Bara Lachala and is further<br />

joined by Jhankar and Millang nallahs in the head reaches. The catchments<br />

<strong>of</strong> these two major tributaries have snow covered peaks at height ranging<br />

from ± 3500 m to 5500 m elevation. The Chandra river and Bhaga river<br />

joins at Tandi to form Chandra-Bhaga i.e. the Chenab. Further downstream<br />

<strong>of</strong> confluence, it is joined by other significant tributaries namely Shansha<br />

nallah near Rashil, Thirot nallah at Thirot, Miyar nallah at Udaipur, Saichu<br />

nallah at Dawag, Mahal Nallah at Killar & Dheda nallah at Lujai d/s <strong>of</strong><br />

Killar. Chenab river drains a catchments <strong>of</strong> about 7500 Sq. Km. before it<br />

crosses in to J&K border.<br />

5.1.1 HYDROMETEOROLOGY OF THE CATCHMENT<br />

This region is a low rainfall area as most <strong>of</strong> the precipitation in the region is<br />

in the form <strong>of</strong> snow. The rainfall takes place during the monsoon months<br />

only and the catchment experiences snowfall during the remaining period <strong>of</strong><br />

the year. There is only one rain gauge station in this region, installed at<br />

Keylong and the rainfall data has not been recorded regularly even at this<br />

station. It is observed that the most <strong>of</strong> the run<strong>of</strong>f in the river results from the<br />

melting <strong>of</strong> snow.


5.2 DISCHARGE DATA AND WATER AVAILABILITY<br />

The discharge data <strong>of</strong> river Chandra at diversion site <strong>of</strong> Chhatru HEP has<br />

been derived from June 1973-May 2000 from the discharge data <strong>of</strong> river<br />

Chandra at Ghousal (site monitored by CWC).<br />

Discharge data <strong>of</strong> river Chandra at Ghousal is given in table 5.1 while the<br />

computed discharge data reduced on catchment area basis at diversion site is<br />

given in Table– 5.2<br />

Based upon ten daily discharge data, a flow duration curve has been<br />

developed. From this curve, it is seen that flow corresponding to 90% &<br />

50% availability works out to 10.41 cumecs & 26.30 cumecs respectively.<br />

The design discharge <strong>of</strong> 75 cumecs is available for 32.15 % <strong>of</strong> the period.<br />

Flow duration curve for lean-season (Dec. to Feb.) has also been developed .<br />

From this curve , it is seen that flow corresponding to 90% & 50%<br />

availability works out to 6.96 cumecs & 12.95 cumecs respectively.<br />

5.2.1 CO-RELATION STUDY<br />

W.B. Langbein’s log deviation method has been used to obtain the coefficient<br />

<strong>of</strong> co-relation between discharges <strong>of</strong> river Chandra at Ghousal and<br />

discharges <strong>of</strong> river Bhaga at Tandi.<br />

The Co-relation factors are as follows:<br />

June-July = 0.92<br />

Aug.-Sept. = 0.96


Oct.-May = 0.96<br />

These calculations have been shown in Table- 5.3<br />

Similarly coefficient <strong>of</strong> co-relation has been obtained between discharges<br />

<strong>of</strong> river Chenab at Udaipur and the sum <strong>of</strong> discharges <strong>of</strong> river Chandra at<br />

Ghousal & river Bhaga at Tandi.<br />

June-July = 0.94<br />

Aug.-Sept. = 0.96<br />

Oct.-May = 0.88<br />

These calculations have been shown in Table-5.4<br />

From the above co-relation factors it is evident that the discharges <strong>of</strong> river<br />

Chandra at Ghousal & river Bhaga at Tandi including river Chenab at<br />

Udaipur are consistent. Thus the discharges <strong>of</strong> river Chandra at Ghousal<br />

have been approved by CWC and used for carrying out studies which stands<br />

submitted to the CWC and comments are awaited.<br />

5.3 DESIGN FLOOD<br />

The <strong>project</strong> falls in Western Himalayas Zone seven in map <strong>of</strong> India. The<br />

total catchment area <strong>of</strong> river Chenab in India is about 31,047 Sq. Kms. The<br />

catchment is mostly fed by snow. The majority percentage <strong>of</strong> the run<strong>of</strong>f in<br />

the catchment is derived from the snow & glaciers which constitutes a<br />

potential reservoir. Winter precipitation which occurs in the form <strong>of</strong> snow<br />

goes on accumulating till summer. As the summer advances, the<br />

accumulated snow melts and releases water into the stream.


Design Flood has been computed on the basis <strong>of</strong> Flood Estimation report for<br />

Western Himalayas-zone 7 & accordingly <strong>hydro</strong>graphs have been prepared.<br />

The max.. flow due to rain contribution comes out to be 291.59 cumecs<br />

which has return period <strong>of</strong> 1 in 50 years. The maximum flow for return<br />

period <strong>of</strong> 1 in 100 years is 321.38 cumecs. The snow contribution has been<br />

taken to be 342.09 cumecs ie the maximum discharge <strong>of</strong> flow during 2 nd<br />

week <strong>of</strong> July in flow series at diversion site. Thus the total design flood<br />

works out to be 663.47 cumecs. Flood frequency analysis has also been<br />

carried out by Gumble’s method.<br />

Return period <strong>of</strong> 1 in 1000 years has been considered for computing the<br />

SPF which works out to be 1377.59 cumecs. The designed flood has been<br />

taken as 1500 cumecs. The computations have been shown in Annexure-V-<br />

1.<br />

5.4 SEDIMENTATION ASPECTS<br />

Detailed studies shall be carried out at DPR stage. However 20% <strong>of</strong> the live<br />

storage has been proposed to be kept reserved for silt deposition in the<br />

reservoir.


Annexure-V-3<br />

Reply to the comments raised by Director Hydrology, CWC, New Delhi on <strong>hydro</strong>logy<br />

vide letter no. 1/HP/26/2004/CWC/131 dated 19.04.04, further intimated by Dy.<br />

Director, HPI, CEA vide letter No. 7/91/HPSEB/2004/HPI/877/dated 21.04.04.<br />

Design flood<br />

1. The water way and free board in barrage have been designed as per design flood <strong>of</strong><br />

1500 cumecs workout by flood frequency analysis for 1000 years return period,<br />

which is already on higher side. However, the same shall be revised at DPR stage<br />

after the finalization <strong>of</strong> design flood as suggested.<br />

2. As suggested efforts to collect data <strong>of</strong> annual instantaneous flood peak series at<br />

Ghousal G&D site from CWC Jammu are being made. The results as per best fit<br />

distribution shall be carried out at DPR stage.<br />

3. SPE values from IMD and instantaneous peaks at Ghousal have not been received<br />

so far, as such study will be carried out as DPR stage.<br />

4. As agreed the design flood shall be reviewed at DPR stage.<br />

5. Recommendations:-<br />

i) The new gauge discharge observation may be opened before the preparation<br />

<strong>of</strong> DPR .<br />

ii) Few SRRG, ORG, station, weather stations may be established in the<br />

<strong>project</strong> area to collect more information regarding precipitation and snow<br />

melt contribution.<br />

iii) The above mentioned suggestions shall be taken care <strong>of</strong> the immediately<br />

after the availability <strong>of</strong> funds for investigation in near future.


PARA DESCRIPTION PAGE<br />

6.0 CONCEPTUAL LAYOUT OF PROJECT<br />

COMPONENTS<br />

VI-1<br />

6.1 FINALIZATION OF CONCEPTUAL LAYOUT VI-1<br />

6.2 PRELIMINARY DESIGN FEATURES VI-2<br />

6.2.1 BARRAGE VI-2<br />

6.2.1.1 GENERAL VI-2<br />

6.2.1.2 RESERVOIR VI-2<br />

6.2.1.3 BARRAGE BAYS VI-3<br />

6.2.1.4 ENERGY DISSIPATION VI-3<br />

6.2.2 RIVER DIVERSION WORKS VI-3 TO VI-4<br />

6.2.2.1 INTAKE STRUCTURE VI-4<br />

6.2.3 DESANDING ARRANGEMENT VI-4 TO VI-5<br />

6.2.4 HEAD RACE TUNNEL VI-5<br />

6.2.4.1 GENERAL VI-5<br />

6.2.4.2 CROSS SECTION VI-6<br />

6.2.5 SURGE SHAFT VI-6<br />

6.2.5.1 GENERAL VI-6<br />

6.2.5.2 HYDRAULIC PARAMETERS VI-6<br />

6.2.5.3 CONCRETE LINING VI- 7<br />

6.2.6 PRESSURE SHAFT VI-7<br />

6.2.6.1 GENERAL VI-7<br />

6.2.6.2 ECONOMIC DIAMETER VI- 8<br />

6.2.7 POWER HOUSE VI-8<br />

6.2.7.1 GENERAL VI-8<br />

6.2.7.2. TYPE VI- 9


6.2.7.3 MACHINE HALL VI-9 TO VI-<br />

10<br />

6.2.7.4 TRANSFORMER HALL VI-10<br />

6.2.8 AUXILIARY SURGE SHAFT AND TAIL RACE<br />

TUNNEL<br />

VI-10<br />

6.3 PRELIMINARY DRAWINGS VI-11<br />

6.4 DESIGN COMPUTATIONS VI-12 TO VI-<br />

33<br />

DRAWINGS<br />

CHHATRU-<br />

FR-1<br />

CHHATRU-<br />

FR-2<br />

CHHATRU-<br />

FR-3<br />

CHHATRU-<br />

FR-4<br />

CHHATRU-<br />

FR-5<br />

CHHATRU-<br />

FR-6<br />

CHHATRU-<br />

FR-7<br />

CHHATRU-<br />

FR-8<br />

CHHATRU-<br />

FR-9<br />

CHHATRU-<br />

PLATE-6.1<br />

VICINITY MAP 1 SHEET<br />

MASTER PLAN OF CHENAB BASIN (CEA<br />

SCHEMES)<br />

1 SHEET<br />

CATCHMENT AREA PLAN 1 SHEET<br />

GENERAL LAYOUT PLAN 1 SHEET<br />

DIVERSION BARRAGE, INTAKE,& DESANDING<br />

BASIN<br />

HEAD RACE TUNNEL, SURGE SHAFT & PRESSURE<br />

SHAFT<br />

POWER HOUSE AND TRANSFORMER HALL PLAN,<br />

L- SECTION AND SINGLE LINE DIAGRAME<br />

2 SHEETS<br />

1 SHEET<br />

3 SHEETS<br />

CONSTRUCTION FACILITIES 1 SHEET<br />

CONSTRUCTION PROGRAME 1 SHEET<br />

AREA CAPACITY CURVE 1 SHEET


CHAPTER – VI<br />

CONCEPTUAL LAYOUT<br />

AND PLANNING


CHAPTER – VI<br />

CONCEPTUAL LAYOUT<br />

AND PLANNING<br />

6.0 CONCEPTUAL LAYOUT OF PROJECT COMPONENTS<br />

6.1 FINALIZATION OF CONCEPTUAL LAYOUT<br />

The proposed Civil Engineering Structures have been planned and designed<br />

to divert and conduct 75 cumecs <strong>of</strong> water, from river Chhatru for generating<br />

108MW <strong>of</strong> power in an underground power house by utilizing a gross head<br />

<strong>of</strong> 177.33m. The main works <strong>of</strong> the <strong>project</strong> comprise a diversion barrage,<br />

intake, underground desanding basins for removing all particles down to<br />

0.20mm size, 6500m long head race tunnel, a restricted orifice type surge<br />

shaft and an underground power house to accommodate 3 vertical axis,<br />

Francis turbines driven generating units each <strong>of</strong> 36 MW. After diversion, all<br />

the civil engineering components have been kept underground keeping in<br />

view the topography <strong>of</strong> the area. Comments on the draft PFR <strong>of</strong> the <strong>project</strong><br />

issued by Director, HCD (NW&S) <strong>of</strong> CWC vide no. CWC<br />

U.O.NO.22/1/03/HCD(NW&S) dated have been<br />

incorporated. A brief geological site specific feasibility note titled “Geotechnical<br />

appraisal” founded on preliminary site inspection about each<br />

component is appended as Para 4.5 in chapter-IV titled “Geographic & Geotechnical<br />

Aspects”.


6.2 PRELIMINARY DESIGN FEATURES<br />

6.2.1 BARRAGE<br />

6.2.1.1 GENERAL<br />

The slope <strong>of</strong> river at the diversion site u/s <strong>of</strong> Chhatru village is <strong>of</strong> the order<br />

<strong>of</strong> 1:23. Peak annual flood <strong>of</strong> river Chandra at diversion site has been<br />

adopted as 1500 cumecs for design <strong>of</strong> spillways/barrage bays. Barrage 185m<br />

long including abutments with crest level <strong>of</strong> barrage bays at El. 3407m &<br />

non over flow section has been proposed to pass the estimated design flood<br />

at FRL El. 3421.00m. The proposed barrage comprises 6 bays <strong>of</strong> 5.00m<br />

each with 3.00m thick piers and is capable <strong>of</strong> passing the estimated design<br />

flood even when one bay is considered inoperative during period <strong>of</strong> high<br />

floods. The max. pond level/ FRL (El. 3421.00m) attained during winter<br />

months shall also cater to peaking requirement . During high flood max.<br />

water level to be attained has been proposed as 3422.00m. Radial gates in<br />

the barrage bays shall be provided from top <strong>of</strong> crest El. 3407m to the bottom<br />

<strong>of</strong> RCC breast wall El. 3413.00m spanning between the piers. The breast<br />

wall is supported on the piers and is provided between El. 3413.00m and El.<br />

3424.00m.<br />

6.2.1.2 RESERVOIR<br />

The full reservoir level (FRL) is fixed at El. 3421.00. The minimum draw<br />

down level (MDDL) has been fixed at El. 3413.50m. The reservoir so<br />

formed has a gross storage capacity <strong>of</strong> 112.50 ha-m at FRL and 25.00 ha-m<br />

at MDDL. Available diurnal storage <strong>of</strong> 70.00 ha-m ( 87.50 -20% reserved<br />

for silt deposits) is sufficient for running the power station as a peaking<br />

station at full installed capacity for 3.00 hrs. The discharge availability in<br />

lean period(Nov. to Feb) in 90% dep. year is 11.18 cumecs. The reservoir<br />

spreads over an area <strong>of</strong> 16.00 hectares and is about 1.00 km long. The area


capacity curve for the reservoir has been drawn from the available contour<br />

plan <strong>of</strong> the area on 1:2500 scale and is shown in Plate No. 6.1<br />

6.2.1.3 BARRAGE BAYS<br />

6 barrage bays 5.00m wide each have been provided to pass the design flood<br />

discharge i.e. 1500 cumecs. Total floor <strong>of</strong> 136m length has been proposed<br />

comprising u/s floor, sloping glacis u/s & d/s (4:1) and d/s floor <strong>of</strong> 50m<br />

including end still. A 4 m deep cut <strong>of</strong>f extending up to 3401m at u/s side <strong>of</strong><br />

the floor and 5.00m deep cut <strong>of</strong>f at the end <strong>of</strong> d/s floor extending up to El.<br />

3390m have been provided to protect the u/s and d/s floor from scour/<br />

piping action. Cement concrete blocks extending 10m each beyond u/s and<br />

D/s floors have been provided. Protection to cement concrete blocks have<br />

been provided with stone filled wire crates extending 10m beyond u/s & d/s<br />

floors. Consolidation grouting has not been proposed in the river bed,<br />

keeping in view the fact that rock is not available upto reasonable depth in<br />

the river bed.<br />

6.2.1.4 ENERGY DISSIPATION<br />

Dissipation <strong>of</strong> energy is proposed to be done by providing a horizontal<br />

stilling basin depressed below the river bed level (El. 3395m) with solid end<br />

sill to facilitate formation <strong>of</strong> hydraulic jump. Layout & details <strong>of</strong> barrage<br />

have been shown in drawing No. CHHATRU-FR-5.<br />

6.2.2 RIVER DIVERSION WORKS<br />

The river diversion works have been designed for a discharge <strong>of</strong> 600<br />

cumecs. The construction <strong>of</strong> diversion works i.e. half <strong>of</strong> barrage, intake<br />

structure from inlet have been proposed to be taken up by making Ist Stage<br />

c<strong>of</strong>fer dam <strong>of</strong> length 300m allowing flow <strong>of</strong> water along the left bank <strong>of</strong><br />

river. After the completion <strong>of</strong> diversion barrage upto El. 3407m & <strong>Power</strong>


intake upto El. 3410m the Ist stage c<strong>of</strong>fer dam shall be removed and water<br />

shall be diverted on right bank <strong>of</strong> river through barrage constructed, by<br />

making 2 nd stage c<strong>of</strong>fer dam. Thereafter, the construction <strong>of</strong> remaining half<br />

<strong>of</strong> the barrage shall be completed. The construction <strong>of</strong> diversion works has<br />

been proposed to be completed within three months period. Construction <strong>of</strong><br />

c<strong>of</strong>fer dam is proposed to be modified as per site conditions after each<br />

monsoon season.. The provision for construction <strong>of</strong> c<strong>of</strong>fer dam has been<br />

made accordingly, adding 50% quantum <strong>of</strong> work being involved due to<br />

repetition <strong>of</strong> job after each season in the cost estimate <strong>of</strong> the <strong>project</strong>. The<br />

provision <strong>of</strong> plain cement concrete <strong>of</strong> grade M-10 has been made on the top<br />

and side slopes <strong>of</strong> c<strong>of</strong>fer dam to prevent the seepage <strong>of</strong> water towards<br />

working area.<br />

6.2.2.1 INTAKE STRUCTURE<br />

The intake structure comprising single intake with eight no. openings,has<br />

been proposed on the right bank <strong>of</strong> river, to handle a discharge <strong>of</strong> 93.75<br />

cumecs. A semi circular trash rack structure with reinforced concrete<br />

columns has been proposed for intake. Crest elevation <strong>of</strong> intake is proposed<br />

as 3410m. Stop logs has been proposed for controlling flow through intake<br />

bays 8 nos.(5.50mx3m) each during repairs. A suitable transition is<br />

provided to convert the rectangular opening into a 6.00m dia circular<br />

approach tunnel. Approach tunnel is 200m long and shall lead the water into<br />

two desanding basins. Details are shown in drawing No. CHHATRU-FR-5.<br />

6.2.3 DESANDING ARRANGEMENT<br />

An underground desanding arrangement to exclude all silt particles down to<br />

0.20mm has been proposed ±100m d/s <strong>of</strong> barrage on the right bank <strong>of</strong> river<br />

Beas. A lateral rock cover more than 1.5xexcavated width has been ensured<br />

for locating chamber No. 1. Rock cover <strong>of</strong> the order <strong>of</strong> twice the width <strong>of</strong>


excavated cavity <strong>of</strong> the chamber has been ensured in between the two<br />

chambers. Stop logs will be provided at the inlet and outlet <strong>of</strong> all the<br />

chambers to facilitate closing <strong>of</strong> any chamber for maintenance/repairs, while<br />

the others will enable continuous operation <strong>of</strong> the power station. Layout<br />

and details <strong>of</strong> desilting arrangement are given in drawing No. CHHATRU-<br />

FR-5.<br />

6.2.4 HEAD RACE TUNNEL<br />

6.2.4.1 GENERAL<br />

The head race tunnel 5.10m dia, 6500m modified horse shoe type has been<br />

proposed to carry a design discharge <strong>of</strong> 75 cumecs from the junction point<br />

<strong>of</strong> feeder tunnels <strong>of</strong> desilting chamber with HRT to the surge shaft. The<br />

tunnel is located along right bank <strong>of</strong> river Chandra. Layout <strong>of</strong> the tunnel has<br />

been fixed keeping in view the topography <strong>of</strong> the area and location <strong>of</strong><br />

construction adit from Chhatru nallah for completing the tunnel excavation<br />

work on schedule. Adequate rock cover has been ensured in entire reach <strong>of</strong><br />

the tunnel. The invert level <strong>of</strong> tunnel at RD-0 is at El. 3402.50m and at<br />

outlet end at El. 3348.45m resulting in a slope <strong>of</strong> 1 in 120.<br />

Three adits each 5m D-shaped at inlet, outlet and at intermediate location<br />

(RD 3500m) have been provided to facilitate construction <strong>of</strong> HRT from four<br />

faces. The inlet and outlet adits are so provided that they shall separate the<br />

construction activity <strong>of</strong> the head race tunnel from that <strong>of</strong> desilting chambers<br />

and surge shaft. The layout <strong>of</strong> the tunnel and other details are indicated in<br />

Drawing. No. CHHATRU-FR-6.


6.2.4.2 CROSS SECTION<br />

Based on geological, hydraulic, structural and functional considerations,<br />

modified horse shoe shaped cross section, 5.10m dia has been adopted. The<br />

tunnel is proposed to be lined with concrete M:20.<br />

6.2.5 SURGE SHAFT<br />

6.2.5.1 GENERAL<br />

The underground restricted orifice type surge shaft <strong>of</strong> 15m dia and 91.80m<br />

height has been proposed at the outlet end <strong>of</strong> Head race tunnel at RD 6500.<br />

Top level <strong>of</strong> surge shaft is proposed at El. 3448.00m. Two adits each 6m Dshaped,<br />

one approaching the top at El. 3438.00m and other at the bottom at<br />

El. 3348.00m have been proposed. The bottom adit will also be utilized to<br />

facilitate excavation <strong>of</strong> surge shaft and horizontal portions <strong>of</strong> pressure shaft.<br />

After execution <strong>of</strong> the <strong>project</strong> this adit will be plugged near junction <strong>of</strong><br />

pressure shaft and rest <strong>of</strong> it will be used as a drainage gallery. General<br />

layout and details <strong>of</strong> surge shaft are shown in drawing No. Gharopa-FR-6.<br />

6.2.5.2 HYDRAULIC PARAMETERS<br />

Surge shaft area has been worked out by using Thomas’s criteria for<br />

incipient stability with factor <strong>of</strong> safety as 1.6m conforming to IS:7396 (Part-<br />

I) 1979. Maximum upsurge and minimum down surge levels have been<br />

computed by computer analysis as per above mentioned IS code. Maximum<br />

upsurge level works out to be 3436.00m and minimum down surge level as<br />

3996.60m. For calculating maximum upsurge and minimum down surge<br />

levels the friction co-efficient have been taken as 0.012 and 0.016<br />

respectively.


6.2.5.2 CONCRETE LINING<br />

It is proposed to provide reinforced concrete lining for surge shaft. Lateral<br />

cover around surge shaft at all heights has been kept more than three times<br />

the excavated diameter <strong>of</strong> the surge shaft. It is assumed that upsurge being<br />

<strong>of</strong> very short duration will not cause any saturation in the surrounding rock<br />

mass.<br />

6.2.6 PRESSURE SHAFT<br />

6.2.6.1 GENERAL<br />

A 4.70m dia pressure shaft with centre line at El. 3351.00m will take <strong>of</strong>f<br />

from surge shaft for leading the water in to turbines. In the initial 75m<br />

horizontal reach, a valve gallery has been proposed to accommodate<br />

butterfly valve.The inclined length <strong>of</strong> main pressure shaft is 340m. Three<br />

nos. branch pressure shaft <strong>of</strong> 2.70m dia totalling 50m in length ,takes <strong>of</strong>f<br />

from the main pressure shaft to feed three units in the power house. The<br />

entire length <strong>of</strong> the pressure shaft will be steel lined. An adit at an elevation<br />

±3348.00m to valve gallery has been provided to facilitate excavation <strong>of</strong><br />

the top horizontal reach and some inclined portion from the top and will also<br />

be utilized as drainage gallery to relieve external pressure. The excavation<br />

<strong>of</strong> remaining inclined portion will be carried out from power house cavity.<br />

The space between liner and excavated rock will be back filled with M-20<br />

conc. Adequate contact grouting will be done at contact points <strong>of</strong> concrete<br />

with liner and rock. Consolidation grouting has also been proposed in the<br />

reach, where the pressure shaft will pass through poor rock. Details <strong>of</strong><br />

pressure shaft are shown in Drawing No. CHHATRU-FR-6.


6.2.6.2 ECONOMIC DIAMETER<br />

Economical dia <strong>of</strong> the pressure shaft has been worked out by cost<br />

optimization studies for various diameters. Accordingly, a diameter <strong>of</strong><br />

4.70m has been adopted to carry the design discharge <strong>of</strong> 75 cumecs with<br />

velocity <strong>of</strong> flow as 4.32m/sec. The diameters <strong>of</strong> branches has been kept as<br />

2.70m.<br />

6.2.7 POWER HOUSE<br />

6.2.7.1 GENERAL<br />

The proposed underground power house is located about 3.50km. d/s <strong>of</strong><br />

Chhatru village on right bank <strong>of</strong> Chandra river. This site has been<br />

considered suitable for underground power house as per geo-technical<br />

appraisal note received from GSI (Ref. Chapter-IV). The tail race tunnel<br />

from power house will discharge in to river Chandra. The erection bay and<br />

transformer hall floor levels, are proposed at El. 3250m. The approach to<br />

power house and transformer hall cavern is through 7m D-shaped main<br />

excess tunnel. The machine hall and transformer hall are proposed in<br />

underground parallel cavities at suitable spacing. The control room is<br />

proposed in power house cavity while the SF6 switchgear is proposed in<br />

transformer hall cavity. A cable cum ventilation gallery/tunnel is proposed,<br />

which will initially be used for carrying out excavation and providing<br />

support system in the crown portion <strong>of</strong> power house and transformers hall<br />

cavities. Vertical and lateral cover each <strong>of</strong> ±200m approx. respectively has<br />

been provided in machine cavity and transformer hall cavity. The safety <strong>of</strong><br />

power house complex from flooding, from tail water end during<br />

construction stage will be adequately ensured.


6.2.7.2 TYPE<br />

Reconnaissance surveys for location <strong>of</strong> underground or surface power house<br />

were undertaken during the site visit <strong>of</strong> <strong>project</strong> area by HPSEB engineers<br />

and GSI authority during Jan. 2004. Surface power house has been ruled<br />

out due to the reason that the power house area remains under snow cover<br />

for maximum period in the year.<br />

Keeping in view the above fact, an underground power house with<br />

underground transformer hall has been proposed on right bank <strong>of</strong> Chandra<br />

river. Also the GIS unnderground 220 KV Switchyard has been proposed<br />

keeping in view the terrain and reliability <strong>of</strong> the system.<br />

6.2.7.3 MACHINE HALL<br />

The internal dimensions <strong>of</strong> power house cavity has been proposed as length<br />

67m and width 15m. The unit bay will be 36m long at 11.50m spacing<br />

while the erection bay and control bay have been proposed 15m and 15m<br />

long respectively . For support system in crown portion <strong>of</strong> cavity 6m long<br />

mechanically anchored , tensioned and grouted rock bolts 1.50m spacing,<br />

staggered has been proposed. 100mm thick shotcreting reinforced with<br />

welded mesh has been proposed in crown portion and sides <strong>of</strong> cavity. The<br />

spacing <strong>of</strong> rock bolts in sides has been kept at 2m c/c staggered. The<br />

columns in unit bay and erection bay have been kept 1.60m x 0.80m. For<br />

columns a nich in the side measuring 0.80mx0.80m has been proposed<br />

which will be supported by grouted anchors 25mm dia at 1m spacing. All<br />

rock bolts will be tensioned to 12 tonnes immediately after installation and<br />

pull out tests will be carried out on 2% rock bolts.<br />

The control bay is proposed on opposite side <strong>of</strong> erection bay in the end <strong>of</strong><br />

power house. Cavern for housing control room and various<br />

auxiliaries/<strong>of</strong>fices, 5 nos. floor have been proposed at El. 3248m, El.


3250m, El. 3254m, El. 3257.50m and El. 3260.50m respectively. The main<br />

inlet valve is proposed to be housed in power house cavity just u/s <strong>of</strong><br />

turbine. EOT crane <strong>of</strong> 125/25 tonnes capacity has been proposed in erection<br />

bay and unit bay to facilitate erection and repair <strong>of</strong> heavy equipment<br />

including main inlet valves.<br />

6.2.7.4 TRANSFORMER HALL<br />

The size <strong>of</strong> transformer hall cavity has been proposed as 60m long, 15m<br />

wide. The clear spacing between these two cavities has been kept at 30m.<br />

In addition to main generator transformers, space for spare transformers and<br />

station transformer has also been provided in the cavern. The transformer<br />

hall cavern will be connected to erection bay by 5mx7m D-shaped gallery<br />

for carriage <strong>of</strong> transformers at erection stage and for repairs. NG rail track<br />

is proposed between transformer hall and erection bay for transportation <strong>of</strong><br />

transformers. The transformer hall will be connected by 3 nos. bus duct<br />

galleries 3m D-shaped.<br />

The detail <strong>of</strong> power house has been shown in Drg. No. Chhatru-PF-7.<br />

6.2.8 AUXILLIARY SURGE SHAFT AND TAIL RACE TUNNEL<br />

The outflow from the end <strong>of</strong> draft tube will be taken through 3 nos. separate<br />

branch tail race tunnels. Vertical lift gates have been proposed in these<br />

branch tail race tunnels to prevent entry <strong>of</strong> silt etc. into draft tube and for<br />

facilitating repair in turbines. Downstream <strong>of</strong> this, all the branch tail race<br />

tunnels will be joined to one main tail race tunnel 6m D shaped .<br />

Auxiliary surge shaft has been proposed at the beginning <strong>of</strong> main tail race<br />

tunnel, which is ±1150m long. Broad crested weir has been proposed at its<br />

outfall.


6.3 PRELIMINARY DRAWINGS<br />

Drg. No.Chhatru-FR-1 Vicinity map 1 Sheet<br />

Drg. No.Chhatru-FR-2 Master Plan <strong>of</strong> Chenab basin(CEA schemes) 1 Shhet<br />

Drg. No.Chhatru-FR-3 Catchment Area Plan 1 Sheet<br />

Drg. No.Chhatru-FR-4 General Layout Plan 1 Sheet<br />

Drg. No.Chhatru-FR-5 Diversion Barrage, Intake, Desanding basin 2 Sheets<br />

Drg. No.Chhatru-FR-6 Head race tunnel, Surge shaft & Pressure shaft 1 Sheet<br />

Drg. No.Chhatru-FR-7 <strong>Power</strong> House & Transformer Hall 3 Sheets<br />

Drg. No.Chhatru-FR-8 Construction Facilities 1 Sheet<br />

Drg. No.Chhatru-FR-9 Construction Programme 1 Sheet<br />

Plate-6.1 Area Capacity Curve 1 Sheet


6.4 DESIGN COMPUTATIONS<br />

A. Diversion Barrage ( REF. DRG. NO. CHHATRU-FR-5)<br />

i) Design Parameters<br />

Design flood discharge = 1500 cum/sec.<br />

Average bed level <strong>of</strong> the river = ± 3405m<br />

Safe exit gradient <strong>of</strong> Nallah material (assumed) = 1 in 4<br />

The water bays <strong>of</strong> the barrage has been so proposed that design flood<br />

discharge i.e. 1500 cum/sec passes through all the bays <strong>of</strong> barrage.<br />

However, stilling basin has been designed corresponding to max. observed<br />

discharge in Chenab river i.e. 928 cumecs Say 1000 cumecs.<br />

Hence design flood discharge for stilling basin = 1000 cumecs<br />

ii) Fixation <strong>of</strong> crest level and water bay<br />

Average bed level <strong>of</strong> river = ± 3405m<br />

The crest level <strong>of</strong> barrage bays has been kept 2m higher than the average<br />

bed level at El. ±3407m . Six No. bays each 5.00m wide with 3m thick pier<br />

has been provided. The total water bay <strong>of</strong> overflow portion works out to be<br />

48.00m[(6x5)+(3.00x6)] . Two meter wide fish ladder Originating from<br />

reservoir, left bank at M.D.D.L. El. ± 3413.50m joining river bed d/s has<br />

been provided.<br />

iii) Storage capacity<br />

The live storage available in barrage reservoir between M.D.D.L. El.<br />

3413.50m and F.R.L. El. 3421m is 87.50 Hect. m. (Ref. area capacity<br />

curve). This storage capacity will run the power station at full installed<br />

capacity for 3 hrs. a day.<br />

CHECKING OF LEVELS AND CALCULATIONS FOR SIZE OF<br />

GATES<br />

Design discharge for power generation = 75 cumecs<br />

Total discharge i/c flushing discharge @ 20% = 75/(1-0.20)<br />

=75/80 = 93.75 cumecs<br />

Fixing crest level <strong>of</strong> intake = ± 3410m


a) F.R.L. Condition<br />

M.D.D.L. = ± 3413.50m<br />

F.R.L. = ± 3421.00 m<br />

Providing one no. power intake, having 8 no. bays each <strong>of</strong> size<br />

= 5.50 m(b)x3m(h)<br />

Intake crest behaves as a rectangular large orifice<br />

H1<br />

H2<br />

Discharge Passed<br />

= 11.00m<br />

= 750m<br />

Q1 = 2/3xCdxLx√ 2g (H1 3/2 -H2 3/2 )<br />

= 2/3x0.61x44√2x9.81 (11.00 3/2 –7.50 3/2 )<br />

= 316.47 cumecs >93.75 cumecs<br />

Hence O.K.


) M.D.D.L CONDITION<br />

H1 = 3.50m<br />

H2 = 0.50m<br />

Q = 2/3xCdxLx√2g (H1 3/2 -H2 3/2 )<br />

= 2/3x0.61x44x√2x9.81 (3.50 3/2 -0.50 3/2 )<br />

= 2/3x0.61x44x4.43x619 =491.00 cumecs > 93.75 cumecs<br />

Hence O.K.<br />

CHECK FOR VELOCITY THROUGH TRASH RACK<br />

Aligning trash rack at 75°<br />

Design discharge through intake/trash rack = 93.75 cumecs<br />

F.R.L. Condition<br />

Length <strong>of</strong> trash rack = xm<br />

19.50/x = Sin75°<br />

x = 19.50/Sin75° = 12.42m<br />

Area = 12.42x44 = 546.62 Sqm.<br />

Less 25% area for trash rack bars = 546.62-546.62x0.25= 409.96 Sqm.<br />

Considering 50% clogging <strong>of</strong> trash rack bars<br />

Net area available during floods = 409.96/2 = 204.98 Sqm.


Velocity through trash rack = 93.75/204.98 0.46m/sec.<br />

M.D.D.L. condition<br />

Length <strong>of</strong> trash rack = 3.50/x = Sin75°<br />

x = 3.50/Sin75<br />

x = 3.62 m<br />

Area available = 3.62x44 = 159.28 Sqm.<br />

Less 25% area <strong>of</strong> rack bars<br />

Net area = 159.28-159.28x0.25 =119.46 Sqm.<br />

Considering 50% area <strong>of</strong> trash rack bars<br />

Net area = 119.46-119.46x0.50 = 59.73 Sqm.<br />

Velocity through trash rack = 93.75/59.73 = 1.50m/sec.<br />

Hence size <strong>of</strong> intake provided and levels fixed are O.K.<br />

Gated barrage is to be provided<br />

Parameters will be as under;<br />

R.B.L. = 3405m<br />

Crest level = 3407m<br />

<strong>of</strong> barrage bays (fixed)<br />

M.D.D.L. = 3413.50m<br />

F.R.L. = 3421m<br />

M.R.L. = 3422m<br />

Top <strong>of</strong> barrage = 3424m<br />

Height <strong>of</strong> structure = 3424-3405 =19m<br />

Design flood = 1500 cum/sec.<br />

Size <strong>of</strong> gate = 8mx8.50m<br />

No. <strong>of</strong> gate = 3 No.<br />

Storage available between El. MDDL 3413.50m and F.R.L. 3421m


Live storage = 112.50-25.00 = 87.50m<br />

Less 20% for sedimentation<br />

Net = 87.50-17.50 = 70 hect .m.<br />

Time in hr = 70x10 4 /(75-10.41)x3600 = 3.01 hours<br />

For Base Load Station<br />

90% available discharge = 10.41 cumecs<br />

Design discharge = 51 cumecs<br />

<strong>Power</strong> = 9.81x51x150x0.92/1000 = 69 MW<br />

Hydraulic design <strong>of</strong> free flowing/ungated structure<br />

Design discharge for power generation = 75 cumecs<br />

Modified discharge including 20% flushing<br />

Discharge in desanding basin = 75/(1-0.20)= 93.75 cum<br />

If it is the head over intake crest to pass 93.75 cumecs discharge<br />

Q = CLH 3/2<br />

93.75 = 1.70x44xH 3/2<br />

H 3/2 = 93.75/1.70x44<br />

H = 1.16m<br />

R.B.L. = 3405m<br />

Crest level <strong>of</strong> over flow bay = 3407m<br />

Crest level <strong>of</strong> intake crest = 3410m<br />

Head over crest to pass 93.75 cumecs discharge = 1.16m<br />

Say 1.20m<br />

Water level = 3410+1.20 = 3411.20m<br />

Hence if ungated barrage is to be provided the level <strong>of</strong><br />

Ungated crest will have to be kept as 3411.20m<br />

Height <strong>of</strong> structure =3411.20-3405 = 6.20m<br />

Live storage (Between El. 3410& 3411.20m)= 12.50-6.25 = 6.25 hacm.<br />

Time in hours = 6.25x10 4 /(75-10.41)x3600 = 0.27 hrs.<br />

If height <strong>of</strong> structure is kept upto El. 3415m<br />

Height <strong>of</strong> structure = 3415-3405 = 10m<br />

Live storage (Between El. 3410 & El. 3415) = 36.89-6.25= 30.64 hacm.


Time in hrs = 30.64x10 4 /(75-100.41)x3600 = 1.31 hrs.<br />

Time to filling up <strong>of</strong> this storage = 8 months.<br />

CALCULATIONS FOR SIZE OF GATES IN BARRAGE BAYS<br />

As per I.S. recommendations, 10% gates are considered to be inoperative during<br />

floods(with min. one gate)<br />

R.B.L. = 3405m<br />

Crest level = 3407m<br />

M.D.D.L. = 3413.50m<br />

F.R.L. = 3421.00m<br />

M.R.L. = 3422.00m<br />

No. <strong>of</strong> barrage bays = 6 nos.<br />

Width <strong>of</strong> each barrage bay =5m<br />

Providing radial gate from El. 3407m to El. 3411.00m & breast wall<br />

Thereafter upto El. 3424m<br />

Size <strong>of</strong> gate = 5mx6m<br />

Discharge through breast wall spillway is estimated by the equation<br />

Q = Cb.L.D. [2g(He+Vo 2 /2g] 0.50<br />

Where L = Total width <strong>of</strong> water bays available<br />

= 5x6 =30m<br />

D = Height <strong>of</strong> opening = 6.00m<br />

He = Head from C/L <strong>of</strong> spillway<br />

He =[(3413.00-3407)/2]+[3421-3413.50]<br />

= 3.00+7.50 =10.50m<br />

Vo = Vel. <strong>of</strong> approach <strong>of</strong> flood water<br />

= 1500/185x 10.50 = 0.77m/sec.


Vel. head = Vo 2 /2g = 0.77 2 /2x9.81 = 0.03<br />

For calculating discharge co-efficient<br />

Head H = 3421-307 = 14.00m<br />

Considering that design head may be exceeded by 25%<br />

H/Hd = 1.25<br />

Design head Hd = H/1.25 = 14/1.25 = 11.20m<br />

Choosing Hd = 11.50m<br />

H/Hd = 1.4/11.50 = 1.22<br />

Corresponding value <strong>of</strong> Cb = 0.809<br />

When all the bays are open<br />

Discharge passed =Q = Cb.L.D. [2g(He+Vo 2 /2g) ] 0.50<br />

When one barrage bay is inoperative<br />

Q = 0.809x30x6.00 [2x9.81(10.50+0.03) ] 0.50<br />

= 2093.07 cumecs<br />

Q = Cb.L.D. [2g(He+Vo 2 /2g) ] 0.50<br />

= 0.809x24x6.00 [2x9.81(10.50+0.03) ] 0.50<br />

= 1674.45 cumecs<br />

HYDRAULIC DESIGN OF STILLING BASIN<br />

Fixation <strong>of</strong> pre-jump velocity and depth <strong>of</strong> flow<br />

The theoretical velocity at the start <strong>of</strong> the jump is calculated by the following relation:<br />

VT = √ 2g (H-0.50 Hd)<br />

Where VT = Theoretical velocity in m/sec.<br />

H = Difference in u/s reservoir<br />

El. and stilling basin invert in meters<br />

H = 3422-3395 = 27m<br />

H = Head over crest <strong>of</strong> barrage bays in meters


= 3422-3407 = 15m<br />

g = Acceleration due to gravity in m/sec = 9.81 m/sec.<br />

VT = √ 2x9.81 (27.00-0.50x15.00)<br />

VT = 19.55m/sec.<br />

Due to surface friction, the actual velocity is less than VT<br />

Considering VA= VT = 19.55m/sec<br />

Discharge equation<br />

Q = A1xV1<br />

Where<br />

1000 = A1x19.55 VA=V1 20.53m/sec.<br />

A1 = 1000/19.55 = 51.15 Sqm. Q = Design flood discharge <strong>of</strong><br />

Stilling basin =1000 cum<br />

L.D1 = 51.15<br />

45.00xD1 = 51.15 ∴ D1 = 51.15/45.00 =1.14m<br />

Froude No. (F) = V1/√ gd1 = 19.55/√9.81x1.14m<br />

= 5.85<br />

For Froude no. 5.85>4.50, U.S.B.R. type-III stilling basin is recommended.<br />

D2 = Depth Conjugate to D1<br />

D2 = D1/2+√2q 2 /D1g +D1 2 /4<br />

Here<br />

q = 1000/45.00 =22.22 cum/sec<br />

D2 = -1.14/2+√2x22.22 2 /1.14x9.81+1.14 2 /4<br />

= -0.57+9.41 = 8.84m<br />

Length <strong>of</strong> basin = 5xD2 = 5x8.84<br />

= 44.21m Say 50m<br />

The floor <strong>of</strong> the basin is set at such a level at to provide 5% more water depth than<br />

Y2<br />

Hence depth <strong>of</strong> basin = 8.89x1.05 = 9.28m


Cistern level = 3405-9.28 = 3395.72m<br />

Hence provided cistern level = 3395m is O.K.<br />

SIZE OF APPROACH TUNNEL<br />

Design discharge Q = 75/0.80 = 93.75 cum/sec.<br />

No. <strong>of</strong> main tunnels = 1 no.<br />

Discharge through each tunnel = 93.75 cum/sec.<br />

Vel. in the tunnel = 3.30m/sec<br />

Dia <strong>of</strong> tunnel = √(93.75/3.30)/4/Π = 6m<br />

After bifurcation<br />

Q through each tunnel = 46.87<br />

V = 3.30 cum/sec.<br />

Dia <strong>of</strong> each tunnel √ 46.87x4/3.30xΠ = 4.25m<br />

After Desilting<br />

Total design discharge, Q = 75 cum/sec.<br />

No. <strong>of</strong> tunnels = 2 nos.<br />

Discharge through each tunnel = 75/2 =37.50 cum/sec<br />

Dia = 4.00m<br />

² =<br />

V = 37.50/Π/4(4.00)<br />

2.98m/sec.<br />

DESIGN OF APPROACH TUNNEL & INTAKE STRUCTURE<br />

A. APPROACH TUNNELS ( Ref. Drawing No. Chhatru-FR-5 sheet 2 <strong>of</strong> 2)<br />

Design discharge to be drawn i/c flushing discharge = 93.75 cum/sec.<br />

No. <strong>of</strong> tunnels = 1 nos.<br />

Discharge through each tunnel = 93.75 cum/sec.


Provide size <strong>of</strong> tunnel = 6m, circular concrete lined<br />

Area <strong>of</strong> each tunnel = Π/4(d²) = Π/4(6)² = 28.27 Sqm.<br />

Vel. through each tunnel = 93.75/28.27 = 3.31 m/sec.<br />

Length <strong>of</strong> tunnel = 200m<br />

B. INTAKE STRUCTURE<br />

Considering bell mouth intake with bottom flat<br />

Width <strong>of</strong> opening = 1.42857 D D = Size <strong>of</strong> conduit i.e. tunnel<br />

= 28.57x6.00 = 8.57m<br />

Height <strong>of</strong> opening<br />

h = h1+h2<br />

h1 [(1.21 tan 2 φ +0.0847) 1/2 +1/2 cosφ -1.1 tanφ )]D<br />

Where φ is the angle <strong>of</strong> inclination with Horizontal = 0°<br />

h1 = [(1.21 tan 2 0+0.0847) 1/2 +(1/2cos 0-1.1 tan0 )] xD<br />

= [(0+0.0847)1/2 + ½]x6<br />

= (0.291+0.50) 6 = 4.75m<br />

h2 = [0.791/ +0.077 tan0]xD<br />

= (0.791+0) x 6 = 4.75m<br />

h = h1+h2 =4.75+4.75 = 9.50m<br />

Provide clear opening for intake = 8.60x9.50m<br />

The opening is rectangular and depress it to circular from starting <strong>of</strong> intake face to<br />

a distance <strong>of</strong> 1.1 D = 1.1x6 = 6.60m<br />

Here<br />

a = 6.60m<br />

b = 3.50m


Hence size <strong>of</strong> bell mouth entrance 8.60m(b)x9.50m(d) from 6m circular section<br />

Min. water cushion provided above the opening <strong>of</strong> intake<br />

= 0.3 he = 0.3x9.50 = 2.85m<br />

El. at top <strong>of</strong> intake = 3413.50-2.85 = 3410.65m<br />

C/L <strong>of</strong> intake = 3410.65-4.75/2 = 3405.90m<br />

C/L <strong>of</strong> approach tunnel = 3405.90m<br />

Hence invert level <strong>of</strong> approach tunnel at RD 0 =3405.90-6/2<br />

=3402.90m<br />

And C/L <strong>of</strong> approach tunnel at inlet = 3405.90m<br />

Invert level as invert = 3402.90m<br />

At inlet <strong>of</strong> desanding basin<br />

Invert level = 3402.50m<br />

Overt level = 3402.50+4.25m<br />

= 3406.75m<br />

HYDRAULIC DESIGN OF DESANDING BASIN (Underground )<br />

(Ref. Drawing No. Chhatru-FR-5 sheet 2 <strong>of</strong> 2)<br />

Design criteria = All particles down to 0.20mm shall be removed<br />

Parameters<br />

Design discharge for power generation = 75 cumecs<br />

Design discharge i/c 20% for deflushing in desanding basin=75/0.80 = 93.75 cumecs<br />

HYDRAULIC DESIGN<br />

Particle size to be removed = 0.020mm and above<br />

Permissible flow through vel. as per camp’s formula<br />

V = 44√d for 1mm>d>0.10mm<br />

V = 44√0.020 = 19.67 cm/sec


Provide v = 19.50 cm/sec<br />

Effective area <strong>of</strong> flow = 93.75/0.1950 = 480.76 Sqm.<br />

Provide 2 No. chambers in the desanding basin<br />

Width <strong>of</strong> each basin = 13.00m<br />

Total width = 13x2 = 26m<br />

Effective area <strong>of</strong> flow <strong>of</strong> each chamber = 480.76/2<br />

= 240.38 Sqm.<br />

CHECK FOR CROSS SECTIONAL AREA<br />

Arch Portion<br />

r = (C²+4h²)/8h = (13²+4x3.50²)/8x3.50 = 7.78m<br />

Sin α/2 = C/2/2 = 6.50/7.78 = 0.835<br />

α/2 = 56.66° α = 113.33°<br />

Length <strong>of</strong> arch =Π/180xαxr<br />

L =Π/180x113.33x7.78<br />

= 15.38m<br />

A Area <strong>of</strong> Arch Portion<br />

A1<br />

A1<br />

= ½[r.L-C(r-h)]<br />

= ½[(7.78x15.38)-13(7.78-3.50)]<br />

= ½(119.65-55.64)<br />

= 32 Sqm.


A2 = Area <strong>of</strong> rectangular Portion<br />

= 13x16.10 = 209.30Sqm.<br />

Total area = A1 + A2 =32+209.30 =241.30 Sqm.>240.38 Sqm.<br />

Hence O.K.<br />

0.20mx0.20m openings are proposed to be provided at the bottom <strong>of</strong> each<br />

pit 10m<br />

c/c to carry the silt to gallery 1.50x1.80m rectangular shaped, from where silted<br />

water will be flushed back to Beas river.<br />

Settling vel. = 2.35cm/sec corresponding to 0.20mm particle<br />

size<br />

Vel. correction W 1 = 0.132xv/√h = 0.132x0.195/√19.60<br />

W 1 = 0.00581<br />

Corrected settling vel. = W-W 1 = 0.02350-0.00581 = 0.017685<br />

Length <strong>of</strong> desanding basin<br />

L = hxV/W-W 1 = 19.60x0.195/0.017685<br />

L = 216.11m Provide L = 381m<br />

Hence size <strong>of</strong> each chamber = 381m(L)x13m(b)x19.60m(h)<br />

No. <strong>of</strong> chambers = 2 nos.<br />

CHECK FOR THE SIZE<br />

Settling time t is given by<br />

t = h/W-W 1 = 19.60/0.017685 = 1108.28 sec.<br />

Water conveyed during this period<br />

Qxt = Discharge per chamber x settling time<br />

= (93.75/2) x 1108.28 = 51950.80 cum<br />

Capacity <strong>of</strong> one chamber = 241.30x381= 91935 cum>51950.80<br />

cum<br />

Hence O.K.<br />

Removal efficiency <strong>of</strong> particle size <strong>of</strong> 0.20mm<br />

ηt = 1-(e) –WxL/vxh<br />

= 1-e –2.35x381/19.50x19.60 = 1-0.0960<br />

= 90.40%<br />

Design <strong>of</strong> transitions


Inlet transition length<br />

= B-b/2tan 12.5º = 13-4.25/2tan 12.5º<br />

= 19.73m Say 20.00m<br />

Outlet transition length<br />

= 13-4.25/2tan 12.5º = 19.73m Say 20.00m<br />

HEAD RACE TUNNEL(REF. DRAWING NO. CHHATRU-FR-6)<br />

Parameters<br />

Design discharge = 75 cumecs<br />

Shape <strong>of</strong> the tunnel (adopted) = Modified horse shoe shaped<br />

Length <strong>of</strong> head race tunnel = 6500m<br />

M.D.D.L. = 3413.50m<br />

Min. down surge level<br />

(as per computer analysis) = 3396.96m<br />

Co-efficient <strong>of</strong> friction = 0.014<br />

HYDRAULIC DESIGN<br />

Calculation for economic diameter<br />

The most economical dia <strong>of</strong> tunnel would be such as to result in a minimum total<br />

value <strong>of</strong> the sum <strong>of</strong> the following.<br />

a) Recurring annual expenditure<br />

According to Manning formula’s<br />

V = 1/nx R 2/3 S 1/2<br />

Where<br />

V = Average vel.<br />

X = Rugosity co-efficient = 0.014<br />

R = Hydraulic mean radius = 0.506287 r<br />

D = Diameter S = Slope


Now<br />

V = 1/n R 2/3 S 1/2 = 1/n (D/4) 2/3 S 1/2<br />

S = 6.40 V²n²/D 1.33 -(i)<br />

In this equation S gives value <strong>of</strong> head loss in meter or hydraulic gradient<br />

If η is the overall efficiency <strong>of</strong> generation<br />

Then<br />

<strong>Power</strong> lost Pe = 9./80xQxSxη KW -(ii)<br />

Where<br />

Q = VxΠ/4 (D²)<br />

Or V = 1.275Q/D² -(iii)<br />

From equation (i) & (iii) we got<br />

S = 6.40n²/D 5.33 x[1.275Q/D²]² - (iv)<br />

Substituting the value <strong>of</strong> S in (ii) we get<br />

revenue lost per year<br />

Pe = 9.80Q [6.40n²/D 5.33 (1.275Q/D²)²]x η KW (A)<br />

Pe = 101.96 Q 3 / D1.33 xn²xη KW<br />

Revenue lost per year<br />

Re = Pex24x365x C0 (B)<br />

From equation A&B<br />

Re = [ 101.96 Q 3 /D5.33xn²xη]x24x365xC0<br />

Re = 8.95x10 5 x Qª/D 5.33 xn 2 xηxC0<br />

Re = 8.95x10 5 x Qª/D 5.33 xηxn 2 xC0<br />

C0 = Selling rate <strong>of</strong> power per unit = Rs. 2.50<br />

η = Overall efficiency = 0.92<br />

Q = Equivalent discharge =Design discharge x Load factor<br />

= 75x0.50 = 37.50 cum/sec.


∴ Re = [8.95x10 5 x(37.50) 3 x0.92x(0.014)²x2.50] /D 5.33<br />

Re = 2.127x10 7 /D 5.33<br />

Annual expenditure/Cost per year (Ae)<br />

Assuming lining thickness = D/16 (Including OB)<br />

Qty. <strong>of</strong> excavation per meter length = Π/4 (D+2xD/16)² = Π/4x81/64 D²<br />

= 0.994 D²<br />

Rate <strong>of</strong> Excavation<br />

Good rock = 903x0.60 = Rs. 541.80<br />

Moderately jointed rock = 1499x0.20 = Rs. 299.80<br />

Poor rock = 1906x0.20 = Rs. 381.20<br />

Total = Rs. 541.80+299.80+381.20 = Rs. 1222.80<br />

Rate <strong>of</strong> over break per cum = 2.3x1222.80 = Rs. 815.20/ cum<br />

Cost <strong>of</strong> excavation including over break = 1222.80+81.52 (10% <strong>of</strong> Rs.815.20)<br />

= Rs. 1304.32<br />

Rate <strong>of</strong> excavation per cum<br />

= Rs. 1304.32<br />

Say Rs. 1305.00<br />

Rate <strong>of</strong> lining M:20 = Rs. 3177 per cum<br />

Qty. <strong>of</strong> steel for ribs @ 18 kg.per cum = 0.018x56037 = Rs. 1008.66<br />

Say Rs. 1009.00<br />

Total cost <strong>of</strong> lining = 3177+1009 = Rs. 4186.00<br />

Area <strong>of</strong> lining = Π(D+D/16)D/16 = 0.2086 D²<br />

Cost <strong>of</strong> excavation = 0.994 D²x1305 = 1297.17 D²<br />

Cost <strong>of</strong> lining = 0.2086D²x4186 = 873.19D²<br />

Total cost = 1297.17 D²+873.19 D²= 2170.36D²<br />

Total cost including over head charges @ 15% on total cost =<br />

2495.91D²


Ae = Annual expenditure @ 15.50% <strong>of</strong> above cost =<br />

= 2495.91D²x0.155 = 386.87 D 2<br />

Now T Re+Ae<br />

T = 2.13x10 7 /D 5.33 +386.87D²<br />

For mix. value<br />

DT/Dd = 0<br />

T = 2.13x10 7 /D 5.33 +386.87 D² =2.13x10 7 xD -5.33 +386.87D²<br />

For min. value<br />

DT/Dd = -5.33 D -6.33 x2.13x10 7 +2D(386.87) = 0<br />

-1.135x10 8 D -6.33 = -773.74D<br />

D 7.33 = 1.135x10 8 /773.74 = 146690.10<br />

D = 5.07m Say 5.10m<br />

Hence dia <strong>of</strong> H.R.T. (fixed) = 5.10m<br />

Vel. in the H.R.T. = 75/20.63 = 3.63m/sec.<br />

D = 5.10m<br />

R = 5.00/2 = 2.55m<br />

r = 0.987580 R =0.987580x2.55 = 2.52m


R = RARIUS OF HYDRAULICALLY EQUIVALENT CIRCLE<br />

AREA OF SECTION = 3.253 572 r 2 = 20.63 Sqm.<br />

PERIMETRE OF SECTION = 6.426 334r = 16.19m<br />

HYDRAULIC RADIUS = 0.506 287 r = 1.27m<br />

A = 0.780 776 r = 1.97m<br />

B = 1.561 553 r = 3.93m<br />

θ = 31º-22’-01”<br />

SURGE SHAFT (REF. DRAWING NO. CHHATRU-FR-6)<br />

Hydraulic Design<br />

Design discharge = 75 cumecs<br />

Size & shape <strong>of</strong> head<br />

race tunnel = 5.10m, Modified horse shoe shaped<br />

Length <strong>of</strong> head race tunnel = 6500m<br />

Value <strong>of</strong> rugosity co-efficient (assumed) = 0.012 to 0.016<br />

Computations<br />

As per IS: code 7396 Part-I<br />

Thoma area <strong>of</strong> surge tank is given by the formula<br />

Ath<br />

L.At/B V1 2 H0 V1 2 /2g<br />

Sectional area <strong>of</strong> H.R.T. 5.10m modified horse shoe shaped<br />

At = 20.63 Sqm<br />

Vel. in H.R.T. = 3.63 m/sec.<br />

BV1 2<br />

= Friction losses in the tunnel & other losses<br />

= 6.4x3.63 2 x0.014 2 x6500/(5.10) 1.33 = 12.30m


For computation <strong>of</strong> Thoma area using min. value <strong>of</strong> rugosity co-fficient<br />

Head losses with n=0.014, = 12.30m<br />

Head losses with n=0.012, = 9.04m Say 9m<br />

Other losses in trash rack approach tunnel & desilting tank = 0.30m<br />

BV1 2<br />

= 12.30+0.30 = 12.60m For n=0.014<br />

And 9.00+0.30=9.30m<br />

With n=0.012<br />

Now, Ho = Net head on turbines<br />

Ho = Net head - losses in the system<br />

Total losses = Losses upto surge shaft + penstock losses<br />

Penstock losses, hf = 0.0085x350x4.32²/2x9.81x4.80 D= 4.80m<br />

= 0.589m Say 0.60m<br />

L= 465m<br />

Q= 75 cumecs<br />

V= 4.32m/sec.<br />

F = 0.0085<br />

Total losses = 12.60+0.60 = 13.20m Say 11m with n=.014<br />

And = 9.30+0.60 = 9.90m with n=0.012<br />

Say 10m<br />

H0= (3418.50-3247.00)-10 = 161.50m<br />

Ath = 6500x20.63x3.63²/161.50x10x2x9.81 = 55.76m 2<br />

Factor for safety = 1.60<br />

Ath = Area required 55.76x1.60 = 89.22m 2<br />

Provide 15m φ surge shaft<br />

Area <strong>of</strong> surge shaft = Π/4(15)² = 176.71 Sqm.


CALCULATIONS FOR AREA OF ORIFICE<br />

Orifice area is so provided as to satisfy Calame and Gaden condition for max. flow<br />

as given below<br />

2*/√2 + ¼ hf ≤ hor ≤ Z*/√2+¾ hf<br />

Here<br />

Z* = Vo √L/gxAt/As =3.63 √ 6500/9.81*20.63/176.71<br />

For N = 0.016<br />

Hf in tunnel system = 16.06m<br />

= 31.92m<br />

= 31.92/√2+16.06/4 ≤ hor ≤ 31.92/√2+3/4x16.06<br />

For n=0.012<br />

Then<br />

= 22.57+4.01≤ hor ≤ 22.57+12.04<br />

= 26.58 ≤ hor ≤ 34.61<br />

31.92/ √2+9.00/4 ≤ hor 31.92/√2+3/4x9.00<br />

22.57+2.25 ≤ hor 22.57+6.75<br />

24.82 ≤ hor 29.32<br />

Adopt Head loss across orifice = 30m<br />

Now<br />

hor = Q0 2 /Cd 2 xA0 2 x2g<br />

A0 = Q/Cd √2g hor = 75/0.62x√19.62x30<br />

A0 = 4.98 Sqm.<br />

D = √4.98x4/Π<br />

D = 2.52m<br />

Provide orifice dia = 2.50m


Max. up surge = 13.10m<br />

As per surge analysis on<br />

computer<br />

Min. Down surge = 11.90m<br />

Max. upsurge level FRL= 3421+14.96 =3435.96m Say 3436.00m<br />

Min. downsurge level MDDL = 3413.50-16.86 =3396.64m<br />

Say 3396.60m<br />

CALCULATIONS FOR SLOPE OF TUNNEL<br />

Invert level <strong>of</strong> tunnel at RD 0 <strong>of</strong> tunnel = 3402.50m<br />

C/L <strong>of</strong> the tunnel at RD 0 = 3402.50+5.10/2<br />

= 3402.50+2.55<br />

= 3405.05m<br />

C/L <strong>of</strong> tunnel at outlet = MDDL-Losses in HRT- 1.5x orifices losses-<br />

depth <strong>of</strong> orifice-radius <strong>of</strong> HRT<br />

= 3413.50-12.30-1.5(30)-2.50-2.55<br />

= 3413.50-12.30-45-2.50-2.55 = 3351.01m<br />

Say 3351.00m<br />

Difference in levels = (3402.50-2.55)-3351 = 54.05m<br />

(RD 0 & RD 6500)<br />

Length <strong>of</strong> tunnel = 6500m<br />

Slope <strong>of</strong> tunnel = 6500/54.05 = 1:120.25<br />

Say1:120<br />

Now<br />

V1 = Q/A = 75/20.63 = 3.63m/sec.<br />

V2 = 1/4 R 2/3 S ½ = 1/0.014x1.27 2/3 (1/120) ½<br />

V2>V1 Hence O.K.<br />

= 7.46m/sec.<br />

PRESSURE SHAFT (Ref. Drawing No. Gharopa-FR-6.)


Parameters<br />

Design discharge = 75 cumecs<br />

Design net head H = 160m<br />

Length <strong>of</strong> penstock = ± 350m<br />

Efficiency <strong>of</strong> turbine = 94%<br />

Rated HP <strong>of</strong> turbine<br />

P =1000x75x160x0.94/75 = 150400 H.P.<br />

No. <strong>of</strong> pressure shaft = 1 No.<br />

Hydraulic Design<br />

Economical dia <strong>of</strong> Pressure shaft<br />

a) By DOLOND’s FORMULA<br />

Diameter = D = 0.176 (P/H) 0.466<br />

= 0.176 (150400/160) 0.466 = 4.27m<br />

b) As per R.S. Nigam’s Hand Book<br />

D ≤ [ 1xfxc 1 xk2xQ 3 xt/ 1100xK1xH] 1/7<br />

Where<br />

H = 160+20% Water hammer effect<br />

= 192m<br />

c 1 = 2444 kg/cm 2 -Allowable stress insteel<br />

(0.2x1347+0.8x2728)<br />

f = 0.0085 = Friction factor<br />

K1<br />

= 75x0.1250 = 9.37 Rs./kg. = Annual cost <strong>of</strong> pressure shaft per kg.<br />

K2 = 2.00 = Value <strong>of</strong> KWH at generator terminal in same<br />

unit<br />

t = 365x24x0.50 = 4380 hrs. = Annual duration <strong>of</strong> operation in hrs.


D = [1x0.02x2444x2.00x(75) 3 x4380/ 1100x9.37x192]1/7= 5.11m<br />

Taking average dia <strong>of</strong> (a) & (b)<br />

Average diameter = 4.27+5.11/2 = 4.69m<br />

Velocity in pressure shaft<br />

Say 4.70m<br />

V = 75/ Π/4(4.70)²<br />

= 4.32m/sec.<br />

Dia <strong>of</strong> Branch penstock (3 units)<br />

Discharge = 75/3 = 25 cumecs<br />

V = 4.32m/sec.<br />

D = √25x4/4.32 x 4/Π = 2.71m<br />

Say 2.70m<br />

CALCULATIONS FOR GROSS HEAD & NET HEAD<br />

F.R.L. in reservoir = 3421.00m<br />

MD.D.L = 3413.50m<br />

Normal water level = 3413.50+7.50x2/3<br />

= 3413.50+5 = 3418.50m<br />

Min. tail water level = 3239.50m<br />

Normal tail water level = 3240.00m<br />

Max. tail water level = 3247m<br />

Max. gross head = Normal reservoir level-Min. tail water<br />

level<br />

= 3418.50-3239.50 = 179m<br />

Min. Gross head = Max. reservoir level -Max. tail water<br />

level<br />

= 3421-3247 = 174m<br />

Design gross head = 174+2/3 (179-174)


= 177.33m<br />

Total losses from intake<br />

to power house = 17.33m<br />

Design Net Head = 180.83-17.33 = 160m<br />

TAIL RACE TUNNEL (Ref. Drawing No. Gharopa-FR-7( Sheet 2 <strong>of</strong> 3).<br />

Data<br />

Design discharge = 75 cumecs<br />

Size shape = 6m, D-shaped<br />

Length <strong>of</strong> tunnel = 1150m<br />

Assumed value <strong>of</strong> Rugosity co-efficient= 0.014<br />

Hydraulic design<br />

i) Under normal conditions the TRT will behave as a free flow tunnel<br />

V = 1/0.014x( 12.60/10.20) 2/3 (1/182.50) .5 = 6.08m/sec.<br />

Discharge passed = 12.60/6.08 = 76.69cum/sec.<br />

ii) Under HFL conditions the TRT will behave as a pressurized conduit<br />

Gross cross sectional area <strong>of</strong> tunnel = [(6x3)+(Π/4x6²/2)] = 32.13<br />

Sqm.<br />

Velocity in tail race tunnel = 75/32.13<br />

= 2.33m/sec.<br />

Fixation <strong>of</strong> crest level <strong>of</strong> T.R.T.<br />

i) Crest level at outfall will behave as a broad crested weir<br />

Now<br />

Q = CLH 3/2<br />

75 = 1.71x6xH 3/2<br />

H = [ 75/1.71x6] 3/2 = 3.76 m<br />

Crest level at outfall = 3240.00-3.76 = 3236.24m


PARA DESCRIPTION PAGE<br />

7.0 GENERAL VII-1<br />

7.1 PATTERN OF FLOWS IN 90% DEPENDABLE AND 50%<br />

MEAN YEAR<br />

VII-1<br />

7.2 HEAD FOR POWER GENRATION VII-2<br />

7.2.1 DESIGN HEAD VII-2<br />

7.2.2. MAXIMUM HEAD VII-2<br />

7. 2.3 MINIMUM HEAD VII-3<br />

7.3 POWER GENERATION IN A 90% DEPENDABLE YEAR<br />

AND 50% MEAN YEAR<br />

VII-3<br />

7.4 INSTALLED CAPACITY STUDIES VII-4<br />

TABLE-7.1 YEARWISE COMPUTATIONS FOR UN-RESTRICTED<br />

ENERGY IN GWH.<br />

TABLE-7.2 COMPUTATION FOR DEPENDABLE YEAR ON THE<br />

BASIS OF ENERGY<br />

VII-5 TO<br />

VII-9<br />

VII-10<br />

TABLE –7.3 90% DEPENDABLE AND 50% MEAN YEAR DISCHARGE VII-11<br />

TABLE- 7.4<br />

& TABLE 7.5<br />

TABLE –7.6<br />

& TABLE 7.7<br />

POWER & ENERGY GENRATION IN 90% DEPENDABLE<br />

YEAR<br />

VII-12 TO<br />

VII-22<br />

POWER & ENERGY GENRATION IN 50% MEAN YEAR VII-23 TO<br />

VII-33<br />

TABLE 7.8 SUMMARY VII-34<br />

TABLE- 7.9 SUMMARY 90% DEPENDABLE YEAR VII-35<br />

TABLE –7.10 SUMMARY 50% MEAN YEAR VII-36<br />

PLATE-7.1 INSTALLED CAPACITY CURVE VII-37<br />

PLATE-7.2 TOTAL ENRGY VS I.C. CURVE VII-38<br />

ANNE.-VII-1 COMMENTS ON POWER POTENTIAL RAISED BY CEA<br />

DT.12.04.04<br />

ANNE.-VII-2 REPLY TO THE COMMENTS RAISED BY CEA<br />

DT.12.04.04<br />

ANNX-V11-3 COMMENTS ON POWER POTENTIAL RAISED BY CEA<br />

DT.13.05.04<br />

ANNX-V11-4 REPLY TO THE COMMENTS RAISED BY CEA<br />

DT.13.05.04<br />

VII-39 -40<br />

VII-41<br />

VII-42-43<br />

VII-44-45


7.0 GENERAL<br />

CHAPTER – VII<br />

POWER POTENTIAL STUDIES<br />

Chhatru Hydro-<strong>electric</strong> Project is essentially a run- <strong>of</strong>- the river<br />

development for generation <strong>of</strong> <strong>hydro</strong>-power on Chandra river in Himachal<br />

Pradesh. It has been contemplated as a peaking station to operate in western<br />

part <strong>of</strong> Northern Regional Grid. Installed capacity <strong>of</strong> the <strong>project</strong> has been<br />

presently kept as 108 MW comprising 3 units <strong>of</strong> 36 MW each with overall<br />

efficiency <strong>of</strong> generation as 0.92.<br />

7.1 PATTERN OF FLOWS IN 90% DEPENDABLE AND 50% MEAN<br />

YEAR<br />

The 27 years discharge data from June 1973 to May, 2000 <strong>of</strong> Chandra river<br />

at Ghousal has been used to develop a series at diversion site <strong>of</strong> Chhatru<br />

HEP on catchment area basis for power generation. Energy generation has<br />

been worked out for all the years as appended in Table 7.1. .Pattern <strong>of</strong> flows<br />

in 90% dependable and 50% mean years has been worked out on the basis<br />

<strong>of</strong> energy generation in 27 years by using Welbull’s relationship P= n/m+1,<br />

where P is percentage exceedence <strong>of</strong> occurrence, n is the event no. in<br />

descending order and m is total no. <strong>of</strong> events, presented in Table 7.2. Flows<br />

in 90% dependable and 50% mean years, so worked out are given in Table<br />

7.3.<br />

7.2 HEAD FOR POWER GENERATION


7.2.1 DESIGN HEAD<br />

Gross head for power generation has been worked as 178.50 m between<br />

weighted reservoir El. 3418.50 m and normal tail water level El. 3240 m.<br />

Losses in water conductor system corresponding to design discharge <strong>of</strong> 75<br />

cumecs from intake to generating units has been worked out as 18.33 m.<br />

Design net head therefore has been taken as 160 m. The calculations are as<br />

follows:<br />

Full Reservoir Level (FRL) = ± 3421.00 m<br />

Min. Draw Down Level (MDDL) = ± 3413.50 m<br />

Normal Tail Water Level (NTWL) = ± 3240.00 m<br />

Weighted Reservoir Level = MDDL+2/3(FRL- MDDL)<br />

= 3413.50+2/3 (3421.00 – 33413.50)<br />

= 3218.50 m<br />

Gross Head = Weighted Reservoir Level – NTWL<br />

= 3418.50 – 3240 = 178.50 m<br />

Losses = 18.33 m<br />

Net Head = Gross Head – Losses<br />

= 178.50 – 18.33 = 160.17m say 160.00m<br />

7.2.2 MAXIMUM HEAD<br />

Maximum gross head has been calculated as the difference <strong>of</strong> Maximum<br />

water level ( ± 3422 m ) & Minimum Tail water level ( ± 3239.50 m) &<br />

works out to be 182.50 m.<br />

7.2.3 MINIMUM HEAD


Minimum gross head has been taken as difference between MDDL( ±<br />

3413.50 m) & Maximum tail water level ( 3247 m) & works out to be<br />

166.50 m.<br />

7.3 POWER GENERATION IN A 90% DEPENDABLE YEAR AND<br />

50% MEAN YEAR<br />

<strong>Power</strong> generation studies in a 90% dependable year corresponding to<br />

installed capacity varying from 78 MW to 159 MW are given in Table 7.4<br />

The energy generation in 90% dependable year corresponding to the<br />

installed capacity <strong>of</strong> 108 MW is 468.83351.91 GWH. The energy generation<br />

in 90% dependable year corresponding to 95% machine availability works<br />

out to be 455.72 GWH as shown in Table 7.5.<br />

<strong>Power</strong> generation studies in a 50% mean year corresponding to installed<br />

capacity varying from 75 MW to 159 MW are given in Table 7.6 The<br />

energy generation in 50% mean year corresponding to the installed capacity<br />

<strong>of</strong> 108 MW is 488.85 GWH. The energy generation in 90% dependable year<br />

corresponding to 95% machine availability works out to be 475.80 GWH as<br />

shown in Table 7.7.


7.4 INSTALLED CAPACITY STUDIES<br />

<strong>Power</strong> generation studies for 90% dependable and 50% mean pattern <strong>of</strong><br />

flows with installed capacity varying from 78 MW to 159 MW have been<br />

done.From the study the incremental increase Vs installed capacity curve &<br />

total energy Vs installed capacity curve have been drawn as shown in Plate<br />

7.1 and Plate 7.2 respectively. The fall in incremental energy occurs beyond<br />

130 MW. Moreover the plant load factor for lean season ( Dec. to Feb. ) is<br />

just below 16% from 126 to 159 MW. While deciding the installed capacity<br />

<strong>of</strong> the <strong>project</strong> it was seen that during 90% dependable year (1992-93),<br />

minimum discharge <strong>of</strong> 10.41 cumecs ( obtained from overall flow duration<br />

curve) and design flow is available in only four 10 daily blocks which is<br />

only 25% <strong>of</strong> the period in 90% dependable year.<br />

Since the <strong>project</strong> is planned as a peaking station for 3 hours to meet with<br />

peaking power shortage in the country , the installed capacity <strong>of</strong> the <strong>project</strong><br />

has been fixed at 108MW with over all PLF <strong>of</strong> 50%. It was further studied<br />

that the minimum discharge during lean season ( Dec. to Feb.) in 90%<br />

dependable year is 11.18 cumecs and therefore peaking <strong>of</strong> 3 hrs. minutes<br />

can be done.<br />

The live pondage capacity <strong>of</strong> 70 Hac-m in terms <strong>of</strong> MW hours worksout to<br />

280.79MW hours. The rest <strong>of</strong> the MW hours shall be met with from<br />

minimum flow available during peaking hours.<br />

It is therefore concluded that the installed capacity <strong>of</strong> 108 MW shall be<br />

economically optimum. An overview <strong>of</strong> <strong>hydro</strong>logical & <strong>Power</strong> studies has<br />

been given in summary table 7.8,7.9 and 7.10 respectively.


Annexure-VII-2<br />

Reply to the comments raised by Dy. Director HPI, CEA, New Delhi on power<br />

potential chapter vide letter No. 7/9/HPSEB/HP&I/2004-778 dated<br />

12.4.2004(Annexure-I).<br />

1. The computations to fix FRL, MDL and tail water have been given in the design<br />

computations incorporated in Chapter VI, Para No. 6.4(A).<br />

2. The live pondage capacity in terms <strong>of</strong> MW hours and nos. <strong>of</strong> peaking hours have<br />

been given in Chapter-VII- Para No. 7.4.<br />

3. The area capacity curve have been annexed as Plate-6.1 in Chapter-VI.<br />

4. The drop between TWL (El. 3240m) <strong>of</strong> Chhatru & FRL(3212.40m) <strong>of</strong> Khoksar<br />

could not be utilized due to the reason that during the site inspection <strong>of</strong> these<br />

<strong>project</strong>s, no suitable site for location <strong>of</strong> power house <strong>of</strong> Chhatru below El. 3240m<br />

and diversion site for Khoksar up stream <strong>of</strong> El. 3212.40m was found as per<br />

topography <strong>of</strong> the area and geological conditions.<br />

5. Summary study <strong>of</strong> power potential aspects has been incorporated in the Chapter-VII<br />

Table 7.8, 7.9 & 7.10.<br />

6. Recommendation for DPR stage:-<br />

The <strong>project</strong> has been planned as per contour interval <strong>of</strong> 20m on the S.O.I. sheet<br />

available in Scale <strong>of</strong> 1:25000. After carrying out the detailed survey <strong>of</strong> the <strong>project</strong><br />

area at higher scale the exact topography <strong>of</strong> the area shall be depicted and there is<br />

possibility <strong>of</strong> increase/decrease in the head considered at present. As such the<br />

installed capacity may fluctuate at DPR stage.


Annexure-VII-4<br />

Reply to the comments <strong>of</strong> CEA on draft PFR <strong>of</strong> Chhatru HEP (108 MW) in<br />

HP, sent by Director (HP&I) vide letter No. 7/9/HPSEB/HP&I/2004/1008<br />

dated 13.05.04.<br />

General Comments<br />

1. Initial Environmental studies alongwith Satellite Remote Sensing<br />

Based Inputs from NRSA, Hyderabad has been incorporated in<br />

Chapter IX, as per scope <strong>of</strong> work.<br />

2. CEA guidelines for financial parameters have been adopted while<br />

preparing the Economic Evaluation <strong>of</strong> the <strong>project</strong> in Chapter XIII.<br />

3. The cost <strong>of</strong> the <strong>project</strong> has been worked out as per CEA guide lines<br />

and tariff calculations for present day cost with IDC @ 10% p.a.<br />

4. The necessary recommendation for further studies have been given<br />

in Chapter-V-3 “Hydrology” P-V-52 & Chapter-VII “<strong>Power</strong><br />

Potential Studies” P-VII-41.<br />

5. Hydrology adopted in PFR has been approved by CWC, by Director<br />

Hydrology, vide letter No. I/HP/26/2004 dated 19.4.04 endorsed by<br />

Director (HP&I) letter No. HPSEB/HPI/877 dated 21.4.04 (P-V-46<br />

& 51).<br />

6. The advice <strong>of</strong> CWC on the layout planning <strong>of</strong> the <strong>project</strong> shall be<br />

taken care <strong>of</strong> at the stage <strong>of</strong> preparing the Detailed Project Report <strong>of</strong><br />

the <strong>project</strong>.<br />

7. The view <strong>of</strong> SP&PA Division <strong>of</strong> CEA on power evacuation shall be<br />

obtained at the final DPR stage, however, the power evacuation<br />

system has been proposed as per proposed evacuation plan Chenab<br />

Valley (Ref. Plate VIII-1 attached).<br />

8. Executive Summary has been incorporated as per CEA guide lines<br />

dated 2 nd Dec. 2003.<br />

9. The geo-technical studies have been got carriedout by GSI and<br />

incorporated in Chapter-IV.


<strong>Power</strong> Potential Studies<br />

Comments <strong>of</strong> power potential studies earlier received vide CEA letter No.<br />

7/9/HPSEB/HP&I/2004-778 dated 12.4.2004 have been incorporated on<br />

P-VII-30-40 as Annexure-VII-1 and reply to the same including<br />

recommendations for further studies has been appended in Annexiure-VII-2<br />

P-VII-41.


PARA DESCRIPTION PAGE<br />

8 POWER EVACUATION VIII-1<br />

8.1 APPRAISAL OF EXISTING POWER EVACUATION<br />

FACILITIES<br />

VIII-1<br />

8.2 GENERATION EQUIPMENT FOR POWER HOUSE VIII-2<br />

8.2.1 MECHANICAL EQUIPMENT VIII-2<br />

8.2.1.1 TURBINES VIII-2<br />

8.2.1.2 GOVERNOR VIII-2 TO VIII-3<br />

8.2.1.3 MAIN INLET VALVES VIII-3<br />

8.2.1.4 COOLING WATER AND FIRE PROTECTION<br />

SYSTEM<br />

VIII-3<br />

8.2.1.5 POTABLE WATER AND SANITARY DRAINAGE VIII-4<br />

8.2.1.6 DRAINAGE AND DEWATERING SYSTEM VIII-4<br />

8.2.1.7 COMPRESSED AIR SYSTEM VIII-4<br />

8.2.1.8 OIL SYSTEM VIII-5<br />

8.2.1.9 VENTILATION AND AIR CONDITIONING VIII-5<br />

8.2.1.10 POWER HOUSE CRANE VIII-5<br />

8.2.2 ELECTRICAL EQUIPMENT VIII-5<br />

8.2.2.1 GENERATOR VIII-5 TO VIII-6<br />

8.2.2.2 EXCITATION SYSTEM VIII-6<br />

8.2.2.3 GENERATOR SWITCH GEAR AND CONNECTING<br />

CABLES<br />

VIII-6 TO VIII-7<br />

8.2.2.4 GENERATOR TRANSFORMERS VIII-7<br />

8.2.2.5 CONTROL AND MONITORING EQUIPMENT VIII-7 TO VIII-8<br />

8.2.2.6 STATION SERVICE /AUXILLARY SUPPLY VIII-8<br />

8.2.2.7 POWER PLANT GROUNDING VIII-8<br />

8.2.2.8 LIGHTING VIII-8<br />

8.2.2.9 SWITCHYARD AND SWITCHING SCHEME VIII-9<br />

8.3 PROPOSED EVACUATION ARRANGEMENT TO<br />

NEAREST FACILITIES<br />

PLATE VIII- PROPOSED EVACUATION PLAN FOR CHENAB<br />

I<br />

VALLEY<br />

VIII-9<br />

VIII-10


8. POWER EVACUATION<br />

CHAPTER – VIII<br />

POWER EVACUATION<br />

8.1 APPRAISAL OF EXISTING POWER EVACUATION FACILITIES<br />

At present there is only 33 KV network in the valley which is connected to<br />

132/33 KV Sub-Station, Bajaura (Sarabai) through 33 KV Sub-Station at<br />

Manali. Independent evacuation system for the up-coming power houses in<br />

the valley will have to be evolved. Number <strong>of</strong> power houses, namely Sach-<br />

Khas (70 MW), Gondala (90 MW), Khoksar (90MW), Chhatru (108 MW)<br />

and Bardang (114 MW) are envisaged to come up in the valley. Individual<br />

evacuation system from these power houses will not be possible due to<br />

inhospitable terrain and corridor problems. The power from these power<br />

houses will have to be pooled in at some centrally located suitable place and<br />

then evacuated through D/C 400 KV system to 400 KV pooling in substation<br />

being planned/set up by POWERGRID for Parbati-III HEP near<br />

Panarsa in Kullu valley. It is proposed to pool in the power <strong>of</strong> <strong>hydro</strong> <strong>electric</strong><br />

<strong>project</strong>s coming up in Chenab valley at Tandi near Keylong which has fairly<br />

flat area for construction <strong>of</strong> sub-station and then evacuate the pooled in<br />

power through 125 Kms, 400 KV D/C line to pooling in sub-station being<br />

set up by POWERGRID at Panarsa via Rohtang Pass. The cost <strong>of</strong> pooling<br />

in sub-station at Tandi, expansion at Panarsa and 400 KV line between<br />

Tandi and Panarsa which is approximated as 240 Crores has not been<br />

included in the <strong>project</strong> cost. This system will be executed by Central/State<br />

Agency. The executing agency <strong>of</strong> this system will charge the wheeling<br />

charges from the promoters <strong>of</strong> these HEPs.


8.2 GENERATION EQUIPMENT FOR POWER HOUSE<br />

8.2.1 MECHANICAL EQUIPMENT<br />

8.2.1.1 TURBINES<br />

The vertical shaft, Francis turbine <strong>of</strong> 36.90 MW capacity with a rated<br />

synchronous speed <strong>of</strong> 428.6 rpm has been found to be suitable in view <strong>of</strong><br />

the over all economy <strong>of</strong> the power house. As per the study there is only<br />

minor difference in the width <strong>of</strong> power house, hence lower speed has been<br />

adopted which has resulted in a suction head <strong>of</strong> 6.96mtrs. below the<br />

minimum tail water level. Lower speed has however increased the overall<br />

cost <strong>of</strong> the equipment marginally, but will be compensated with the<br />

reduction in the wear & tear <strong>of</strong> under water parts <strong>of</strong> turbine due to silt which<br />

is usually high in Himalayan rivers. Each turbine shall be provided with<br />

suitable oil pressure unit, electro hydraulic governor and other requisite<br />

control equipment.<br />

8.2.1.2 GOVERNOR<br />

Since Chhatru power house will be connected with 400 KV Pooling in<br />

Tandi sub-station being set up by Central/State Agency for evacuation <strong>of</strong><br />

power from all the <strong>project</strong>s located in the valley, it is <strong>of</strong> prime importance<br />

that the governor accuracy and sensitivity is <strong>of</strong> high order so as to ensure<br />

proper behaviour <strong>of</strong> the regulators. For any change in the system load to<br />

avoid hunting and over regulation, it is proposed to provide Electro<br />

Hydraulic governor. The governing system for each unit will have an<br />

individual oil pressure system consisting <strong>of</strong> oil to air mixer and an oil tank<br />

with two pumps as well as the automatic control equipment. Speed etc.<br />

would be indicated both on the governor cubicle and on the unit control


oard to facilitate supervision <strong>of</strong> operation <strong>of</strong> the unit. The controls would<br />

include provision for emergency shut down <strong>of</strong> unit in case <strong>of</strong> :-<br />

Loss <strong>of</strong> Pressure in the oil pressure vessel <strong>of</strong> Governor oil system.<br />

Excessive temperature rise in Bearing.<br />

Excessive speed rise <strong>of</strong> the unit.<br />

Electrical faults.<br />

8.2.1.3 Main inlet valves<br />

A main inlet valve <strong>of</strong> the Butterfly with flow guides type would be provided<br />

at each turbine inlet for maintenance <strong>of</strong> the turbine and for emergency<br />

isolation <strong>of</strong> the turbine in the event <strong>of</strong> governor failure. Each valve shall be<br />

actuated by means <strong>of</strong> servomotor which shall be fed from an independent<br />

oil pressure unit. Closing <strong>of</strong> the valve shall be through counter weights.<br />

Each valve unit shall constitute a complete independent unit with its own<br />

operating system for opening and closing, which will be connected to the<br />

automatic start and stop sequence <strong>of</strong> the respective turbine unit.<br />

8.2.1.4 COOLING WATER AND FIRE PROTECTION SYSTEM<br />

A pumping system would be provided to supply adequate quantity <strong>of</strong> water<br />

from the tail race for cooling <strong>of</strong> the turbine and generator bearings,<br />

generator air coolers and selected plant services.<br />

Water for fire protection would be taken from an elevated reservoir<br />

providing both reliable operation and ample capacity to fight fire in the<br />

power house. A back up water supply to this reservoir would also be<br />

provided.


8.2.1.5 POTABLE WATER AND SANITARY DRAINAGE<br />

Water from the cooling water system would be used to supply the plant’s<br />

potable and sanitary water needs. The potable water would be filtered and<br />

chemically treated as required. Sanitary sewerage would be treated in a<br />

septic system before discharge in to tail race <strong>of</strong> power plant.<br />

8.2.1.6 DRAINAGE AND DEWATERING SYSTEM<br />

A separate drainage and de-watering system with suitable number <strong>of</strong> pumps<br />

would be provided to drain and pump out miscellaneous inflows and ground<br />

water seepage in the power house.<br />

Starting and stopping <strong>of</strong> the pumps would be automatic and controlled by<br />

level switches in the drainage sump.<br />

8.2.1.7 COMPRESSED AIR SYSTEM<br />

A high pressure compressed air plant would be installed to meet the<br />

requirements <strong>of</strong> the governor oil system and the oil pressure system <strong>of</strong> the<br />

spherical valves.<br />

A low pressure compressed air plant would also be installed to meet the<br />

requirements <strong>of</strong> the station pneumatic tools, breaking and other general<br />

purpose in the power house.<br />

8.2.1.8 OIL SYSTEM<br />

A portable dehydration unit comprising <strong>of</strong> oil heaters, Filters, tank etc.<br />

would be provided in the power station for the treatment <strong>of</strong> governor/<br />

Bearings and switch gear oils.


8.2.1.9 VENTILATION AND AIR CONDITIONING<br />

<strong>Power</strong> house would be provided with ventilation system as required for the<br />

underground power house work areas and <strong>of</strong>fices. An air conditioning<br />

system would be provided to maintain the control room at the selected<br />

design temperature and humidity levels. The temperature and humidity level<br />

would be selected to suit the requirements <strong>of</strong> equipment and staff.<br />

8.2.1.10 POWER HOUSE CRANE<br />

In order to expedite the completion <strong>of</strong> various construction activities <strong>of</strong> the<br />

power house and keeping in view the dimension <strong>of</strong> power house, <strong>electric</strong><br />

over head travelling bridge crane having capacity <strong>of</strong> 125/25 tonnes would be<br />

installed in the power house primarily for erection, maintenance and repair<br />

<strong>of</strong> the generating units. The crane would be equipped with motor control<br />

system providing suitable procedure for equipment erection.<br />

8.2.2 ELECTRICAL EQUIPMENT<br />

8.2.2.1 GENERATOR<br />

Each generator shall be <strong>of</strong> vertical shaft, salient pole type, Synchronous<br />

generator directly coupled to the <strong>hydro</strong> turbine and having a rated out put <strong>of</strong><br />

40 MVA with 0.9 lag power factor. The generator bearing arrangement<br />

shall be <strong>of</strong> conventional type i.e. suspended type. It is proposed to equip the<br />

generators with dynamic braking in addition to the friction brakes. The<br />

generator shall have class-F insulation in line with modern practice and<br />

temperature restricted to class-B insulation.<br />

The generator will be air cooled with a closed ventilation system using air<br />

water heat exchanger placed around the stator frame. The generators are


proposed to be equipped with the following <strong>electric</strong>al protection<br />

equipment:-<br />

High speed differential protection for generator.<br />

Generator Over Voltage protection.<br />

Back up over current protection.<br />

Stator earth fault relay protection.<br />

Negative Phase Sequence Current protection.<br />

Rotor Field Circuit earth Fault Relay & protection.<br />

Loss <strong>of</strong> excitation relay schemes.<br />

Generator thermal relay protection.<br />

Phase balance relay.<br />

8.2.2.2 EXCITATION SYSTEM<br />

The excitation system <strong>of</strong> the generator will be <strong>of</strong> static type and will include<br />

static type voltage regulator <strong>of</strong> latest design, field suppression equipment<br />

and the associated accessories.<br />

The power for the excitation system will be taken from the generator main<br />

bus by means <strong>of</strong> a dry type or epoxy encased step down transformer. The<br />

excitation system will be self contained requiring only an external power<br />

source for field flashing at unit starting. The field flashing supply will be<br />

taken from the station battery.<br />

The excitation system including the voltage regulator will be placed in the<br />

cubicles adjacent to the generator pit.<br />

8.2.2.3 GENERATOR SWITCH GEAR AND CONNECTING CABLES


Each generator shall be connected to its step up transformer by means <strong>of</strong> 11<br />

kV bus ducts. Current transformers required for protection, control and<br />

metering will be located and form part <strong>of</strong> the bus ducts assemblies.<br />

The generator switch gear will be <strong>of</strong> the metal enclosed type placed in a<br />

separate room close to the generator. It will include the generator phase<br />

equipment and connections shown in the attached single line diagram. The<br />

equipment for the generator neutral side will be placed in a cubicle adjacent<br />

to the generator pit.<br />

8.2.2.4 GENERATOR TRANSFORMERS<br />

10 Nos. generator transformers <strong>of</strong> 15 MVA, 11/ 220/ / 3 kV , single phase,<br />

50 Hz rating will be provided and placed in a separate cavern on the down<br />

stream side <strong>of</strong> power house. The OFWF type <strong>of</strong> cooling is proposed for<br />

generator transformer.<br />

8.2.2.5 CONTROL AND MONITORING EQUIPMENT<br />

The plant will be designed to be operated as an attended type. Unit control<br />

will be provided locally while central control will be from various control<br />

panels located in the control and relay room <strong>of</strong> the power house. Control<br />

equipment will include metering and control panels, protections for<br />

supervision and operation <strong>of</strong> the generator turbine, 11 kV switch gear ,<br />

auxiliary power system, transformers and 220 kV switch gear.<br />

The control equipment will also include the PLC and Telecommunication<br />

equipment required for the transmission lines. Provision for connection to<br />

the state load dispatch center will also be provided. The control system<br />

shall be fully computerized.


8.2.2.6 STATION SERVICE/ AUXILIARY SUPPLY<br />

The station service supply is proposed to be taken through 11 kV Local<br />

Distribution system. In addition, for reliability, 500 KVA DG sets shall also<br />

be provided for the black start capability. This will also feed local area ,<br />

Colony, head works etc. The unit auxiliaries shall be fed through 11/0.415<br />

kV, 500 KVA transformers connected to each generator. The auxiliaries can<br />

also be fed from 2 Nos., 11/0.415 kV, 1 MVA station service transformers,<br />

which are connected to 11 kV bus connected to 11 kV local supply.<br />

8.2.2.7 POWER PLANT GROUNDING<br />

8.2.2.8 LIGHTING<br />

The power station will be provided with a complete earthing system. All<br />

exposed conductive parts and equipment in the power house and switch yard<br />

will be connected to the grounding system. The grounding system will be<br />

designed to minimize the “Step” and “Touch” potential within acceptable<br />

limits.<br />

The power plant lighting , following normal practice, will comprise <strong>of</strong><br />

interior and exterior lights as appropriate. While the majority <strong>of</strong> the<br />

illuminaries will be AC powered, emergency lighting will be DC supplied<br />

from station battery system. The emergency lighting will be provided only<br />

for essential locations e.g. control room, exit tunnels etc.<br />

8.2.2.9 SWITCH YARD AND SWITCHING SCHEME<br />

Keeping in view the terrain at the power house and reliability <strong>of</strong> the system,<br />

GIS underground 220 KV Switchyard with double bus and single breaker<br />

has been envisaged. Provision <strong>of</strong> Bus Coupler has also been made. It will


e located above the generator transformers in the transformer cavern.<br />

Switchgear shall be connected to the generator transformers through 220<br />

KV oil to SF-6 connectors. The Switchgear shall be connected through app.<br />

250 mtr long 220 KV Bus ducts to the pothead yard through bus duct tunnel.<br />

This has been envisaged because power <strong>of</strong> this power house (108 MW) shall<br />

be pooled in with the down stream Khoksar (90MW) power house<br />

transmission system by LILOing one Ckt <strong>of</strong> Khoksar- Tandi 220KV line for<br />

final pooling in at Tandi 400 KV pooling point. Space requirements for pot<br />

head yard will be app. 60 X 20 mtrs.<br />

8.3 PROPOSED EVACUATION ARRANGEMENT TO NEAREST<br />

FACILITIES<br />

It is proposed to evacuate the power generated at Chhatru <strong>project</strong> by<br />

LILOing one ckt. <strong>of</strong> 220KV D/C line from Khoksar to 400 kV Pooling point<br />

at Tandi which is proposed in this basin . Beyond this point, the evacuation<br />

will be through 400 KV D/C Network to Panarsa Pooling in Sub-Station <strong>of</strong><br />

PGCIL .


PARA DESCRIPTION PAGE<br />

9.1 DESCRIPTION OF THE PROJECT IX-1<br />

9.2 DESCRIPTION OF ENVIRONMENT IX-1<br />

9.2.1 PHYSICAL RESOURCE IX-1<br />

9.2.2 HYDROLOGY IX-1<br />

9.2.3 GEOLOGY IX-1<br />

9.2.4 SOIL IX-2<br />

9.3 ECOLOGICAL RESOURCE IX-2<br />

9.3.1 FORESTS IX-2<br />

9.3.2 FLORA AND FAUNA IX-2<br />

9.3.3 FLORA IX-2<br />

9.3.4 MECHICINAL PLANTS IX-2<br />

9.3.5 FAUNA IX-3<br />

9.4 BASELINE ENVIRONMENTAL STATUS IX-3<br />

9.4.1 CLIMATE AND TEMPERATURE IX-3<br />

9.4.2 TEMPERATURE, RAINFALL AND SNOWFALL DATA<br />

OF PATSCO (ADJOINING LAHAUL VALLEY)<br />

9.5 ENVIRONMENTAL IMPACT ASSESSMENT AND<br />

EVALUATION<br />

IX-3 TO IX-4<br />

IX-5<br />

9.5.1 IMPACT IDENTIFICATION IX-5<br />

9.5.2 IMPACT IDENTIFICATION DURING CONSTRUCTION<br />

PHASE<br />

9.5.3 IMPACT IDENTIFICATION DURING OPERATIONAL<br />

PHASE<br />

IX-5<br />

IX-6<br />

9.5.4 PREDICTION OF IMPACTS IX-7<br />

9.5.5 IMPACT ON AIR ENVIRONMENT IX-7<br />

9.5.6 IMPACT ON NOISE ENVIRONMENT IX-7<br />

9.5.7 IMPACT ON WATER ENVIRONMENT IX-7<br />

9.5.8 IMPACTS ON FLORA AND FAUNA IX-7<br />

9.6 E.R&R ASPECTS IX-7


9.7 ENVIRONMENTAL MANAGEMENT PLAN<br />

(MITIGATION MEASURES)<br />

IX-8<br />

9.7.1 ENVIRONMENTAL MANAGEMENT IX-8<br />

9.7.2 ENVIRONMENTAL MANAGEMENT AT<br />

CONSTRUCTION STAGE<br />

IX-8<br />

9.7.3 SITE PREPARATION IX-8<br />

9.7.4 CONSTRUCTION IX-8<br />

9.7.4.1 AIR ENVIRONMENT IX-8<br />

9.7.4.2 NOISE ENVIRONMENT IX-9<br />

9. 7.4.3 WATER ENVIRONMENT IX-9<br />

9.7.4.4 GREEN BELT DEVELOPMENT (COMPENSATORY<br />

AFFORESTATION)<br />

IX-9<br />

9.7.4.5 DISPOSAL OF MUCK IX-10<br />

Annexure-IX-<br />

1<br />

SATELLITE REMOTE SENSING BASED INPUTS FOR<br />

INITIAL ENVIRONMENTAL STUDIES FROM NRSA<br />

STUDY BACKGROUND IX-11TO IX-12<br />

OBJECTIVE IX-12 TO IX-<br />

13<br />

SALIENT FEATURES OF THE CHHATRU HYDRO<br />

POWER SITE<br />

SATELLITE DATA USED IX-14<br />

BRIEF METHODOLOGY OF SATELLITE DATA<br />

ANALYSIS<br />

IX-13 TO IX-<br />

14<br />

IX-14 TO IX-<br />

15<br />

OUTPUTS PROVIDED IX-15 TO IX-<br />

16<br />

LIST OF TABLE IX-16<br />

TABLE-1 LANDUSE-LAND COVER INFORMATION WITHIN THE<br />

SUBMERGENCE AREA.<br />

TABLE-2 LANDUSE-LAND COVER INFORMATION WITHINTHE 7<br />

KM RADIUS FROM THE DAM SITE AT CHHATRU<br />

IX-16<br />

IX-16


CRITICAL ANALYSIS OF SATELLITE BASED INITIAL<br />

ENVIRONMENTAL STUDY<br />

IX-17 -<br />

TO IX-18<br />

CONCLUSION & RECOMMENDATION IX-18<br />

LIST OF MAPS<br />

1.a IRS ID PAN+LISS III MERGED SATELLITE IMAGE OF<br />

21 ST SEPTEMBER, 2001.<br />

1.b SATELLITE DERIVED LANDUSE-LAND COVER MAP<br />

OF SORROUNDINGS OF PROPOSED HYDRO POWER<br />

SITE AT CHHATRU, HIMACHAL PRADESH.<br />

1.c LANDUSE-LAND COVER MAP OF SURROUNDINGS<br />

UPSTREAM OF PROPOSED DAM SITE AT CHHATRU<br />

1.d MAP OF NATIONAL PARKS /SANCTUARIES AND THE<br />

LOCATION OF CHHATRU HYDRO POWER SITE AND 7<br />

KM RADIUS CIRCLE FROM THE DAM SITE.<br />

IX-19<br />

IX-20<br />

IX-21<br />

IX-22


CHAPTER IX<br />

ENVIRONMENT ASPECTS<br />

9.1 A. Description <strong>of</strong> the Project<br />

This Project is a run-<strong>of</strong>-river scheme on river Chandra with diversion barrage at<br />

about 5 km upstream <strong>of</strong> Chhatru. The <strong>Power</strong> house is located about 3.5 km<br />

downstream <strong>of</strong> Chhatru village. The Project falls in Tehsil Keylong, District Lahaul<br />

& Spiti <strong>of</strong> Himachal Pradesh.<br />

The Project envisages construction <strong>of</strong> diversion structure + 19m high, for the<br />

diversion <strong>of</strong> + 75 cumecs <strong>of</strong> discharge through a +6.5 km long tunnel to an<br />

underground <strong>Power</strong> House utilizing a gross head <strong>of</strong> + 177.33m for generating 108<br />

MW <strong>of</strong> power.<br />

9.2 B. Description <strong>of</strong> Environment<br />

9.2.1 B.1 Physical Resource<br />

9.2.2 B.1.1 Hydrology<br />

Chenab is a major river <strong>of</strong> the Indus Basin originating from the snow covered<br />

slopes <strong>of</strong> Great Himalaya <strong>of</strong> Pir-Panjal ranges in Lahaul Spiti district and flows in a<br />

steep gradient with a series <strong>of</strong> loops and bends. The two major rivers in the head<br />

ridges namely Chandra and Bhaga form the Chanra Bhaga (Chenab) river.<br />

The river Chandra originates from Bara lacha and is further augmented by Chandra<br />

Tal. The river, after flowing for more than 48 km in south westerly direction turns<br />

abruptly to the west and flows for another 64 km until it meets the Bhaga river at<br />

Tandi. The average fall <strong>of</strong> the river is 1 in 60. The first 80 km <strong>of</strong> the valley is<br />

completely uninhabited, represented by barren, eroding mountain slopes, with large<br />

alluvial flats and fans at places.<br />

The Chandra Bhaga (Chenab) flows North West and maintains an average fall <strong>of</strong> 1<br />

in 176. After traversing a distance <strong>of</strong> about 101 km from the confluence at Tandi, it


passes at karunala in to Pangi valley <strong>of</strong> Chamba District. From Thirot onwards the<br />

river, in places, passes through rocky gorges several metres deep.<br />

9.2.3 B.1.2 Geology:<br />

Great mass <strong>of</strong> the mountains is composed <strong>of</strong> ancient rocks <strong>of</strong> the lurian age, chiefly<br />

Schists, Slates and Balaini conglomerates. The principal rock formation is Mica<br />

schist, Shale and Sandstone. Taken as a whole, the rock system is very fragile and<br />

liable to erosion, which is <strong>of</strong>ten accentuated by the rigours <strong>of</strong> severe winter,<br />

avalanches and the strong winds that accompany them.<br />

The insulation and absence <strong>of</strong> any water action has led to the accumulation <strong>of</strong><br />

abundant detrital products on dry uplands and valleys forming the mantle rock <strong>of</strong><br />

regolith <strong>of</strong> fresh, un decomposed fragments. The bare mountains thus exhibit<br />

typical desert colouration <strong>of</strong> rocks due to peculiar solar weathering. The right bank<br />

is generally rocky with steep slopes.<br />

9.2.4 B.1.3 Soil:<br />

The soil is generally grey and light, charactrised by scanty plant cover and low<br />

fertility status. In the absence <strong>of</strong> any substantial leaching <strong>of</strong> minerals from the soil,<br />

the bases are continuously added to the soil complex, rendering pH to the alkaline<br />

side.<br />

The soil in the Chandra valley is loam to sandy loam with gravel. Its depth varies<br />

inversely with slope. Generally on ridges, spurs, precipitous slopes and southern<br />

aspects soil tends to be shallow and dry with numerous outcrops <strong>of</strong> bare rocks or its<br />

strew with boulders. In the vicinity <strong>of</strong> villages and nearby areas, denuded slopes are<br />

subjected to year round concentrated grazing leading to poor soil. On northern<br />

aspects, in folds and hollows as also on easier slopes the soil is fairly deep and<br />

fertile for tree growth.<br />

9.3 B.2 Ecological Resource<br />

9.3.1 B.2.1 Forests<br />

The area is totally devoid <strong>of</strong> any vegetation except for a small patch <strong>of</strong> Birch forerst<br />

on the left bank. The reason for absence <strong>of</strong> vegetation is high altitude, rocky<br />

mountains and very cold climate. However some plantation <strong>of</strong> Broad leafed species<br />

has been raised.<br />

9.3.2 B.2.2 Flora and Fauna<br />

9.3.3 B.2.2.1 Flora


The only Trees species found in the area is Birch- Betula utilis.<br />

9.3.4 B.2.2.2 Medicinal plants<br />

Important Medicinal Plants found in the area are:<br />

S.N. Common Name Botanical Name<br />

1 Patish Aconitum heterophyllum<br />

2 Mitha Telia Aconitum violaceum<br />

3 Gandha Artemisia maritima<br />

4 Karoo Picorhiza kurroo<br />

5 Ban Kakri Podophyllum hexandrum<br />

6 Dhup Jurinea macrocephala<br />

7 Shingli Mingli Dioscorea deltoides<br />

8 Patishan roots Heracleum candicans spp.<br />

9 Chora Angelica glauca<br />

9.3.5 B.2.3 Fauna:<br />

No mammal, Bird or Fish worth its name is found in this area.<br />

9.4 C. Baseline Environmental status<br />

9.4.1 C.1 Climate and temperature<br />

The high mountains <strong>of</strong> Central Himalaya act as a barrier and block the rain bearing<br />

winds from the south and as such, receive very little or no rain during the whole<br />

year. However, during winters, which usually starts from the end <strong>of</strong> September in<br />

most <strong>of</strong> the areas receives snowfall and this continues even up to May. Summers<br />

are brief while winters are quite long.<br />

9.4.2 C.1.1 Temperature, rainfall and snowfall data <strong>of</strong> Patseo (adjoining Lahaul<br />

Valley)<br />

Year Month Temperature o C Snow Fall-cm Rain Fall-mm<br />

Max Min<br />

1983 Nov 1.14 -4.54 0 0<br />

Dec -0.22 -5.76 1.25 0<br />

Jan -1.86 -8.76 4.57 0<br />

1984 Feb -2.21 -8.15 4.37 0<br />

Mar 2.83 -5.44 7.07 0<br />

April 3.20 -3.62 5.28 0<br />

May 5.22 -1.07 0 0.75<br />

Nov 1.59 0.389 1.5 0


1985<br />

1986<br />

1987<br />

1988<br />

1989<br />

1992<br />

1993<br />

1994<br />

Dec -1.54 -5.65 14.70 0<br />

Jan<br />

-3.41 -8.96 6.74 0<br />

Feb -1.41 -9.37 4.28 0<br />

March 1.00 -4.63 6 0<br />

April 2.96 -2.94 11.08 0<br />

May 4.77 -0.99 15.5 0<br />

Nov 1.55 -3.59 0 0<br />

Dec -0.04 -5.25 5.44 0<br />

Jan -1.81 -8.58 1.5 0<br />

Feb -1.48 -8.30 6.3 0<br />

March -0.58 -6.78 6.91 0<br />

April 2.35 -4.44 7.67 0<br />

May 3.93 -1.87 3.67 0<br />

Nov 1.70 -4.08 11.37 0<br />

Dec -2.09 -8.06 12.45 0<br />

Jan -1.93 -9.06 8.6 0<br />

Feb -1.33 -7.67 6.86 0<br />

March 1.05 -6.36 6.7 0<br />

April 2.33 -4.15 19.46 0<br />

May 2.02 -4.32 0 0<br />

Dec 1.60 -4.63 5 0<br />

Jan -2.09 -6.96 4.57 0<br />

Feb -0.96 -6.89 8.42 0<br />

March -0.02 -6.91 13.96 0<br />

April 2.87 -3.29 0<br />

Nov 1.56 -3.59 3.69 0<br />

Dec 0.24 5.40 5.72 0<br />

Jan -1.74 -7.99 8.29 0<br />

Feb -1.88 -7.28 5.30 0<br />

march 1.31 -5.51 5.13 0<br />

April 2.07 -4.38 4 0<br />

Nov 3.15 -3.82 3.40 0<br />

Dec 0.35 -6.53 3.67 0<br />

Jan -2.44 -8.61 9.31 0<br />

Feb 0.14 -5.96 7.64 0<br />

march 0.22 -6.90 20.78 0<br />

April 3.90 -4.42 10 0<br />

Nov 2.50 -4.04 6.5 0<br />

Dec 0.77 -7.06 0 0<br />

Jan -1.72 -8.42 9.62 0<br />

Feb -0.84 -10.26 7.45 0<br />

March 2.83 -5.96 5.22 0<br />

April 3.32 -4.26 8.44 0


1995<br />

1996<br />

1999<br />

2000<br />

May 5.94 -1.40 9.16 0.6<br />

Nov 2.89 -4.07 0 0<br />

Dec -0.84 -6.07 7.35 0<br />

Jan -2.59 -10.72 5.67 0<br />

Feb -1.12 -7.32 5.89 0<br />

March 0.90 -6.72 5.90 0<br />

April 2.66 -3.58 8.87 0<br />

Nov -1.14 -6.59 3.00 0<br />

Dec -10.6 -18.7 5.31 0<br />

Jan -1.74 -8.04 13.36 0<br />

Feb 1.30 -7.75 15.68 0<br />

March 1.55 -5.60 9.56 0<br />

April 2.78 -3.82 9 0<br />

Nov 2.31 -4.99 4 0<br />

Dec 1.76 -6.44 1 0<br />

Jan -0.07 -7.99 0 0<br />

Feb 0.18 -7.87 0 0<br />

March 1.71 -8.95 5.80 0<br />

April 4.14 -2.24 2.17 0<br />

May 8.14 0.74 0 0<br />

Air, Water, Soil and Sound data will be collected at the time <strong>of</strong> doing detailed EIA.<br />

Since this is pre feasibility report, this has not been done at this stage.<br />

9.5 D. ENVIRONMENT IMPACT ASSESSMENT AND EVALUATION<br />

9.5.1 D.1 Impact Identification<br />

Environmental impacts both direct and indirect on various environmental attributes<br />

due to Chhatru Hydropower <strong>project</strong> in the surrounding environment, during<br />

construction & operational Phase are discussed.<br />

9.5.2 D.1.1 Impact identification during construction phase<br />

The impacts due to the construction <strong>of</strong> Chhatru HEP and power house installation<br />

commence from the exploration activities, construction <strong>of</strong> barrage, tunnels and<br />

approach roads, etc., may continue up to generation <strong>of</strong> hydel power, with the nature<br />

and extent <strong>of</strong> impacts varying throughout the stage <strong>of</strong> <strong>project</strong> development.<br />

Activities like site preparation, approach roads, excavation, drilling, blasting,<br />

foundations, tunneling, deployment <strong>of</strong> machinery, erection, transportation ,dumping<br />

are taken up during construction phase. The likely impacts on the environment due<br />

to these activities are listed in table.<br />

Tunneling and foundation works will involve land excavation, filling and concrete<br />

works effecting environment by noise and dust pollution. Structural, deployment <strong>of</strong>


machinery, approach roads construction and erection work will also result in dust,<br />

noise pollution and vehicular traffic. Material handling and transportation may<br />

significantly increase noise pollution.<br />

The labour for various activities during the construction phase shall be engaged<br />

from the surrounding villages. Some essential services are also required to be<br />

provided. This will have an impact on drinking water supply and sanitary facilities.<br />

Economy <strong>of</strong> the nearby area will be improved due to increased job opportunities<br />

with corresponding increase in income. Other associated business activities like<br />

transport, hotels, consumer goods etc., will also be benefited.<br />

The major environmental parameters likely to be effected during construction phase<br />

are noise, dust pollution and sanitation. Water spraying during high dust will<br />

minimise the dust level to some extent. A proper temporary housing with water<br />

supply and sanitation for workers should be planned. The effect due to construction<br />

phase is however, <strong>of</strong> temporary in nature and has no permanent effect on<br />

environment.<br />

Construction Phase Activity Potential Environmental<br />

Impact<br />

Site work / providing other<br />

facilities.<br />

Construction <strong>of</strong> approach<br />

roads, tunneling works and<br />

construction <strong>of</strong> under<br />

ground <strong>Power</strong> Station<br />

Clearing and grading Negligible<br />

Temporary facilities, such<br />

as, sheds approach roads,<br />

sanitary facilities.<br />

Earth work comprising <strong>of</strong><br />

excavation and trenches.<br />

Dust emission and change<br />

in traffic intensity.<br />

Soil erosion, run <strong>of</strong>f,<br />

increase in traffic, Dust<br />

emission<br />

Dust, visual and noise<br />

pollution<br />

Dust and noise pollution<br />

Foundation work, piling and<br />

construction <strong>of</strong> check dams.<br />

Construction <strong>of</strong> permanent<br />

structures like roads, colony<br />

etc<br />

Mechanical erection and Dust, noise and visual<br />

utility systems.<br />

impact.<br />

Excavation Dust, soil erosion,<br />

wastewater generation and<br />

noise<br />

Drilling and blasting Dust, noise and health<br />

hazards<br />

Dumping Dust, noise and visual<br />

Transportation Dust, noise and visual<br />

9.5.3 D.1.2 Impact identification during operational phase


There would be little environmental and ecological changes during the operational<br />

phase. The main activities that may cause environmental impact on the surrounding<br />

environment during <strong>project</strong> completion and after during operation are:<br />

i. Transportation <strong>of</strong> excessive solid waste material (muck)<br />

ii. Dumping <strong>of</strong> solid waste material<br />

iii. Removal <strong>of</strong> temporary facilities, cleaning etc.<br />

9.5.4 D.2 Prediction <strong>of</strong> Impacts<br />

The impact during the construction <strong>of</strong> Chhatru HEP on environment (air, water,<br />

noise, land etc. are predicted in this section. The construction activity may cause<br />

some adverse impacts on the surrounding environment unless proper environmental<br />

management plan is adopted.<br />

9.5.5 D.2.1 Impact on air environment.<br />

Considerable amount <strong>of</strong> air pollution will be caused during different stages <strong>of</strong><br />

construction <strong>of</strong> tunnels, barrage, roads and other operations such as excavation,<br />

drilling, blasting, loading and transportation <strong>of</strong> material. Suspended Particulate<br />

Matter (SPM) is the main pollutant during construction. Most <strong>of</strong> the dust arises<br />

from drilling, blasting, excavation, crushing and transportation operations. Large<br />

quantities <strong>of</strong> dust become wind borne and are carried away from overburden<br />

dumps. The fugitive dust released during the construction activities may cause<br />

immediate effect on the construction workers who are directly exposed to the<br />

fugitive dust. Vegetation will also be adversely affected as deposition <strong>of</strong> dust on the<br />

leaves will choke the photosynthesis activity, which, in turn, will have adverse<br />

effect on the health <strong>of</strong> the plants. However, the dust does not travel to longer<br />

distance because the <strong>project</strong> site is located in between hills and V-shaped valleys.<br />

9.5.6 D.2.2 Impact on noise environment<br />

The noise will be generated at the time <strong>of</strong> construction <strong>of</strong> barrage, powerhouse,<br />

tunnel boring machine operations, pumps, drilling machines, dumpers, etc.<br />

Continuous exposure <strong>of</strong> workers to high level <strong>of</strong> noise may result in annoyance,<br />

fatigue, and may cause temporary shift <strong>of</strong> threshold limit <strong>of</strong> hearing and even<br />

permanent loss <strong>of</strong> hearing. During operational phase, noise level will be increased<br />

due trouncing machinery and vehicular movement in the area. However, these<br />

impacts are only localized.<br />

9.5.7 D.2.3 Impact on water environment.<br />

During the construction <strong>of</strong> barrage, tunnel, and power house surface water (river<br />

water) may get polluted due to the generation <strong>of</strong> large quantities <strong>of</strong> suspended


particulate matter at the time <strong>of</strong> transportation <strong>of</strong> muck and waste water (sewage)<br />

coming from temporary arrangements like <strong>of</strong>fices, labour camp sheds, etc.,<br />

9.5.8 D.2.4 Impacts on Flora and Fauna<br />

Since there is no vegetation worth its name nor any wild life, there will not be any<br />

adverse impact. There is no Wild Life Sanctuary or National Park in the Project<br />

area.<br />

However, Compensatory afforestation will be done as per the general stipulations<br />

given by the Govt. <strong>of</strong> India MOEF at the time <strong>of</strong> sanction <strong>of</strong> diversion <strong>of</strong><br />

Forestland<br />

9.6 E. R & R Aspects<br />

Since the Project is a run-<strong>of</strong>-the-river type and there is no storage, therefore, there is<br />

no submergence. Hence, no dwellings, houses or hamlets will be submerged. So,<br />

there is no displacement and resettlement is involved.<br />

9.7 F. ENVIRONMENTAL MANAGEMENT PLAN (MITIGATION<br />

MEASURES)<br />

Environmental Management Plan (EMP) aims at the preservation <strong>of</strong> ecological<br />

system by considering certain mitigating measures at the proposed site. The<br />

mitigation measures are used to minimize or prevent adverse impacts on<br />

environment due to the proposed development activity. Some <strong>of</strong> the major criteria<br />

governing the environmental measures will be adopted, and the same is described in<br />

the following paragraphs.<br />

9.7.1 F.1 Environmental Management<br />

The EMP is required to ensure sustainable development in the area <strong>of</strong> 10 Km radius<br />

<strong>of</strong> the proposed Chhatru HEP site.<br />

It is expected that the study area shall not be affected much with the proposed<br />

activity and likely to get new economic fillip due to hydel power generation, not<br />

only for the study area but also for the region as a whole.<br />

The majority <strong>of</strong> the environmental impact pertains to the construction phase. It is<br />

planned to take corrective measures to ensure that these effects are kept to bare<br />

minimum. The EMP will therefore, be initiated during planning stage itself.<br />

Catchment Area Treatment Plan, which will be prepared at a later stage, will form<br />

part <strong>of</strong> the Environmental Management Plan. However, there is not much scope <strong>of</strong><br />

plantation in the area.


9.7.2 F.1.1 Environmental management at construction stage<br />

9.7.3 F.1.1.1 Site preparation<br />

Dust emission (fugitive) and solid waste will be generated during initial site<br />

preparation activity and there will be slight increase in the noise levels around the<br />

site. The environmental impacts during the clearing or clearing for site preparation<br />

will be temporary, localised and negligible. Water sprays at appropriate location<br />

will be provided for dust suppression, hence reducing the impacts. Solid waste will<br />

be disposed <strong>of</strong>f along with the muck at the designated sites.<br />

9.7.4 F.1.1.2 Construction<br />

9.7.4.1 Air environment<br />

As discussed earlier, construction <strong>of</strong> Chhatru HEP and powerhouse activities will<br />

generate large quantities <strong>of</strong> dust during drilling, blasting, loading and transportation<br />

operations. The following measures are required be taken to mitigate the fugitive<br />

dust from different operations.<br />

To avoid the dust generation from the drilling operations, wet-drilling methods will<br />

be adopted.<br />

Ceasing dust -generating activities during high winds<br />

Covering <strong>of</strong> vehicles carrying solid waste (muck).<br />

Watering <strong>of</strong> haul roads and other roads at regular intervals<br />

Plantation near muck disposal places and dumping yards.<br />

9.7.4.2 Noise environment<br />

The major noise generating sources from the proposed activity are working<br />

machinery, blasting and movement <strong>of</strong> vehicles. The following control measures are<br />

to be undertaken to bring down the noise levels.<br />

Traffic (vehicular movement) to be managed to produce a smooth flow instead <strong>of</strong> a<br />

noisier stop -and start flow.<br />

Ensuring timely preventive maintenance <strong>of</strong> the equipment involved. Since a well<br />

maintained equipment is generally quieter than poorly maintained equipment.<br />

Ensuring usage <strong>of</strong> personal protective devices i.e., earmuffs and earplugs by<br />

workers, working in high noise activity centers.


Plantation in the vicinity <strong>of</strong> the construction area will further reduce the noise<br />

levels.<br />

9.7.4.3 Water environment<br />

During construction phase the wastewater (sewage) coming from temporary<br />

arrangements like <strong>of</strong>fices, labour camp sheds, canteens etc., and impact due to soil<br />

erosion during monsoon period may cause surface water pollution.<br />

Some <strong>of</strong> the control measures adopted for controlling water pollution are as<br />

follows:<br />

Establishing septic tanks followed by soak pits to treat the domestic waste water<br />

generated from the <strong>of</strong>fices, canteens, labour camp sheds.<br />

Construction <strong>of</strong> Check dams /rock fill dams, wherever necessary to reduce siltation<br />

and suspended solids.<br />

9.7.4.4 Green belt development (Compensatory Afforestation)<br />

Afforestation is proposed to be done in open areas with moderate slope. This has to<br />

be supplemented with engineering/vegetative works like gully plugging and check<br />

dams etc where ever required. There is very limited scope <strong>of</strong> plantation. Where ever<br />

plantation is undertaken it should be closed to grazing, lopping etc. For proper<br />

protection, it is necessary that the area is fenced and the fence is maintained<br />

properly. Plants need to be protected till they attain a height, which is above grazing<br />

level.<br />

9.7.4.5 DISPOSAL OF MUCK<br />

By constructing a 6.5 km long tunnel, the quantity <strong>of</strong> muck to be generated is<br />

estimated to be more than 0.50 lac M 3 . After applying the swell factor, the volume<br />

to be disposed <strong>of</strong>f will be about 0.75 lac M 3 . It is expected that 25-35 % <strong>of</strong> this will<br />

be used for making aggregates. The rest will require to be disposed <strong>of</strong>f in a planned<br />

manner.<br />

This is the most important aspect to be dealt with. It is proposed that at different<br />

locations dumping sites will be identified at suitable places. Retaining walls will be<br />

constructed. After the filling is done, rehabilitation <strong>of</strong> this site will be done to<br />

ensure that neither it flows in to the water stream nor it poses any other<br />

environmental threat. Plantation, wherever possible, will also be done on these sites<br />

so that these get stabilised over a period <strong>of</strong> time and do not pose any environmental<br />

problem.


Annexure-IX-1<br />

REPORT OF SATELLITE DATA ANALYSIS<br />

SATELLITE REMOTE SENSING BASED INPUTS FOR<br />

INITIAL ENVIRONMENTAL STUDIES<br />

IN<br />

RESPECT OF 6 PROPOSED HYDRO-POWER SITES<br />

IN CHENAB BASIN IN HIMACHAL PRADESH<br />

NAME OF THE HYDRO-POWER SITE : CHHATRU<br />

1. Study Background<br />

Central Electricity Authority (CEA) under <strong>Ministry</strong> <strong>of</strong> power, Govt. <strong>of</strong> India<br />

has earlier identified 399 potential <strong>hydro</strong><strong>electric</strong> sites in the country with an<br />

installed capacity <strong>of</strong> 1,07,000 Megawatt ( MW). With a view to preparing<br />

an action plan to develop this <strong>hydro</strong><strong>electric</strong> potential and prioritizing the<br />

implementation <strong>of</strong> <strong>hydro</strong>-<strong>electric</strong> <strong>project</strong>s, a Ranking study was taken up by<br />

the CEA in 2001. This Ranking study identified 162 most potential sites<br />

with a total installed capacity <strong>of</strong> 50,560 MW for development.<br />

Preparation <strong>of</strong> Pre-Feasibility Reports (PFR) <strong>of</strong> these 162 sites has been<br />

initiated by the CEA in 2002 with works entrusted to a number <strong>of</strong><br />

Consultants, namely, National Hydro<strong>electric</strong> <strong>Power</strong> Corporation (NHPC),<br />

North Eastern Electric <strong>Power</strong> Corporation (NEEPCO), Water and <strong>Power</strong><br />

Consultancy Services India Limited (WAPCOS), Satluj Jal Vidyut Nigam<br />

Limited (SVJNL), Himachal Pradesh State Electricity Board (HPSEB),<br />

Uttaranchal Jal Vidyut Nigam Limited (UJVNL) and Kerala <strong>Power</strong><br />

Corporation Limited (KPCL) with time target <strong>of</strong> completion <strong>of</strong> the whole<br />

exercise by September 2003. To oversee the progress <strong>of</strong> the PFRs<br />

preparation in time and with full cooperation <strong>of</strong> the Central Government<br />

agencies, a Central Coordination Committee consisting <strong>of</strong> Central<br />

Electricity Authority (CEA), Central Water Commission (CWC), India<br />

Meteorological Department (IMD), <strong>Ministry</strong> <strong>of</strong> Environment & Forest,<br />

Survey <strong>of</strong> India, Geological Survey <strong>of</strong> India (GSI) and National Remote


Sensing Agency (NRSA) was constituted by the CEA with Member<br />

(Hydro-power) as its representatives <strong>of</strong> the Consultants to take stock <strong>of</strong> the<br />

completion <strong>of</strong> the studies. One <strong>of</strong> the mandates <strong>of</strong> PFR preparation is<br />

“Initial Environmental Study” with respect to each <strong>of</strong> the 162 proposed sites<br />

using satellite remote sensing data.<br />

As is well known in India and elsewhere in the world, space technology<br />

plays a very important role in terrain mapping and scientific assessment <strong>of</strong><br />

the ground condition at speed, and is ideally suitable for inaccessible<br />

mountainous regions where majority <strong>of</strong> these <strong>hydro</strong><strong>electric</strong> dam/diversion<br />

site are located. Computer processing <strong>of</strong> satellite digital data <strong>of</strong> the dam/<br />

diversion site and their immediate environ provides wealth <strong>of</strong> information<br />

for preparation <strong>of</strong> the Pre-Feasibility Reports. The Potential <strong>of</strong> this<br />

technology was amply demonstrated in the preliminary ranking study <strong>of</strong> the<br />

81 proposed <strong>hydro</strong>-<strong>electric</strong> sites in Indus Basin completed by NRSA in<br />

October 2001 on behalf <strong>of</strong> CEA. In view <strong>of</strong> this, NRSA has been<br />

approached by a number <strong>of</strong> consultants, namely, NHPC and HPSEB to take<br />

up Initial Environmental Studies in respect <strong>of</strong> 37 proposed <strong>hydro</strong>- power<br />

sites located in the States <strong>of</strong> Arunachal Pradesh., Himachal Pradesh, Jammu<br />

& Kashmir and Madhya Pradesh using most recent satellite remote sensing<br />

data.<br />

Himachal Pradesh State Electricity Board (HPSEB), Sundernagar has<br />

approached NRSA for satellite remote sensing based inputs for initial<br />

environmental study <strong>of</strong> 6 <strong>hydro</strong>- power sites located in Chenab Basin in<br />

Himachal Pradesh.<br />

This Report deals with Chhatru <strong>hydro</strong>-power site.<br />

2. Objective<br />

Principal objective <strong>of</strong> the satellite based study is to acquire Indian Remote<br />

Sensing satellites (IRS IC/1 D ) LISS-III and PAN sensor digital data <strong>of</strong><br />

the <strong>hydro</strong>- power sites and to make quick analysis <strong>of</strong> these data in terms <strong>of</strong>


estimation <strong>of</strong> the submergence area at proposed Full Reservoir Level (FRL)<br />

and mapping <strong>of</strong> land use-land cover information within and in immediate<br />

surrounding <strong>of</strong> the proposed submergence area as inputs for Initial<br />

Environmental Study (IES) <strong>of</strong> the Pre-Feasibility Report.<br />

The specific objectives and scope <strong>of</strong> the study are :<br />

• To estimate the area <strong>of</strong> submergence at proposed FRL <strong>of</strong> the proposed<br />

<strong>hydro</strong>- power sites.<br />

• To analyse the satellite data for identifying broad land use-land cover<br />

categories like agricultural land, forest land, barren land, scrub land,<br />

water bodies, settlements, infrastructural features (roads and bridges)<br />

and to estimate the area under each <strong>of</strong> the categories within and in<br />

immediate surrounding <strong>of</strong> the proposed submergence area at FRL.<br />

• To prepare land use- land cover map at 1:50,000 scale and/or 1:25,000<br />

scale <strong>of</strong> the submergence area and its immediate surrounding for each<br />

<strong>hydro</strong>-power site.<br />

3. Salient Features <strong>of</strong> the Chhatru Hydro-<strong>Power</strong> Site<br />

Proposed <strong>hydro</strong>-power site is located at Chhatru in Chenab River Basin<br />

in Himachal Pradesh falling in Survey <strong>of</strong> India topo sheeets No. 52 H/3<br />

& 52 H/7. The proposed <strong>project</strong> scheme at Chhatru envisages<br />

construction <strong>of</strong> a Dam on Chandra river and a power house. The Head<br />

Race Tunnel from the dam to the power house is proposed to be 8.5 km<br />

in length. The river water will be stored in the reservoir which will be<br />

diverted through the Head-Race Tunnel to the <strong>Power</strong> House for <strong>hydro</strong>power<br />

generation. The geographic location <strong>of</strong> Dam and <strong>Power</strong> House<br />

for this <strong>hydro</strong>-power site given below:


Dam <strong>Power</strong> House<br />

Latitude : 32°18’08” N 32°20’ 9” N<br />

Longitude : 77° 24’ 41” E 77° 20’ 51” E<br />

4. Satellite data Used<br />

Indian Remote Sensing Satellite, IRS-ID LISS and PAN sensors data <strong>of</strong> 21 st<br />

September,2001 covering the study site were procured from the NRSA<br />

Data Centre (NDC) after intensive browsing <strong>of</strong> the available satellite data<br />

for cloud-free and radiometric suitability, IRS-Id covers the study site by<br />

satellite geo- reference number Path 95 and Row 48. These data are<br />

geometrically and radiometrically corrected digital data products which can<br />

be used readily in Window based image analysis platform.<br />

5. Brief Methodology <strong>of</strong> Satellite Data Analysis<br />

Image processing and analysis was done using ERDAS Imagine image<br />

analysis s<strong>of</strong>tware in Windows platform. Satellite data <strong>of</strong> IRS ID LISS III<br />

sensor provides 23.5 m spatial resolution and PAN sensor provides 5.8 m<br />

spatial resolution. The two sensor data were geocoded and digitally merged<br />

using IHS transformation technique. Baseline information layers (like<br />

rivers/streams) and infrastructural features (like roads and bridges),<br />

settlements/ villages were initially interpreted on the digital image scene.<br />

Subsequently, image classification technique was performed to obtain the<br />

land use-land cover categories <strong>of</strong> the study area.<br />

Output maps were composed in the image processing system which provide<br />

the land use/land cover information alongwith other interpreted information<br />

such as roads, settlements etc. , within the 7 Km. radius from the dam site.<br />

The Full Reservoir Level (FRL) boundary, provided by the HPSEB,<br />

Sundernagar was superimposed on the satellite data as well as on the land<br />

use- land cover map. Area statistics <strong>of</strong> different land use-land cover


categories were generated within the submergence area at FRL and within<br />

the 7 Km. radius circle from the dam site.<br />

6. Outputs provided<br />

Based on the analysis <strong>of</strong> satellite data and other available ancillary<br />

information, the following outputs were generated:<br />

• Map 1 (a) Shows IRS 1 D PAN + LISS III merged satellite<br />

image <strong>of</strong> 21 st September, 2001 on 1:50,000 scale covering 7 km.<br />

radius from the dam site overlaid with FRL, location <strong>of</strong> dam site and<br />

power house.<br />

• Map 1 (b) Shows satellite derived landuse- landcover map on<br />

1:50,000 scale covering 7 km radius from the dam site overlaid<br />

with FRL, location <strong>of</strong> dam site and power house. Land use/land<br />

cover map shows the following categories: Forest (High and<br />

Medium and low Dense Forest), Agricultural Land, Open Scrub,<br />

Barren and Rock Outcrop, Snow, River course/ Dry River Bed.<br />

• Map 1 (c) Show the land use – land cover classes and their<br />

corresponding area statistics in hectares within the submergence area<br />

on 1:25000 scale overlaid with FRL, location <strong>of</strong> dam site and power<br />

house.<br />

• Map 1 (d) Shows the location <strong>of</strong> the National parks/Wildlife<br />

Sanctuaries vis-à-vis the location <strong>of</strong> the dam/<strong>Power</strong> House and 7 km<br />

radius area around the dam site.<br />

• Table. 1 Landuse-landcover Information within the<br />

Submergence Area.


S. No. Landuse-land cover Area under % <strong>of</strong> the total<br />

category<br />

submergence(Ha) submergence area<br />

1. High Dense Forest Nil Nil<br />

2. Medium Dense<br />

Forest<br />

Nil Nil<br />

3. Low Dense forest Nil Nil<br />

4. Open scrub Nil Nil<br />

5. Barren/Rock<br />

Outcrop<br />

9.25 55.22<br />

6. Snow Nil Nil<br />

7. Agriculture land Nil Nil<br />

8. Human Settlement Nil Nil<br />

9. River Course<br />

including dry river<br />

bed<br />

7.50 44.78<br />

Total 16.75 100<br />

• Table. 2 Landuse-landcover Information within the 7 Km<br />

Radius from the Dam site at Chhatru<br />

S. No. Landuse-land cover Area under % <strong>of</strong> the total<br />

category<br />

submergence(Ha) submergence area<br />

1. High Dense Forest - -<br />

2. Medium Dense<br />

Forest<br />

98 0.64<br />

3. Low Dense forest 42 0.27<br />

4. Open scrub 4270 27.74<br />

5. Barren/Rock<br />

Outcrop<br />

8665 56.29<br />

6. Snow 2210 14.36<br />

7. Agriculture land 108 0.70<br />

Total Area 15393 100.00


7. Critical Analysis <strong>of</strong> Satellite based Initial Environmental Study<br />

• Total area under submergence at proposed FRL is estimated to be<br />

16.75 ha (Table 1).<br />

• It is observed that the landuse -landcover is mostly dominated by<br />

barren /rock outcrop which is 9.25 ha (55.22% <strong>of</strong> the submergence<br />

area). It is followed by open scrub, which is present to the extent <strong>of</strong><br />

7.5 ha (44.78% <strong>of</strong> the submergence area at the proposed FRL).<br />

• There is no agricultural area present within the proposed<br />

submergence area which is positive sign to develop the<br />

proposed <strong>hydro</strong>power site.<br />

• There are no surface water bodies other than the river course.<br />

The area under river course including dry river bed is<br />

estimated to be 7.50 ha.<br />

• In the absence <strong>of</strong> available information from other sources<br />

about the existence and spatial extent <strong>of</strong> national parks and<br />

Wildlife sanctuaries, best efforts were made to collect<br />

information from the Internet. The information available in<br />

website <strong>of</strong> United Nations Environment programme World<br />

Conservation Monitoring Center (http;//www.unep-<br />

wcmc.org) regarding Himachal Pradesh State and its<br />

National Parks/Wild Sanctuaries, were browsed through.<br />

The information at hand is made use in preparing map 1 (d)<br />

which depicts the latitude and longitude <strong>of</strong> dam site and the<br />

sanctuaries/national parks. 7 km. radius circle around the<br />

dam is plotted and the radial distance to the various national<br />

park/sanctuary were estimated around the nearest national<br />

park/sanctuary which are <strong>of</strong> significant only are measured on<br />

the map 1 (d). The following points are observed from the<br />

map 1(d).


- The nearest sanctuaries are Mani, Kais and Kanwar which are about<br />

at distance <strong>of</strong> 28 Km, 38 Km. and 45 Km. respectively whose sizes<br />

interms <strong>of</strong> aerial extent are in the figure 1(d).<br />

- Since 7 Km. radius around the dam site was considered as the area <strong>of</strong><br />

study, efforts were made to check whether the geo-coordinates <strong>of</strong><br />

this Wildlife Sanctuary is falling within the area <strong>of</strong> study. The map<br />

No. 1(d) explains the location <strong>of</strong> the sanctuary vis-à-vis the dam site<br />

and the power house.<br />

8. Conclusion & Recommendation<br />

1. Satellite based study has provided insight into the landuselandcover<br />

pattern and their spatial extent within the<br />

submergence area at FRL and within the 7 Km radius<br />

vicinity <strong>of</strong> the proposed dam site. Such detail information on<br />

a scale <strong>of</strong> 1:25,000 are not available from any other sources<br />

at present.<br />

2. There is no agricultural land within submergence area. The<br />

environmental cost on this score is therefore nil.<br />

3. Settlements in the submergence area looks to be Nil. This has<br />

to be verified on the ground for detailed information.<br />

4. The forest vegetation in the submergence area is nil, hence it<br />

is a positive thing in respect <strong>of</strong> environmental impact due to<br />

the development <strong>of</strong> proposed <strong>hydro</strong> power site.<br />

5. The submergence area landuse-landcover mainly comprises<br />

<strong>of</strong> barren (denuded hills).<br />

6. The nearest sanctuaries are Mani, Kais and Kanawar which<br />

are about at distance <strong>of</strong> 28 Km. 38 Km and 45 Km<br />

respectively. The respective sizes <strong>of</strong> these sanctuaries are<br />

3180 ha, 1419 ha and 6070 ha. Hence, in view <strong>of</strong> the small<br />

sizes <strong>of</strong> these sanctuaries, development <strong>of</strong> this <strong>hydro</strong> power<br />

site may not have any significant impact on these sanctuaries


since the fetch distance <strong>of</strong> the reservoir submergence will be<br />

around 1.3 km. only.


PARA DESCRIPTION PAGE<br />

9.0 DESCRIPTION OF THE PROJECT IX-1<br />

9.1 Description <strong>of</strong> environment IX-1 TO IX-2<br />

9.2 Ecological resource IX-2 TO IX-3<br />

9.3 Baseline Environmental status IX-3 TO IX-6<br />

9.4 Environment impact assessment and evaluation IX-6 TO IX-10<br />

9.5 R&R aspects IX-10<br />

9.6 Environmental management plan (mitigation<br />

measures)<br />

9.7 INITIAL ENVIRONMENTAL STUDIES IX-13<br />

IX-10 TO IX-13<br />

ANNEXURE-IX-1 REPORT OF SATELLITE DATA ANALYSIS IX-14 TO IX<br />

iRS ID PAN + LISS III MERGED SATELLITE<br />

IMAGE OF 21 ST SEPTEMBER,2001.<br />

satellite derived land use- LAND COVER MAP OF<br />

SURROUNDINGS OF PROPOSED HYDRO<br />

POWER SITE AT KHOKSAR, HIMACHAL<br />

PRADESH.<br />

LAND USE-land cover map <strong>of</strong> immediate<br />

surroundings upstream <strong>of</strong> proposed dam site at<br />

khoksar.<br />

MAP OF NATIONAL PARKS/SANCTUARIES<br />

AND THE LOCATION OF KHOKSAR HYDRO<br />

POWER SITE AND 7 KM. RADIUS CIRCLE FROM<br />

THE DAM SITE.<br />

MAP- 1 (a)<br />

MAP- 1 (b)<br />

MAP- 1 (c)<br />

MAP- 1 (d)


PARA DESCRIPTION PAGE<br />

10.0 IDENTIFICATION OF THE BROAD INFRASTRUCTURAL<br />

REQUIREMENT FOR IMPLEMENTATION OF PROJECT<br />

10.1 ROADS X-1<br />

10.1.1 GENERAL X-1<br />

10.1.2 PROJECT ROADS X-2<br />

10.2 BUILDINGS X-2<br />

X-1


10.2.1 COLONY AT SUNDERNAGAR X-2<br />

10.2.2 COLONY AT VILLAGE CHHATRU X-3<br />

10.2.3 OFFICE COMPLEX FOR OUTLET SIDE WORKS X-3<br />

10.2.4 SCHOOL & HOSPITAL X-4<br />

10.2.5 FIELD HOSTEL AND REST HOUSE X-4<br />

10.3 DUMP AREA X-4<br />

10.4 JOB FACILITIES X-4<br />

10.5 QUARRY SITES X-4<br />

10.6 TELEPHONES X-5<br />

10.6.1 INTERNAL TELEPHONE SYSTEM X-5<br />

10.6.2 EXTERNAL TELEPHONE SYSTEM X-5<br />

10.7 WIRELESS SYSTEM X-5<br />

10.8 PLANT AREA X-5 TO<br />

X-6<br />

10.9 FIELD WORKSHOP X-6<br />

10.10 CONSTRUCTION POWER X-6<br />

10.11 SAFETY X-6 TO<br />

X-7


CHAPTER – X<br />

INFRASTRUCTURE<br />

10.0 IDENTIFICATION OF THE BROAD INFRASTRUCTURAL<br />

REQUIREMENT FOR IMPLEMENTATION OF THE PROJECT<br />

10.1 ROADS<br />

Chhatru Hydel Project is situated in Lahaul & Spiti Distt. <strong>of</strong> Himachal<br />

Pradesh. The barrage site on Chandra river about 5 km. u/s <strong>of</strong> Chhatru<br />

village is located about 407 Kms. from Chandigarh, which is approachable<br />

through an all weather road from Chandigarh to Manali(315 km)by NH-21,<br />

from Manali to Gramphu (Shiprang) motorable road (June to Oct.),70 km.<br />

and then to diversion site motorable raod (July to Sept.) 22 km. along<br />

Manali-Leh road. <strong>Power</strong> House site is only approachable by constructing a<br />

link road about 7 km. from suspension bridge on Manali-Leh road. The<br />

power house is about 8.50 km. d/s <strong>of</strong> proposed diversion site.<br />

Adequate provision for residential and non-residential accommodations with<br />

necessary amenities has been made for construction and design staff<br />

proposed for the <strong>project</strong>. Workshop, stores, POL pumps, explosive<br />

magazine and other infrastructural facilities have also been provided in the<br />

estimate. Necessary provision for telecommunication, medical , educational<br />

facilities and safety /security measures have also been made in the report.<br />

All infrastructure facilities proposed ro this <strong>project</strong> has been shown in Drg.<br />

No. Chhatru- FR-8.


10.1.1 GENERAL<br />

A total <strong>of</strong> about 2 km. length <strong>of</strong> (5/7m. wide) road shall be needed to<br />

connect the existing motorable road with the various <strong>project</strong> components.<br />

The widening <strong>of</strong> existing roads in the total length <strong>of</strong> 8.50 kms. has been<br />

proposed.<br />

10.1.2 PROJECT ROADS<br />

Approach road 5/7 m. wide, 4.9 Km. long will connect different work sites<br />

<strong>of</strong> the <strong>project</strong> with the existing motorable road.<br />

The following roads have been proposed.<br />

1. C/O proposed road to top <strong>of</strong> surge shaft<br />

and power house<br />

= 10.00 km.<br />

2. C/O proposed road to adit <strong>of</strong> HRT = 4.00 km<br />

3. C/O proposed road from main road to colony,<br />

Dumping areas & quarry site etc. = 6.00 km.<br />

4. Re-aligning <strong>of</strong> existing main road along<br />

proposed reservoir = 2.00 km<br />

Total = 17.00 km.<br />

5. Widening <strong>of</strong> existing motorable road from<br />

Diversion site <strong>of</strong> Khoksar HEP to power house<br />

<strong>of</strong> Chhatru HEP = 17.00 km.<br />

Total = 17.00 km.<br />

6. Provision <strong>of</strong> R..C.C.bridge in place <strong>of</strong><br />

existing suspension bridge = 1No.


10.2 BUILDINGS<br />

It is proposed to construct residential and non-residential colonies for this<br />

<strong>project</strong> at village Baran in private land.<br />

10.2.1 COLONY AT SUNDERNAGAR<br />

A permanent residential/non-residential complex for design organization will be<br />

constructed at Sundernagar. The same can be used for monitoring/planning liaison<br />

purpose after the completion <strong>of</strong> the <strong>project</strong>.<br />

10.2.2 COLONY AT VILLAGE CHHATRY<br />

Residential/non-residential colony for the construction <strong>of</strong> the <strong>project</strong> is<br />

proposed to be constructed at village Chhatru which is about 5 km from barrage<br />

and 3.50 km. from power house. Labour huts , stores and field <strong>of</strong>fices will be<br />

constructed nearby the <strong>project</strong> components on the small terraces available.<br />

10.2.3 OFFICE COMPLEX FOR OUTLET SIDE WORKS<br />

Office complex for the construction <strong>of</strong> power house complex, penstock, surge<br />

shaft and tunnel from outlet end is proposed on the terrace available near the<br />

inlet <strong>of</strong> main access tunnel to power house.<br />

10.2.4 SCHOOL & HOSPITAL


Adequate provision <strong>of</strong> buildings for Hospital, school etc.has been made in the<br />

<strong>project</strong> estimate under Sub-Head K-buildings to cater for construction force.<br />

First aid posts shall be provided at all <strong>project</strong> sites.<br />

10.2.5 FIELD HOSTEL & REST HOUSE<br />

Field hostel is proposed to be constructed in the <strong>project</strong> area near residential<br />

colony.<br />

10.3 DUMP AREA<br />

The muck <strong>of</strong> open & underground excavation shall be dumped in dump areas<br />

located d/s <strong>of</strong> diversion structure and inlet <strong>of</strong> HRT. The dumping station for<br />

power house muck may be proposed at 4.50 km from power house. Dump<br />

areas chosen are located much above the river/nallah banks and are provided<br />

with suitable retaining walls etc. Bull dozers shall be deployed in dump areas<br />

for spreading and compaction <strong>of</strong> dumped material.<br />

10.4 JOB FACILTIES<br />

Flat terraces available near the <strong>project</strong> components wherever possible shall be<br />

utilized for job facilities like stacking <strong>of</strong> construction material, D.G. sets, truck,<br />

trailers, cement carriers, road rollers and site <strong>of</strong>fice stores etc.<br />

10.5 QUARRY SITES<br />

The material in the river bed may be suitable for aggregate. Rock from<br />

different quarries in the vicinity <strong>of</strong> the <strong>project</strong> may also be identified, to assess<br />

their suitability for manufacturing aggregate.


10.6 TELEPHONE<br />

10.6.1 INTERNAL TELEPHONE SYSTEM<br />

It is proposed to have an independent telephone exchange for this <strong>project</strong>. All<br />

important work sites, <strong>of</strong>fices within the <strong>project</strong> area will be connected by<br />

telephones. A 50-lines capacity private automatic exchange (PBX) for the<br />

<strong>project</strong> will be provided .<br />

10.6.2 EXTERNAL TELEPHONE SYSTEM<br />

Telecommunication link between <strong>project</strong> sites and outside places will be<br />

provided by existing communication net work <strong>of</strong> Post & Telegraph<br />

Department connected to the nearest P&T exchange at Manali. This system<br />

would be operated and maintained by P&T Department on rental basis.<br />

<strong>Power</strong> Line communication carrier system is also proposed for the <strong>project</strong>.<br />

10.7 WIRELESS SYSTEM<br />

On the pattern <strong>of</strong> other on going hydel <strong>project</strong>s in H.P., fixed type VHF<br />

Wireless link is proposed to be provided between <strong>project</strong> sites and design <strong>of</strong>fice<br />

at Kullu, which will be further connected to existing wireless system <strong>of</strong> HPSEB<br />

at Shimla.<br />

10.8 PLANT AREAS<br />

Plant area for different sites <strong>of</strong> work have been provided near respective sites.<br />

It is proposed to install a central aggregate crushing, processing and<br />

classification plant near quarry site proposed at 15 miles station which will<br />

fulfill the requirements <strong>of</strong> aggregates for barrage & inlet end works and


powerhouse site to cater for the requirements <strong>of</strong> works <strong>of</strong> HRT from outlet end,<br />

surge shaft, penstock and powerhouse and appurtenant works. An adequate<br />

capacity batching and mixing plant will be installed near barrage to cater the<br />

requirements <strong>of</strong> concrete for all inlet side works including tunnel lining. Other<br />

batching and mixing plants <strong>of</strong> requisite capacity will be provided near power<br />

house site for concreting work in power house complex , pressure shaft, head<br />

race tunnel and surge shaft.<br />

Central compressor houses will be located near tunnel portal to meet up the<br />

requirements <strong>of</strong> the compressed air.<br />

10.9 FIELD WORKSHOP<br />

The workshops/repair shops are proposed to be established near barrage site &<br />

power house site.<br />

10.10 CONSTRUCTION POWER<br />

10.11 SAFETY<br />

Requirement <strong>of</strong> construction power will be met form existing transmission net<br />

work in the area by suitably augmenting the same to meet requirement <strong>of</strong> the<br />

<strong>project</strong> at various sites. Necessary provision for providing power lines and<br />

distribution system has been made in the <strong>project</strong> estimate.<br />

Adequate provision for stand by diesel generating sets has been made in the<br />

<strong>project</strong> estimate to meet up power requirements in the event <strong>of</strong> power failures,<br />

shutdowns / breakdown.<br />

Safety is an essential job requirement for a highly mechanized work set up.<br />

Adequate provision for fire fighting arrangements and security arrangements


has been made in the <strong>project</strong> estimate by way <strong>of</strong> police post/check-post and<br />

check barriers etc.<br />

Adequate safety/preventive measures against accidents are proposed to be taken<br />

in accordance with the following Indian Standard Codes:<br />

IS: 4756 For safety in tunneling work.<br />

IS 3996 For scaffolds and ladders.<br />

(Part I&II)<br />

IS: 3764 For excavation work.<br />

IS: 4081 For blasting and related drilling operations.<br />

IS: 4138 For working in compressed air.


PARA DESCRIPTION PAGE<br />

11.0 CONSTRUCTION PLANNING & SCHEDULE XI-1<br />

11.1 GENERAL APPROACH FOR CONSTRUCTION PLANNING FOR<br />

EXECUTION OF PROJECT COMPONENTS<br />

XI- 1<br />

11.1.1 CONSTRUCTION METHODOLOGY & EQUIPMENT PLANNING XI-1<br />

11.1.2 GENERAL XI-1<br />

11.1.3 COMPLETION TIME AND AVAILABLE WORKING SEASON XI-2<br />

11.1.4 APPROACH ROAD AND THE LOCATION OF THE PROJECT XI- 2<br />

11.1.5 CONSTRUCTION MATERIAL XI- 2<br />

11.1.5.1 CEMENT XI- 2<br />

11.1.5.2 STEEL XI-2 TO XI-3<br />

11.1.5.3 AGGREGATE XI- 3<br />

11.1.6 STORES, LUBRICATION& WORK SHOP XI- 3<br />

11.1.7 AGGREGATE PROCESSING PLANTS. XI- 3<br />

11.1.8 PLANT AREAS XI-3 TO XI-4<br />

11.1.9 DUMP AREAS XI-4<br />

11.1.10 PRE-CONSTRUCTION FACILITIES XI-4<br />

11.1.11 EQUIPMENT PROVISION XI- 4<br />

11.2 CONSTRUCTION SCHEDULE XI- 5<br />

11.2.1 INFRASTRUCTURAL WORKS XI-5<br />

11.2.2 DIVERSION BARRAGE XI-5<br />

11.2.3 INTAKE STRUCTURE XI-5 TO XI-6<br />

11.2.4 DESILTING TANK XI- 6<br />

11.2.5 MECHANICAL WORKS FOR THE ABOVE FEATURES XI- 6<br />

11.2.6 HEAD RACE TUNNEL XI-6 TO XI-7<br />

11.2.7 SURGE SHAFT XI- 6 TO XI-7<br />

11.2.8 PRESSURE SHAFT XI-7<br />

11.2.9 POWER HOUSE XI- 7<br />

11.2.10 TAIL RACE TUNNEL XI- 7<br />

11.2.11 INSTALLATION TESTING AND COMMISSIONING XI-7


CHAPTER – XI<br />

CONSTRUCTION PLANNING & SCHEDULE


11.0 CONSTRUCTION PLANNING & SCHEDULE<br />

11.1 GENERAL APPROACH FOR CONSTRUCTION PLANNING AND<br />

EXECUTION OF PROJECT COMPONENTS<br />

11.1.1 CONSTRUCTION METHODOLOGY & EQUIPMENT PLANNING<br />

11.1.2 GENERAL<br />

Chhatru Hydel Project is a 108 MW capacity run <strong>of</strong> the river scheme in<br />

Lahaul & Spiti District <strong>of</strong> H.P envisages utilization <strong>of</strong> 75 cumecs <strong>of</strong> design<br />

discharge and 177.83m <strong>of</strong> gross head. Diversion barrage about 5 km. u/s <strong>of</strong><br />

Chhatru village and power house about 3.50 km d/s <strong>of</strong> Chhatru village has<br />

been proposed . The <strong>project</strong> comprises following main civil structures:<br />

Barrage<br />

Intake structure<br />

Desilting arrangement<br />

Head Race Tunnel<br />

Surge Shaft<br />

Pressure shaft<br />

<strong>Power</strong> House<br />

Tail race tunnel<br />

11.1.3 COMPLETION TIME AND AVAILABLE WORKING SEASON<br />

Construction programme, selection <strong>of</strong> methodology and equipment have<br />

been planned with the aim <strong>of</strong> commissioning <strong>of</strong> the <strong>project</strong> in four and half<br />

years. Available working season in a year shall be <strong>of</strong> 12 months for all


underground works, 9 months for surface works above river bed and eight<br />

months for the works in the river bed.<br />

11.1.4 APPROACH ROAD AND THE LOCATION OF THE PROJECT<br />

A total <strong>of</strong> about 22 Km road (5/7 m wide) shall be needed to connect the<br />

existing motorable road with the <strong>project</strong> components i.e. Adit to HRT,<br />

surge shaft area, <strong>Power</strong> house and colony area .<br />

11.1.5 CONSTRUCTION MATERIAL<br />

11.1.5.1 CEMENT<br />

11.1.5.2 STEEL<br />

ACC cement factory located at Barmana in Distt. Bilaspur (HP), on NH-21<br />

and at a distance <strong>of</strong> 215 Kms from the <strong>project</strong> site shall be the main source<br />

<strong>of</strong> cement for meeting the entire cement requirement <strong>of</strong> the <strong>project</strong>. Bagged<br />

cement shall be transported in trucks and stored in <strong>project</strong> stores at different<br />

sites.<br />

Steel stockyard at Parwanoo, 400 Kms. from main <strong>project</strong> store, shall be the<br />

main source <strong>of</strong> structural and reinforcement/ tor. steel. Sizeable quantities <strong>of</strong><br />

reinforcement steel and structural steel shall have to be stocked and<br />

replenished regularly. Penstock steel plates if not available indigenously<br />

however, may have to be imported to suit the design specifications.<br />

11.1.5.3 AGGREGATE<br />

The material in the river bed may be suitable for aggregate, however, the<br />

same has to be got tested at detailed investigation stage.


Rock from different quarries in the vicinity <strong>of</strong> the <strong>project</strong> may also be got<br />

identified, to assess their suitability for manufacturing aggregate. Rock<br />

extracted from the quarries as well as from tunnel will be crushed and<br />

classified to various sizes <strong>of</strong> aggregate in batching and mixing plant one<br />

near the barrage site and other near power house ( for excavated material<br />

from tunnel).<br />

11.1.6 STORES, LUBRICATION & WORK SHOP<br />

The Petrol/diesel pumps, explosives magazine, workshops and other<br />

construction facilities shall be provided to facilitate execution <strong>of</strong> the <strong>project</strong>.<br />

While central stores for storage <strong>of</strong> cement, T&P articles, steel yard as well<br />

as timber yard and main workshop shall be provided . Site stores and field<br />

workshops will be established near respective sites. Petrol/diesel pump shall<br />

be established near the power house site.<br />

11.1.7 AGGREGATE PROCESSING PLANTS<br />

Two aggregate crushing classification and sand manufacturing plants shall<br />

be installed near each site <strong>of</strong> work and 2 nos. batching and mixing plants<br />

shall be located near <strong>Power</strong> house& barrage site.<br />

11.1.8 PLANT AREAS<br />

Plant areas for locating air compressor house, cement, aggregate, T&P<br />

stores and water storage tanks etc., shall be located near each site <strong>of</strong> work<br />

and 2 nos. batching and mixing plants shall be located near <strong>Power</strong> house&<br />

barrage site.<br />

11.1.9 DUMP AREAS


The muck <strong>of</strong> underground excavation shall be dumped in dump areas<br />

located within 1to 4.5 km from each portal. Dump areas for over ground<br />

excavation in barrage shall be at a maximum distance <strong>of</strong> 1 km and power<br />

house area at a distance <strong>of</strong> 4.50 km.. Dump areas chosen are located much<br />

above the river/nallah banks and are provided with suitable retaining walls<br />

etc. Bull dozers shall be deployed in dump areas for spreading and<br />

compaction <strong>of</strong> dumped material.<br />

11.1.10 PRE-CONSTRUCTION FACILITIES<br />

Pre construction facilities such as land acquisition for labour huts, plant<br />

areas, stores, residential and non residential buildings, approach roads,<br />

construction <strong>of</strong> bridges and explosive magazine in the valley shall be made<br />

available to facilitate construction <strong>of</strong> the <strong>project</strong>.<br />

11.1.11 EQUIPMENT PROVISION<br />

Since main works <strong>of</strong> the <strong>project</strong> are proposed to be executed on contract<br />

basis except the required infrastructural facilities as such the necessary<br />

provision <strong>of</strong> machinery like material trucks, trailors, cement carriers, motor<br />

grader and road rollers etc. has been made under Q-special-T&P, for<br />

carrying out the works <strong>of</strong> infrastructural facilities. Provisions for personal<br />

carriers, ambulance and field workshop equipment have also been made<br />

under <strong>project</strong> estimate.<br />

11.2 CONSTRUCTION SCHEDULE<br />

The <strong>project</strong> has been proposed to be completed in 4½ years. Method <strong>of</strong> execution <strong>of</strong><br />

various components and selection <strong>of</strong> equipments have been done with the object <strong>of</strong><br />

commissioning first <strong>hydro</strong> unit by the end <strong>of</strong> 3 rd month <strong>of</strong> the fifth year, the second unit


y the end <strong>of</strong> 5 th month <strong>of</strong> fifth year and the third unit by the end <strong>of</strong> 6 th month <strong>of</strong> fifth<br />

year.<br />

11.2.1 INFRASTRUCTURAL<br />

It is proposed that all infrastructural works on the <strong>project</strong> comprising roads, buildings,<br />

adits, workshops, stores, utility works, surveys, development <strong>of</strong> quarries, leveling <strong>of</strong> area<br />

for installation <strong>of</strong> equipment and plants, pre-qualification <strong>of</strong> tenders, award <strong>of</strong> contracts,<br />

detailed design <strong>of</strong> components and other preliminary works shall be continued upto 4 th<br />

year <strong>of</strong> <strong>project</strong> execution.<br />

11.2.2 DIVERSION BARRAGE<br />

i) C<strong>of</strong>fer dam:- During 7 th month <strong>of</strong> <strong>project</strong> construction.<br />

ii) Excavation <strong>of</strong> barrage Const. Ist stage<br />

From 8 th month to 13 th month <strong>of</strong> <strong>project</strong> construction.<br />

iii) Concreting <strong>of</strong> barrage Ist stage<br />

From 10 th month to 21 st month.<br />

iv) C<strong>of</strong>fer dam 2 nd stage<br />

During 22 nd month.<br />

v) Excavation <strong>of</strong> barrage 2 nd stage<br />

From 23 rd month to 31 st month.<br />

vi) Concreting <strong>of</strong> barrage 2 nd stage<br />

From 32 nd month to 36 th moth.<br />

11.2.3 INTAKE STRUCTURE<br />

Excavation:- From 22 nd month to 25 th month.<br />

Concreting:- From 26 th month to 37 th .<br />

11.2.4 DESILTING TANK


Excavation:- From 7 th month to 15 th month.<br />

Concreting:- From 13 th month to 36 th month.<br />

11.2.5 MECHANICAL WORKS FOR THE ABOVE FEATURES<br />

From 19 th to 48 th months.<br />

11.2.6 HEAD RACE TUNNEL<br />

Excavation from RD 0 to 3440m and 7000m to 3440m<br />

From 4 th month to 37 th month.<br />

Concreting from RD 0 to 3440m and 7000m to 3440m.<br />

From 38 th month to 46 th month.<br />

Grouting :- From 47 th month to 48 th month.<br />

From RD 700m to 9150m and 11300m to 9150m.<br />

Excavation from 13th month to 33rd month.<br />

Concreting from 34 th month to 39 th month.<br />

Grouting from 40th month to 41 st month.<br />

11.2.7 SURGE SHAFT<br />

Excavation from 13th month to 23rd month.<br />

Concreting:- From 24 th month to 31 st month.<br />

Grouting & Clean up:- From 32 nd month to 36 th month.


11.2.8 PRESSURE SHAFT<br />

Excavation:- From 13 th month to 21 st month.<br />

Concreting& linner:- From 22nd month to 38th months.<br />

11.2.9 POWER HOUSE<br />

Excavation:- From 13 th month to 26th month.<br />

Concreting:- From 27th month to 40th months.<br />

11.2.10 TAIL RACE TUNNEL<br />

Excavation:- From 19 th month to 22nd month.<br />

Concreting:- In 43 rd month.<br />

11.2.11 INSTALLATION, TESTING AND COMMISSIONING<br />

Installation <strong>of</strong> <strong>hydro</strong> units shall be started from the 32 nd month. A period <strong>of</strong><br />

3 months for testing and commissioning <strong>of</strong> each unit has been provided with<br />

first unit proposed to be commissioned in 51 st month and second unit in 53 rd<br />

month <strong>of</strong> construction and 3 rd unit in 54 th month thus completing the<br />

construction <strong>of</strong> the <strong>project</strong> as a whole in 54 month duration.


PARA DESCRIPTION PAGE<br />

12.0 GENERAL XII-1<br />

12.1 BASIS OF THE ESTIMATE XII-1<br />

12.2 DESCRIPTION OF ITEMS XII-2<br />

12.2.1 UNIT-I CIVIL WORKS XII-2 TO XII-4<br />

12.2.2 UNIT-III ELECTRICAL WORKS XII-5<br />

12.2.2.1 P-PRODUCTION XII-5<br />

12.2.2.2 T-TRANSMISSION XII-5<br />

12.3 DETAILED ESTIMATE OF COST XII-5 TO XII-34


12.0 GENERAL<br />

12.1 BASIS OF ESTIMATE<br />

CHAPTER – XII<br />

COST ESTIMATES<br />

The estimate <strong>of</strong> Unit-I Civil Works has been prepared to arrive at the capital<br />

cost <strong>of</strong> the Chhatru Hydel Project. The price level <strong>of</strong> the estimate Oct.,<br />

2003. It is presumed that major civil works will be executed on contract<br />

basis. The cost estimate does not include following items:-<br />

- Escalation after Oct., 2003<br />

- Interest during construction.<br />

Detailed estimate <strong>of</strong> cost for Unit-I civil works is based mainly upon<br />

various designs/drawings finalised for appurtenant structures and the rates<br />

for principal items <strong>of</strong> works as per guide lines furnished by CEA vide letter<br />

dt. 24 th Oct. 2003. A provision <strong>of</strong> 3% has been made for contingencies for<br />

C-works under Unit-I works. Guidelines for preparation <strong>of</strong> <strong>project</strong> estimate<br />

issued by CWC during March, 1997 have also been followed for<br />

formulation <strong>of</strong> the estimate.<br />

12.2 DESCRIPTION OF ITEMS<br />

12.2.2 UNIT-I CIVIL WORKS<br />

Under the heading civil works provision has been made for various<br />

components <strong>of</strong> the <strong>project</strong> as detailed here under;


A-Preliminary<br />

Under this sub-head, provision <strong>of</strong> Rs. 501.25 lac has been made for surveys<br />

and investigations conducted or to be conducted to arrive at the optimum<br />

designs <strong>of</strong> <strong>project</strong> components.<br />

B- Land<br />

This covers the provision for acquisition <strong>of</strong> land for construction <strong>of</strong> the<br />

<strong>project</strong> components, colonies, <strong>of</strong>fices and store complexes and<br />

compensation for trees and standing crops. Provision for forest trees in the<br />

<strong>project</strong> area has also been included. A L.S.provision for Rs. 350.00 lac has<br />

been made under this sub-head in the absence <strong>of</strong> data , which could not be<br />

collected being <strong>project</strong> area under snow cover during winter.<br />

C-Works<br />

This covers the cost <strong>of</strong> civil engineering structures comprising c<strong>of</strong>fer dam<br />

and diversion barrage. The cost on this sub head worksout to Rs.9572.95<br />

Lac.<br />

J <strong>Power</strong> Plant<br />

This covers the cost <strong>of</strong> Intake ,desanding chamber, head race tunnel, surge<br />

shaft, pressure shaft, underground power house complex and tail race<br />

tunnel. The total cost works to be Rs. 20057.42 lac.


K- Buildings<br />

Buildings both residential and non- residential have been grouped separately<br />

under permanent and temporary catagories. Under the permanent catagories,<br />

all those buildings have been included which will be subsequently utilised<br />

for the operation and maintenance <strong>of</strong> <strong>project</strong> whereas, under the temporary<br />

category, credit to the extent <strong>of</strong> 15% has been given to the <strong>project</strong> on<br />

account <strong>of</strong> resale there<strong>of</strong>. The cost has been worked out on basis <strong>of</strong> plinth<br />

area rates as notified by HPPWD.. A provision <strong>of</strong> Rs.1341.94 lac has been<br />

made under this sub-head.<br />

X-Environment & Ecology<br />

A provision <strong>of</strong> Rs.470 lac has been made under this sub-head maintaining<br />

and improving the environmental status <strong>of</strong> the <strong>project</strong> area and fir<br />

afforestation <strong>of</strong> affected area.<br />

II-Establishment<br />

A provision under this head has been made for Rs. 2760.24 lac i.e. 8% <strong>of</strong> I-<br />

Works.<br />

V-Receipts & Recoveries<br />

This provision covers estimated recoveries by way <strong>of</strong> resale or transfer <strong>of</strong><br />

special T&P and temporary buildings. The amount thus works out to Rs.<br />

328.84 lac only.


M-Plantation<br />

This covers the cost <strong>of</strong> plantation and protection <strong>of</strong> plants to be planted<br />

along <strong>project</strong> roads, colonies and in <strong>project</strong> area. Accordingly a provision <strong>of</strong><br />

25.00 lac has been made under this sub-head.<br />

O- Miscellaneous<br />

A provision <strong>of</strong> Rs. 966.77 lac has been made for meeting cost <strong>of</strong> various<br />

items listed therein.<br />

Q-Special T&P<br />

As the major civil works have been proposed to be got done on contract<br />

basis. Machinery required for departmental activities like infrstructural<br />

works, there subsequent repair/ maintenance and supervison works has<br />

mainly been includeed under theisd sub-head. A provision <strong>of</strong> Rs. 496.71 lac<br />

has been made under this sub-head.<br />

R-Communication<br />

A provision <strong>of</strong> Rs. 656.70 lac under this sub-head covers the cost <strong>of</strong> roads.<br />

The road width have been planned to cater to the anticipated traffic<br />

including movement <strong>of</strong> heavy trailors. Cost <strong>of</strong> roads is based on the rates<br />

as notified by State HPPWD .<br />

A provision <strong>of</strong> Rs. 38679.07 Lac.has been made to cover the costs under<br />

this subhead.


12.2.2 UNIT-III ELECTRICAL WORKS<br />

12.2.2.1 P-PRODUCTION<br />

Cost <strong>of</strong> generating plants and equipments is based on current budgetory<br />

prices. Prices <strong>of</strong> auxiliary equipments and services are based on historical<br />

prices.Excise duty has been considered @ 16% <strong>of</strong> the component. CST,<br />

Insurance and transport to site has been taken @ 6% <strong>of</strong> the cost <strong>of</strong><br />

respective component. Erection and commissioning charges have also been<br />

taken @ 10% as per experience gained on similar installations in the state. A<br />

provision <strong>of</strong> Rs. 13612.06 lacs has been made to cover the costs under this<br />

sub-head.<br />

12.2.2.2 T-TRANSMISSION<br />

It is proposed to evacuate the power generated at Chhatru <strong>project</strong> by<br />

LILOing <strong>of</strong> 220 KV D/C line from Khoksar to 400 KV Pooling point at<br />

Tandi which is proposed in this basin. Beyond this point the evacuation will<br />

be through 400 KV D/C net work to Panarsa Poolung in sub station <strong>of</strong><br />

PGCIL. The cost is based on detailed analysis on actual requirement and<br />

amounts to Rs. 844.68 lacs.<br />

12.3 DETAILED ESTIMATE OF COST<br />

Detailed estimate <strong>of</strong> cost as explained in above paras is given in succeeding<br />

paras.


PARA DESCRIPTION PAGE<br />

13.0 GENERAL XIII-1<br />

13.1 CAPITAL COST OF THE PROJECT XIII-1 TO XIII-2<br />

13.2 ECONOMIC JUSTIFICATION XIII-2<br />

13.3 CAPITAL STRUCTURE XIII-3<br />

13.4 REVENUE ANTICIPATION XIII-3<br />

13.5 REPAYMENT PERIOD XIII-3<br />

13.6 COST PER MW XIII-3<br />

13.7 INTEREST DURING CONSTRUCTION XIII-4<br />

13.8 ENERGY AVAILABLE FOR SALE XIII-4<br />

13.9 RATE OF DEPRECIATION XIII-4<br />

13.10 OPERATION AND MAINTENANCE<br />

CHARGES<br />

XIII-4<br />

13.11 CALCULATION OF TARRIF XIII-5<br />

13.12 INDIRECT BENEFIT XIII-6<br />

13.13 MERITS OF THE PROJECT XIII-6<br />

13.14 CONSTRUCTION SCHEDULE XIII-6<br />

ANNEXURE-13.1-(a)<br />

TO 13.1(c)<br />

ABSTRACT OF COST ESTIMATES OF<br />

CIVIL WORKS, P-PRODUCTION & T-<br />

TRANSMISSION<br />

ANNEXURE-13.2 YEARWISE PHASING OF FUNDS XIII-10<br />

ANNEXURE-13.3 CALCULATION OF INTEREST DURING<br />

CONSTRUCTION AT POWER HOUSE<br />

BUS BARS<br />

ANNEXURE-13.4 WEIGHTED AVERAGE DEPRECIATION<br />

ANNEXURE-13.5 LEVELLISED TARRIF OF ENERGY FOR<br />

90% DEPENDABLE YEAR AT POWER<br />

HOUSE BUS BARS.<br />

XIII-7 TO XIII-9<br />

XIII-11<br />

XIII-12<br />

XIII-13TO XIII-<br />

14


13.0 GENERAL<br />

CHAPTER-XIII<br />

ECONOMIC EVALUATION<br />

Chhatru Hydro- <strong>electric</strong> Project has been contemplated as a run <strong>of</strong> the river<br />

development on Chandra River in Lahul & Spiti district <strong>of</strong> Himachal<br />

Pradesh. This <strong>project</strong> is estimated to cost Rs. 531.36 Cr. at price level <strong>of</strong><br />

Oct,,2003. The cost at power bus bar worksout to Rs. 522.91 Cr.Abstract<br />

<strong>of</strong> cost estimate <strong>of</strong> Civil works, P-Production and T-Transmission have been<br />

given as per Annexure13.1-(a) to13.1-(c). Year wise phasing <strong>of</strong> expenditure<br />

for capital required on this <strong>project</strong> is given as per Annexure-13.2. Interest<br />

during construction has been considered as per Annexure- 13.3.


Depreciation on Civil and Electrical works has been worked out as 3.00% as<br />

per Annexure-13.4.The levelised tariff <strong>of</strong> energy generated at power house<br />

bus bars has been worked out as Rs. 2.28 per unit during 90% dependable<br />

year as per Annexure-13.5. The cost <strong>of</strong> energy in the Ist year <strong>of</strong> operation<br />

worksout to Rs. 2.89 per unit.<br />

13.1 CAPITAL COST OF THE PROJECT<br />

Abstract <strong>of</strong> the capital cost <strong>of</strong> the <strong>project</strong>, to the price level <strong>of</strong> Oct., 2003 is<br />

as under: -<br />

S.No. Description Amount<br />

(Rs. in Cr.)<br />

1. Unit-I Civil works 386.79<br />

2. P-Production (Electrical works) 136.12<br />

Total Generation Cost 522.91<br />

3. Transmission 8.45<br />

Grand total 531.36<br />

13.2 ECONOMIC JUSTIFICATION<br />

PGCIL will construct a Parbati pooling point at down stream <strong>of</strong> Parbati<br />

stage-III HEP at Pnarsa and which will cater the power <strong>of</strong> Chhatru HEP<br />

through 220 KV D/C to Khoksar and then to 400 KV Tandi pooling point..<br />

As laid down to CEA and CERC Guidelines, economic justification <strong>of</strong> a


hydel <strong>project</strong> is to be done by comparing cost <strong>of</strong> alternative sources<br />

<strong>of</strong> energy in that region. The levelized tariff <strong>of</strong> this <strong>project</strong> in 90%<br />

dependable year works out as Rs. 2.28/ unit at power use bus bars as per<br />

Annexure-13.5 ).This <strong>project</strong> will provide power at cheaper rates in<br />

comparison to thermal power rate which , at present is more than Rs.3.75 /<br />

unit. Additionally this <strong>project</strong> will provide pollution free power for years<br />

together at much cheaper rates considering the escalation in coal prices for<br />

Thermal <strong>Power</strong>.<br />

13.3 CAPITAL STRUCTURE<br />

Capital structure has been assumed as 70% debt from Financial Institution<br />

and 30% equity from Govt.<br />

13.4 REVENUE ANTICIPATION<br />

<strong>Power</strong> tariff for supply <strong>of</strong> power at powerhouse bus bars has been assumed<br />

as Rs. 2.75 per unit. Revenue has been assessed accordingly for 90%<br />

dependable year as Rs. 125.32 cr.<br />

13.5 REPAYMENT PERIOD<br />

.<br />

Normally, the leading financial institutions in India prescribe a repayment<br />

period <strong>of</strong> 15 years including 3 to 4 years moratorium period. A period <strong>of</strong> 12<br />

years has therefore been taken into account, as repayment period in fixation<br />

to tariff.


13.6 COST PER MW<br />

The estimated cost <strong>of</strong> the <strong>project</strong> at Oct 2003 price level is Rs. 531.36 Cr.<br />

including transmission and Rs. 522.91 Cr. at power bus bar for an installed<br />

capacity <strong>of</strong> 108W. This gives a capital cost <strong>of</strong> Rs. 4.92 Cr.per MW <strong>of</strong><br />

installed capacity including cost <strong>of</strong> transmission and Rs. 4.84 Cr. per MW<br />

at generation. At present price level, the cost <strong>of</strong> medium <strong>hydro</strong>-<strong>electric</strong><br />

<strong>project</strong> at Rs. 6.00 crore per MW is considered to be reasonable. From this<br />

criterion, the cost per MW for Gharopa Hydel Project is reasonable making<br />

the <strong>project</strong> suitable for exploitation.<br />

13.7 INTEREST DURING CONSTRUCTION<br />

The detail <strong>of</strong> expenditure during the construction period and the calculation<br />

<strong>of</strong> interest during construction have been shown in Annexure-13.3. It is<br />

seen that IDC @ 10.00 % on loan works out to Rs. 62.24. at power house<br />

bus bars.<br />

13.8 ENERGY AVAILABLE FOR SALE<br />

As per power studies <strong>of</strong> the <strong>project</strong>, the total energy generation in 90%<br />

dependable year has been arrived at 455.72 MUs. As per Govt. <strong>of</strong> India<br />

Guide Lines, an auxiliary consumption @ 0.7% and transformation losses<br />

@ 0.5% have been considered at power house bus bars .<br />

13.9 RATE OF DEPRECIATION<br />

As per the revised guide lines circulated by Govt. <strong>of</strong> India, <strong>Ministry</strong> <strong>of</strong><br />

<strong>Power</strong>, Vide notification dated 29 th March, 1994, the weighted rate <strong>of</strong><br />

depreciation has been worked out on the basis <strong>of</strong> straight line formula. The


ate <strong>of</strong> depreciation works out to 3.00% <strong>of</strong> the <strong>project</strong> cost as per<br />

Annexure-13.5.<br />

13.10 OPERATION AND MAINTENANCE CHARGES<br />

As per the guide lines <strong>of</strong> <strong>Ministry</strong> <strong>of</strong> <strong>Power</strong>, Govt. <strong>of</strong> India, the Operation<br />

and Maintenance charges inclusive <strong>of</strong> insurance have been taken as 1.50 %<br />

<strong>of</strong> the capital cost.<br />

11 CALCULATION OF TARIFF<br />

Calculation <strong>of</strong> tariff for primary energy during 35 years <strong>of</strong> operation for<br />

90% dependable year has been worked out as per GOI notification shown in<br />

Annexure-13.5 comprising the following.<br />

i) Interest on loan from PFC @ 10.00 % p.a.<br />

ii) Interest on working capital @ 9.75 % required for 2 months <strong>of</strong><br />

average billing for sale <strong>of</strong> <strong>electric</strong>ity and operation and maintenance<br />

expenses for one month.<br />

iii) O&M charges including insurance charges @ 1.5% p.a.<br />

iv) Income tax @ 35% and surcharge @ 10% on income tax has been<br />

considered.<br />

v) Discounting rate @ 12% for tariff calculation .<br />

vi) Free power for home state @ 12%.


At power house bus bar, it will be seen that sale rate <strong>of</strong> power shall be Rs.<br />

2.89 per unit during Ist year <strong>of</strong> operation and Rs. 1.37 per unit during 13 th<br />

year i.e after repayment <strong>of</strong> loan. The levelised tariff rate works out to Rs.<br />

2.28 per unit at power house bus bars.<br />

13.12 INDIRECT BENEFIT<br />

Besides providing pollution free power at a cheap rate to the Northern Grid;<br />

discussed in preceding paras, this <strong>project</strong>, located in Lahul & Spiti district <strong>of</strong><br />

HP will help in the overall development <strong>of</strong> the people <strong>of</strong> the area..<br />

Employment to skilled/non-skilled labour <strong>of</strong> the area, industrial and<br />

economic development are additional benefits from this <strong>project</strong>. Keeping<br />

these points in view, this <strong>project</strong> merits consideration for an implementation.<br />

13.13 MERITS OF THE PROJECT<br />

Gharopa HEP (108 MW) is a down stream development <strong>of</strong> proposed<br />

Khoksar (90 MW). Following are the strengths and weaknesses <strong>of</strong> the<br />

<strong>project</strong>.<br />

i) Project sites are located on the right bank <strong>of</strong> existing motorable<br />

road.<br />

ii) No resettlement <strong>of</strong> people required for construction <strong>of</strong> <strong>project</strong>.<br />

iii) Construction material is locally available.<br />

iv) Almost all the major sites <strong>of</strong> the <strong>project</strong> viz. Diversion, inlet portal<br />

and adit portal <strong>of</strong> HRT and power house are connected with NH-21.<br />

v) The levellised tariff works out to be Rs. 2.28 per unit at power<br />

house bus bar which is on lower side.


13.14 CONSTRUCTION SCHEDULE<br />

The construction <strong>of</strong> the <strong>project</strong> has been proposed to be completed in four<br />

and half years <strong>of</strong> period. The construction schedule has been presented in<br />

drawing No. Gharopa-FR-8 (attached).


CONSTRUCTION ORGANISATION<br />

PRE CONSTRUCTION STAGE<br />

FOR FIRST ONE YEAR<br />

S.E. (C/M ) 1/2<br />

E.E.-I (C) E.E.-II (C) E.E.-III (M) E.E.-IV (E)<br />

Land Acquisition Detialed surveys, R/M <strong>of</strong> w / shop, Arrangement <strong>of</strong><br />

c/o residential & non collection <strong>of</strong> G&D vehicles & procure - construction power<br />

residential buildings data, c/o adits & ment <strong>of</strong> stores & electrification <strong>of</strong><br />

and <strong>project</strong> roads. W/shop facilities. Equipments. Resd. Buildings.<br />

CONSTRUCTION STAGE<br />

Chief Enginer (C) Chief Enginer (E)<br />

Construction 1/2 Construction 1/3<br />

Four year Four year<br />

S.E.-Admn.& Works. S.E.-Admn&Works.<br />

(C/M) ( E)<br />

E.E.Admn. E.E.Works E.E.Admn. E.E.Works<br />

(C/M) (C/M) (E) (E)<br />

S.E.-Civil. -I S.E.-II (M ) 1/2 S.E.-P/H( E) S.E.T(E)1/2<br />

A.O. C/M A.O. C/M A.O. C/M A.O. C/M<br />

E.E. I (C) E.E.I I (C) E.E.III (C) E.E.IV (C) E.E.I (M) E.E.II (M) E.E. I (E) E.E.I I (E) E.E.III (E) E.E.IV (E) E.E.I (E) E.E.II (E)<br />

Barrage Rana aqueduct,HRT Surge shaft <strong>Power</strong> house & Tail Work shop, Pen stock fabrication, <strong>Power</strong> house , Sub station & Testing & Planning &<br />

Intake & Adits. & pressure Race works. Transport & fabrication & errection Works. Switch yard. commissioning Monitoring. Transmation & P L C C<br />

& Control survey, shaft Colony at Snail/ Stores. <strong>of</strong> Gates, hoist & Const.<br />

D/Tank colony & road maint.<br />

G/D data collection<br />

& Silt lab.<br />

civil works Anti Roads trash racks etc.<br />

HIMACHAL PRADESH STATE ELECTRICITY BOARD<br />

DIRECTOR PLANNING CIRCLE NO.I<br />

SAWRA KUDDU 110 MW<br />

CONSTRUCTION ORGANISATION CHART<br />

DSGN. CHKD. RECM.<br />

DRWN. SUBM. APPED.<br />

SUNDERNAGAR , APRIL-2003 DRG.NO.SAWRA KUDDU-PR-19


DESIGN ORGANISATION<br />

PRE CONSTRUCTION STAGE<br />

FOR FIRST HALF YEAR<br />

Director-D(C)1/4 Director-D(E)1/4<br />

E.E.-I(C) E.E.-I(E)<br />

Design <strong>of</strong> bridges &<br />

Roads, Preparation &<br />

processing <strong>of</strong> tenders<br />

etc., infrastructure<br />

facilities like adits,<br />

w/shop & stores<br />

Const. power,<br />

preliminary enquiry<br />

for generating<br />

equipment &<br />

turbines etc.<br />

Chief Engineer (C/M) Chief Engineer(E)<br />

Construction 1/3 Construction 1/3<br />

S.E. Admn & Four year Two year<br />

Works(C/M)<br />

Director Design C/M Director Design (E) S.E.Admn & Works<br />

E.E.Works E.E.Works Thrre year (E)<br />

(C/M) (C/M)<br />

E.E.I(C/M) E.E.II(C/M) E.E.III(C/M) E.E.IV(C/M) E.E.I(E) E.E.II(E) E.E.III(E) E.E.IV(E)<br />

Design <strong>of</strong><br />

infrastructure,<br />

job facilities,<br />

preparation &<br />

prosesing <strong>of</strong><br />

tenders,<br />

estimation,<br />

scheduling<br />

const.<br />

material<br />

Monitoring cost<br />

control & PERT/CPM<br />

planning, mech.<br />

desining <strong>of</strong> gates,<br />

hoisting, trash rack &<br />

penstock<br />

instrumentation & soil<br />

testing<br />

Specification<br />

design &<br />

const. design<br />

<strong>of</strong> barrage,<br />

intake<br />

structure,<br />

D/tanks.<br />

Construction Stage<br />

Specification,<br />

design & const.<br />

design <strong>of</strong> HRT,<br />

S/shaft, <strong>Power</strong><br />

House & Tail<br />

race<br />

Specification,<br />

design &<br />

tenders <strong>of</strong><br />

Generation<br />

equipments.<br />

Specification,<br />

design & tenders<br />

<strong>of</strong> <strong>Power</strong> house<br />

auxiliaries.<br />

Design &<br />

procurement<br />

<strong>of</strong><br />

Transmission<br />

lines &<br />

equipments<br />

DSGN. CHKD. RECM.<br />

DRWN. SUBM. APP.<br />

E.E.Admn. E.E.Works<br />

(E) (E)<br />

Specification,<br />

design & const.<br />

design <strong>of</strong> substation<br />

& switch<br />

yard<br />

HIMACHAL PRADESH STATE ELECTRICITY BOARD<br />

DIRECTOR PLANNING CIRCLE NO.I<br />

SAWRA KUDDU 110 MW<br />

DESIGN ORGANISATION CHART<br />

SUNDERNAGAR , APRIL-2003 DRG.NO.SAWRA KUDDU--PR-18


S No. Description Quantity Unit 1st Year 2nd Year 3rd Year 4th Year 5th Half year<br />

A PRE-CONSTRUCTION<br />

1 INFRASTRUCTURE<br />

i) a) Preliminary Job<br />

ii) b) Land Acquisition Job<br />

iii) c) Procurement Job<br />

2 AGGREGATE PROCESSING Job<br />

B WORK SCHEDULE<br />

1. Diversion Barrage<br />

i) C<strong>of</strong>fer dam Ist Stage Job<br />

ii) Excavation <strong>of</strong> barrage 1st stage 325300 Cum<br />

iii) Concreting <strong>of</strong> barrage 1st stage 54166 Cum<br />

iv) C<strong>of</strong>fer dam 2nd stage Job<br />

v) Excavation 2nd stage 325300 Cum<br />

vi) Concreting <strong>of</strong> 2nd stage 54166 Cum<br />

2. Iuntake structure<br />

i) Excavation 7890 Cum<br />

ii) Concreting 1830 Cum<br />

3. Desilting Tank<br />

i) Excavation 239450 Cum<br />

ii) Concreting 51900 Cum<br />

4. Mechanical works for the above features<br />

5. HRT<br />

a) Excavation from RD 0 to 3500 104760 Cum<br />

i) Concreting 18170 Cum<br />

ii) Grouting & clean up Job<br />

b) Excavation from RD 6500 to 3500 89240 Cum<br />

i) Concreting 15480 Cum<br />

ii) Grouting & clean up Job<br />

6 Surge shaft<br />

i) Excavation 15900 Cum<br />

ii) Concreting 3977 Cum<br />

iii) Grouting & cleanup Job<br />

7. Pressure Shaft<br />

i) Excavation 29900 Cum<br />

ii) Concreting & steel lining 3720 Cum<br />

8. <strong>Power</strong> house<br />

i) Excavation 61000 Cum<br />

ii) Concreting<br />

a) Sub-structure 9000 Cum<br />

b) Super structure 8000 Cum<br />

9. Auxilliary surge shaft<br />

and Tail Race Tunnel<br />

i) Excavation 45900 Cum<br />

ii) Concreitng 5100 Cum<br />

10. Installation, testing<br />

Unit No.I Job<br />

Unit No.II Job<br />

Unit No.III Job<br />

Months 3 6 9 12 15 18 21 24 27 30 33 36 39 42 45 48 51 54


S. NO. DESCRIPTION UNIT RATE<br />

A EXCAVATION<br />

1 Common excavation Cum 125.00<br />

2 Excavation in hard rock Cum 300.00<br />

3 Excavation in rock in tunnel Cum 1000.00<br />

4 Surge shaft excavation<br />

Without raise climber Cum 1200.00<br />

B<br />

C<br />

D<br />

E<br />

F<br />

APPENDIX-A<br />

RATES FOR MAJOR ITEMS OF CIVIL WORKS<br />

With raise climber Cum 1500.00<br />

Rock support<br />

Rock bolting (including drilling)<br />

25 mm RM 400.00<br />

32 mm RM 525.00<br />

36mm RM 625.00<br />

Shotcret rate without wiremesh Cum 4000.00<br />

Wiremesh Sq M 200<br />

Steel supprt<br />

Earth dam/Rockfill dam<br />

MT 42000.00<br />

1 Rate per cum earth fill in Dam (for lead 1 km.<br />

2 Rate per cum rock fill in Dam (for lead 1 km.)<br />

Cum 142.00<br />

From excavated material Cum 156.00<br />

From quarry Cum 318.00<br />

3 Rate per cum <strong>of</strong> impervious core in Dam( lead 1 km.) Cum 154.00<br />

4 Inverted filter (for lead 1 km) Cum 701.00<br />

5 Stone pitching (for lead 1 km Cum 581.00<br />

6 Incremental rate for each additional lead <strong>of</strong> 1 km. or par Cum 20.00<br />

Concreteing (including form work)<br />

1 Concrete lead 10 km (For lead <strong>of</strong> 10 Km. for aggegate quarry)<br />

M 25 Cum 3610.00<br />

M 20 Cum 3390.00<br />

M 15 Cum 2930.00<br />

M 10 Cum 2560.00<br />

2 Incremental rate for each additional lead <strong>of</strong> 5 km. or par Cum 100.00<br />

3 Concrete Cut-<strong>of</strong>f wall Sq m 20000.00<br />

4 Precast lagging including cost <strong>of</strong> reinforcement Cum 7000.00<br />

5 Concrete linging in DT & HRT ( M 20)<br />

Reinforcement Steel and Steel and Structural Steel<br />

Cum 4000.00<br />

1 Reforcement MT 27000.00<br />

2 Penstock liner MT 70000.00<br />

Hydro-Mechanical Work<br />

1 Radial gate MT 100000.00<br />

2 Sluicegate MT 100000.00<br />

3 Stoplog gate MT 60000.00<br />

4 Trashrack MT 50000.00<br />

5 Embedded parts MT 50000.00<br />

6 Hoist (Based on lifting capacity) MT 100000.00


APPENDIX-B<br />

RIVER DIVERSION ARRANGEMENT<br />

COFFER DAM (U/S & U/S)<br />

S. NO.<br />

1.0 Surface Excavation<br />

DESCRIPTION UNIT QTY. RATE (Rs.)<br />

Amt.in<br />

Lac<br />

1.1 Common excavation Cum 25000 125.00 31.25<br />

2.0 Embankment Construction<br />

2.1 Earth/rock rill Cum 50000 156.00 78.00<br />

2.1 Impervious core Cum NIL<br />

2.3 Filter Cum NIL<br />

3.0 Concrete<br />

3.1 M 10 Cum 7600 2560.00 194.56<br />

3.2 M 15 Cum NIL<br />

3.3 Concrete cut-<strong>of</strong>f wall if required Cum NIL<br />

Sub-Total (A) <strong>of</strong> 1 to 3<br />

4.0 Miscellaeneous<br />

4.1<br />

Various Miscellaneous works like wiremesh/steel fibre<br />

reinforcement , drilling & grouting, etc. (0.0 to 0.50% <strong>of</strong> Sub-<br />

Total (A) dpending upon the iste conditions & type <strong>of</strong><br />

303.81<br />

structure)<br />

0.50% 303.81 1.52<br />

Sub-Total (B) <strong>of</strong> 1 to 4 305.33<br />

5.0 Dewatering (3% <strong>of</strong> Sub-Total (B)<br />

6.0 Contingencies (3% <strong>of</strong> Sub-Total (B) except on<br />

3% 305.33 9.16<br />

L.S. items) 3% 305.33 9.16<br />

7.0 Work Charges Establishment (2% <strong>of</strong> Sub-Total(B)<br />

except on L.S. items)<br />

2% 305.33 6.11<br />

Total <strong>of</strong> 1 to 7 329.76


BARRAGE, CELLULAR WALL, RETAINING WALL & FISH LADDER<br />

S. NO. DESCRIPTION UNIT QTY. RATE (Rs.)<br />

Amt.in<br />

Lac<br />

1.0 Surface Excavation<br />

1.1 Common excavation Cum 325300 125.00 406.63<br />

1.2 Rock Excavation Cum 325300 300.00 975.90<br />

2.0 Support System<br />

2.1 Rock bolts M 300.00 525.00 1.58<br />

2.2 Shotcreting Cum 65.00 4000.00 2.60<br />

3.0 Fill Works<br />

3.1 Compacted Earthfill Cum NIL<br />

3.2 Compacted clay fill Cum 3000 156.00 4.68<br />

4.0 Concrete including form work<br />

4.1 Precast Concrete Block M-20 Cum 3500 7000.00 245.00<br />

4.2 M-15 Cum 26910 2930.00 788.46<br />

4.3 M-20 in Upstream Floor, road bridge Cum 7790 3390.00 264.08<br />

4.4 M-25 downstream floor and spillway glacis <strong>of</strong> barrage, piers<br />

& breast walls, trunion beam, fish ladder, retaining wall if<br />

required. Cum 70133 3610.00 2531.80<br />

4.5 Concrete lining in Channel Sides M-20 Cum NIL<br />

5.0 Steel<br />

5.1 (i) Reinforcement Steel Ton 7800 27000.00 2106.00<br />

5.2 (ii) Structrul Steel Ton 1200 70000.00 840.00<br />

6.0 Stone Pitching<br />

Cum. 4000 581.00 23.24<br />

Sub-Total (A) <strong>of</strong> 1 to 6 8189.97<br />

7.0 Miscellaeneous<br />

7.1<br />

Various Miscellaneous works like Site Clearance, drilling &<br />

grouting, PVC pipes & waterstops, Metal works, Launching<br />

Apron, Crate Work, Filter Below C.C. Block, Masonary<br />

Works, Archetectural Works (4-5% <strong>of</strong> Sub-Total (A)<br />

depdnding upon the site conditions & type <strong>of</strong> structure. 4-5% 0.05 8189.97 368.55<br />

Sub-Total (B) <strong>of</strong> 1 to to 7 8558.51<br />

8.0 Instrumentation ( 1% <strong>of</strong> Sub-Total (B) 1% 8558.51 85.59<br />

9.0 Dewatering (2% <strong>of</strong> Sub-Total (B) 2% 8558.51 171.17<br />

10.0 Contingencies (3% <strong>of</strong> Sub-Total (B) except on 3% 8558.51 256.76<br />

L.S. items)<br />

11.0 Work Charges Establishment (2% <strong>of</strong> Sub-Total(B) 2% 8558.51 171.17<br />

except on L.S. items)<br />

Sub-Total (B) <strong>of</strong> 1 to to 11 9243.19


INTAKE STRUCTURE<br />

APPENDIX-C<br />

S. NO. DESCRIPTION UNIT QTY.<br />

RATE<br />

(Rs.) Amt.in Lac<br />

1.0 Surface Excavation<br />

1.1 Common excavation Cum 1050 125.00 1.31<br />

1.2 Rock excavatin Cum 6840 300.00 20.52<br />

2.0 Underground excavation Cum NIL<br />

3.0 Support System<br />

3.1 Rockbolts M NIL<br />

3.2 Steel Rib Supports Ton NIL<br />

3.3 Shotrreting Cum NIL<br />

3.4 Concrete lagging if required Cum. NIL<br />

4.0 Concrete<br />

4.1 M-10 Cum 100 2560.00 2.56<br />

4.2 M 15 Cum NIL<br />

4.3 M 20 Cum NIL<br />

4.4 M 25 Cum 1730 3610.00 62.45<br />

5.0 steel<br />

5.1 (i) Reinforcing Steel Ton 173 27000 46.71<br />

5.2 (Ii) Structural Steel Ton 100 27000 27.00<br />

Sub-Total (A) <strong>of</strong> 1 to 5 160.56<br />

6.0 Miscellaeneous and Ancillary Works<br />

6.1 Various Miscellaneous works like<br />

wiremesh/steel fibre reinforcement , drilling &<br />

grouting, PVC pipes for drainge, slope<br />

protection works etc. (1-2% <strong>of</strong> Sub-Total (A)<br />

dpending upon the iste conditions & type <strong>of</strong><br />

structure) 1 to 2% 1.50% 160.56 2.41<br />

Cum<br />

Sub-Total (B) <strong>of</strong> 1 to 6 162.96<br />

7.0 Instrumentation ( 1% <strong>of</strong> Sub -Total )B) 1% 162.96 1.63<br />

8.0 Dewatering (1% <strong>of</strong> Sub-Total (B) 1% 162.96 1.63<br />

9.0 Contingencies (3% <strong>of</strong> Sub-Total (B) except<br />

on L.S. items) 3% 162.96 4.89<br />

10.0 Work Charges Establishment (2% <strong>of</strong> Sub-<br />

Total(B) except on L.S. items) 2% 162.96 3.26<br />

Total <strong>of</strong> 1 to 10 337.34


DESANDING CHAMBER<br />

S. NO. DESCRIPTION UNIT QTY. RATE (Rs Amt.in Lac<br />

1.0 Surface Excavation<br />

1.1 Common excavation Cum NIL<br />

1.2 Rock excavatin Cum NIL<br />

2.0 Underground excavation Cum 239450 1000.00 2394.50<br />

3.0 Support System<br />

3.1 Rockbolts M 69500 625 434.38<br />

3.2 Steel Rib Supports Ton 605 42000 254.10<br />

3.3 Shotrreting Cum 6720 4000 268.80<br />

3.4 Concrete lagging if required Cum. NIL<br />

4.0 Concrete<br />

4.2 M 15 Cum 17100 2930.00 501.03<br />

4.3 M 20 Cum 34800 4000.00 1392.00<br />

4.4 M 25 Cum NIL<br />

5.0 Reinforcing Steel Ton 350 27000 94.50<br />

Sub-Total (A) <strong>of</strong> 1 to 5 5339.31<br />

6.0 Miscellaeneous and Ancillary Works<br />

6.1<br />

Various Miscellaneous works like<br />

wiremesh/steel fibre reinforcement , drilling &<br />

grouting etc. (3-4% <strong>of</strong> Sub-Total (A) dpending<br />

upon the iste conditions & type <strong>of</strong> structure) 3 to 4% 3.50% 5339.31 186.88<br />

Sub-Total (B) <strong>of</strong> 1 to 6 5526.18<br />

7.0 Instrumentation ( 1% <strong>of</strong> Sub -Total )B) 1% 5526.18 55.26<br />

8.0 Dewatering (2% <strong>of</strong> Sub-Total (B) 2% 5526.18 110.52<br />

9.0 Contingencies (3% <strong>of</strong> Sub-Total (B) except<br />

on L.S. items) 3% 5526.18 165.79<br />

10.0 Work Charged Establishment (2% <strong>of</strong> Sub-<br />

Total(B) except on L.S. items) 2% 5526.18 110.52<br />

Total <strong>of</strong> 1 to 10 5968.28


HEAD RACE & TAIL RACETUNNEL<br />

S. NO. DESCRIPTION UNIT QTY.<br />

RATE<br />

(Rs.) Amt.in Lac<br />

1.0 Surface Excavation<br />

1.1 Common excavation Cum 100 125.00 0.13<br />

1.2 Rock excavatin Cum 400 300.00 1.20<br />

2.0 Underground excavation Cum 239900 1000.00 2399.00<br />

3.0 Support System<br />

3.1 Rockbolts M 92700 625 579.38<br />

3.2 Steel Rib Supports Ton 1342 42000 563.64<br />

3.3 Shotrreting Cum 10800 4000 432.00<br />

3.4 Concrete lagging if required Cum. NIL<br />

4.0 Concrete<br />

4.2 M 15 Cum 22400 2930.00 656.32<br />

4.3 M 20 Cum 16350 4000.00 654.00<br />

4.4 M 25 Cum NIL<br />

5.0 Reinforcing Steel Ton 795 27000 214.65<br />

Sub-Total (A) <strong>of</strong> 1 to 5 5500.31<br />

6.0 Miscellaeneous and Ancillary Works<br />

6.1 Various Miscellaneous works like<br />

wiremesh/steel fibre reinforcement , drilling &<br />

grouting, PVC pipes for drainge etc. (7-8% <strong>of</strong><br />

Sub-Total (A) dpending upon the iste<br />

conditions & type <strong>of</strong> structure) 7 to 8% 8% 5500.31 440.02<br />

Sub-Total (B) <strong>of</strong> 1 to 6 5940.33<br />

7.0 Instrumentation ( 1% <strong>of</strong> Sub -Total )B) 1% 5940.33 59.40<br />

8.0 Dewatering (2% <strong>of</strong> Sub-Total (B) 2% 5940.33 118.81<br />

9.0 Contingencies (3% <strong>of</strong> Sub-Total (B) except<br />

on L.S. items) 3% 5940.33 178.21<br />

10.0 Work Charges Establishment (2% <strong>of</strong> Sub-<br />

Total(B) except on L.S. items) 2% 5940.33 118.81<br />

Total <strong>of</strong> 1 to 10 6415.56


SURGE SHAFT<br />

S. NO. DESCRIPTION UNIT QTY.<br />

1.0 Surface Excavation<br />

1.1 Common excavation Cum NIL<br />

1.2 Rock excavatin Cum NIL<br />

RATE<br />

(Rs.) Amt.in Lac<br />

2.0 Underground excavation<br />

2.1 Surge Shaft excavation Cum 15900 1200 190.8<br />

2.2 Surge shaft excavation with raise borer Cum NIL<br />

2.3 Concrete lagging if required Cum NIL<br />

3.0 Support System<br />

3.1 Rockbolts M 9100 525 47.775<br />

3.2 Steel Rib Supports Ton 162 42000 68.04<br />

3.3 Shotcreting Cum 500 4000 20<br />

4.0 Concrete<br />

4.1 M 20 Cum 3840 3390 138.62<br />

4.2 M 25 Cum 137 3610 4.6443<br />

5.0 Steel Works<br />

5.1 Reinforcing Steel Ton 263 27000 71.01<br />

5.2 Steel liner Ton 92 70000 64.4<br />

Sub-Total (A) <strong>of</strong> 1 to 5 605.29<br />

6.0 Miscellaeneous<br />

6.1 Various Miscellaneous works like site<br />

clearance , drilling & grouting,wire mesh<br />

reinforcement, Airpipess, Lift arrangement,<br />

other steel works etc. (1-2% <strong>of</strong> Sub-Total (A)<br />

dpending upon the iste conditions & type <strong>of</strong><br />

structure) 1 to 2% 1.50% 605.29 9.08<br />

Sub-Total (B) <strong>of</strong> 1 to 6 614.37<br />

7.0 Instrumentation ( 1% <strong>of</strong> Sub -Total )B) 1% 614.37 6.14<br />

8.0 Dewatering (2% <strong>of</strong> Sub-Total (B) 2% 614.37 12.29<br />

9.0 Contingencies (3% <strong>of</strong> Sub-Total (B) except<br />

on L.S. items) 3% 614.37 18.43<br />

10.0 Work Charges Establishment (2% <strong>of</strong> Sub-<br />

Total(B) except on L.S. items) 2% 614.37 12.29<br />

Total <strong>of</strong> 1 to 10 663.52<br />

Add cost provision for auxilliary s/shaft @<br />

30% <strong>of</strong> cost <strong>of</strong> main surge shaft 30% 663.52 199.057<br />

G Total 862.58


PRESSURE SHAFT<br />

S. NO. DESCRIPTION UNIT QTY.<br />

RATE<br />

(Rs.) Amt.in Lac<br />

1.0 Underground excavation Cum 29900 1000.00 299.00<br />

2.0 Support System<br />

2.1 Rock bolts M 6200 525.00 32.55<br />

2.2 Steel ribs Support Ton NIL<br />

2.3 Shotcreting Cum 7970 4000.00 318.80<br />

3.0 Concrete<br />

3.1 M 15 backfill concrete Cum 3720 2930.00 109.00<br />

4.0 Penstock steel liners Ton 1460 70000 1022.00<br />

Sub-Total A) <strong>of</strong> 1 to 4 2643.93<br />

5.0 Miscellaeneous and Ancillary Works<br />

5.1 Various Miscellaneous works like<br />

wiremesh/steel fibre reinforcement , drilling &<br />

grouting, PVC pipes for drainge, slope<br />

protection works etc. (2-3% <strong>of</strong> Sub-Total (A)<br />

dpending upon the iste conditions & type <strong>of</strong><br />

structure) 2- 3% 2.50% 2643.93 66.10<br />

Sub-Total (B) <strong>of</strong> 1 to 5 2710.02<br />

6.0 Instrumentation ( 1% <strong>of</strong> Sub -Total )B) 1% 2710.02 27.10<br />

7.0 Dewatering (1% <strong>of</strong> Sub-Total (B) 1% 2710.02 27.10<br />

8.0 Contingencies (3% <strong>of</strong> Sub-Total (B) except<br />

on L.S. items) 3% 2710.02 81.30<br />

9.0 Work Charges Establishment (2% <strong>of</strong> Sub-<br />

Total(B) except on L.S. items) 2% 2710.02 54.20<br />

Total <strong>of</strong> 1 to 9 2899.73


POWER HOUSE COMPLEX<br />

S. NO. DESCRIPTION UNIT QTY.<br />

RATE<br />

(Rs.) Amt.in Lac<br />

1.0 Surface Excavation<br />

1.1 Common excavation Cum<br />

1.2 Rock excavation Cum 1000 300.00 3.00<br />

2.0 Underground excavation if underground<br />

<strong>Power</strong> House<br />

2.1 Excavation <strong>of</strong> P/H cavern, transformer cum<br />

MIV cavern and draft tube gate Cum 60000 1000.00 600.00<br />

3.0 Support System<br />

3.1 Rockbolts M 30000 625 187.50<br />

3.2 Steel Rib Supports Ton 300 42000 126.00<br />

3.3 Shotrreting Cum 1300 4000 52.00<br />

3.4 Concrete lagging if required Cum<br />

4.0 Concrete<br />

4.1 M 15 Cum NIL<br />

4.2 M 20 Cum 17000 4000 680.00<br />

4.3 M 25 Cum. NIL<br />

5.0 Reinforcing Steel Ton 1200 27000 324.00<br />

6.0 Structural Steel for ro<strong>of</strong> trusses etc. Ton NIL<br />

Sub-Total A) <strong>of</strong> 1 to 6 1972.50<br />

7.0 Miscellaeneous and Ancillary Works<br />

7.1 Various Miscellaneous works like site<br />

clearance,wiremesh/steel fibre reinforcement<br />

, drilling & grouting, flooring, water pro<strong>of</strong>ing<br />

system, swellex anchor, doors & windows,<br />

painting , lift arrangement, architectural<br />

works, other metal works etc. (4-5% <strong>of</strong> Sub-<br />

Total (A) dpending upon the iste conditions &<br />

type <strong>of</strong> structure)<br />

4 to 5 % 5% 1972.50 98.63<br />

Sub-Total (B) <strong>of</strong> 1 to 7 2071.13<br />

8.0 Instrumentation ( 1% <strong>of</strong> Sub -Total )B) 1% 2071.13 20.71<br />

9.0 Dewatering (2% <strong>of</strong> Sub-Total (B) 2% 2071.13 41.42<br />

10.0 Contingencies (3% <strong>of</strong> Sub-Total (B) except<br />

on L.S. items) 3% 2071.13 62.13<br />

11.0 Work Charges Establishment (2% <strong>of</strong> Sub-<br />

Total(B) except on L.S. items) 2% 2071.13 41.42<br />

Total <strong>of</strong> 1 to 11 2236.82


SWITCHYARD<br />

S. NO. DESCRIPTION UNIT QTY.<br />

RATE<br />

(Rs.) Amt.in Lac<br />

1.0 Under ground Excavation<br />

1.1 Common excavation Cum<br />

1.2 Rock excavation Cum 11696 1000.00 116.96<br />

2.0 Supports System<br />

2.1 Rockbolts M 1200 525 6.30<br />

2.2 Steel ribs suppots (if required) Ton 70 42000 29.40<br />

2.3 Shotcreting Cum<br />

3.0 Earth work in filling if required<br />

4.0 Concrete<br />

4.1 M 15 Cum 1400 2930.00 41.02<br />

4.2 M 20 Cum 100 3390.00 3.39<br />

4.3 M 25 Cum. NIL<br />

5.0 Reinforcing Steel Ton 43 27000 11.61<br />

6.0 Stone/Brick Masonary Cum NIL<br />

Sub-Total (A) <strong>of</strong> 1 to 6 208.68<br />

7.0 Miscellaeneous<br />

7.1 Various Miscellaneous works like Site<br />

clearence, PVC pippes,Control block building<br />

work like flooring,doors,windowes etc.<br />

including wate supply and sewerage, Boulder<br />

pitching,Metalworks etc. (4-5 % <strong>of</strong> Sub<br />

Total(A) depending on thte site conditions &<br />

type pf structure) 4 to 5% 4.50% 208.68 9.39<br />

Sub-Total (B) <strong>of</strong> 1 to 7 218.07<br />

8.0 Dewatering (2% <strong>of</strong> Sub-Total (B) 2% 218.07 4.36<br />

9.0 Contingencies (3% <strong>of</strong> Sub-Total (B) except<br />

on L.S. items) 3% 218.07 6.54<br />

10.0 Work Charges Establishment (2% <strong>of</strong> Sub-<br />

Total(B) except on L.S. items) 2% 218.07 4.36<br />

Total <strong>of</strong> 1 to 10 233.34


ADITS<br />

S. NO. DESCRIPTION UNIT QTY.<br />

RATE<br />

(Rs.) Amt.in Lac<br />

1.0 Surface Excavation<br />

1.1 Common excavation Cum 100 125.00 0.13<br />

1.2 Rock excavation Cum 200 300.00 0.60<br />

2.0 Under ground excavation<br />

2.1 Excavation <strong>of</strong> adits Cum 32650 1000 326.50<br />

3.0 Supports System<br />

3.1 Rockbolts M 16000 625 100.00<br />

3.2 Steel ribs suppots (if required) Ton 280 42000 117.60<br />

3.3 Shotcreting Cum 2830 4000 113.20<br />

3.4 Concrete lagging if required Cum NIL<br />

4.0 Concrete<br />

4.1 M 10 Cum 750 2560 19.20<br />

4.2 M 15 Cum NIL<br />

4.3 M 20 Cum. NIL<br />

4.3 M 25 Cum. NIL<br />

5.0 Reinforcing Steel Ton NIL<br />

Sub-Total (A) <strong>of</strong> 1 to 5 677.23<br />

6.0 Miscellaeneous<br />

6.1 Various Miscellaneous works like drilling &<br />

grouting, wiremesh reinforcement ,masonary<br />

works,PVC pipes for drainage etc. (3-4 % <strong>of</strong><br />

Sub Total(A) depending on the site conditions<br />

& type pf structure)<br />

3 to 4% 3.50% 677.23 23.70<br />

Sub-Total (B) <strong>of</strong> 1 to 6 700.93<br />

7.0 Instrumentaion (1% <strong>of</strong> Sub-Total (B) 1% 700.93 7.01<br />

8.0 Dewatering (2% <strong>of</strong> Sub-Total (B)<br />

Contingencies (3% <strong>of</strong> Sub-Total(B) except on<br />

2% 700.93 14.02<br />

9.0 L.S. items)<br />

Work Charges Establishment (2% <strong>of</strong> Sub-<br />

3% 700.93 21.03<br />

10.0 Total(B) except on L.S. items) 2% 700.93 14.02<br />

Total <strong>of</strong> 1 to 10 757.00


Hydro-Mechaniocal Works<br />

S. NO. DESCRIPTION UNIT QTY.<br />

1.0 DIVERSION TUNNEL WORKS<br />

Gate (size) Ton Ton<br />

Embeded Parts Ton NIL<br />

Rope drum Hoist (as per capacity) Set NIL<br />

Hoist supporting structure & trestle Set NIL<br />

RATE<br />

(Rs.) Amt.in Lac<br />

2.0 SPILL WAY STRUCTURE<br />

a Radial gates (Size) 5.00mx6m Ton 120 100000 120.00<br />

Embedded parts (including anchorage) Ton 42 50000 21.00<br />

Hydraulic hoist Set 2 100000 2.00<br />

b Bulk head gates (size )5.00mx6m Ton 12.4 100000 12.38<br />

Embedded parts Ton 4.3 50000 2.17<br />

Gantry Crane Set 1 500000 5.00<br />

3.0 INTAKE STRUCTURE<br />

a Intake Gate (size) Ton NIL<br />

Embedded parts for Intake gates Ton NIL<br />

Rope Drum Hoist (as per capacity) Set NIL<br />

Hoist Plateform & trustle Set NIL<br />

b Bulk head gates (size) 5.50mx3m Ton 40 100000 40.00<br />

Embedded Parts For Bulk Head Gates Ton 15 50000 7.50<br />

Gantry Crane as per capacity Set 1 500000 5.00<br />

4.0 THRASH RACKS/TRASH RACK CLEANING MACHINE<br />

a Trash Rack Cleaning Machine Set 1 100000 1.00<br />

b Thrash Racks and embedded parts Ton 49 50000 24.50<br />

5.0 Desanding Basin<br />

Stoplogs Ton 70 60000 42.00<br />

Embedded parts Ton 26 50000 13.00<br />

Gantry Crane Set 1 500000 5.00<br />

6.0 DRFT TUBE GATE<br />

gates (size) 4mx6.50m Ton 7.500 100000 7.50<br />

Embedded Parts For Draft Tube Gates Ton 2.500 50000 1.25<br />

Gantry Crane (as per capacity) Set 1 500000 5.00<br />

7.0 TAIL RACE<br />

a Outlet Stoplogs Set NIL<br />

b Embedded parts Ton NIL<br />

8.0 SURGE SHAFT<br />

a Stoplogs Ton 35 60000 21.00<br />

b Embedded parts Ton 13 50000 6.50<br />

c Travelling Hoist Set 1 500000 5.00<br />

G/Total (1to8) 346.79


J - <strong>Power</strong> Plant and Civil Works<br />

S.No. Description Unit Qty. RATE (Rs Amt.in Lac<br />

I) C<strong>of</strong>fer Dam 329.76<br />

II) Barrage 9,243.19<br />

C-Works 9572.95<br />

III) Intakes Structure 337.34<br />

IV) Desanding Chamber 5968.28<br />

V) Head Race Tunnel & Tailrace Tunnel 6,415.56<br />

VI) Surge Shaft 862.58<br />

VII) Pressure Shaft 2899.73<br />

VIII) <strong>Power</strong> House Complex 2236.82<br />

IX) Switch Yard 233.34<br />

X) Adits 757.00<br />

XI) Hydro-Mechaniocal Works 346.79<br />

Total J-<strong>Power</strong> Plant 20,057.42


Chhatru HEP (108MW ) in Chenab Basin <strong>of</strong> HIMACHAL PREDESH<br />

ABSTRACT OF COST OF CIVIL WORK<br />

Annex -D<br />

S.N. Description<br />

Amount in Lac<br />

A CIVIL WORKS<br />

1 DIRECT CHARGES<br />

I-Works<br />

A-Priliminary 501.25<br />

B-Land 350.00<br />

C-Works 9572.95<br />

J-<strong>Power</strong> Plant Civil Works 20,057.42<br />

K- Buildings 1341.94<br />

M-Plantation 25.00<br />

O-Miscelleoneous 966.77<br />

P- Maintenance 335.05<br />

Q- Special Tools & Plants 496.71<br />

R- Communication 656.70<br />

X- Envoirment & Ecology 470.00<br />

Y- Losses on Stock 79.27<br />

Total <strong>of</strong> I-Works 34853.06<br />

II - Establishment @ 8% <strong>of</strong> cost <strong>of</strong> I-Works 2760.24<br />

Less B- Land<br />

III - Tools & Plants @ 1% <strong>of</strong> cost <strong>of</strong> I - Works 348.53<br />

IV _ Suspence 680.04<br />

V - Recipts & Recoveries ( - )<br />

2 INDIRECT CHARGES<br />

a) Capatilised Value <strong>of</strong> Abatement <strong>of</strong> Land Revenue<br />

@5% <strong>of</strong> cost <strong>of</strong> land<br />

328.84<br />

TOTAL DIRECT CHARGES 38313.03<br />

17.50<br />

b) Audit & Account Charges @ 1% <strong>of</strong> cost <strong>of</strong> I - Works 348.53<br />

TOTAL INDIRECT CHARGES 366.03<br />

TOTAL DIRECT & INDIRECT CHARGES 38679.07<br />

Lac.


ABSTRACT OF COST<br />

A Civil Works 38679.07 Lac.<br />

B Electrical Works<br />

P- Production 13612.06 Lac.<br />

T-Transmission 844.68 Lac.<br />

TOTAL COST 53135.80 Lac.


S.N.<br />

1 Land Required for<br />

A. Reservoir submergence area<br />

B. Project features<br />

C. Township,store area and roads<br />

D. Quarry site<br />

E. Muck disposal Area & Job facilities<br />

F. Transit Camp And Guest Houses & Colony<br />

G. Project roads<br />

Name <strong>of</strong> Project Component<br />

H. Land for Rehablitation Purpose<br />

Total A<br />

Forest/<br />

Govt.<br />

/Pvt.<br />

Land<br />

Rates in<br />

Rs.Lacs./Ha<br />

Govt. 20.00 Nil<br />

Pvt.<br />

Area in<br />

Hac.<br />

Govt. 10.00 Nil<br />

Govt. 2.00 Nil<br />

Pvt. 4.00<br />

Govt. 1.50 Nil<br />

Govt. 1.00 Nil<br />

Pvt. 4.00<br />

Pvt. 6.00<br />

6.00<br />

NIL Nil<br />

2 Cost for impletation <strong>of</strong> R&R Plan L.S<br />

Total B<br />

3<br />

Cost <strong>of</strong> establishment for land acquisition<br />

and Rehablitation @6.25 % <strong>of</strong> item B<br />

6.25% 0.00<br />

4 Solitanium Charges @30 % <strong>of</strong> the cost <strong>of</strong><br />

the private land<br />

5 Interest Charges on amount <strong>of</strong> award for<br />

the period between taking over the possetion<br />

<strong>of</strong> land date <strong>of</strong> award @12 % per annum on<br />

25% <strong>of</strong> cost <strong>of</strong> total compensation for thte 2<br />

30% 0.00<br />

years<strong>of</strong> the cost <strong>of</strong> the private land<br />

12% 0.00 2<br />

6<br />

Lega charges @1 % <strong>of</strong> total compensation<br />

7 Labour and material charges for<br />

measurment & demarkation <strong>of</strong> land<br />

1% 0.00<br />

/Properties @ 1% <strong>of</strong> cost <strong>of</strong> land acquisition<br />

1% 0.00<br />

Total<br />

Total land<br />

B - LAND<br />

LS<br />

54.50 Hac.


Total Govt. land<br />

Total Private land<br />

40.50 Hac.<br />

14.00 Hac.


S.N. DESCRIPTION OF BUILDING UNIT<br />

TOTAL<br />

PLINTH<br />

AREA<br />

RATE IN Rs.<br />

1.0 Residential Building<br />

1.1 Permanent residential building Sq. m. 8800 4200<br />

Service Charges @ 31%<br />

1.2 Tem,porary Buildings Sq. m. 6000 3780<br />

Service Charges @ 27%<br />

Total Residential buildings<br />

2.0 Non - Residential Buildings<br />

2.1 Permanent Non - Residential Buildg. Sq. m. 9800 3800<br />

Service Charges @ 22.50%<br />

2.2 Temporary Non Residential Buildg. Sq. m. 2755 3420<br />

Service Charges @ 20.50%<br />

Total Non - Residential buildings<br />

K -BUILDING<br />

Grand Total (Residential + Non - Residential )


S.N. DESCRIPTIOPN<br />

QTY. UNIT RATE<br />

1.0 CAPITAL COST<br />

1.1 Electrification 5 YEAR 90000<br />

1.2<br />

1.3<br />

1.4<br />

2<br />

2.1 Maintenance & <strong>Power</strong> arrangements<br />

2.2 R &M <strong>of</strong> water supply facilities<br />

i.e. 8% <strong>of</strong> capital cost<br />

5 YEAR 3.40<br />

2.3 R & M <strong>of</strong> sanitation & drainage facilities<br />

i.e. 8% <strong>of</strong> capital cost<br />

2.4 R & M <strong>of</strong> Telecommunication system and<br />

5 YEAR 3.40<br />

post <strong>of</strong>ffice<br />

5 YEAR 0.42<br />

2.5 R & M <strong>of</strong> Hospital<br />

5 YEAR 10.00<br />

2.6 R & M <strong>of</strong> rest house and field hostel<br />

5 YEAR 1.00<br />

2.7<br />

2.8<br />

2.9<br />

Water supply, purification and distribution<br />

arrangements including puchase <strong>of</strong> water<br />

tankers, cost <strong>of</strong> tanks and chlorination<br />

Providing sewerage disposal and storm water<br />

drains at various coloney sites.<br />

Furnishing & equiping rest houses field<br />

hostels, hospitals schools etc.<br />

Maintenance & Service charges during<br />

execution period<br />

R & M <strong>of</strong> Research & Quality control<br />

laboratories<br />

Labour welfare compensation and<br />

retrenchment benfits<br />

O-MISCELLANEOUS<br />

Providing sequrity police including R & M <strong>of</strong><br />

Posts<br />

LS<br />

LS<br />

LS<br />

5 YEAR 25.00<br />

5 YEAR 15.00<br />

5 YEAR 5.00<br />

2.10 R & M <strong>of</strong> inspection vehicles and staff cars 5 YEAR 35.00


2.11 R & M <strong>of</strong> school buses and staff buses @ 2.5<br />

lakh per vehicle<br />

2.12<br />

5 YEAR 10.00<br />

5 YEAR 8.00<br />

2.13 R &M <strong>of</strong> field workshops<br />

5 YEAR 0.42<br />

2.14 Maintenance & Running <strong>of</strong> schools<br />

5 YEAR 35.00<br />

3.0 Miscelleonous<br />

3.1 Foundeation stone laying<br />

L.S<br />

3.2 Model exhibition<br />

L.S<br />

3.3 Group insurance<br />

L.S<br />

3.4 Compensation <strong>of</strong> accidents<br />

L.S<br />

3.5<br />

R & M <strong>of</strong> Ambulence @ RS 2.50 Lakh per<br />

Year per Vehicle<br />

Trainning <strong>of</strong> personnel abroad including<br />

study courses and visits<br />

L.S<br />

3.6 Others<br />

L.S<br />

TOTAL


Amount<br />

Rs.Lacs.<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0<br />

0<br />

0<br />

0<br />

350.00


AMT. IN<br />

LAC.<br />

369.60<br />

114.58<br />

226.80<br />

61.24<br />

772.21<br />

372.40<br />

83.79<br />

94.22<br />

19.32<br />

569.73<br />

1341.94


AMOUNT<br />

4.5<br />

43<br />

43<br />

50<br />

17.01<br />

17.01<br />

2.10<br />

50.00<br />

5.00<br />

125.00<br />

75.00<br />

25.00<br />

175.00


50.00<br />

40.00<br />

2.10<br />

175.00<br />

5.00<br />

8.00<br />

15.00<br />

25.00<br />

8.00<br />

8.00<br />

966.77


A-Preliminary<br />

Sr.No. Description Unit Qty. Rate Amount<br />

(lacs)<br />

1. Exprenditure on investigations alredy conducted 14.00<br />

2. Pre-construction and const. Stage investigations:<br />

I) Topographical surveys by the deptt. and survey<br />

<strong>of</strong> India L.S. 50.00<br />

ii) Hydro-meteorological data collection for 5 years<br />

including stablishing self rcording rain/snow<br />

gauge stations, climato-logical laboratory,<br />

silt laboratory and conducting sediment<br />

silt & water tests etc. L.S. 47.25<br />

iii) Geological and geophysical explorations,<br />

geotechnical testing and data collection<br />

sieismological observations and laboratories L.S. 40.00<br />

iv) Construction material testinmg, establishing<br />

soil and rock testing laboratory L.S. 45.00<br />

v) Environment and ecological surveys L.S. 10.00<br />

vi) Hydraulic model studies and testing L.S. 55.00<br />

3. Training <strong>of</strong> engineers and technicians L.S. 30.00<br />

4. Construction <strong>of</strong> access paths and jeepable<br />

roads, for investigation. L.S. 45.00<br />

5. Inspection vehicles for investiqation I/c<br />

R/M charges L.S. 25.00<br />

6. Surveys, drawing mathematicqal and <strong>of</strong>fice<br />

equipment like photo-copier, ammonia<br />

printing machine etc. L.S. 40.00<br />

7. Consultants fees L.S. 35.00<br />

8. Publication <strong>of</strong> brochures, <strong>project</strong> reports .<br />

comprising design reports, estimates, bulletins<br />

completion reports,history <strong>of</strong> the poject etc L.S. 40.00<br />

9. Personal computer along with CGA,<br />

printer and plotter etc. L.S. 25.00<br />

Total 501.25


Q- Special T&P<br />

S.No. Description Unit Qty. Rate Amount<br />

(in Rs.) (lacs)<br />

1. Hydraulic excavator Bucket capacity Nos 2 7500000 150<br />

2.0 cum "<br />

2. Dumper 20 ton capacity " 8 3200000 256<br />

3. Working platform 2 4000000 80<br />

4. Grouting pump " 1 700000 7<br />

5. Grout hole drilling crawler " 1 1500000 15<br />

6. Hydraulic rubber-wheel based drilling " 2 1500000 30<br />

2-boom jumbo<br />

7. Tower crane 25m/3 tons " 1 1E+07 100<br />

8. Concrete pump 40 cum/hr. 2 4500000 90<br />

9. Motor grader 10 tons 145 HP " 1 6500000 65<br />

10. Concrete lorry with 2.5 cum rotary drum " 1 1900000 19<br />

mixer 2.5 rotary drum mixer<br />

11. Draining pump (8 bar water <strong>hydro</strong>phore) " 20 75000 15<br />

30 HP<br />

12. Draining pump 10 HP " 20 50000 10<br />

13. Internal vibrator with <strong>electric</strong> motor<br />

& converter " 1 30000 0.3<br />

14. Transformer 315 KVA " 3 215000 6.45<br />

15. Shotcreting robot 1 8000000 80<br />

16. Hydraulic excavator 1.0 cum " 1 5000000 50<br />

17. Batching plant " 2 4800000 96<br />

18. Wheel loader 1.15 cum " 1 2200000 22<br />

19. Crawler dozer 180 HP " 1 4050000 40.5<br />

20. Air compressor <strong>electric</strong> 500 cfm " 5 750000 37.5<br />

21. Air compressor diesel 500 cfm 148 HP " 5 750000 37.5<br />

22. Jack hammer 52 lbs " 5 30000 1.5<br />

23. Pavement breaker " 1 30000 0.3<br />

24. Concrete mixer 10/7 cft " 4 80000 3.2<br />

25. Transit mixer 14/10 cft " 1 130000 1.3<br />

26. Pneumatic concrtete placer " 1 100000 1<br />

27. Grout pump " 1 700000 7<br />

28. Tipper 4.5 cum " 1 630000 6.3<br />

29. Material truck " 1 800000 8<br />

30. Coarse aggregate processing plant 30 ton " 2 3000000 60<br />

31. wagon drill " 1 800000 8<br />

32. Bus " 3 800000 24<br />

33. Car " 9 400000 36<br />

34 Jeep 20 400000 80<br />

35 Pick up van 4 450000 18<br />

36 Ambulance 2 450000 9<br />

37 Workshop equipment L.S 15<br />

Total cost <strong>of</strong> Q-Special T&P 1485.85<br />

Cost <strong>of</strong> personal carriers 167<br />

Cost <strong>of</strong> Q-Special T& P other than personal<br />

carriers 1318.85<br />

Cost <strong>of</strong> Q-Special T & P chargeable to estimate<br />

25% <strong>of</strong> (cost <strong>of</strong> Q-Special T&P other than<br />

personal carriers) 1318.9 25% 329.71<br />

Cost <strong>of</strong> personal carrier chargeable to<br />

estimate=100% 167 100% 167.00


Total 496.71


R-Comunication<br />

S.No. Description Unit Qty. Rate Amount<br />

(in lacs) (lacs)<br />

1<br />

2<br />

3<br />

4<br />

C/O proposed road from main road (suspension bridge) to<br />

surge shaft and power house 5/7m wide i/c metalling &<br />

tarring.<br />

C/O proposed road from main road to adit <strong>of</strong> HRT 5/7m<br />

wide i/c metalling & tarring.<br />

C/O proposed road from main road to colony 5/7m wide i/c<br />

metalling & tarring.<br />

Realignment <strong>of</strong> existing main road along the reservoir 5/7m<br />

wide i/c metalling & tarring.<br />

Km. 10 17.9 179.00<br />

Km. 4 17.9 71.60<br />

Km. 6 17.9 107.40<br />

Km. 2 17.9 35.80<br />

5 Widening <strong>of</strong> existing motorable road from diversion <strong>of</strong><br />

Khoksar HEP to diversion <strong>of</strong> Chhatru HEP 5/7m wide i/c<br />

metalling & tarring.<br />

Km. 17 14.3 243.10<br />

6 Proposed permanent RCC bridge in place <strong>of</strong> existig<br />

suspension bridge 7.50m wide.<br />

Rmt 22 0.9 19.80<br />

Total 656.70


S.No. Description Unit Qty. Rate Amount<br />

(in Rs.) (lacs)<br />

X-Environment and Ecology<br />

I) Cost <strong>of</strong> compensatory afforestation in <strong>project</strong> L.S. 20.00<br />

2) Cost <strong>of</strong> fule wood L.S. 30.00<br />

3)Cost <strong>of</strong> health facility L.S. 3.00<br />

4) Cost <strong>of</strong> catchment area treatment plan L.S. 400.00<br />

5) Cost <strong>of</strong> reclamation and plantation L.S. 9.00<br />

60 Cost <strong>of</strong> environment monitoring cell L.S. 8.00<br />

V-Receipt & Recoveries<br />

I) Temporary Buildings -<br />

Total 470.00<br />

Cost <strong>of</strong> temporary buildings 321.02 15% 48.15<br />

Credit @15 % -<br />

ii) Q-Special T&P Recoveries under the -<br />

sub-head<br />

'@ 75% <strong>of</strong> Q-Special T&P charged to estimate -<br />

other than personal carriers 329.71 75% 247.28<br />

-<br />

iii) Cost recoverable on a/c <strong>of</strong> resale value <strong>of</strong> personal<br />

carrier @20% <strong>of</strong> capital cost 167 20% 33.40<br />

Total 328.84


Y- Losses on stock<br />

Provision made @ 0.25% on the cost <strong>of</strong> I-Works less<br />

A-Preliminary, B-Land, M-Plantation, O-Misc., P-Maintenance,<br />

Q-Special T&P and X-Environment & Ecology. 31,708.28<br />

I-Works 34,853.06<br />

Less:<br />

A-Preliminary 501.25<br />

B-Land 350.00<br />

M-Plantation 25.00<br />

O-Miscellaneous, % <strong>of</strong> I Works less (A+B+Q) 966.77<br />

P-Maintence 335.05<br />

Q-Speci8al Tools & Plant 496.71<br />

X-Environment and Ecology 470.00<br />

Total 3144.78<br />

P - Maintenance<br />

0.25% 79.27<br />

1% <strong>of</strong> I- works less (A+B+Q) 1% 33505.10 335.05<br />

I-Works 34853.06<br />

less - A- Preliminary 501.25<br />

B-Land 350.00<br />

Q- Special T&P 496.71<br />

Net Total 33505.10


Name <strong>of</strong> <strong>project</strong>:- Chhatru HEP (108MW ) in Chenab Basin<br />

<strong>of</strong> Himachal Predesh<br />

ABSTRACT OF COST OF CIVIL WORK<br />

S.N.<br />

Annexure -13.1 (a)<br />

Annex -D<br />

Amount (in<br />

Crores) (June<br />

2003)<br />

A CIVIL WORKS<br />

1 DIRECT CHARGES<br />

I-Works<br />

A-Priliminary 501.25<br />

B-Land 350.00<br />

C-Works 9572.95<br />

J-<strong>Power</strong> Plant Civil Works 20057.42<br />

K- Buildings 1341.94<br />

M-Plantation 25.00<br />

O-Miscelleoneous 966.77<br />

P- Maintenance 335.05<br />

Q- Special Tools & Plants 496.71<br />

R- Communication 656.70<br />

X- Envoirment & Ecology 470.00<br />

Y- Losses on Stock 79.27<br />

Total <strong>of</strong> I-Works 34853.06<br />

II - Establishment @ 8% <strong>of</strong> cost <strong>of</strong> I-Works Less B- Land 2760.24<br />

III - Tools & Plants @ 1% <strong>of</strong> cost <strong>of</strong> I - Works 348.53<br />

IV _ Suspence 680.04<br />

2 INDIRECT CHARGES<br />

Description<br />

V - Recipts & Recoveries ( - )<br />

a) Capatilised Value <strong>of</strong> Abatement <strong>of</strong> Land Revenue<br />

@5% <strong>of</strong> cost <strong>of</strong> land<br />

328.84<br />

TOTAL DIRECT CHARGES 38313.03<br />

17.50<br />

b) Audit & Account Charges @ 1% <strong>of</strong> cost <strong>of</strong> I - Works 348.53<br />

TOTAL INDIRECT CHARGES 366.03<br />

TOTAL DIRECT & INDIRECT CHARGES 38679.07


CHHATRU HYDRO-ELECTRIC-PROJECT (108 MW)<br />

Annexure -13.1 (b)<br />

COST ESTIMATES OF ELECTRO-MECHANICAL WORKS FOR PRE-FEASIBILITY REPORT<br />

Sl.No Item Qty Rate Amount Excise Duty* Total<br />

Rs.(Lakhs) Rate Amount Amount<br />

(Rs. Lakhs) (Rs. Lakhs)<br />

1 2 3 4 5 6 7 8<br />

1 Generating Unit and 11 KV Bus Duct 36MW,<br />

428.6 RPM with net Head <strong>of</strong> 160 mtrs.<br />

3 Rs.5600/KW 6048.00 16% 967.68 7015.68<br />

2 Step-up transformer, 11/220KV,15MVA,single<br />

phase<br />

10 Rs.260/KVA 390.00 16% 62.40 452.40<br />

3 Auxiliary Electrical Equipment for <strong>Power</strong><br />

Stations (Except transformer) (5% <strong>of</strong> item 1).<br />

302.40 16% 48.38 350.78<br />

4 Auxiliary Equipment and Services for <strong>Power</strong><br />

Stations (5% <strong>of</strong> item-1)<br />

302.40 16% 48.38 350.78<br />

5 220 KV Switchyard GIS. 6 bays 300 Lacs/bay 1800.00 16% 288.00 2088.00<br />

6 Spares (5% <strong>of</strong> 1 and 3% <strong>of</strong> 2-5) 386.24 16% 61.80 448.04<br />

7 Sub-Total-1: 9229.04 10705.68<br />

8 Central Sales Tax ** 4% <strong>of</strong> item 1 to 6 428.23<br />

9 Transportation & Insurance 6% <strong>of</strong> item-7 642.34<br />

10 Erection and Commissioning 8% <strong>of</strong> item-7<br />

(except spares)<br />

820.61<br />

11 Sub-Total-2 : 12596.86<br />

12 Establishment, Contingency, other charges<br />

11% <strong>of</strong> item-7 (excluding duties)<br />

1015.20<br />

Grand Total :- 13612.06<br />

Say Rs. 13612 Lacs


Annexure -13.1 ( c )<br />

CHHATRU HYDRO-ELECTRIC-PROJECT<br />

TRANSMISSION WORKS - COST ESTIMATES<br />

MAIN ABSTRACT OF COST OF TRANSMISSION<br />

Sr.No. Description Amount ( in Lacs)<br />

1 Preliminary Works ( Annex. 1) 5.10<br />

2 Detailed Surveying ( Annex. 2) 1.74<br />

3 Compensation for land, Trees,<br />

Crops, Tree cutting and<br />

afforestation ( Annex. 3)<br />

13.20<br />

4 Transmission Line ( Annex. 4) 626.00<br />

5 Terminal Equipment at Tandi<br />

(LILO <strong>of</strong> one ckt. <strong>of</strong> Khoksar-<br />

Tandi 220Kv D/C line)<br />

0.00<br />

6 PLCC Equipment at Tandi 69.6<br />

7 Buildings 15<br />

8 Vehicles and Workshop<br />

machinery ( Annex. 13)<br />

34<br />

Sub Total-I 764.64<br />

9 Contingency @ 3% on Item 1 to<br />

8<br />

22.94<br />

Sub Total-II 787.58<br />

10 Establishment charges @ 4%, 57.10<br />

GRAND TOTAL 844.68<br />

Say Rs. 845 LACS


YEAR- WISE PHASING OF FUNDS<br />

Installed Capacity 108MW (3*36 MW)<br />

108 MW<br />

Peaking Capacity 108 MW<br />

Energy @ 90% Dependable Year (Over all Efficie<br />

455.72 Million Units<br />

Rate <strong>of</strong> Interest<br />

10.00%<br />

Discounting Rate<br />

12.00%<br />

ea<br />

Civil Works<br />

Electrical Works<br />

Transmission<br />

TOTAL<br />

Rs in Crores<br />

386.79<br />

136.12<br />

8.45<br />

531.36<br />

Civil Works Electrical Works<br />

Transmission<br />

Generation<br />

Gen.+<br />

Trans<br />

2 3 4 5 6 7 col. 3+5 Col3+5+7<br />

% Funds<br />

Reqd.<br />

Rs in<br />

Crores<br />

%<br />

Funds<br />

Reqd.<br />

Annexure 13.2<br />

Rs in<br />

Crores % Funds Reqd. Rs in Crores Rs in Crores<br />

Rs in<br />

Crores<br />

1 5.0% 19.34 0.0% 0.00 0.0% 0.00 19.34 19.34<br />

5.0% 19.34 2.5% 3.40 0.0% 0.00 22.74 22.74<br />

2 7.5% 29.01 5.0% 6.81 5.0% 0.42 35.82 36.24<br />

7.5% 29.01 5.0% 6.81 5.0% 0.42 35.82 36.24<br />

3 15.0% 58.02 10.0% 13.61 10.0% 0.84 71.63 72.48<br />

15.0% 58.02 17.5% 23.82 15.0% 1.27 81.84 83.11<br />

4 17.5% 67.69 20.0% 27.22 22.5% 1.90 94.91 96.81<br />

17.5% 67.69 20.0% 27.22 22.5% 1.90 94.91 96.81<br />

5 10.0% 38.68 20.0% 27.22 20.0% 1.69 65.90 67.59<br />

T 100% 386.79 100.0% 136.12 100.0% 8.45 522.91 531.36


ESCALATED COST<br />

Annexure<br />

Escalation on civil works 0.00% (Yerly)<br />

Escalation on elect. works 0.00% (Yerly)<br />

Gen.+<br />

ea Civil Works Electrical Works<br />

Transmission<br />

Generation Trans<br />

Envisaged Escalated Envisaged Escalated Envisaged Escalated Escalated Escalated<br />

2 3 4 5 6 7 col 3+ 5 col 3+5+7<br />

E<br />

x<br />

p<br />

.<br />

A<br />

l<br />

r<br />

e<br />

a<br />

d<br />

y<br />

i<br />

n<br />

c<br />

u<br />

r<br />

r<br />

e<br />

d 0.14 0.14 0.14 0.14<br />

19.20 19.20 0.00 0.00 0.00 0.00 19.20 19.20<br />

19.34 19.34 3.40 3.40 0.00 0.00 22.74 22.74<br />

29.01 29.01 6.81 6.81 0.42 0.42 35.82 36.24<br />

29.01 29.01 6.81 6.81 0.42 0.42 35.82 36.24<br />

58.02 58.02 13.61 13.61 0.84 0.84 71.63 72.48<br />

58.02 58.02 23.82 23.82 1.27 1.27 81.84 83.11<br />

67.69 67.69 27.22 27.22 1.90 1.90 94.91 96.81<br />

67.69 67.69 27.22 27.22 1.90 1.90 94.91 96.81<br />

38.68 38.68 27.22 27.22 1.69 1.69 65.90 67.59<br />

T<br />

G<br />

386.65 386.65 136.12 136.12 8.45 8.45 522.77 531.22<br />

.<br />

T<br />

386.79 386.79 136.12 136.12 8.45 8.45 522.91 531.36<br />

o<br />

Esclation: 0.00 0.00 0.00 0.00 0.00


COST OF THE PROJECT INCLUDING IDC. (At power house bus bars)<br />

Rate <strong>of</strong><br />

interest:-<br />

EQUITY 30% 156.87<br />

Loan @ 10.00% 70% 366.04<br />

Discounting factor 12.00% Total 522.91<br />

Annexure 13.3<br />

H<br />

a<br />

l<br />

f-<br />

Y<br />

e Phasing <strong>of</strong><br />

NPV <strong>of</strong><br />

a Escalated Equity LOAN loan Op.<br />

Int fin. From Int fin. From<br />

Total Discountin NPV <strong>of</strong> Esclated<br />

r Hard Cost 30% 70% Bal. Interest on loan. Eq.30% Loan.70% Total Loan Equity g Factor IDC Cost<br />

2 3 4 5 6 7 8 9 10<br />

19.34 5.80 13.54 0 0.34 0.10 0.24 13.77 5.90 1.00 0.34 19.34<br />

22.74 6.82 15.92 13.77 1.09 0.33 0.76 16.68 7.15 0.94 1.03 21.46<br />

35.82 10.74 25.07 30.46 2.15 0.64 1.50 26.58 11.39 0.89 1.91 31.88<br />

35.82 10.74 25.07 57.03 3.48 1.04 2.43 27.51 11.79 0.84 2.92 30.07<br />

71.63 21.49 50.14 84.54 5.48 1.64 3.84 53.98 23.13 0.79 4.34 56.74<br />

81.84 24.55 57.29 138.51 8.36 2.51 5.85 63.14 27.06 0.75 6.25 61.16<br />

94.91 28.47 66.44 201.65 11.74 3.52 8.22 74.66 32.00 0.70 8.28 66.91<br />

94.91 28.47 66.44 276.31 15.48 4.64 10.83 77.27 33.12 0.67 10.29 63.12<br />

65.90 19.77 46.13 353.58 14.12 4.24 9.89 56.02 24.01 0.63 8.86 41.35<br />

T 522.91 156.87 366.04 62.24 18.67 43.56 409.60 175.54 44.22 392.02<br />

Original Cost 522.91<br />

Esc. 0.00<br />

Hard Escalated 522.91 89.36% 89.36% Loan 409.60 70.00%<br />

IDC = 62.24 10.64% 10.64% Equity 175.54 30.00%<br />

Total = 585.15 100% 100.00% Total 585.15


COST OF THE PROJECT INCLUDING IDC. (At purchase center)<br />

Switch 2<br />

Rate <strong>of</strong><br />

interest:-<br />

EQUITY 30.00% 159.41<br />

Loan @ 10.00% 70.00% 371.95<br />

Discounting factor 12.00% Total 531.36<br />

Annexure 13.3 (b)<br />

H<br />

a<br />

l<br />

f-<br />

Y<br />

e Phasing <strong>of</strong><br />

NPV <strong>of</strong><br />

a Escalated Equity LOAN loan Op.<br />

Int fin. From Int fin. From<br />

Total Discountin NPV <strong>of</strong> Esclated<br />

r Hard Cost 30% 70% Bal. Interest on loan. Eq.30% Loan.70% Total Loan Equity g Factor IDC Cost<br />

2 3 4 5 6 7 8 9 10<br />

19.34 5.80 13.54 0 0.34 0.10 0.24 13.77 5.90 1.00 0.34 19.34<br />

22.74 6.82 15.92 13.77 1.09 0.33 0.76 16.68 7.15 0.94 1.03 21.46<br />

36.24 10.87 25.37 30.46 2.16 0.65 1.51 26.88 11.52 0.89 1.92 32.25<br />

36.24 10.87 25.37 57.33 3.50 1.05 2.45 27.82 11.92 0.84 2.94 30.43<br />

72.48 21.74 50.73 85.15 5.53 1.66 3.87 54.60 23.40 0.79 4.38 57.41<br />

83.11 24.93 58.17 139.75 8.44 2.53 5.91 64.08 27.46 0.75 6.31 62.10<br />

96.81 29.04 67.77 203.83 11.89 3.57 8.32 76.09 32.61 0.70 8.38 68.25<br />

96.81 29.04 67.77 279.92 15.69 4.71 10.98 78.75 33.75 0.67 10.43 64.39<br />

67.59 20.28 47.31 358.67 14.34 4.30 10.04 57.35 24.58 0.63 9.00 42.41<br />

T 531.36 159.41 371.95 62.96 18.89 44.07 416.03 178.30 44.72 398.03<br />

Original Cost 531.36<br />

Esc. 0.00<br />

Hard Escalated 531.36 89.41% 89.41% Loan 416.03 70.00%<br />

IDC = 62.96 10.59% 10.59% Equity 178.30 30.00%<br />

Total = 594.32 ###### 100.00% Total 594.32


Annexure -13.4<br />

DETAIL OF DEPRECIATION<br />

Life in % Rate Cost (Rs.in Dep. (Rs.<br />

years <strong>of</strong> Dep. Lac.) in Lac.)<br />

I-CIVIL WORKS<br />

Diversion Barrage 50 1.95 9,243.19 180.24<br />

Intake Structure 50 1.95 337.34 6.58<br />

Desanding Chamber 50 1.95 5,968.28 116.38<br />

Head Race Tunnel &<br />

Tail Race<br />

50 1.95 6,415.56 125.10<br />

Surge Shaft 35 3.4 862.58 29.33<br />

Pressure Shaft 35 3.4 2,899.73 98.59<br />

P/ House 35 3.4 2,236.82 76.05<br />

Buildings. 50 3.02 233.34 7.05<br />

R-Communication 50 3.02 757.00 22.86<br />

Total 28,953.82 662.18<br />

II-ELECTRICAL WORKS<br />

Generating Plant and Equi 35 3.4 5500 187.00<br />

Transformers 25 7.84 390 30.58<br />

Switchgears etc. 25 7.84 20 1.57<br />

Communication equipeme 15 12.77 180 22.99<br />

Batteries and DC equipts. 5 33.44 45 15.05<br />

Air conditioning and venti 15 12.77 50 6.39<br />

Bus ducts 50 1.95 150 2.93<br />

Plant handling equipts. 5 33.44 800 267.52<br />

Total 10294.96 534.01<br />

G. Total 39,248.78 1196.19<br />

Rate <strong>of</strong> Depreciation-<br />

Say<br />

3.05<br />

3%


Calculations for Levelised Tariff For Chhatru Hydro Electric Project (AT POWER HOUSE BUS BARS)<br />

Assumtions<br />

( without free power)<br />

Cost Of Project Rs. 522.91 Crores<br />

IDC Rs. 62.24 Crores<br />

Total Cost 585.15 Crores<br />

Loan<br />

70%<br />

Equity<br />

30% Return on Equity (Post Tax) 16.0%<br />

Loan amount<br />

409.60 Crores Income Tax @ 35% + 10% Surcharge 38.5%<br />

Design Energy 455.72 Million Units Assumed Sale Rate :<br />

Rs. 2.75 per unit<br />

Free <strong>Power</strong><br />

0%<br />

Available Energy<br />

Interest Rate<br />

455.72<br />

10.0%<br />

Million Units<br />

Working Capital: 1 month O&M Charges including spares + Actual recievables for 2 months<br />

Repayment Period<br />

12 Years Rs. 21.37 Crores<br />

O&M Charges<br />

1.5%<br />

Depreciation(yearly)<br />

3.00% (Straight Line Method up 90% <strong>of</strong> the value)<br />

Aux. Consumption<br />

0.7% Dep. Amount 90% <strong>of</strong> the total cost 526.63 Lac.<br />

Transformation Losses<br />

0.5% Dep. Amount recovered 526.63 Lac.<br />

Interest on Working Captial<br />

9.75%<br />

Discount Rate<br />

12.00%<br />

Transmission Losses 0.00%<br />

Year 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18<br />

Capacity Charges<br />

1 Interest on debt Rs. Crores 39.25 35.84 32.43 29.01 25.60 22.19 18.77 15.36 11.95 8.53 5.12 1.71 0.00 0.00 0.00 0.00 0.00 0.00<br />

2 Depreciation @ 3.00% Rs. Crores 17.55 17.55 17.55 17.55 17.55 17.55 17.55 17.55 17.55 17.55 17.55 17.55<br />

a AAD 1/12 <strong>of</strong> loan minus dep. Rs. Crores 16.58 16.58 16.58 16.58 16.58 16.58 16.58 16.58 16.58 16.58 16.58 16.58<br />

b Total Depriciation Rs. Crores 34.13 34.13 34.13 34.13 34.13 34.13 34.13 34.13 34.13 34.13 34.13 34.13 5.09 5.09 5.09 5.09 5.09 5.09<br />

3 Return on Equity Rs. Crores 28.09 28.09 28.09 28.09 28.09 28.09 28.09 28.09 28.09 28.09 28.09 28.09 28.09 28.09 28.09 28.09 28.09 28.09<br />

4 O&M Charges Rs. Crores 8.78 8.78 8.78 8.78 8.78 8.78 8.78 8.78 8.78 8.78 8.78 8.78 8.78 8.78 8.78 8.78 8.78 8.78<br />

5 Interest on W.C Rs. Crores 2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08<br />

6 Income Tax on ROE Rs. Crores 17.58 17.58 17.58 17.58 17.58 17.58 17.58 17.58 17.58 17.58 17.58 17.58 17.58 17.58 17.58 17.58 17.58 17.58<br />

7 Total<br />

129.92 126.50 123.09 119.68 116.26 112.85 109.44 106.02 102.61 99.20 95.78 92.37 61.62 61.62 61.62 61.62 61.62 61.62<br />

8 Equated energy Sent Out Rs/Kwh 2.89 2.81 2.73 2.66 2.58 2.51 2.43 2.35 2.28 2.20 2.13 2.05 1.37 1.37 1.37 1.37 1.37 1.37<br />

9 Discounted Calculations<br />

10 Rate<br />

12.00% 12.00% 12.00% 12.00% 12.00% 12.00% 12.00% 12.00% 12.00% 12.00% 12.00% 12.00% 12.00% 12.00% 12.00% 12.00% 12.00% 12.00%<br />

11 Discounting Factor<br />

1.00 0.89 0.80 0.71 0.64 0.57 0.51 0.45 0.40 0.36 0.32 0.29 0.26 0.23 0.20 0.18 0.16 0.15<br />

12 Discounted Equated Charge Rs/Kwh 2.89 2.51 2.18 1.89 1.64 1.42 1.23 1.07 0.92 0.79 0.68 0.59 0.35 0.31 0.28 0.25 0.22 0.20<br />

Levelised Tariff(Discounted) Rs/Kwh<br />

Annexure 13.5<br />

2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28


Annexure 13.5 Contd.<br />

19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35<br />

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00<br />

5.09 5.09 5.09 5.09 5.09 5.09 5.09 5.09 5.09 5.09 5.09 5.09 5.09 5.09 5.09 5.09 5.09<br />

28.09 28.09 28.09 28.09 28.09 28.09 28.09 28.09 28.09 28.09 28.09 28.09 28.09 28.09 28.09 28.09 28.09<br />

8.78 8.78 8.78 8.78 8.78 8.78 8.78 8.78 8.78 8.78 8.78 8.78 8.78 8.78 8.78 8.78 8.78<br />

2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08 2.08<br />

17.58 17.58 17.58 17.58 17.58 17.58 17.58 17.58 17.58 17.58 17.58 17.58 17.58 17.58 17.58 17.58 17.58<br />

61.62 61.62 61.62 61.62 61.62 61.62 61.62 61.62 61.62 61.62 61.62 61.62 61.62 61.62 61.62 61.62 61.62<br />

1.37 1.37 1.37 1.37 1.37 1.37 1.37 1.37 1.37 1.37 1.37 1.37 1.37 1.37 1.37 1.37 1.37<br />

12.00% 12.00% 12.00% 12.00% 12.00% 12.00% 12.00% 12.00% 12.00% 12.00% 12.00% 12.00% 12.00% 12.00% 12.00% 12.00% 12.00%<br />

0.13 0.12 0.10 0.09 0.08 0.07 0.07 0.06 0.05 0.05 0.04 0.04 0.03 0.03 0.03 0.02 0.02<br />

0.18 0.16 0.14 0.13 0.11 0.10 0.09 0.08 0.07 0.06 0.06 0.05 0.05 0.04 0.04 0.03 0.03<br />

2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28


CHHATRU HYDRO-ELECTRIC-PROJECT<br />

TRANSMISSION WORKS - COST ESTIMATES<br />

MAIN ABSTRACT OF COST OF TRANSMISSION<br />

Sr.No. Description Amount ( in Lacs)<br />

1 Preliminary Works ( Annex. 1) 5.10<br />

2 Detailed Surveying ( Annex. 2) 1.74<br />

3 Compensation for land, Trees,<br />

Crops, Tree cutting and afforestation<br />

( Annex. 3)<br />

13.20<br />

4 Transmission Line ( Annex. 4) 626.00<br />

5 Terminal Equipment at Tandi (LILO<br />

<strong>of</strong> one ckt. <strong>of</strong> Khoksar-Tandi<br />

220Kv D/C line)<br />

0.00<br />

6 PLCC Equipment at Tandi 69.6<br />

7 Buildings 15<br />

8 Vehicles and Workshop machinery<br />

( Annex. 13)<br />

34<br />

Sub Total-I 764.64<br />

9 Contingency @ 3% on Item 1 to 8 22.94<br />

Sub Total-II 787.58<br />

10 Establishment charges @ 4%, Tools<br />

and Plants @ 1%, Losses on stock<br />

@ 0.25%, Maintenance during<br />

construction @ 1%, Audit and<br />

accounts charges @ 1%<br />

57.10<br />

GRAND TOTAL 844.68<br />

Say Rs. 845 LACS


CHHATRU HYDRO-ELECTRIC-PROJECT<br />

TRANSMISSION WORKS - COST ESTIMATES<br />

COST OF PRELIMINARY WORKS<br />

Annexure-1<br />

Sr.No Description Qty Amount in Lacs<br />

1 Cost <strong>of</strong> Temporary Sheds and<br />

camping requirement ( Annex.- 1.1)<br />

2.5<br />

2 Cost <strong>of</strong> Reconnaisance and<br />

Preliminary survey ( Annex.- 1.2)<br />

0.60<br />

3 PTCC Clearance LS 2<br />

TOTAL<br />

Sheet 2<br />

5.10


CHHATRU HYDRO-ELECTRIC-PROJECT<br />

TRANSMISSION WORKS - COST ESTIMATES<br />

Annexure-1.1<br />

ABSTRACT OF COST FOR TEMPORARY SHEDS AT EACH<br />

CAMPING SITE<br />

Sr. No Description Qty Rate Unit Amount in Rs<br />

1 Temporary Sheds <strong>of</strong> CGI<br />

Sheets on sides and top with<br />

wooden ballies posts and<br />

Wooden Rafters<br />

100 700 Sq.Mtr 70000<br />

2 One Swiss Engineer Cottage,<br />

Engineer tent ( 3.65 x 3.65)<br />

1 5500 No 5500<br />

3 Four Labour tents for<br />

Chowkidars Double Ply<br />

4 5500 Nos 22000<br />

4 Area Fencing with Angle Iron/<br />

wooden Posts and barbed<br />

wire etc.<br />

1 22000 LS 22000<br />

5 Miscellaneous Tools for<br />

setting up Camp<br />

1 5500 LS 5500<br />

6 Total Cost <strong>of</strong> Each Camp 125000<br />

7 Number <strong>of</strong> Camps required<br />

for surveying the<br />

Transmission System under<br />

Sorang HEP<br />

2 Nos<br />

8 TOTAL COST OF 2 CAMPS 250000<br />

Sheet 3<br />

Say Rs 2.5<br />

Lacs


CHHATRU HYDRO-ELECTRIC-PROJECT<br />

TRANSMISSION WORKS - COST ESTIMATES<br />

Annexure-1.2<br />

ABSTRACT OF COST FOR RECONNAISANCE AND<br />

PRELIMINARY SURVEY OF 220 KV D/C LINES.<br />

Sr. No Description<br />

Reconnaisance and<br />

Preliminary survey ( Unit 1<br />

km <strong>of</strong> length )<br />

Qty Rate Unit Amount in Rs<br />

A SURVEYING PARTY<br />

I) Surveyor (Regular) 1 6000 No 6000<br />

ii) Beldar 6 2250 No 13500<br />

iii) Chowkidar 2 2250 Nos 4500<br />

Sub Total 24000<br />

B Labour for Reconnaisance<br />

and Preliminary survey <strong>of</strong> 1<br />

km <strong>of</strong> line<br />

Assuming 4 days for 1 Km<br />

<strong>of</strong> line and 25 working days<br />

in a month<br />

3840<br />

C Wooden Pegs 16 9 Nos 144<br />

Total (B+C) 3984<br />

Cost <strong>of</strong> conducting<br />

preliminary Survey per Km<br />

Line length<br />

3984<br />

Cost <strong>of</strong> conducting<br />

preliminary Survey for 15<br />

Kms Line length<br />

15 Kms. 59760<br />

Say Rs 0.60<br />

Sheet 4<br />

Lacs


CHHATRU HYDRO-ELECTRIC-PROJECT<br />

TRANSMISSION WORKS - COST ESTIMATES<br />

COST OF DETAILED SURVEYING OF 220 KV D/C LINE.<br />

Sr. No Description Qty Rate Unit Amount in Rs<br />

A SURVEYING PARTY<br />

Assuming 4 days for<br />

conducting <strong>of</strong> survey <strong>of</strong> 1<br />

km <strong>of</strong> line<br />

(I) Surveyor (Regular) 1 6000 No 6000<br />

(ii) Beldar (Daily Wages) 6 2250 Nos 13500<br />

(iii) Chowkidar (Daily Wages) 2 2250 Nos 4500<br />

(iv) Labour for 4 days<br />

( Assuming 4 days for 1 km<br />

and 25 working days in a<br />

month)<br />

3840<br />

(v) Wooden pegs 16 9 Nos 144<br />

Total 3984<br />

B Stacking ( Unit 1 Km <strong>of</strong><br />

line)<br />

0<br />

(I) Surveyor (Regular) 1 6000 Nos 6000<br />

(ii) Beldar (Daily Wages) 12 2250 Nos 27000<br />

(iii) Chowkidar (Daily Wages) 2 2250 4500<br />

Sub Total 37500<br />

(iv) Labour for 4 days<br />

( Assuming 4 days for 1 km<br />

and 25 working days in a<br />

month)<br />

6000<br />

(v) Stone Marking Pillars 8 80 Nos 640<br />

Total 6640<br />

C Transportation<br />

Camp Shifting Etc. 1000<br />

Total (A+B+C) 11624<br />

Cost <strong>of</strong> Detailed survey <strong>of</strong><br />

15 Kms <strong>of</strong> Line<br />

15 kms. 174360<br />

Say Rs 1.74<br />

Sheet 5<br />

Lacs<br />

Annexure-2


CHHATRU HYDRO-ELECTRIC-PROJECT<br />

TRANSMISSION WORKS - COST ESTIMATES<br />

Annexure-3<br />

COST OF COMPENSATION FOR LAND, TREES, CROPS,<br />

TREE CUTTING AND AFFORESTATION<br />

Sr. No Description Qty Rate Unit Amount in Rs<br />

1 Compensation for tree<br />

cutting and afforestation<br />

15 20000 Kms 300000<br />

2 Compensation for land<br />

falling under the towers and<br />

rent for camping site<br />

15 50000 Kms 750000<br />

3 Compensation to damage to<br />

crops under the line<br />

15 18000 Kms 270000<br />

Total 1320000<br />

Say Rs 13.2<br />

Lacs<br />

Sheet 6


CHHATRU HYDRO-ELECTRIC-PROJECT<br />

TRANSMISSION WORKS - COST ESTIMATES<br />

ESTIMATE OF COST FOR 220 KV D/C TRANSMISSION LINE FROM<br />

BARDANG TO TANDI 400 KV POOLING-IN STATION.<br />

Sr. No Description Qty Rate Unit Amount in Lacs<br />

1 220 KV D/C line (Snow<br />

Zone) ( Annex. 5)<br />

15 35.40 Kms 531.00<br />

2 Retaining Walls 65<br />

3 Benching <strong>of</strong> towers 30<br />

TOTAL 626.00<br />

Sheet 7


Annexure-4


CHHATRU HYDRO-ELECTRIC-PROJECT<br />

TRANSMISSION WORKS - COST ESTIMATES<br />

BREAK UP ESTIMATE FOR 1 KM OF 220 KV D/C LINE.<br />

(SNOW ZONE)<br />

Conductor size= 0.4 Sq. Inch Cu. Eq. "ACSR" ZEBRA<br />

Earth Wire Size= 7/3.18 mm GSS 140 Kgf Quality.<br />

Normal Span= 350 MTS<br />

Annexure-5<br />

Sr. No Description Qty Rate Unit Amount in Rs<br />

1 Steel for towers<br />

(Prefabricated galvanized/<br />

painted) ( Annex. 6)<br />

39.27 31000 MT 1217370.00<br />

2 Nuts and Bolts ( Annex. 6) 1.96 60000 MT 117600<br />

3 Tower Accessories<br />

( Annex. 7)<br />

4 Conductor ( Allowing<br />

1.5% for Sag and wastage)<br />

5 Conductor Accessories<br />

(Annex. 8)<br />

6 Ground Wire ( Allowing<br />

1.5% for Sag and Wastage)<br />

24770<br />

6.09 140000 Kms 852600<br />

16590<br />

1004.18 40 Kg 40167.2<br />

7 Ground Wire Accessories (<br />

Annex. 9)<br />

5760<br />

8 INSULATORS (ANNEX.<br />

10)<br />

I) Suspension 48 350 Nos 16800<br />

ii) Tension 510 400 Nos 204000<br />

9 INSULATOR<br />

HARDWARE (<br />

ANNEX. 12)<br />

I) Suspension 3 1600 Set 4800<br />

ii) Tension 30 2100 Set 63000<br />

10 Foundation Material, Sand,<br />

Bajri and Concrete<br />

(Annex. 7).<br />

55.37 3200 Cu Mt. 177184<br />

Sub Total 2740641.20


Sr. No Description Qty Rate Unit Amount in Rs<br />

11 Transportation @5%,<br />

Insutrance @ 1% and CST<br />

@ 4% ( Total 10% on Item<br />

1 to 10)<br />

274064.12<br />

12 Erection Charges<br />

( Annex. 11)<br />

525741.72<br />

GRAND TOTAL 3540447.04<br />

Say Rs 35.4<br />

Sheet 8 Lacs


CHHATRU HYDRO-ELECTRIC-PROJECT<br />

TRANSMISSION WORKS - COST ESTIMATES<br />

Annexure-5<br />

BREAK UP ESTIMATE FOR 1 KM OF 220 KV S/C LINE ON D/C TOWERS<br />

(NON SNOW ZONE)<br />

Conductor size= 0.4 Sq. Inch Cu. Eq. "ACSR" ZEBRA<br />

Earth Wire Size= 7/3.18 mm GSS 140 Kgf Quality.<br />

Normal Span= 350 MTS<br />

Sr. No Description Qty Rate Unit Amount in Rs<br />

1 Steel for Towers ( Prefabricated<br />

galvanised/ Painted ) Annex. 8<br />

27.13 31000 MT 841133.33<br />

2 Nuts and bolts ( Annex. 8) 1.36 60000 MT 81600<br />

3 Tower Accessories ( Annex. 9) 24770<br />

4 Conductor ( Allowing 1.5% for<br />

Sag and wastage)<br />

3.045 140000 Km 426300<br />

5 Conductor Accessories (Annex.<br />

10)<br />

8295<br />

6 Ground Wire Allowing (1.5% for<br />

Sag and Wastage)<br />

1004.18 40 Kg 40167.2<br />

7 Ground Wire Accessories (<br />

Annex. 11)<br />

5760<br />

8 INSULATORS (ANNEX. 12)<br />

I) Suspension 22.5 350 Nos 7875<br />

ii) Tension 240 400 Nos 96000<br />

9 INSULATOR HARDWARE<br />

(ANNEX. 12)<br />

I) Suspension 1.5 1600 Set 2400<br />

ii) Tension 15 2100 Set 31500<br />

10 Foundation Material, Sand, Bajri<br />

and concrete (Annex. 8)<br />

25.33 3200 Cu. Mt 81056<br />

Sub Total 1646856.53<br />

11 Transportation @ 5%, Insurance<br />

@ 1% and CST @ 4% ( Total<br />

10% on Item 1 to 10)<br />

164685.65<br />

12 Erection Charges ( Annex. 14) 292049.56<br />

GRAND TOTAL 2103591.7<br />

Say Rs 21.0<br />

Sheet 9 Lacs


Annexure-6<br />

CHHATRU HYDRO-ELECTRIC-PROJECT<br />

1 Span 350 Mtr<br />

2<br />

No. <strong>of</strong> Towers per 10 Km<br />

TRANSMISSION WORKS - COST ESTIMATES<br />

Type <strong>of</strong> Tower Normal Tower Tower with<br />

3 mtr extn.<br />

Tower with 6<br />

mtr extn.<br />

Total<br />

W ( 0-2) 3 1 1 5<br />

X ( 2-15) 3 1 1 5<br />

Y ( 15-30) 10 1 1 12<br />

Z ( 30-60) 8 8<br />

Total 24 3 3 30<br />

3 No. <strong>of</strong> Tower<br />

Foundation / 10<br />

Kms<br />

W-Type X-Type Y-Type Z-Type<br />

Normal Soil 5 5 12 8<br />

4<br />

WEIGHT FOR TOWERS INCLUDING NUTS AND BOLTS<br />

Type <strong>of</strong> Tower Wt. Of Normal Wt. Of 3 Wt. Of 6 mtr.<br />

Tower mtr. Extn Extn<br />

W(0-2) 6.5x3=19.5 7.3 8.2<br />

X ( 2-15) 3x11.9= 35.7 13.5 14.6<br />

Y ( 15-30) 10x13.9= 139 15.7 17.2<br />

Z ( 30-60) 8x17.7=141.6<br />

Total 335.8 36.5 40<br />

5 TOTAL I/C<br />

NUTS AND<br />

BOLTS<br />

6 WT. OF NUTS<br />

AND BOLTS (<br />

5% OF TOWER<br />

WEIGHT)<br />

7 TOWER STEEL<br />

PER KM<br />

TOWER WEIGHT, CONCRETE FOR FOUNDATION<br />

AND EXCAVATION FOR FOUNDATION<br />

(SNOW ZONE)<br />

412.3 MT<br />

19.60 MT<br />

39.27 MT


8 WT. OF NUTS<br />

AND BOLTS<br />

PER KM<br />

1.96 MT<br />

9 VOLUME OF CONCRETE AND EXCAVATION FOR TOWER FOUNDATION<br />

Type <strong>of</strong> Tower No. <strong>of</strong> Tower<br />

Foundations<br />

/10 kms<br />

Volume <strong>of</strong><br />

Excavation<br />

( Cu. Mtr.)<br />

Volume <strong>of</strong><br />

Concrete (<br />

M^3)<br />

W 5 176.5 17.5<br />

X 5 334 39<br />

Y 12 1393.2 207.6<br />

Z 8 1453.6 289.6<br />

Total 30 3357.3 553.7<br />

10 VOLUME OF<br />

CONCRETE PER<br />

KM<br />

55.37 Cu. Mt<br />

11 VOLUME OF<br />

EXCAVATION<br />

PER KM<br />

335.73 Cu. Mt.<br />

Sheet 10


CHHATRU HYDRO-ELECTRIC-PROJECT<br />

TRANSMISSION WORKS - COST ESTIMATES<br />

Annexure-8<br />

TOWER WEIGHT, CONCRETE, FOR FOUNDATION<br />

AND EXCAVATION FOR FOUNDATION<br />

(NON SNOW ZONE)<br />

1 Span 350 Mtr<br />

2<br />

No. <strong>of</strong> Towers per 10 Km<br />

Type <strong>of</strong> Tower Normal Tower with 3 Tower with 6 Total<br />

Tower mtr extn. mtr extn.<br />

S ( 0-2) 3 1 1 5<br />

T ( 2-15) 3 1 1 5<br />

U ( 15-30) 10 1 1 12<br />

V ( 30-60) 8 8<br />

Total 24 3 3 30<br />

3 No. <strong>of</strong> Tower<br />

Foundation / 10<br />

Kms<br />

S-Type T-Type U-Type V-Type<br />

4<br />

Normal Soil 5 5 12 8<br />

WEIGHT FOR TOWERS INCLUDING NUTS AND BOLTS<br />

Type <strong>of</strong> Tower Wt. Of<br />

Normal<br />

Tower<br />

Wt. Of 3 mtr.<br />

Extn<br />

Wt. Of 6 mtr.<br />

Extn<br />

S(0-2) 6x3=18 6.7 7.6<br />

T ( 2-15) 3x7.5=<br />

22.5<br />

8.5 9.7<br />

U ( 15-30) 10x9.2=<br />

92<br />

10.4 11.9<br />

V ( 30-60) 8x12.2=9<br />

7.6<br />

Total 230.1 25.6 29.2<br />

5 TOTAL 284.9 MT<br />

6 WT. OF NUTS<br />

AND BOLTS (<br />

5% OF TOWER<br />

WEIGHT)<br />

13.60 MT<br />

7 TOWER<br />

STEEL PER<br />

KM<br />

27.13 MT


TOWER WEIGHT, CONCRETE, FOR FOUNDATION<br />

AND EXCAVATION FOR FOUNDATION<br />

(NON SNOW ZONE)<br />

8 WT. OF NUTS<br />

AND BOLTS<br />

PER KM<br />

1.36 MT<br />

9<br />

VOLUME OF CONCRETE AND EXCAVATION FOR TOWER<br />

FOUNDATION<br />

Type <strong>of</strong> Tower No. <strong>of</strong><br />

Tower<br />

Foundatio<br />

ns /10<br />

kms<br />

Volume <strong>of</strong><br />

Excavation (<br />

Cu. Mtr.)<br />

Volume <strong>of</strong><br />

Concrete (<br />

M^3)<br />

S 5 164.55 16<br />

T 5 252.15 26.2<br />

U 12 656.4 71.4<br />

V 8 934.48 139.68<br />

Total 30 2007.58 253.28<br />

10 VOLUME OF<br />

CONCRETE PER<br />

KM<br />

25.33 Cu. Mt<br />

11 VOLUME OF<br />

EXCAVATION<br />

PER KM<br />

Sheet 21<br />

200.76 Cu. Mt.


Annexure-7<br />

CHHATRU HYDRO-ELECTRIC-PROJECT<br />

TRANSMISSION WORKS - COST ESTIMATES<br />

TOWER FIXTURE FOR 220 KV D/C LINE.<br />

Sr. No Description Qty Rate Unit Amount in Rs<br />

1 Earthing Sets<br />

I) Counterpoise 25 3000 Nos 75000<br />

ii) Pipe Type 5 1400 NOs 7000<br />

2 Danger Plates 30 300 Nos 9000<br />

3 Number Plates 30 300 Nos 9000<br />

4 Bird Guard 5 540 Sets 2700<br />

5 Phase Plates 60 250 Sets 15000<br />

6 Anti Climbing 30 2500 Nos 75000<br />

7 Barbed wire<br />

Galvanised<br />

1000 40 Kg 40000<br />

8 Circuit Plates 60 250 Nos 15000<br />

Total Cost per 10 Kms 247700<br />

9 Cost per Km 24770<br />

Sheet 11


Annexure-8<br />

CHHATRU HYDRO-ELECTRIC-PROJECT<br />

TRANSMISSION WORKS - COST ESTIMATES<br />

CONDUCTOR ACCESSORIES FOR 220 KV D/C LINE.<br />

Sr. No Description Qty Rate Unit Amount in Rs<br />

1 Preformed Armour rods sets<br />

complete with Ferrules for<br />

Suspension Towers ( 2x3x5)<br />

30 550 Nos 16500<br />

2 Stock Bridge vibration<br />

Dampers ( 30x 2 x 3<br />

x2=360)<br />

360 330 Nos 118800<br />

3 Mid Span Compression Joints 52 300 Nos 15600<br />

4 Other Miscellaneous Items<br />

e.g. PG Clamps, Binding<br />

Wire etc.<br />

1 LS 15000<br />

Total Cost per 10 Kms 165900<br />

5 Cost <strong>of</strong> conductor<br />

Accessories per Km<br />

16590<br />

Sheet 13


Annexure-9<br />

CHHATRU HYDRO-ELECTRIC-PROJECT<br />

TRANSMISSION WORKS - COST ESTIMATES<br />

EARTHWIRE ACCESSORIES<br />

Sr. No Description Qty Rate Unit Amount in Rs<br />

1 Mid Span Compression<br />

Joint Assembly<br />

14 100 Nos 1400<br />

2 Suspension Assembly for<br />

GSS Wire 7/3.15 mm<br />

(2x5=10)<br />

10 300 Nos 3000<br />

3 Compression Type<br />

Tension Assembly for<br />

GSS Wire 7/3.15 mm<br />

with Terminal Jumpers<br />

( 25x2x 2=100)<br />

100 400 Nos 40000<br />

4 Flexible grounding Leads<br />

for Earthing GSS Wire<br />

(1x2x5+2x2x25)<br />

110 120 Nos 13200<br />

Total Cost for 10 Kms 57600<br />

Cost for 1 Km<br />

sheet 15<br />

5760


Annexure-10<br />

CHHATRU HYDRO-ELECTRIC-PROJECT<br />

TRANSMISSION WORKS - COST ESTIMATES<br />

QUANTITIES OF HARDWARES AND INSULATORS<br />

FOR 220 KV D/C LINE.<br />

Sr. No Description<br />

Qty<br />

Snow Zone<br />

A FOR SUSPENSION TOWERS<br />

I) Number <strong>of</strong> suspension Insulators Strings<br />

per 10 Kms ( Nos)<br />

30<br />

ii) Number <strong>of</strong> Discs per Suspension insulators<br />

Strings (Nos)<br />

16<br />

iii) Number <strong>of</strong> suspension Insulators Discs per<br />

10 Kms ( Nos)<br />

480<br />

iv) Number <strong>of</strong> suspension Insulators Discs per<br />

Kms ( Nos)<br />

48<br />

v) Number Suspension Hardware per 10 Kms<br />

( Sets)<br />

30<br />

vi) Number Suspension Hardware per Kms<br />

( Sets)<br />

3<br />

B FOR TENSION TOWERS<br />

I) Number <strong>of</strong> Tension Insulator Strings per 10<br />

Kms ( Nos)<br />

300<br />

ii) Number <strong>of</strong> Tension Discs per String ( Nos) 17<br />

iii) Number <strong>of</strong> Tension Discs per 10 Km<br />

( Nos)<br />

5100<br />

iv) Number <strong>of</strong> Tension Discs per Km ( Nos) 510<br />

v) Number <strong>of</strong> Tension Hardware per 10 Km<br />

( Sets)<br />

vi) Number <strong>of</strong> Tension Hardware per Km<br />

( Sets)<br />

Sheet 16<br />

300<br />

30


CHHATRU HYDRO-ELECTRIC-PROJECT<br />

TRANSMISSION WORKS - COST ESTIMATES<br />

SCHEDULE OF COST ANALYSIS FOR ERECTION<br />

CHARGES OF 220 KV D/C LINE ( SNOW ZONE)<br />

Annexure-11<br />

Sr. No Description Qty Rate Unit Amount in Rs<br />

1 Excavation and Backfill per<br />

Km<br />

335.73 185 Cu Mt 62110.05<br />

2 Concreting I/c Dewatering<br />

etc.<br />

55.37 4500 M^3 249165<br />

3 Erection <strong>of</strong> Towers 39.27 4000 MT 157066.67<br />

4 Stringing <strong>of</strong> Conductor 1 50000 Km 50000<br />

5 Stringing <strong>of</strong> Earth Wire 1 3800 Km 3800<br />

6 Earthing <strong>of</strong> Towers 3 1000 Nos 3000<br />

7 Fixing <strong>of</strong> Tower<br />

Accessories<br />

3 200 Nos 600<br />

Total Cost <strong>of</strong> Erection <strong>of</strong><br />

Towers per Km<br />

Sheet 17<br />

525741.72


KHOKSAR HYDRO-ELECTRIC-PROJECT<br />

TRANSMISSION WORKS - COST ESTIMATES<br />

Annexure-14<br />

SCHEDULE OF COST ANALYSIS FOR ERECTION<br />

CHARGES OF 220 KV S/C LINE ON D/C TOWERS (NON SNOW ZO<br />

Sr. No Description Qty Rate Unit Amount in Rs<br />

1 Excavation and<br />

Backfill per Km<br />

200.76 185 Cu Mt 37140.23<br />

2 Concreting I/c<br />

Dewatering etc.<br />

25.33 4500 M^3 113976<br />

3 Erection <strong>of</strong> Towers 27.13 4000 MT 108533.33<br />

4 Stringing <strong>of</strong> Conductor 1 25000 Km 25000<br />

5 Stringing <strong>of</strong> Earth<br />

Wire<br />

1 3800 Km 3800<br />

6<br />

3 1000 Nos 3000<br />

Earthing <strong>of</strong> Towers<br />

7 Fixing <strong>of</strong> Tower<br />

Accessories<br />

Total Cost <strong>of</strong><br />

Erection <strong>of</strong> Towers<br />

per Km<br />

Sheet 18<br />

3 200 Nos 600<br />

292049.56


ONE)


KHOKSAR HYDRO-ELECTRIC-PROJECT<br />

TRANSMISSION WORKS - COST ESTIMATES<br />

SCHEDULE OF COST ANALYSIS FOR TERMINAL<br />

EQUIPMENT AT TANDI<br />

Annexure-12<br />

Sr. No Description Qty Rate Unit Amount in<br />

Lacs<br />

1 220 KV SF6 Out doortype 3<br />

phase Circuit Breaker<br />

complete<br />

2 15 Nos 30<br />

2 220 KV Control and Relay<br />

Panels<br />

2 9.3 Nos 18.6<br />

3 220 KV 3 phase Isolators<br />

without Earth Swicth<br />

4 3.2 Sets 12.8<br />

4 220 KV 3 phase Isolators<br />

with Earth Swicth<br />

2 4.3 Sets 8.6<br />

5 220 KV LAs 6 0.78 Nos 4.68<br />

6 Multi Core Multi Ratio CTs 6 2 Nos 12<br />

7 Structures 60 0.32 MT 19.2<br />

8 Bus Bar Material and<br />

Insulators<br />

Lot LS 14<br />

9 <strong>Power</strong> and Control Cables<br />

and EI Works etc.<br />

Lot LS 24<br />

Sub Total-I 143.88<br />

10 Transportation @ 5%, Spares<br />

@ 3%, Insurance @ 1%, CST<br />

@ 4%,Civil Works @ 8% (<br />

Total 21% on Sub Total-I)<br />

30.21<br />

12 Erection and commissioning<br />

Charges @ 10% <strong>of</strong> Sub Total-<br />

I)<br />

14.39<br />

GRAND TOTAL<br />

Sheet 19<br />

188.48


CHHATRU HYDRO-ELECTRIC-PROJECT<br />

TRANSMISSION WORKS - COST ESTIMATES<br />

VEHICLES AND WORKSHOP MACHINERY<br />

Annexure-12<br />

Sr. No Description Qty Rate Unit Amount in Lacs<br />

1 7.5 Tons Trucks 2 8.5 Nos 17<br />

2 Jeep/ Car 2 3.5 Nos 7<br />

3 Maintenance van 1 4.5 Nos 4.5<br />

4 Workshop Equipment such as<br />

Lathe , Welding Sets, Drilling<br />

machines , <strong>Power</strong> Hacksaw etc.<br />

Lot LS 5.5<br />

TOTAL<br />

Sheet 20<br />

34


CHHATRU HYDRO-ELECTRIC-PROJECT (108 MW)<br />

COST ESTIMATES OF ELECTRO-MECHANICAL WORKS FOR PRE-FEASIBILITY REPORT<br />

Sl.No. Item Qty Rate Amount Excise Duty* Total<br />

Rs.(Lakhs) Rate Amount Amount<br />

(Rs. Lakhs) (Rs. Lakhs)<br />

1 2 3 4 5 6 7 8<br />

1 Generating Unit and 11 KV Bus Duct 36MW,<br />

428.6 RPM with net Head <strong>of</strong> 160 mtrs.<br />

3 Rs.5600/KW 6048.00 16% 967.68 7015.68<br />

2 Step-up transformer, 11/220KV,15MVA,single<br />

phase<br />

10 Rs.260/KVA 390.00 16% 62.40 452.40<br />

3 Auxiliary Electrical Equipment for <strong>Power</strong><br />

Stations (Except transformer) (5% <strong>of</strong> item 1).<br />

302.40 16% 48.38 350.78<br />

4 Auxiliary Equipment and Services for <strong>Power</strong><br />

Stations (5% <strong>of</strong> item-1)<br />

302.40 16% 48.38 350.78<br />

5 220 KV Switchyard GIS. 6 bays 300 Lacs/bay 1800.00 16% 288.00 2088.00<br />

6 Spares (5% <strong>of</strong> 1 and 3% <strong>of</strong> 2-5) 386.24 16% 61.80 448.04<br />

7 Sub-Total-1: 9229.04 10705.68<br />

8 Central Sales Tax ** 4% <strong>of</strong> item 1 to 6 428.23<br />

9 Transportation & Insurance 6% <strong>of</strong> item-7 642.34<br />

10 Erection and Commissioning 8% <strong>of</strong> item-7<br />

(except spares)<br />

820.61<br />

11 Sub-Total-2 : 12596.86<br />

12 Establishment, Contingency, other charges<br />

11% <strong>of</strong> item-7 (excluding duties)<br />

1015.20<br />

Grand Total :- 13612.06<br />

Say Rs. 13612 Lacs


DISCHARGE IN CUMECS<br />

350.00<br />

300.00<br />

250.00<br />

200.00<br />

150.00<br />

100.00<br />

50.00<br />

TIME IN HOURS<br />

0 1 2 3 4<br />

Effective rain fall in Cm<br />

CHHATRU HEP<br />

DESIGN FLOOD HYDROGRAPH FIG-A-II<br />

Qp = 291.59 Cumecs<br />

0.00<br />

0 2 4 6 8 10 12 14 16 18 20<br />

TIME IN HOURS<br />

Series1


CHHATRU HEP<br />

STANDARD PROJECT FLOOD HYDROGRAPH (SUG)<br />

TIME ORDINATE RAINFALL EXCESS IN CM. SUB TOTAL BASE TOTAL<br />

IN OF SUH DSRO IN FLOW FLOW IN<br />

HOURS IN 0.11 1.52 5.75 0.71 CUMECS IN CUMECS<br />

CUMECS CUMECS<br />

1 2 3 4 5 6 7 8 9 10<br />

1 0 0.00 0.00 2.40 2.40<br />

2 1 0.11 0.00 0.11 2.40 2.51<br />

3 7.5 0.79 1.52 0.00 2.30 2.40 4.70<br />

4 20.28 2.13 11.38 5.75 0.00 19.26 2.40 21.66<br />

5 40.25 4.23 30.76 43.14 0.71 78.83 2.40 81.23<br />

6 27.5 2.89 61.05 116.65 5.33 185.91 2.40 188.31<br />

7 15 1.58 41.71 231.50 14.40 289.19 2.40 291.59 PEAK<br />

8 8 0.84 22.75 158.17 28.58 210.34 2.40 212.74<br />

9 5.2 0.55 12.13 86.28 19.53 118.48 2.40 120.88<br />

10 3.5 0.37 7.89 46.01 10.65 64.92 2.40 67.32<br />

11 2.5 0.26 5.31 29.91 5.68 41.16 2.40 43.56<br />

12 1.55 0.16 3.79 20.13 3.69 27.78 2.40 30.18<br />

13 0.75 0.08 2.35 14.38 2.49 19.29 2.40 21.69<br />

14 0.3 0.03 1.14 8.92 1.78 11.86 2.40 14.26<br />

15 0 0.00 0.46 4.31 1.10 5.87 2.40 8.27<br />

16 0 0.00 0.00 1.73 0.53 2.26 2.40 4.66<br />

17 0.00 0.00 0.21 0.21 2.40 2.61<br />

18 0.00 0.00 0.00 2.40 2.40<br />

19 0.00 0.00 2.40 2.40<br />

20 0.00 2.40 2.40<br />

21 2.40 2.40<br />

22 0.00<br />

Flood for 1 in 100 years can be worked out from Fuller's formula as<br />

Q 100 =<br />

Q 50 (1+0.80 log T 100/1+0.80log T 50)<br />

Annexuure - 2<br />

= 321.38 Cumecs<br />

Snow contribution = = 342.09 Cumecs<br />

(Snow contribution has been taken as the maximum discharge in the flow series during<br />

the 2nd week <strong>of</strong> July)<br />

Total design flood = 663.468 Cumecs<br />

Say 665 Cumecs<br />

REM-<br />

ARKS


CHHATRU HEP Annexure - 1<br />

Cumputation <strong>of</strong> Equivalent slope <strong>of</strong> river Chenab in respect <strong>of</strong> Chhatru HEP<br />

S.No.<br />

Ruduced<br />

RD In K<br />

Level<br />

m<br />

in m<br />

leanth <strong>of</strong><br />

each<br />

segment<br />

Li in Km<br />

Height<br />

above (Di-1+Di) In<br />

Li X (Di-1+Di)<br />

Datum Di m<br />

in m<br />

1 2 3 4 5 6 7<br />

1 0.00 3405.00 0.00 0.00 0.00 0.00<br />

2 0.75 3420.00 0.75 15.00 15.00 11.25<br />

3 2.05 3440.00 1.30 35.00 50.00 65.00<br />

4 2.75 3460.00 0.70 55.00 90.00 63.00<br />

5 3.68 3480.00 0.93 75.00 130.00 120.90<br />

6 4.43 3500.00 0.75 95.00 170.00 127.50<br />

7 4.93 3520.00 0.50 115.00 210.00 105.00<br />

8 5.38 3540.00 0.45 135.00 250.00 112.50<br />

9 6.28 3560.00 0.90 155.00 290.00 261.00<br />

10 6.58 3580.00 0.30 175.00 330.00 99.00<br />

11 7.03 3600.00 0.45 195.00 370.00 166.50<br />

12 7.46 3620.00 0.43 215.00 410.00 176.30<br />

13 8.81 3640.00 1.35 235.00 450.00 607.50<br />

14 9.81 3680.00 1.00 275.00 510.00 510.00<br />

15 11.41 3720.00 1.60 315.00 590.00 944.00<br />

16 12.51 3760.00 1.10 355.00 670.00 737.00<br />

17 14.11 3800.00 1.60 395.00 750.00 1200.00<br />

18 16.11 3840.00 2.00 435.00 830.00 1660.00<br />

19 17.91 3880.00 1.80 475.00 910.00 1638.00<br />

20 23.91 3920.00 6.00 515.00 990.00 5940.00<br />

21 27.91 3960.00 4.00 555.00 1070.00 4280.00<br />

22 31.41 4000.00 3.50 595.00 1150.00 4025.00<br />

Total 22849.45<br />

S = Li X (Di-1+Di)/ L 2 = 23.16<br />

m/Km<br />

Datum = 3405 m I,e R.L. <strong>of</strong> river bed at point <strong>of</strong> study.


ESTIMATE OF DESIGN FLOOD FOR CHHATRU HEP<br />

UNIT HYDROGRAPH METHOD<br />

COMPUTATION OF ONE HOUR SYNTHETIC UNIT GRAPH<br />

Ref;- FLOOD ESTIMATION REPORT FOR WESTERN HIMALAYAS - ZONE 7 (CWC)<br />

i) Name <strong>of</strong> zone Western Himalayas<br />

ii) Name <strong>of</strong> river Chandra River in Chenab basin<br />

iii) Shape <strong>of</strong> Catchment Leaf Shaped<br />

iv) Location Lat. 32°-18'-08"<br />

Long. 77°-24'-39"<br />

v) Topography Steep slope<br />

Step -1 Physiographic Parameters<br />

1 Permanent Snow Line 4000 m<br />

2 Total catchment area at diversion site 1583 Sq. Km<br />

(Ref. Drg. No Chhatru-PR-3)<br />

3 Permaqnent snow covered area above EL4000m. 1535 Sq.km.<br />

4. Catchment area contribution to run-<strong>of</strong>f ( Ref.FIG - A) 48 Sq.km.<br />

5. Length <strong>of</strong> the longest (Stream) ( L ) 31.41 Km<br />

6 Length <strong>of</strong> the longest (Stream) from a point<br />

apposit to C.G. <strong>of</strong> catchment to point <strong>of</strong> study (LC) 11.80 Km<br />

7 Equivalent stream slope (S) 23.16 m/Km<br />

(Refer Annexure-1)<br />

Step -2:1-hr. Synthetic unit graph<br />

I) tp = 2.498(LxLC/S) 0.,156<br />

Annexure V - 1<br />

3.85 hrs<br />

4.00 hr<br />

and taken 0.5 hr. less than the completed value for<br />

highest peak. = 3.50 hrs<br />

ii) qp = 1.048(tp) -0.178<br />

0.84 Cum/SqKm<br />

iii) W50 = 1.954x(LxLC/S) 0.099<br />

2.57 hrs<br />

iv) W75= 0.972x(LxLC/S) 0.124<br />

1.37 hrs<br />

v) Wr50= 0.189x(W50) 1.769<br />

1.00 hrs<br />

vi) Wr75= 0.419x(W75) 1.246<br />

0.62 hrs<br />

vii) TB= 7.845x(tp) 0.453<br />

Taking tp in multiple <strong>of</strong> 1-0 hr. I.e.<br />

13.84 hrs<br />

viii) Qp = qpxA 40.25 Cumecs<br />

Estimated parameter <strong>of</strong> unit graph in Step-1 were plotted on a graph paper as shown in<br />

Fig. A-I. The plotted points were joined to draw synthetic unit graph. The discharge<br />

ordinates(Qi) <strong>of</strong> the unit graph at ti=tr=1 hr. interval were summed up and multiplied by<br />

tr=1 and compared with the volume <strong>of</strong> 1.00cm direct run-<strong>of</strong>f depth over the catchment<br />

computed from the formula.<br />

Q= Axd/0.36xtr<br />

Where A = Catchment area in Sq.km.<br />

d= 1.0m depth<br />

ti= tr(the unit duration <strong>of</strong> the UG)=1 hr.<br />

The following limb <strong>of</strong> the <strong>hydro</strong>graph is suitably modified without altering the points <strong>of</strong><br />

synthetic parameters.<br />

133 Cumecs


Step-3 Estimation <strong>of</strong> design storms<br />

a) Design storm duration<br />

The design storm duration TD has been adopted as 1,1x1xtp<br />

TD = 1.1xtp<br />

TD = 1.1x3.5 3.85 Say 4 Hrs<br />

b) Estimation <strong>of</strong> point rain fall and areal rainfall for storm duration<br />

Catchment under study was located on Plate-9, P=-58, showing 50 year 24 hr./ point<br />

rainfal. The point fainfall was found to be = 16 cm.<br />

Coversion factor read from Fig. 3, P-67 to convert 50-yr. 24 hr. point rainfall to<br />

50 yr. 4 hr. point rainfall is = 0.65<br />

Hence 50 year 4 hr, point rainfall is = 10.40 cm.<br />

Areal reduction factor = 0.97 corresp. to the C.A. = 48<br />

Sqkm. For TD = 4 hr. was interpolated from<br />

Annexure-4.2. P-42,for conversion <strong>of</strong> point rainfall to areal rainfall.<br />

50Year 4 hr. Areal rainfall worked out to be = 10.08 cm.<br />

The 50-yr. 4 hr. areal rainfall spilt in to 1-hr. rainfall increments using time<br />

distribution co-efficient given in Annexure-4.1, P-41.<br />

A design loss rate <strong>of</strong> 0.20 cm/hr. as recommended in para 3.5,P-15<br />

has been used to get effective rainfall hyetograph.<br />

Duration<br />

Hourly effective rainfall increments Table - 1<br />

Distribution<br />

co-efficient<br />

increment<br />

1 2 3 4 5 6<br />

1 0.62 6.25 6.25 0.50 5.75<br />

2 0.82 8.27 2.02 0.50 1.52<br />

3 0.94 9.48 1.21 0.50 0.71<br />

4 1.00 10.08 0.61 0.50 0.11<br />

Step-4 Estimation <strong>of</strong> base flow<br />

Taking design base flow <strong>of</strong> = 0.05 cumecs per Sq.km. as recommended.<br />

in para 3.6 P-15, the base flow as ground water estimated as<br />

2.4 cumecs for 48 Sq.km. catchment area.<br />

Step-5 Estimation <strong>of</strong> 50 year flood<br />

Storm<br />

rainfall<br />

(cm)<br />

a) Compputaiton <strong>of</strong> flood peak<br />

Rainfall<br />

increments<br />

(cm)<br />

Loss per<br />

hr. (cm)<br />

Effective rainfall<br />

increments<br />

For estimation <strong>of</strong> the peak discharge , the effective rainfall increments were<br />

re-arranged against ordinates such that the maximum effective rainfall<br />

is placed against the maximum U.G. oridnate,next lower value <strong>of</strong> effective<br />

rainfall against next lower value <strong>of</strong> U.G. ordinate and so on as shown in<br />

column (2) in Table - 2.Sum <strong>of</strong> the product <strong>of</strong> U.G. ordinates and effective<br />

rainfall increments gives total direct surface run <strong>of</strong>f to which<br />

base flow is added to get total peak discharge.


50 year Peak flood Table - 2<br />

U.G.<br />

1 hr.<br />

Time hrs.<br />

ordinates<br />

effective<br />

Direct run-<strong>of</strong>f<br />

cumecs<br />

rainfall<br />

1 2 3 4<br />

1 20.28 0.71 14.40<br />

2 40.25 5.75 231.50<br />

3 27.50 1.52 41.71<br />

4 15.00 0.11 1.58<br />

Total 289.19<br />

Base flow 2.40<br />

50 year flood peak 291.59<br />

Say 292 Cumecs<br />

b) Computation <strong>of</strong> design flood <strong>hydro</strong>graph<br />

Effective rainfall increments shown in col. 3 <strong>of</strong> table-2 in step 5. above were<br />

reversed to obtain critical sequence as shown below<br />

( Critical sequence <strong>of</strong> rain fall )<br />

Time in hrs. Crirital 1-hr. effective rainfall sequence cms.<br />

1 0.11<br />

2 1.52<br />

3 5.75<br />

4 0.71<br />

Table - 3.<br />

For computation <strong>of</strong> design flood <strong>hydro</strong>graph, the U.G. ordinates were tabulated in<br />

Col. (2) <strong>of</strong> Annexure-2. The critical sequence <strong>of</strong> effective rainfall increments were<br />

entered in col. 3 to 6 horizontally. Direct run <strong>of</strong> resulting from each <strong>of</strong> the<br />

effective rainfall increments was obntained by multiplying effective rainfall<br />

depths with the synthetic U.G. ordinates in col. 2 and direct run <strong>of</strong>f<br />

values were entered in columns against each unit with a successive lag <strong>of</strong> 1 hr.<br />

since the unit duration <strong>of</strong> S.U.G. is 1 hr. Direct run <strong>of</strong>f values are shown in col. 3 to 6.<br />

Direct run <strong>of</strong>f values were added horizontally and total direct run<strong>of</strong>fis shown in col. 7. Adding<br />

Adding total base flow <strong>of</strong> = 2.40 cumecs ( col.8) .<br />

Design flood <strong>hydro</strong>graph ordinates in col.9 were obtained. Design<br />

flood <strong>hydro</strong>graph was plotted against time as shown fig. A-II<br />

The peak obtained was = 291.59 cumecs for 1 in 50 years<br />

which talies with the peak shown in Table-2<br />

Flood for 1 in 100 years can be worked out from Fuller's formula<br />

and has been worked out as = 321.38 Cumecs (i)<br />

Snow contribution = = 342.09 Cumecs (ii)<br />

(Snow contribution has been taken as the maximum discharge in flow series during<br />

the 2nd week <strong>of</strong> July)<br />

The total design flood (i) + (ii) 663.47 cumecs<br />

The design flood has also been worked out by Gumble's flood frequency method<br />

considering top eight flood events <strong>of</strong> G&D site w.e.f. June 1973 to May 2001 as per data<br />

collected from CWC, Chenab Divn, Jammu vide letter Dt.13/1/04 (copy encl. Annexure. 3)<br />

which is = 1377.59 Cumecs for 1000 years (Annxure-4)<br />

However design flood <strong>of</strong> 1500 cumecs has been considered for computation<br />

<strong>of</strong> HFL for designing the diversion stucture <strong>of</strong> this <strong>project</strong>


1 HOUR SYNTHETIC UG<br />

ORDINATES<br />

1 HOUR SYNTHETIC<br />

UG PARAMETERS<br />

CA = 48.00 Sq. Km. 0 0<br />

tr = 1.00 Hr 1 1<br />

Qp = 40.25 Cumecs 2 7.5<br />

qp = 0.84 Hrs 3 20.28<br />

tp = 3.50 Hrs 4 40.25<br />

Tm = 4.00 Hrs 5 27.5<br />

TB = 13.84 Hrs 6 15<br />

W50 = 2.57 Hrs 7 8<br />

W75 = 1.37 Hrs 8 5.2<br />

Wr50= 1.00 Hrs 9 3.5<br />

Wr75 = 0.62 Hrs 10 2.5<br />

d = 1.00 Cm 11 1.55<br />

12 0.75<br />

13 0.3<br />

Q = A X d /tr X0,36 14 0<br />

133.33 Cumecs TOTAL 133.33


CHHATRU HEP ANNEXURE-4 ( i )<br />

DESIGN FLOOD - GUMBLE'S FLOOD FREQUENCY ANALYSIS<br />

C.A AT GHOUSAL 2406.25 SqKm<br />

C.A AT CHHATRU 1583 SqKm<br />

C.F. 0.658<br />

Sr. No. Date/ Year Max.Flood Discharge Max.Flood Discharge Max.Flood Discharge Q' - Q (Q ' - Q )^2<br />

in Cumecs at G& D in Cumecs at Q in Cumecs in<br />

Site Ghousal Diversion Site Descending order (Cumecs) (Cumecs)<br />

1 8.8.78 625 411 611 -121.870 14852.40<br />

2 25.7.87 636 418 579 -90.293 8152.77<br />

3 21.7.88 631 415 570 -81.082 6574.37<br />

4 29.7.89 866 570 461 28.124 790.96<br />

5 19.7.91 700 461 445 43.913 1928.34<br />

6 6.7.95 676 445 418 70.228 4931.92<br />

7 8.7.98 928 611 415 73.517 5404.75<br />

8 10.7.99 880 579 411 77.464 6000.70<br />

TOTAL 3909 0 48636<br />

MEAN DISCHARGE Q ' 488.63<br />

TOTAL NO. OF YEARS n 8<br />

Standard deviation d = (Q ' - Q )/n-1<br />

= 83.35<br />

Co-efficient <strong>of</strong> variation Cv = d / Q'<br />

Cv = 0.1706<br />

For 8 years period<br />

Reduced standard deviation Sn = 0.9496 Refer book Irrigation Engg &<br />

Reduced mean Yn = 0.4952 Hyd. Structure by S.K.Garg<br />

Q max. = Q' (1+Cv*(Y-Yn)/Sn) Page No.441<br />

= 488.63(1+0.1706*(Y-0.4952)/0.9496) 445.16<br />

Q max. = 445.16+87.78Y 87.78


CHHATRU HEP ANNEXURE-4 ( ii )<br />

COMPUTATION OF DESIGN FLOOD<br />

RETURN Xt = REDUCED VARIATE MAX. FLOOD INST. FLOOD PROBABILITY<br />

PERIOD log log( T/T-1) Y= Qmax = 1.15 TIMES OF<br />

T in Years 0.834032 - 2.302585Xt 445.16+87.78Y MAX.FLOOD % AGE<br />

10000 -4.362 10.878 1400.062 1610.07 0.01<br />

5000 -4.061 10.185 1339.213 1540.10 0.02<br />

1000 -3.362 8.575 1197.902 1377.59 0.1<br />

500 -3.061 7.882 1137.013 1307.57 0.2<br />

200 -2.662 6.964 1056.449 1214.92 0.5<br />

100 -2.360 6.268 995.384 1144.69 1<br />

50 -2.057 5.570 934.095 1074.21 2<br />

25 -1.751 4.867 872.350 1003.20 4<br />

10 -1.340 3.918 789.120 907.49 10<br />

Considering Design Flood <strong>of</strong> 1000 Years Return Period to be SPF<br />

which works Out to be = 1377.59 Cumecs


DISCHARGE (CUMECS)<br />

45<br />

40<br />

35<br />

30<br />

25<br />

20<br />

15<br />

10<br />

5<br />

0<br />

tr<br />

Wr50=1.00<br />

Hrs<br />

Tm=4 hrs CHHATRU HEP<br />

Wr75=0.62<br />

Hrs<br />

1 cm rainfall excess<br />

tp=3,50 HRS<br />

TB =13.84 Hrs<br />

SYNTHETIC UNIT HYDROGRAPH FIG-A-II<br />

Qp=40.25 Cumecs<br />

W 75= 1.37Hrs<br />

W 50 =2.57 Hrs<br />

0 2 4 6 8 10 12 14 16<br />

TIME (HOURS)


COMPUTATION NO- Chhatru HEP -PR-SS <strong>chhatru</strong> HEP<br />

REF DRG. NO-<strong>chhatru</strong>-PFR-<br />

CALCULATIONS OF UPSURGE & DOWNSURGE IN SURGE SHAFT<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

BASIC PARAMETERS 1) DIAMETER OF HRT =<br />

2) LENGTH OF HRT =<br />

3) DESIGN DISCHARGE =<br />

4) VELOCITY IN HRT =<br />

5) DIAMETER OF MAIN<br />

PENSTOCK =<br />

6) NO. OF MAIN PENSTOCK<br />

7) DIAMETER OF BRANCH<br />

PENSTOCK =<br />

8) NO.OF BRANCH PENSTOC<br />

9) VELOCITY IN PENSTOCK<br />

10) DIAMETER OF SURGE<br />

SHAFT =<br />

11) SURGE HT. NEGLECTIN<br />

LOSSES = Z* =<br />

12) HEAD LOSS IN ORIFIC<br />

MAXIMUM =<br />

MINIMUM =<br />

AVERAGE =<br />

13) RUGOSITY COEFFICIEN<br />

MAXIMUM =<br />

MINIMUM =<br />

AVERAGE =<br />

14) FRICTION COEFFICIEN<br />

MAXIMUM =<br />

MINIMUM =<br />

AVERAGE =<br />

15) HEAD LOSS IN HRT =h<br />

MAXIMUM =<br />

MINIMUM =<br />

AVERAGE =<br />

16) COEFFICIENT OF HYDR<br />

MAXIMUM =<br />

MINIMUM =<br />

AVERAGE =<br />

17) COEFFICIENT OF RESI<br />

MAXIMUM =<br />

MINIMUM =<br />

AVERAGE =<br />

18) TIME INTERVAL<br />

IN SECONDS =


CASE - I MAXIMUM UPSURGE FOR TOTAL REJECTION ( 100 - 0 )%<br />

AT MAXIMUM RESERVOIR LEVEL & MINIMUM LOSSES IN HRT<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

TIME VELOCITY UPSURGE CHANGE TOTAL V1^2 x<br />

INTERVAL IN HRT Z IN UPSUR- UPSURGE (B+N+1/2g)<br />

dt in V1 IN GE z+dz =Z<br />

sec. M/SEC. dz<br />

1 2 3 4 5 6<br />

0.00 3.64 -9.84 0.00 -9.84 0.00<br />

10.00 3.64 -9.84 4.20 -5.64 37.93<br />

20.00 3.15 -5.64 3.64 -2.00 28.44<br />

30.00 2.75 -2.00 3.18 1.18 21.69<br />

40.00 2.40 1.18 2.78 3.96 16.59<br />

50.00 2.09 3.96 2.42 6.38 12.58<br />

60.00 1.81 6.38 2.09 8.47 9.38<br />

70.00 1.54 8.47 1.78 10.25 6.79<br />

80.00 1.28 10.25 1.48 11.73 4.71<br />

90.00 1.03 11.73 1.19 12.92 3.06<br />

100.00 0.79 12.92 0.92 13.84 1.80<br />

110.00 0.56 13.84 0.64 14.48 0.89<br />

120.00 0.32 14.48 0.37 14.85 0.30<br />

130.00 0.10 14.85 0.11 14.96 0.03<br />

140.00 -0.13 14.96 -0.15 14.81 0.05<br />

150.00 -0.36 14.81 -0.41 14.40 0.36<br />

160.00 -0.58 14.40 -0.67 13.73 0.96<br />

170.00 -0.80 13.73 -0.92 12.81 1.84<br />

180.00 -1.02 12.81 -1.18 11.63 2.99<br />

190.00 -1.24 11.63 -1.44 10.19 4.42<br />

200.00 -1.46 10.19 -1.69 8.50 6.14<br />

210.00 -1.68 8.50 -1.95 6.56 8.13<br />

220.00 -1.90 6.56 -2.20 4.36 10.41


CASE - II MINIMUM DOWNSURGE AT MDDL OF RESERVOIR AT MINIMUM<br />

HEAD LOSSES IN HRT (100-0-33.33)% , V1 = 3.64<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

TIME VELOCITY MAXIMUM<br />

INTERVAL IN HRT Z in DOWN V1^2(-B-N+1/<br />

COMPUTATION NO- <strong>chhatru</strong> HEP -PR-SS<br />

REF DRG. NO-chhBHR-<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

1 2 3 4 5 6<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

140.00 -0.13 14.96 -0.15 14.81 -0.05<br />

150.00 -0.36 14.81 -0.41 14.40 -0.35<br />

160.00 -0.57 14.40 -0.66 13.75 -0.89<br />

170.00 -0.76 13.75 -0.88 12.87 -1.60<br />

180.00 -0.93 12.87 -1.08 11.79 -2.40<br />

190.00 -1.07 11.79 -1.24 10.55 -3.19<br />

200.00 -1.18 10.55 -1.37 9.18 -3.88<br />

210.00 -1.26 9.18 -1.46 7.72 -4.42<br />

220.00 -1.31 7.72 -1.52 6.20 -4.78<br />

230.00 -1.34 6.20 -1.54 4.66 -4.94<br />

240.00 -1.33 4.66 -1.54 3.12 -4.90<br />

250.00 -1.30 3.12 -1.51 1.61 -4.71<br />

260.00 -1.26 1.61 -1.45 0.16 -4.38<br />

270.00 -1.19 0.16 -1.38 -1.22 -3.94<br />

280.00 -1.12 -1.22 -1.29 -2.51 -3.45<br />

290.00 -1.03 -2.51 -1.19 -3.70 -0.73<br />

300.00 -0.96 -3.70 -1.11 -4.81 -0.64


CASE - II MINIMUM DOWNSURGE AT MDDL OF RESERVOIR AT MINIMUM<br />

Contd. HEAD LOSSES IN HRT . (100-0-33.33<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

TIME VELOCITY MAXIMUM -BV1^2<br />

INTERVAL IN HRT DZ in DOWN -N(V1-V2)^2<br />

dt in V1 IN m Z in m SURGE +1/2G*V1^2<br />

sec. M/SEC. Z+DZ (3+4)<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

1 2 3 4 5 6<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

240.00 -1.33 -3.66 3.12 -0.54 -28.47<br />

250.00 -0.89 -3.15 -0.54 -3.69 -19.91<br />

260.00 -0.54 -2.74 -3.69 -6.43 -14.13<br />

270.00 -0.23 -2.38 -6.43 -8.81 -9.97<br />

280.00 0.06 -2.06 -8.81 -10.87 -6.87<br />

290.00 0.32 -1.75 -10.87 -12.62 -4.56<br />

300.00 0.58 -1.45 -12.62 -14.07 -2.90<br />

310.00 0.84 -1.15 -14.07 -15.22 -1.82<br />

320.00 1.10 -0.85 -15.22 -16.07 -1.29<br />

330.00 1.36 -0.55 -16.07 -16.62 -1.31<br />

340.00 1.63 -0.24 -16.62 -16.86 -1.95<br />

350.00 1.91 0.09 -16.86 -16.77 -3.28<br />

360.00 2.22 0.44 -16.77 -16.33 -5.44<br />

370.00 2.55 0.82 -16.33 -15.51 -8.65<br />

380.00 2.91 1.24 -15.51 -14.27 -13.28<br />

390.00 3.33 1.72 -14.27 -12.55 -19.93<br />

400.00 3.82 2.29 -12.55 -10.26 -29.63


~~~<br />

5.10 METRES<br />

6500.00 METRES<br />

75.00 CUMECS.<br />

3.64 M/Sec.<br />

4.70 METRES<br />

K = 1.00 NOS.<br />

2.70 METRES<br />

CK = 3.00 NOS.<br />

K =<br />

MAIN = 4.33 M/Sec.<br />

BRANCH = 4.37 M/Sec.<br />

15.00 METRES<br />

NG<br />

CE =hor<br />

NT =n<br />

NT =f<br />

hf<br />

31.82 METRES<br />

30.19 METRES<br />

27.42 METRES<br />

29.20 METRES<br />

0.02<br />

0.01<br />

0.01<br />

0.02<br />

0.01<br />

0.01<br />

15.38 METRES<br />

9.84 METRES<br />

13.40 METRES<br />

RAULIC LOSSES IN HRT =B<br />

1.16 CASE-I<br />

0.74<br />

1.01<br />

CASE-II(i)<br />

ISTANCE FOR ORIFICE =N<br />

2.28<br />

2.07 CASE-II(ii)<br />

2.21<br />

10.00


~~~<br />

COL.(5+6) dv=-g/ L dt<br />

*Col.7<br />

7 8<br />

0.00 0.00<br />

32.30 -0.49<br />

26.44 -0.40<br />

22.87 -0.35<br />

20.54 -0.31<br />

18.96 -0.29<br />

17.85 -0.27<br />

17.04 -0.26<br />

16.44 -0.25<br />

15.98 -0.24<br />

15.64 -0.24<br />

15.37 -0.23<br />

15.15 -0.23<br />

14.99 -0.23<br />

14.86 -0.22<br />

14.76 -0.22<br />

14.69 -0.22<br />

14.64 -0.22<br />

14.62 -0.22<br />

14.62 -0.22<br />

14.64 -0.22<br />

14.69 -0.22<br />

14.77 -0.22


m/sec. v2 = 0.00 m/sec.<br />

~~~<br />

dv= -g/l dtx<br />

COL. Col.7<br />

~~~<br />

~~~<br />

7 8<br />

14.86 -0.22<br />

14.05 -0.21<br />

12.85 -0.19<br />

11.26 -0.17<br />

9.39 -0.14<br />

7.36 -0.11<br />

5.30 -0.08<br />

3.30 -0.05<br />

1.42 -0.02<br />

-0.28 0.00<br />

-1.79 0.03<br />

-3.10 0.05<br />

-4.22 0.06<br />

-5.17 0.08<br />

-5.96 0.09<br />

-4.43 0.07<br />

-5.44 0.08


0.00


V1 = 1.34 m/sec. v2 = 1.46 m/sec.<br />

~~~<br />

dv= -g/l dtx<br />

COL. *Col.7<br />

(5+6)<br />

~~~<br />

~~~<br />

7 8<br />

-29.01 0.44<br />

-23.60 0.36<br />

-20.56 0.31<br />

-18.78 0.28<br />

-17.74 0.27<br />

-17.18 0.26<br />

-16.97 0.26<br />

-17.04 0.26<br />

-17.36 0.26<br />

-17.93 0.27<br />

-18.81 0.28<br />

-20.05 0.30<br />

-21.77 0.33<br />

-24.16 0.36<br />

-27.55 0.42<br />

-32.48 0.49<br />

0.00 0.00


(0-33.33)% (0-100)% (100-0)%<br />

V1 = 0.00 0.00<br />

V2 = 4.37 4.33<br />

V1 = 1.34 3.64<br />

V2 = 1.46 0.00<br />

VI 1.63<br />

VII 1.46


COMPUTATION NO-<br />

REF DRG. NO-UHL<br />

CALCULATIONS OF<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

BASIC PARAMETER


CASE - I<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

TIME VELOCITY<br />

INTERVAL IN HRT<br />

dt in V1 IN<br />

sec. M/SEC.<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

1 2<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

0.00 3.05<br />

10.00 3.05<br />

20.00 2.72<br />

30.00 2.44<br />

40.00 2.21<br />

50.00 2.00<br />

60.00 1.81<br />

70.00 1.64<br />

80.00 1.47<br />

90.00 1.32<br />

100.00 1.16<br />

110.00 1.02<br />

120.00 0.88<br />

130.00 0.74<br />

140.00 0.60<br />

150.00 0.46<br />

160.00 0.33<br />

170.00 0.20<br />

180.00 0.07<br />

190.00 -0.06<br />

200.00 -0.19<br />

210.00 -0.32<br />

220.00 -0.45


CASE - II<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

TIME VELOCITY<br />

INTERVAL IN HRT<br />

COMPUTATION NO-<br />

REF DRG. NO-UHL<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

1 2<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

190.00 -0.06<br />

200.00 -0.19<br />

210.00 -0.32<br />

220.00 -0.44<br />

230.00 -0.55<br />

240.00 -0.65<br />

250.00 -0.74<br />

260.00 -0.82<br />

270.00 -0.88<br />

280.00 -0.93<br />

290.00 -0.97<br />

300.00 -0.99<br />

310.00 -1.00<br />

320.00 -1.00<br />

330.00 -0.98<br />

340.00 -0.96<br />

350.00 -0.93


-0.89<br />

-0.89


CASE - II<br />

Contd.<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

TIME VELOCITY<br />

INTERVAL IN HRT<br />

dt in V1 IN<br />

sec. M/SEC.<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

1 2<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

320.00 -1.00<br />

330.00 -0.78<br />

340.00 -0.56<br />

350.00 -0.36<br />

360.00 -0.15<br />

370.00 0.06<br />

380.00 0.26<br />

390.00 0.47<br />

400.00 0.68<br />

410.00 0.90<br />

420.00 1.12<br />

430.00 1.35<br />

440.00 1.59<br />

450.00 1.84<br />

460.00 2.11<br />

470.00 2.40<br />

480.00 2.71


- UHL STAGE-III-PR-SS-<br />

L-PR-15<br />

F UPSURGE & DOWNSURGE IN SURGE SHAFT<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

RS 1) DIAMETER OF HRT =<br />

2) LENGTH OF HRT =<br />

3) DESIGN DISCHARGE =<br />

4) VELOCITY IN HRT =<br />

5) DIAMETER OF MAIN<br />

PENSTOCK =<br />

6) NO. OF MAIN PENSTOCK =<br />

7) DIAMETER OF BRANCH<br />

PENSTOCK =<br />

8) NO.OF BRANCH PENSTOCK =<br />

9) VELOCITY IN PENSTOCK =<br />

10) DIAMETER OF SURGE<br />

SHAFT =<br />

11) SURGE HT. NEGLECTING<br />

LOSSES = Z* =<br />

12) HEAD LOSS IN ORIFICE =hor<br />

MAXIMUM =<br />

MINIMUM =<br />

AVERAGE =<br />

13) RUGOSITY COEFFICIENT =n<br />

MAXIMUM =<br />

MINIMUM =<br />

AVERAGE =<br />

14) FRICTION COEFFICIENT =f<br />

MAXIMUM =<br />

MINIMUM =<br />

AVERAGE =<br />

15) HEAD LOSS IN HRT =hf<br />

MAXIMUM =<br />

MINIMUM =<br />

AVERAGE =<br />

MAIN =<br />

BRANCH =<br />

16) COEFFICIENT OF HYDRAULIC LOSSES IN HRT<br />

MAXIMUM =<br />

MINIMUM =<br />

AVERAGE =<br />

17) COEFFICIENT OF RESISTANCE FOR ORIFICE =<br />

MAXIMUM =<br />

18) TIME INTERVAL<br />

IN SECONDS =<br />

MINIMUM =<br />

AVERAGE =


MAXIMUM UPSURGE FOR TOTAL REJECTION ( 100 - 0 )%<br />

AT MAXIMUM RESERVOIR LEVEL & MINIMUM LOSSES IN HRT<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

UPSURGE CHANGE TOTAL V1^2 x COL.(5+6)<br />

Z IN UPSUR- UPSURGE (B+N+1/2g)<br />

GE z+dz =Z<br />

dz<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

3 4 5 6 7<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

-12.65 0.00 -12.65 0.00 0.00<br />

-12.65 3.11 -9.54 40.33 30.79<br />

-9.54 2.77 -6.77 31.95 25.18<br />

-6.77 2.49 -4.28 25.82 21.54<br />

-4.28 2.25 -2.03 21.10 19.07<br />

-2.03 2.04 0.01 17.31 17.32<br />

0.01 1.85 1.86 14.20 16.05<br />

1.86 1.67 3.52 11.59 15.11<br />

3.52 1.50 5.02 9.37 14.40<br />

5.02 1.34 6.36 7.48 13.85<br />

6.36 1.19 7.55 5.86 13.41<br />

7.55 1.04 8.59 4.48 13.07<br />

8.59 0.89 9.48 3.32 12.80<br />

9.48 0.75 10.23 2.34 12.57<br />

10.23 0.61 10.84 1.55 12.39<br />

10.84 0.47 11.31 0.93 12.24<br />

11.31 0.34 11.65 0.47 12.12<br />

11.65 0.20 11.85 0.17 12.02<br />

11.85 0.07 11.92 0.02 11.94<br />

11.92 -0.06 11.86 0.02 11.87<br />

11.86 -0.20 11.66 0.16 11.82<br />

11.66 -0.33 11.33 0.45 11.78<br />

11.33 -0.46 10.88 0.87 11.75


MINIMUM DOWNSURGE AT MDDL OF RESIRVOIR AT MAXIMUM<br />

HEAD LOSSES IN HRT (100-0-50)% , V1 = 3.05 m/sec. v2 = 0.<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

MAXIMUM<br />

Z in DOWN V1^2(-B-N+1/2G COL.<br />

- UHL STAGE-III-PR-SS-<br />

L-PR-16<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

3 4 5 6 7<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

11.92 -0.06 11.86 -0.01 11.87<br />

11.86 -0.20 11.66 -0.13 11.53<br />

11.66 -0.32 11.34 -0.34 10.99<br />

11.34 -0.45 10.89 -0.65 10.24<br />

10.89 -0.56 10.33 -1.03 9.30<br />

10.33 -0.66 9.67 -1.44 8.23<br />

9.67 -0.75 8.91 -1.86 7.05<br />

8.91 -0.83 8.08 -2.27 5.81<br />

8.08 -0.90 7.18 -2.63 4.55<br />

7.18 -0.95 6.23 -2.94 3.29<br />

6.23 -0.98 5.25 -3.17 2.08<br />

5.25 -1.01 4.24 -3.32 0.92<br />

4.24 -1.02 3.22 -3.39 -0.17<br />

3.22 -1.02 2.21 -3.38 -1.17<br />

2.21 -1.00 1.20 -3.29 -2.09<br />

1.20 -0.98 0.22 -3.14 -2.92<br />

0.22 -0.95 -0.72 -2.94 -3.66


-0.65


MINIMUM DOWNSURGE AT MDDL OF RESERVOIR AT MAXIMUM<br />

HEAD LOSSES IN HRT (100-0-50)% , V1 = 0.92 m/sec. v2 = 2.<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

MAXIMUM -BV1^2<br />

DZ in DOWN -N(V1-V2)^2 COL.<br />

m Z in m SURGE +1/2G*V1^2 (5+6)<br />

Z+DZ (3+4)<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

3 4 5 6 7<br />

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~<br />

-3.28 3.22 -0.06 -20.21 -20.27<br />

-3.02 -0.06 -3.08 -16.49 -19.57<br />

-2.77 -3.08 -5.85 -13.30 -19.15<br />

-2.53 -5.85 -8.38 -10.55 -18.93<br />

-2.30 -8.38 -10.68 -8.20 -18.88<br />

-2.06 -10.68 -12.74 -6.22 -18.96<br />

-1.82 -12.74 -14.56 -4.59 -19.15<br />

-1.58 -14.56 -16.14 -3.32 -19.46<br />

-1.33 -16.14 -17.47 -2.41 -19.88<br />

-1.08 -17.47 -18.55 -1.88 -20.43<br />

-0.82 -18.55 -19.37 -1.75 -21.12<br />

-0.56 -19.37 -19.93 -2.07 -22.00<br />

-0.28 -19.93 -20.21 -2.88 -23.09<br />

0.01 -20.21 -20.20 -4.26 -24.46<br />

0.32 -20.20 -19.88 -6.32 -26.20<br />

0.65 -19.88 -19.23 -9.19 -28.42<br />

1.01 -19.23 -18.22 -13.10 0.00


4.15 METRES<br />

9000.00 METRES<br />

41.30 CUMECS.<br />

3.05 M/Sec.<br />

3.40 METRES<br />

1.00 NOS.<br />

2.40 METRES<br />

2.00 NOS.<br />

4.55 M/Sec.<br />

4.56 M/Sec.<br />

13.00 METRES<br />

29.52 METRES<br />

30.76 METRES<br />

27.20 METRES<br />

29.49 METRES<br />

0.02<br />

0.01<br />

0.01<br />

0.02<br />

0.01<br />

0.02<br />

19.77 METRES<br />

12.65 METRES<br />

17.22 METRES<br />

=B<br />

2.12 CASE-I V1 =<br />

1.36<br />

1.85<br />

V2 =<br />

CASE-II V1 =<br />

=N V2 =<br />

3.30<br />

2.92<br />

3.16<br />

10.00


dv=-g/ L dt<br />

*Col.7<br />

8 UPSURGE<br />

0.00 0.00<br />

-0.34 0.00<br />

-0.27 0.00<br />

-0.23 0.00<br />

-0.21 0.00<br />

-0.19 0.00<br />

-0.17 0.00<br />

-0.16 0.00<br />

-0.16 0.00<br />

-0.15 0.00<br />

-0.15 0.00<br />

-0.14 0.00<br />

-0.14 0.00<br />

-0.14 0.00<br />

-0.14 0.00<br />

-0.13 0.00<br />

-0.13 0.00<br />

-0.13 0.00<br />

-0.13 11.92<br />

-0.13 11.86<br />

-0.13 11.66<br />

-0.13 11.33<br />

-0.13 10.88


00 m/sec.<br />

dv= -g/l dtx<br />

Col.7<br />

8<br />

-0.13<br />

-0.13<br />

-0.12<br />

-0.11<br />

-0.10<br />

-0.09<br />

-0.08<br />

-0.06<br />

-0.05<br />

-0.04<br />

-0.02<br />

-0.01<br />

0.00<br />

0.01<br />

0.02<br />

0.03<br />

0.04


0.00


28 m/sec.<br />

dv= -g/l dtx<br />

*Col.7<br />

8<br />

0.22<br />

0.21<br />

0.21<br />

0.21<br />

0.21<br />

0.21<br />

0.21<br />

0.21<br />

0.22<br />

0.22<br />

0.23<br />

0.24<br />

0.25<br />

0.27<br />

0.29<br />

0.31<br />

0.00


(0-50)% (0-100)% (100-0)%<br />

0.00 0.00<br />

4.56 4.55<br />

0.96 3.05<br />

2.28 0.00


(0-25)%<br />

V1 = 0.00<br />

V2 = 0.00<br />

V1 =<br />

V2 =


0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00


0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00


(0-50)% (0-100)% (100-0)%<br />

0.00<br />

0.00<br />

0.00<br />

0.00


CHHATRU HYDRO-ELECTRIC PROJECT<br />

TABLE 7.2<br />

COMPUTATIONS FOR DEPENDABLE YEAR ON THE BASIS OF ENERGY<br />

S.No. ANNUAL GENERATION GENERATION IN MU<br />

IN DESCENDING ORDER % DEP. YEAR<br />

YEAR IN MU. YEAR IN MU.<br />

1 1973-74 988.34 1998-99 1302.18 3.57<br />

2 1974-75 635.24 1999-00 1231.36 7.14<br />

3 1975-76 853.23 1987-88 1039.94 10.71<br />

4 1976-77 702.96 1973-74 988.34 14.29<br />

5 1977-78 833.62 1991-92 973.55 17.86<br />

6 1978-79 952.55 1994-95 966.89 21.43<br />

7 1979-80 927.92 1988-89 963.47 25.00<br />

8 1980-81 899.67 1978-79 952.55 28.57<br />

9 1981-82 787.20 1996-97 937.25 32.14<br />

10 1982-83 835.86 1979-80 927.92 35.71<br />

11 1983-84 885.81 1989-90 920.92 39.29<br />

12 1984-85 849.10 1990-91 909.46 42.86<br />

13 1985-86 804.87 1995-96 905.47 46.43<br />

14 1986-87 895.05 1980-81 899.67 50.00 50% mean<br />

15 1987-88 1039.94 1986-87 895.05 53.57 YEAR<br />

16 1988-89 963.47 1983-84 885.81 57.14<br />

17 1989-90 920.92 1975-76 853.23 60.71<br />

18 1990-91 909.46 1984-85 849.10 64.29<br />

19 1991-92 973.55 1982-83 835.86 67.86<br />

20 1992-93 755.22 1977-78 833.62 71.43<br />

21 1993-94 765.29 1997-98 833.35 75.00<br />

22 1994-95 966.89 1985-86 804.87 78.57<br />

23 1995-96 905.47 1981-82 787.20 82.14<br />

24 1996-97 937.25 1993-94 765.29 85.71<br />

25 1997-98 833.35 1992-93 755.22 89.29 90% Dep<br />

26 1998-99 1302.18 1976-77 702.96 92.86 YEAR<br />

27 1999-00 1231.36 1974-75 635.24 96.43


POWER & ENERGY GENERATION IN TABLE 7.4<br />

90% DEPENDABLE YEAR (1992-93)<br />

Net Head = 160.00 mtr<br />

Eff. = 0.92<br />

90% Dep. Un-res. Restricted<br />

YEAR <strong>Power</strong> Energy <strong>Power</strong> Energy<br />

1992-93 MW GWH MW GWH<br />

MONTH PERIOD DISCHA. 78<br />

I 59.21 85.50 20.52 78.00 18.72<br />

JUN II 134.86 194.75 46.74 78.00 18.72<br />

III 173.02 249.85 59.96 78.00 18.72<br />

I 132.89 191.90 46.06 78.00 18.72<br />

JUL II 196.70 284.05 68.17 78.00 18.72<br />

III 218.41 315.40 83.26 78.00 20.59<br />

I 162.49 234.65 56.32 78.00 18.72<br />

AUG II 155.26 224.20 53.81 78.00 18.72<br />

III 163.15 235.60 62.20 78.00 20.59<br />

I 139.47 201.40 48.34 78.00 18.72<br />

SEP II 68.42 98.80 23.71 78.00 18.72<br />

III 44.08 63.65 15.28 63.65 15.28<br />

I 39.47 57.00 13.68 57.00 13.68<br />

OCT II 32.24 46.55 11.17 46.55 11.17<br />

III 28.95 41.80 11.04 41.80 11.04<br />

I 22.37 32.30 7.75 32.30 7.75<br />

NOV II 18.42 26.60 6.38 26.60 6.38<br />

III 16.45 23.75 5.70 23.75 5.70<br />

I 15.79 22.80 5.47 22.80 5.47<br />

DEC II 15.13 21.85 5.24 21.85 5.24<br />

III 15.13 21.85 5.77 21.85 5.77<br />

I 13.82 19.95 4.79 19.95 4.79<br />

JAN II 13.16 19.00 4.56 19.00 4.56<br />

III 12.50 18.05 4.77 18.05 4.77<br />

I 11.84 17.10 4.10 17.10 4.10<br />

FEB II 11.18 16.15 3.88 16.15 3.88<br />

III 11.84 17.10 3.28 17.10 3.28<br />

I 11.84 17.10 4.10 17.10 4.10<br />

MAR II 12.50 18.05 4.33 18.05 4.33<br />

III 12.50 18.05 4.77 18.05 4.77<br />

I 13.82 19.95 4.79 19.95 4.79<br />

APR II 15.13 21.85 5.24 21.85 5.24<br />

III 20.39 29.45 7.07 29.45 7.07<br />

I 32.89 47.50 11.40 47.50 11.40<br />

MAY II 29.60 42.75 10.26 42.75 10.26<br />

III 55.92 80.75 21.32 78.00 20.59<br />

TOTAL ENERGY 755.22 395.07<br />

P. L. FACTOR 0.58<br />

INC.INC. IN ENR. 0.00<br />

GWH / MW 5.07<br />

% AGE UTILISN 52.31<br />

PLF (LEAN- P.) 0.25


MONTH PERIOD<br />

I<br />

JUN II<br />

III<br />

I<br />

JUL II<br />

III<br />

I<br />

AUG II<br />

III<br />

I<br />

SEP II<br />

III<br />

I<br />

OCT II<br />

III<br />

I<br />

NOV II<br />

III<br />

I<br />

DEC II<br />

III<br />

I<br />

JAN II<br />

III<br />

I<br />

FEB II<br />

III<br />

I<br />

MAR II<br />

III<br />

I<br />

APR II<br />

III<br />

I<br />

MAY II<br />

III<br />

TOTAL ENERGY<br />

P. L. FACTOR<br />

INC.INC. IN ENR.<br />

GWH / MW<br />

% AGE UTILISN<br />

PLF (LEAN- P.)<br />

POWER & ENERGY GENERATION IN<br />

90% DEPENDABLE YEAR (1992-93)<br />

TABL<br />

Net Head = 160.00 mtr<br />

Eff. = 0.92<br />

Restricted Restrict Restrict<br />

<strong>Power</strong> Energy <strong>Power</strong> Energy <strong>Power</strong><br />

MW GWH MW GWH MW<br />

81 84 87<br />

81.00 19.44 84.00 20.16 85.50<br />

81.00 19.44 84.00 20.16 87.00<br />

81.00 19.44 84.00 20.16 87.00<br />

81.00 19.44 84.00 20.16 87.00<br />

81.00 19.44 84.00 20.16 87.00<br />

81.00 21.38 84.00 22.18 87.00<br />

81.00 19.44 84.00 20.16 87.00<br />

81.00 19.44 84.00 20.16 87.00<br />

81.00 21.38 84.00 22.18 87.00<br />

81.00 19.44 84.00 20.16 87.00<br />

81.00 19.44 84.00 20.16 87.00<br />

63.65 15.28 63.65 15.28 63.65<br />

57.00 13.68 57.00 13.68 57.00<br />

46.55 11.17 46.55 11.17 46.55<br />

41.80 11.04 41.80 11.04 41.80<br />

32.30 7.75 32.30 7.75 32.30<br />

26.60 6.38 26.60 6.38 26.60<br />

23.75 5.70 23.75 5.70 23.75<br />

22.80 5.47 22.80 5.47 22.80<br />

21.85 5.24 21.85 5.24 21.85<br />

21.85 5.77 21.85 5.77 21.85<br />

19.95 4.79 19.95 4.79 19.95<br />

19.00 4.56 19.00 4.56 19.00<br />

18.05 4.77 18.05 4.77 18.05<br />

17.10 4.10 17.10 4.10 17.10<br />

16.15 3.88 16.15 3.88 16.15<br />

17.10 3.28 17.10 3.28 17.10<br />

17.10 4.10 17.10 4.10 17.10<br />

18.05 4.33 18.05 4.33 18.05<br />

18.05 4.77 18.05 4.77 18.05<br />

19.95 4.79 19.95 4.79 19.95<br />

21.85 5.24 21.85 5.24 21.85<br />

29.45 7.07 29.45 7.07 29.45<br />

47.50 11.40 47.50 11.40 47.50<br />

42.75 10.26 42.75 10.26 42.75<br />

80.75 21.32 80.75 21.32 80.75<br />

403.86 411.93<br />

0.57 0.56<br />

8.79 8.06<br />

4.99 4.90<br />

53.48 54.54<br />

0.24 0.23


MONTH PERIOD<br />

I<br />

JUN II<br />

III<br />

I<br />

JUL II<br />

III<br />

I<br />

AUG II<br />

III<br />

I<br />

SEP II<br />

III<br />

I<br />

OCT II<br />

III<br />

I<br />

NOV II<br />

III<br />

I<br />

DEC II<br />

III<br />

I<br />

JAN II<br />

III<br />

I<br />

FEB II<br />

III<br />

I<br />

MAR II<br />

III<br />

I<br />

APR II<br />

III<br />

I<br />

MAY II<br />

III<br />

TOTAL ENERGY<br />

P. L. FACTOR<br />

INC.INC. IN ENR.<br />

GWH / MW<br />

% AGE UTILISN<br />

PLF (LEAN- P.)<br />

LE 7.4<br />

Energy<br />

GWH<br />

20.52<br />

20.88<br />

20.88<br />

20.88<br />

20.88<br />

22.97<br />

20.88<br />

20.88<br />

22.97<br />

20.88<br />

20.88<br />

15.28<br />

13.68<br />

11.17<br />

11.04<br />

7.75<br />

6.38<br />

5.70<br />

5.47<br />

5.24<br />

5.77<br />

4.79<br />

4.56<br />

4.77<br />

4.10<br />

3.88<br />

3.28<br />

4.10<br />

4.33<br />

4.77<br />

4.79<br />

5.24<br />

7.07<br />

11.40<br />

10.26<br />

21.32<br />

419.63<br />

0.55<br />

7.70<br />

4.82<br />

55.56<br />

0.22<br />

N


MONTH PERIOD<br />

I<br />

JUN II<br />

III<br />

I<br />

JUL II<br />

III<br />

I<br />

AUG II<br />

III<br />

I<br />

SEP II<br />

III<br />

I<br />

OCT II<br />

III<br />

I<br />

NOV II<br />

III<br />

I<br />

DEC II<br />

III<br />

I<br />

JAN II<br />

III<br />

I<br />

FEB II<br />

III<br />

I<br />

MAR II<br />

III<br />

I<br />

APR II<br />

III<br />

I<br />

MAY II<br />

III<br />

TOTAL ENERGY<br />

P. L. FACTOR<br />

INC.INC. IN ENR.<br />

GWH / MW<br />

% AGE UTILISN<br />

PLF (LEAN- P.)<br />

POWER & ENERGY GENERATION IN<br />

90% DEPENDABLE YEAR (1992-93)<br />

TABLE 7.4<br />

Net Head = 160.00 mtr<br />

Eff. = 0.92<br />

Restric Restricted Restricted<br />

<strong>Power</strong> Energy <strong>Power</strong> Energy <strong>Power</strong> Energy<br />

MW GWH MW GWH MW GWH<br />

90 93 96<br />

85.50 20.52 85.50 20.52 85.50 20.52<br />

90.00 21.60 93.00 22.32 96.00 23.04<br />

90.00 21.60 93.00 22.32 96.00 23.04<br />

90.00 21.60 93.00 22.32 96.00 23.04<br />

90.00 21.60 93.00 22.32 96.00 23.04<br />

90.00 23.76 93.00 24.55 96.00 25.34<br />

90.00 21.60 93.00 22.32 96.00 23.04<br />

90.00 21.60 93.00 22.32 96.00 23.04<br />

90.00 23.76 93.00 24.55 96.00 25.34<br />

90.00 21.60 93.00 22.32 96.00 23.04<br />

90.00 21.60 93.00 22.32 96.00 23.04<br />

63.65 15.28 63.65 15.28 63.65 15.28<br />

57.00 13.68 57.00 13.68 57.00 13.68<br />

46.55 11.17 46.55 11.17 46.55 11.17<br />

41.80 11.04 41.80 11.04 41.80 11.04<br />

32.30 7.75 32.30 7.75 32.30 7.75<br />

26.60 6.38 26.60 6.38 26.60 6.38<br />

23.75 5.70 23.75 5.70 23.75 5.70<br />

22.80 5.47 22.80 5.47 22.80 5.47<br />

21.85 5.24 21.85 5.24 21.85 5.24<br />

21.85 5.77 21.85 5.77 21.85 5.77<br />

19.95 4.79 19.95 4.79 19.95 4.79<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

18.05 4.77 18.05 4.77 18.05 4.77<br />

17.10 4.10 17.10 4.10 17.10 4.10<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

17.10 3.28 17.10 3.28 17.10 3.28<br />

17.10 4.10 17.10 4.10 17.10 4.10<br />

18.05 4.33 18.05 4.33 18.05 4.33<br />

18.05 4.77 18.05 4.77 18.05 4.77<br />

19.95 4.79 19.95 4.79 19.95 4.79<br />

21.85 5.24 21.85 5.24 21.85 5.24<br />

29.45 7.07 29.45 7.07 29.45 7.07<br />

47.50 11.40 47.50 11.40 47.50 11.40<br />

42.75 10.26 42.75 10.26 42.75 10.26<br />

80.75 21.32 80.75 21.32 80.75 21.32<br />

426.98 434.32 441.66<br />

0.54 0.53 0.53<br />

7.34 7.34 7.34<br />

4.74 4.67 4.60<br />

56.54 57.51 58.48<br />

0.22 0.21 0.20


MONTH PERIOD<br />

I<br />

JUN II<br />

III<br />

I<br />

JUL II<br />

III<br />

I<br />

AUG II<br />

III<br />

I<br />

SEP II<br />

III<br />

I<br />

OCT II<br />

III<br />

I<br />

NOV II<br />

III<br />

I<br />

DEC II<br />

III<br />

I<br />

JAN II<br />

III<br />

I<br />

FEB II<br />

III<br />

I<br />

MAR II<br />

III<br />

I<br />

APR II<br />

III<br />

I<br />

MAY II<br />

III<br />

TOTAL ENERGY<br />

P. L. FACTOR<br />

INC.INC. IN ENR.<br />

GWH / MW<br />

% AGE UTILISN<br />

PLF (LEAN- P.)<br />

POWER & ENERGY GENERATION IN<br />

90% DEPENDABLE YEAR (1992-93)<br />

TABLE 7.4<br />

Net Head = 160.00 mtr N<br />

Eff. = 0.92<br />

Restricted Restricted Restrict<br />

<strong>Power</strong> Energy <strong>Power</strong> Energy <strong>Power</strong> Energy<br />

MW GWH MW GWH MW GWH<br />

99 102 105<br />

85.50 20.52 85.50 20.52 85.50 20.52<br />

99.00 23.76 102.00 24.48 105.00 25.20<br />

99.00 23.76 102.00 24.48 105.00 25.20<br />

99.00 23.76 102.00 24.48 105.00 25.20<br />

99.00 23.76 102.00 24.48 105.00 25.20<br />

99.00 26.14 102.00 26.93 105.00 27.72<br />

99.00 23.76 102.00 24.48 105.00 25.20<br />

99.00 23.76 102.00 24.48 105.00 25.20<br />

99.00 26.14 102.00 26.93 105.00 27.72<br />

99.00 23.76 102.00 24.48 105.00 25.20<br />

98.80 23.71 98.80 23.71 98.80 23.71<br />

63.65 15.28 63.65 15.28 63.65 15.28<br />

57.00 13.68 57.00 13.68 57.00 13.68<br />

46.55 11.17 46.55 11.17 46.55 11.17<br />

41.80 11.04 41.80 11.04 41.80 11.04<br />

32.30 7.75 32.30 7.75 32.30 7.75<br />

26.60 6.38 26.60 6.38 26.60 6.38<br />

23.75 5.70 23.75 5.70 23.75 5.70<br />

22.80 5.47 22.80 5.47 22.80 5.47<br />

21.85 5.24 21.85 5.24 21.85 5.24<br />

21.85 5.77 21.85 5.77 21.85 5.77<br />

19.95 4.79 19.95 4.79 19.95 4.79<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

18.05 4.77 18.05 4.77 18.05 4.77<br />

17.10 4.10 17.10 4.10 17.10 4.10<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

17.10 3.28 17.10 3.28 17.10 3.28<br />

17.10 4.10 17.10 4.10 17.10 4.10<br />

18.05 4.33 18.05 4.33 18.05 4.33<br />

18.05 4.77 18.05 4.77 18.05 4.77<br />

19.95 4.79 19.95 4.79 19.95 4.79<br />

21.85 5.24 21.85 5.24 21.85 5.24<br />

29.45 7.07 29.45 7.07 29.45 7.07<br />

47.50 11.40 47.50 11.40 47.50 11.40<br />

42.75 10.26 42.75 10.26 42.75 10.26<br />

80.75 21.32 80.75 21.32 80.75 21.32<br />

448.96 455.58 462.21<br />

0.52 0.51 0.50<br />

7.30 6.62 6.62<br />

4.53 4.47 4.40<br />

59.45 60.32 61.20<br />

0.20 0.19 0.18


MONTH PERIOD<br />

I<br />

JUN II<br />

III<br />

I<br />

JUL II<br />

III<br />

I<br />

AUG II<br />

III<br />

I<br />

SEP II<br />

III<br />

I<br />

OCT II<br />

III<br />

I<br />

NOV II<br />

III<br />

I<br />

DEC II<br />

III<br />

I<br />

JAN II<br />

III<br />

I<br />

FEB II<br />

III<br />

I<br />

MAR II<br />

III<br />

I<br />

APR II<br />

III<br />

I<br />

MAY II<br />

III<br />

TOTAL ENERGY<br />

P. L. FACTOR<br />

INC.INC. IN ENR.<br />

GWH / MW<br />

% AGE UTILISN<br />

PLF (LEAN- P.)<br />

POWER & ENERGY GENERATION IN<br />

90% DEPENDABLE YEAR (1992-93)<br />

Net Head 160.00 mtr<br />

TABLE 7.4<br />

Eff. = 0.92<br />

Restrict Restricted Restrict<br />

<strong>Power</strong> Energy <strong>Power</strong> Energy <strong>Power</strong> Energy<br />

MW GWH MW GWH MW GWH<br />

108 111 114<br />

85.50 20.52 85.50 20.52 85.50 20.52<br />

108.00 25.92 111.00 26.64 114.00 27.36<br />

108.00 25.92 111.00 26.64 114.00 27.36<br />

108.00 25.92 111.00 26.64 114.00 27.36<br />

108.00 25.92 111.00 26.64 114.00 27.36<br />

108.00 28.51 111.00 29.30 114.00 30.10<br />

108.00 25.92 111.00 26.64 114.00 27.36<br />

108.00 25.92 111.00 26.64 114.00 27.36<br />

108.00 28.51 111.00 29.30 114.00 30.10<br />

108.00 25.92 111.00 26.64 114.00 27.36<br />

98.80 23.71 98.80 23.71 98.80 23.71<br />

63.65 15.28 63.65 15.28 63.65 15.28<br />

57.00 13.68 57.00 13.68 57.00 13.68<br />

46.55 11.17 46.55 11.17 46.55 11.17<br />

41.80 11.04 41.80 11.04 41.80 11.04<br />

32.30 7.75 32.30 7.75 32.30 7.75<br />

26.60 6.38 26.60 6.38 26.60 6.38<br />

23.75 5.70 23.75 5.70 23.75 5.70<br />

22.80 5.47 22.80 5.47 22.80 5.47<br />

21.85 5.24 21.85 5.24 21.85 5.24<br />

21.85 5.77 21.85 5.77 21.85 5.77<br />

19.95 4.79 19.95 4.79 19.95 4.79<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

18.05 4.77 18.05 4.77 18.05 4.77<br />

17.10 4.10 17.10 4.10 17.10 4.10<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

17.10 3.28 17.10 3.28 17.10 3.28<br />

17.10 4.10 17.10 4.10 17.10 4.10<br />

18.05 4.33 18.05 4.33 18.05 4.33<br />

18.05 4.77 18.05 4.77 18.05 4.77<br />

19.95 4.79 19.95 4.79 19.95 4.79<br />

21.85 5.24 21.85 5.24 21.85 5.24<br />

29.45 7.07 29.45 7.07 29.45 7.07<br />

47.50 11.40 47.50 11.40 47.50 11.40<br />

42.75 10.26 42.75 10.26 42.75 10.26<br />

80.75 21.32 80.75 21.32 80.75 21.32<br />

468.83 475.46 482.08<br />

0.50 0.49 0.48<br />

6.62 6.62 6.62<br />

4.34 4.28 4.23<br />

62.08 62.96 63.83<br />

0.18 0.17 0.17


MONTH PERIOD<br />

I<br />

JUN II<br />

III<br />

I<br />

JUL II<br />

III<br />

I<br />

AUG II<br />

III<br />

I<br />

SEP II<br />

III<br />

I<br />

OCT II<br />

III<br />

I<br />

NOV II<br />

III<br />

I<br />

DEC II<br />

III<br />

I<br />

JAN II<br />

III<br />

I<br />

FEB II<br />

III<br />

I<br />

MAR II<br />

III<br />

I<br />

APR II<br />

III<br />

I<br />

MAY II<br />

III<br />

TOTAL ENERGY<br />

P. L. FACTOR<br />

INC.INC. IN ENR.<br />

GWH / MW<br />

% AGE UTILISN<br />

PLF (LEAN- P.)<br />

POWER & ENERGY GENERATION IN<br />

90% DEPENDABLE YEAR (1992-93)<br />

Net Head = 160.00 mtr<br />

TABLE 7.4<br />

Eff. = 0.92<br />

Restricted Restricted Restrict<br />

<strong>Power</strong> Energy <strong>Power</strong> Energy <strong>Power</strong> Energy<br />

MW GWH MW GWH MW GWH<br />

117 120 123<br />

85.50 20.52 85.50 20.52 85.50 20.52<br />

117.00 28.08 120.00 28.80 123.00 29.52<br />

117.00 28.08 120.00 28.80 123.00 29.52<br />

117.00 28.08 120.00 28.80 123.00 29.52<br />

117.00 28.08 120.00 28.80 123.00 29.52<br />

117.00 30.89 120.00 31.68 123.00 32.47<br />

117.00 28.08 120.00 28.80 123.00 29.52<br />

117.00 28.08 120.00 28.80 123.00 29.52<br />

117.00 30.89 120.00 31.68 123.00 32.47<br />

117.00 28.08 120.00 28.80 123.00 29.52<br />

98.80 23.71 98.80 23.71 98.80 23.71<br />

63.65 15.28 63.65 15.28 63.65 15.28<br />

57.00 13.68 57.00 13.68 57.00 13.68<br />

46.55 11.17 46.55 11.17 46.55 11.17<br />

41.80 11.04 41.80 11.04 41.80 11.04<br />

32.30 7.75 32.30 7.75 32.30 7.75<br />

26.60 6.38 26.60 6.38 26.60 6.38<br />

23.75 5.70 23.75 5.70 23.75 5.70<br />

22.80 5.47 22.80 5.47 22.80 5.47<br />

21.85 5.24 21.85 5.24 21.85 5.24<br />

21.85 5.77 21.85 5.77 21.85 5.77<br />

19.95 4.79 19.95 4.79 19.95 4.79<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

18.05 4.77 18.05 4.77 18.05 4.77<br />

17.10 4.10 17.10 4.10 17.10 4.10<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

17.10 3.28 17.10 3.28 17.10 3.28<br />

17.10 4.10 17.10 4.10 17.10 4.10<br />

18.05 4.33 18.05 4.33 18.05 4.33<br />

18.05 4.77 18.05 4.77 18.05 4.77<br />

19.95 4.79 19.95 4.79 19.95 4.79<br />

21.85 5.24 21.85 5.24 21.85 5.24<br />

29.45 7.07 29.45 7.07 29.45 7.07<br />

47.50 11.40 47.50 11.40 47.50 11.40<br />

42.75 10.26 42.75 10.26 42.75 10.26<br />

80.75 21.32 80.75 21.32 80.75 21.32<br />

488.70 495.33 501.95<br />

0.48 0.47 0.47<br />

6.62 6.62 6.62<br />

4.18 4.13 4.08<br />

64.71 65.59 66.46<br />

0.17 0.16 0.16


MONTH PERIOD<br />

I<br />

JUN II<br />

III<br />

I<br />

JUL II<br />

III<br />

I<br />

AUG II<br />

III<br />

I<br />

SEP II<br />

III<br />

I<br />

OCT II<br />

III<br />

I<br />

NOV II<br />

III<br />

I<br />

DEC II<br />

III<br />

I<br />

JAN II<br />

III<br />

I<br />

FEB II<br />

III<br />

I<br />

MAR II<br />

III<br />

I<br />

APR II<br />

III<br />

I<br />

MAY II<br />

III<br />

TOTAL ENERGY<br />

P. L. FACTOR<br />

INC.INC. IN ENR.<br />

GWH / MW<br />

% AGE UTILISN<br />

PLF (LEAN- P.)<br />

POWER & ENERGY GENERATION IN<br />

90% DEPENDABLE YEAR (1992-93)<br />

TABLE 7.4<br />

Net Head = 160.00 mtr<br />

Eff. = 0.92<br />

Restricted Restrict Restrict<br />

<strong>Power</strong> Energy <strong>Power</strong> Energy <strong>Power</strong> Energy<br />

MW GWH MW GWH MW GWH<br />

126 129 132<br />

85.50 20.52 85.50 20.52 85.50 20.52<br />

126.00 30.24 129.00 30.96 132.00 31.68<br />

126.00 30.24 129.00 30.96 132.00 31.68<br />

126.00 30.24 129.00 30.96 132.00 31.68<br />

126.00 30.24 129.00 30.96 132.00 31.68<br />

126.00 33.26 129.00 34.06 132.00 34.85<br />

126.00 30.24 129.00 30.96 132.00 31.68<br />

126.00 30.24 129.00 30.96 132.00 31.68<br />

126.00 33.26 129.00 34.06 132.00 34.85<br />

126.00 30.24 129.00 30.96 132.00 31.68<br />

98.80 23.71 98.80 23.71 98.80 23.71<br />

63.65 15.28 63.65 15.28 63.65 15.28<br />

57.00 13.68 57.00 13.68 57.00 13.68<br />

46.55 11.17 46.55 11.17 46.55 11.17<br />

41.80 11.04 41.80 11.04 41.80 11.04<br />

32.30 7.75 32.30 7.75 32.30 7.75<br />

26.60 6.38 26.60 6.38 26.60 6.38<br />

23.75 5.70 23.75 5.70 23.75 5.70<br />

22.80 5.47 22.80 5.47 22.80 5.47<br />

21.85 5.24 21.85 5.24 21.85 5.24<br />

21.85 5.77 21.85 5.77 21.85 5.77<br />

19.95 4.79 19.95 4.79 19.95 4.79<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

18.05 4.77 18.05 4.77 18.05 4.77<br />

17.10 4.10 17.10 4.10 17.10 4.10<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

17.10 3.28 17.10 3.28 17.10 3.28<br />

17.10 4.10 17.10 4.10 17.10 4.10<br />

18.05 4.33 18.05 4.33 18.05 4.33<br />

18.05 4.77 18.05 4.77 18.05 4.77<br />

19.95 4.79 19.95 4.79 19.95 4.79<br />

21.85 5.24 21.85 5.24 21.85 5.24<br />

29.45 7.07 29.45 7.07 29.45 7.07<br />

47.50 11.40 47.50 11.40 47.50 11.40<br />

42.75 10.26 42.75 10.26 42.75 10.26<br />

80.75 21.32 80.75 21.32 80.75 21.32<br />

508.58 515.20 521.82<br />

0.46 0.46 0.45<br />

6.62 6.62 6.62<br />

4.04 3.99 3.95<br />

67.34 68.22 69.10<br />

0.15 0.15 0.15


MONTH PERIOD<br />

I<br />

JUN II<br />

III<br />

I<br />

JUL II<br />

III<br />

I<br />

AUG II<br />

III<br />

I<br />

SEP II<br />

III<br />

I<br />

OCT II<br />

III<br />

I<br />

NOV II<br />

III<br />

I<br />

DEC II<br />

III<br />

I<br />

JAN II<br />

III<br />

I<br />

FEB II<br />

III<br />

I<br />

MAR II<br />

III<br />

I<br />

APR II<br />

III<br />

I<br />

MAY II<br />

III<br />

TOTAL ENERGY<br />

P. L. FACTOR<br />

INC.INC. IN ENR.<br />

GWH / MW<br />

% AGE UTILISN<br />

PLF (LEAN- P.)<br />

POWER & ENERGY GENERATION IN<br />

90% DEPENDABLE YEAR (1992-93)<br />

TABLE 7.4<br />

Net Head = 160.00 mtr<br />

Eff. = 0.92<br />

Restricted Restrict Restrict<br />

<strong>Power</strong> Energy <strong>Power</strong> Energy <strong>Power</strong> Energy<br />

MW GWH MW GWH MW GWH<br />

135 138 141<br />

85.50 20.52 85.50 20.52 85.50 20.52<br />

135.00 32.40 138.00 33.12 141.00 33.84<br />

135.00 32.40 138.00 33.12 141.00 33.84<br />

135.00 32.40 138.00 33.12 141.00 33.84<br />

135.00 32.40 138.00 33.12 141.00 33.84<br />

135.00 35.64 138.00 36.43 141.00 37.22<br />

135.00 32.40 138.00 33.12 141.00 33.84<br />

135.00 32.40 138.00 33.12 141.00 33.84<br />

135.00 35.64 138.00 36.43 141.00 37.22<br />

135.00 32.40 138.00 33.12 141.00 33.84<br />

98.80 23.71 98.80 23.71 98.80 23.71<br />

63.65 15.28 63.65 15.28 63.65 15.28<br />

57.00 13.68 57.00 13.68 57.00 13.68<br />

46.55 11.17 46.55 11.17 46.55 11.17<br />

41.80 11.04 41.80 11.04 41.80 11.04<br />

32.30 7.75 32.30 7.75 32.30 7.75<br />

26.60 6.38 26.60 6.38 26.60 6.38<br />

23.75 5.70 23.75 5.70 23.75 5.70<br />

22.80 5.47 22.80 5.47 22.80 5.47<br />

21.85 5.24 21.85 5.24 21.85 5.24<br />

21.85 5.77 21.85 5.77 21.85 5.77<br />

19.95 4.79 19.95 4.79 19.95 4.79<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

18.05 4.77 18.05 4.77 18.05 4.77<br />

17.10 4.10 17.10 4.10 17.10 4.10<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

17.10 3.28 17.10 3.28 17.10 3.28<br />

17.10 4.10 17.10 4.10 17.10 4.10<br />

18.05 4.33 18.05 4.33 18.05 4.33<br />

18.05 4.77 18.05 4.77 18.05 4.77<br />

19.95 4.79 19.95 4.79 19.95 4.79<br />

21.85 5.24 21.85 5.24 21.85 5.24<br />

29.45 7.07 29.45 7.07 29.45 7.07<br />

47.50 11.40 47.50 11.40 47.50 11.40<br />

42.75 10.26 42.75 10.26 42.75 10.26<br />

80.75 21.32 80.75 21.32 80.75 21.32<br />

528.45 535.07 541.70<br />

0.45 0.44 0.44<br />

6.62 6.62 6.62<br />

3.91 3.88 3.84<br />

69.97 70.85 71.73<br />

0.14 0.14 0.14


MONTH PERIOD<br />

I<br />

JUN II<br />

III<br />

I<br />

JUL II<br />

III<br />

I<br />

AUG II<br />

III<br />

I<br />

SEP II<br />

III<br />

I<br />

OCT II<br />

III<br />

I<br />

NOV II<br />

III<br />

I<br />

DEC II<br />

III<br />

I<br />

JAN II<br />

III<br />

I<br />

FEB II<br />

III<br />

I<br />

MAR II<br />

III<br />

I<br />

APR II<br />

III<br />

I<br />

MAY II<br />

III<br />

TOTAL ENERGY<br />

P. L. FACTOR<br />

INC.INC. IN ENR.<br />

GWH / MW<br />

% AGE UTILISN<br />

PLF (LEAN- P.)<br />

POWER & ENERGY GENERATION IN<br />

90% DEPENDABLE YEAR (1992-93)<br />

TABLE 7.4<br />

Net Head = 160.00 mtr<br />

Eff. = 0.92<br />

Restricted Restrict Restrict<br />

<strong>Power</strong> Energy <strong>Power</strong> Energy <strong>Power</strong> Energy<br />

MW GWH MW GWH MW GWH<br />

144 147 150<br />

85.50 20.52 85.50 20.52 85.50 20.52<br />

144.00 34.56 147.00 35.28 150.00 36.00<br />

144.00 34.56 147.00 35.28 150.00 36.00<br />

144.00 34.56 147.00 35.28 150.00 36.00<br />

144.00 34.56 147.00 35.28 150.00 36.00<br />

144.00 38.02 147.00 38.81 150.00 39.60<br />

144.00 34.56 147.00 35.28 150.00 36.00<br />

144.00 34.56 147.00 35.28 150.00 36.00<br />

144.00 38.02 147.00 38.81 150.00 39.60<br />

144.00 34.56 147.00 35.28 150.00 36.00<br />

98.80 23.71 98.80 23.71 98.80 23.71<br />

63.65 15.28 63.65 15.28 63.65 15.28<br />

57.00 13.68 57.00 13.68 57.00 13.68<br />

46.55 11.17 46.55 11.17 46.55 11.17<br />

41.80 11.04 41.80 11.04 41.80 11.04<br />

32.30 7.75 32.30 7.75 32.30 7.75<br />

26.60 6.38 26.60 6.38 26.60 6.38<br />

23.75 5.70 23.75 5.70 23.75 5.70<br />

22.80 5.47 22.80 5.47 22.80 5.47<br />

21.85 5.24 21.85 5.24 21.85 5.24<br />

21.85 5.77 21.85 5.77 21.85 5.77<br />

19.95 4.79 19.95 4.79 19.95 4.79<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

18.05 4.77 18.05 4.77 18.05 4.77<br />

17.10 4.10 17.10 4.10 17.10 4.10<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

17.10 3.28 17.10 3.28 17.10 3.28<br />

17.10 4.10 17.10 4.10 17.10 4.10<br />

18.05 4.33 18.05 4.33 18.05 4.33<br />

18.05 4.77 18.05 4.77 18.05 4.77<br />

19.95 4.79 19.95 4.79 19.95 4.79<br />

21.85 5.24 21.85 5.24 21.85 5.24<br />

29.45 7.07 29.45 7.07 29.45 7.07<br />

47.50 11.40 47.50 11.40 47.50 11.40<br />

42.75 10.26 42.75 10.26 42.75 10.26<br />

80.75 21.32 80.75 21.32 80.75 21.32<br />

548.32 554.94 561.57<br />

0.43 0.43 0.43<br />

6.62 6.62 6.62<br />

3.81 3.78 3.74<br />

72.60 73.48 74.36<br />

0.13 0.13 0.13


MONTH PERIOD<br />

I<br />

JUN II<br />

III<br />

I<br />

JUL II<br />

III<br />

I<br />

AUG II<br />

III<br />

I<br />

SEP II<br />

III<br />

I<br />

OCT II<br />

III<br />

I<br />

NOV II<br />

III<br />

I<br />

DEC II<br />

III<br />

I<br />

JAN II<br />

III<br />

I<br />

FEB II<br />

III<br />

I<br />

MAR II<br />

III<br />

I<br />

APR II<br />

III<br />

I<br />

MAY II<br />

III<br />

TOTAL ENERGY<br />

P. L. FACTOR<br />

INC.INC. IN ENR.<br />

GWH / MW<br />

% AGE UTILISN<br />

PLF (LEAN- P.)<br />

POWER & ENERGY GENERATION IN<br />

90% DEPENDABLE YEAR (1992-93)<br />

Net Head = 160.00 mtr<br />

TABLE 7.4<br />

Eff. = 0.92<br />

Restricted Restrict Restrict<br />

<strong>Power</strong> Energy <strong>Power</strong> Energy <strong>Power</strong> Energy<br />

MW GWH MW GWH MW GWH<br />

153 156 159<br />

85.50 20.52 85.50 20.52 85.50 20.52<br />

153.00 36.72 156.00 37.44 159.00 38.16<br />

153.00 36.72 156.00 37.44 159.00 38.16<br />

153.00 36.72 156.00 37.44 159.00 38.16<br />

153.00 36.72 156.00 37.44 159.00 38.16<br />

153.00 40.39 156.00 41.18 159.00 41.98<br />

153.00 36.72 156.00 37.44 159.00 38.16<br />

153.00 36.72 156.00 37.44 159.00 38.16<br />

153.00 40.39 156.00 41.18 159.00 41.98<br />

153.00 36.72 156.00 37.44 159.00 38.16<br />

98.80 23.71 98.80 23.71 98.80 23.71<br />

63.65 15.28 63.65 15.28 63.65 15.28<br />

57.00 13.68 57.00 13.68 57.00 13.68<br />

46.55 11.17 46.55 11.17 46.55 11.17<br />

41.80 11.04 41.80 11.04 41.80 11.04<br />

32.30 7.75 32.30 7.75 32.30 7.75<br />

26.60 6.38 26.60 6.38 26.60 6.38<br />

23.75 5.70 23.75 5.70 23.75 5.70<br />

22.80 5.47 22.80 5.47 22.80 5.47<br />

21.85 5.24 21.85 5.24 21.85 5.24<br />

21.85 5.77 21.85 5.77 21.85 5.77<br />

19.95 4.79 19.95 4.79 19.95 4.79<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

18.05 4.77 18.05 4.77 18.05 4.77<br />

17.10 4.10 17.10 4.10 17.10 4.10<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

17.10 3.28 17.10 3.28 17.10 3.28<br />

17.10 4.10 17.10 4.10 17.10 4.10<br />

18.05 4.33 18.05 4.33 18.05 4.33<br />

18.05 4.77 18.05 4.77 18.05 4.77<br />

19.95 4.79 19.95 4.79 19.95 4.79<br />

21.85 5.24 21.85 5.24 21.85 5.24<br />

29.45 7.07 29.45 7.07 29.45 7.07<br />

47.50 11.40 47.50 11.40 47.50 11.40<br />

42.75 10.26 42.75 10.26 42.75 10.26<br />

80.75 21.32 80.75 21.32 80.75 21.32<br />

568.19 574.82 581.44<br />

0.42 0.42 0.42<br />

6.62 6.62 6.62<br />

3.71 3.68 3.66<br />

75.24 76.11 76.99<br />

0.13 0.12 0.12


POWER & ENERGY GENERATION IN TABLE 7.6<br />

50% MEAN YEAR (1980-81)<br />

Net Head = 160.00 mtr<br />

Eff. = 0.92<br />

50% Mean. Un-res. Restricted<br />

YEAR <strong>Power</strong> Energy <strong>Power</strong> Energy<br />

1980-81 MW GWH MW GWH<br />

MONTH PERIOD DISCHA. 78<br />

I 132.89 191.90 46.06 78.00 18.72<br />

JUN II 154.60 223.25 53.58 78.00 18.72<br />

III 219.73 317.30 76.15 78.00 18.72<br />

I 231.57 334.39 80.25 78.00 18.72<br />

JUL II 223.68 323.00 77.52 78.00 18.72<br />

III 205.91 297.35 78.50 78.00 20.59<br />

I 223.02 322.05 77.29 78.00 18.72<br />

AUG II 146.71 211.85 50.84 78.00 18.72<br />

III 165.13 238.45 62.95 78.00 20.59<br />

I 103.29 149.15 35.80 78.00 18.72<br />

SEP II 65.13 94.05 22.57 78.00 18.72<br />

III 45.39 65.55 15.73 65.55 15.73<br />

I 35.52 51.30 12.31 51.30 12.31<br />

OCT II 23.03 33.25 7.98 33.25 7.98<br />

III 18.42 26.60 7.02 26.60 7.02<br />

I 13.82 19.95 4.79 19.95 4.79<br />

NOV II 13.16 19.00 4.56 19.00 4.56<br />

III 13.16 19.00 4.56 19.00 4.56<br />

I 11.84 17.10 4.10 17.10 4.10<br />

DEC II 11.18 16.15 3.88 16.15 3.88<br />

III 10.53 15.20 4.01 15.20 4.01<br />

I 11.18 16.15 3.88 16.15 3.88<br />

JAN II 10.53 15.20 3.65 15.20 3.65<br />

III 9.87 14.25 3.76 14.25 3.76<br />

I 9.87 14.25 3.42 14.25 3.42<br />

FEB II 10.53 15.20 3.65 15.20 3.65<br />

III 11.84 17.10 3.28 17.10 3.28<br />

I 11.18 16.15 3.88 16.15 3.88<br />

MAR II 11.18 16.15 3.88 16.15 3.88<br />

III 11.84 17.10 4.51 17.10 4.51<br />

I 12.50 18.05 4.33 18.05 4.33<br />

APR II 17.10 24.70 5.93 24.70 5.93<br />

III 24.34 35.15 8.44 35.15 8.44<br />

I 86.18 124.45 29.87 78.00 18.72<br />

MAY II 109.21 157.70 37.85 78.00 18.72<br />

III 128.28 185.25 48.91 78.00 20.59<br />

TOTAL ENERGY 899.67 389.24<br />

P. L. FACTOR 0.57<br />

INC.INC. IN ENR. 0.00<br />

GWH / MW 4.99<br />

% AGE UTILISN 43.26<br />

PLF (LEAN- P.) 0.20


POWER & ENERGY GENERATION IN TABLE 7.6<br />

50% MEAN YEAR (1980-81)<br />

Net Head = 160.00 mtr<br />

Eff. = 0.92<br />

Restricted Restrict Restrict<br />

<strong>Power</strong> Energy <strong>Power</strong> Energy <strong>Power</strong> Energy<br />

MW GWH MW GWH MW GWH<br />

81 84 87<br />

81.00 19.44 84.00 20.16 87.00 20.88<br />

81.00 19.44 84.00 20.16 87.00 20.88<br />

81.00 19.44 84.00 20.16 87.00 20.88<br />

81.00 19.44 84.00 20.16 87.00 20.88<br />

81.00 19.44 84.00 20.16 87.00 20.88<br />

81.00 21.38 84.00 22.18 87.00 22.97<br />

81.00 19.44 84.00 20.16 87.00 20.88<br />

81.00 19.44 84.00 20.16 87.00 20.88<br />

81.00 21.38 84.00 22.18 87.00 22.97<br />

81.00 19.44 84.00 20.16 87.00 20.88<br />

81.00 19.44 84.00 20.16 87.00 20.88<br />

65.55 15.73 65.55 15.73 65.55 15.73<br />

51.30 12.31 51.30 12.31 51.30 12.31<br />

33.25 7.98 33.25 7.98 33.25 7.98<br />

26.60 7.02 26.60 7.02 26.60 7.02<br />

19.95 4.79 19.95 4.79 19.95 4.79<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

17.10 4.10 17.10 4.10 17.10 4.10<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

15.20 4.01 15.20 4.01 15.20 4.01<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

15.20 3.65 15.20 3.65 15.20 3.65<br />

14.25 3.76 14.25 3.76 14.25 3.76<br />

14.25 3.42 14.25 3.42 14.25 3.42<br />

15.20 3.65 15.20 3.65 15.20 3.65<br />

17.10 3.28 17.10 3.28 17.10 3.28<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

17.10 4.51 17.10 4.51 17.10 4.51<br />

18.05 4.33 18.05 4.33 18.05 4.33<br />

24.70 5.93 24.70 5.93 24.70 5.93<br />

35.15 8.44 35.15 8.44 35.15 8.44<br />

81.00 19.44 84.00 20.16 87.00 20.88<br />

81.00 19.44 84.00 20.16 87.00 20.88<br />

81.00 21.38 84.00 22.18 87.00 22.97<br />

399.54 409.83 420.13<br />

0.56 0.56 0.55<br />

10.30 10.30 10.30<br />

4.93 4.88 4.83<br />

44.41 45.55 46.70<br />

0.19 0.19 0.18


POWER & ENERGY GENERATION IN TABLE 7.6<br />

50% MEAN YEAR (1980-81)<br />

Net Head = 160.00 mtr<br />

Eff. = 0.92<br />

Restric Restricted Restricte<br />

<strong>Power</strong> Energy <strong>Power</strong> Energy <strong>Power</strong> Energy<br />

MW GWH MW GWH MW GWH<br />

90 93 96<br />

90.00 21.60 93.00 22.32 96.00 23.04<br />

90.00 21.60 93.00 22.32 96.00 23.04<br />

90.00 21.60 93.00 22.32 96.00 23.04<br />

90.00 21.60 93.00 22.32 96.00 23.04<br />

90.00 21.60 93.00 22.32 96.00 23.04<br />

90.00 23.76 93.00 24.55 96.00 25.34<br />

90.00 21.60 93.00 22.32 96.00 23.04<br />

90.00 21.60 93.00 22.32 96.00 23.04<br />

90.00 23.76 93.00 24.55 96.00 25.34<br />

90.00 21.60 93.00 22.32 96.00 23.04<br />

90.00 21.60 93.00 22.32 94.05 22.57<br />

65.55 15.73 65.55 15.73 65.55 15.73<br />

51.30 12.31 51.30 12.31 51.30 12.31<br />

33.25 7.98 33.25 7.98 33.25 7.98<br />

26.60 7.02 26.60 7.02 26.60 7.02<br />

19.95 4.79 19.95 4.79 19.95 4.79<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

17.10 4.10 17.10 4.10 17.10 4.10<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

15.20 4.01 15.20 4.01 15.20 4.01<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

15.20 3.65 15.20 3.65 15.20 3.65<br />

14.25 3.76 14.25 3.76 14.25 3.76<br />

14.25 3.42 14.25 3.42 14.25 3.42<br />

15.20 3.65 15.20 3.65 15.20 3.65<br />

17.10 3.28 17.10 3.28 17.10 3.28<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

17.10 4.51 17.10 4.51 17.10 4.51<br />

18.05 4.33 18.05 4.33 18.05 4.33<br />

24.70 5.93 24.70 5.93 24.70 5.93<br />

35.15 8.44 35.15 8.44 35.15 8.44<br />

90.00 21.60 93.00 22.32 96.00 23.04<br />

90.00 21.60 93.00 22.32 96.00 23.04<br />

90.00 23.76 93.00 24.55 96.00 25.34<br />

430.42 440.72 450.55<br />

0.55 0.54 0.54<br />

10.30 10.30 9.83<br />

4.78 4.74 4.69<br />

47.84 48.99 50.08<br />

0.17 0.17 0.16


POWER & ENERGY GENERATION IN TABLE 7.6<br />

50% MEAN YEAR (1980-81)<br />

Net Head = 160.00 mtr<br />

Eff. = 0.92<br />

Restricted Restrict Restrict<br />

<strong>Power</strong> Energy <strong>Power</strong> Energy <strong>Power</strong> Energy<br />

MW GWH MW GWH MW GWH<br />

99 102 105<br />

99.00 23.76 102.00 24.48 105.00 25.20<br />

99.00 23.76 102.00 24.48 105.00 25.20<br />

99.00 23.76 102.00 24.48 105.00 25.20<br />

99.00 23.76 102.00 24.48 105.00 25.20<br />

99.00 23.76 102.00 24.48 105.00 25.20<br />

99.00 26.14 102.00 26.93 105.00 27.72<br />

99.00 23.76 102.00 24.48 105.00 25.20<br />

99.00 23.76 102.00 24.48 105.00 25.20<br />

99.00 26.14 102.00 26.93 105.00 27.72<br />

99.00 23.76 102.00 24.48 105.00 25.20<br />

94.05 22.57 94.05 22.57 94.05 22.57<br />

65.55 15.73 65.55 15.73 65.55 15.73<br />

51.30 12.31 51.30 12.31 51.30 12.31<br />

33.25 7.98 33.25 7.98 33.25 7.98<br />

26.60 7.02 26.60 7.02 26.60 7.02<br />

19.95 4.79 19.95 4.79 19.95 4.79<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

17.10 4.10 17.10 4.10 17.10 4.10<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

15.20 4.01 15.20 4.01 15.20 4.01<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

15.20 3.65 15.20 3.65 15.20 3.65<br />

14.25 3.76 14.25 3.76 14.25 3.76<br />

14.25 3.42 14.25 3.42 14.25 3.42<br />

15.20 3.65 15.20 3.65 15.20 3.65<br />

17.10 3.28 17.10 3.28 17.10 3.28<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

17.10 4.51 17.10 4.51 17.10 4.51<br />

18.05 4.33 18.05 4.33 18.05 4.33<br />

24.70 5.93 24.70 5.93 24.70 5.93<br />

35.15 8.44 35.15 8.44 35.15 8.44<br />

99.00 23.76 102.00 24.48 105.00 25.20<br />

99.00 23.76 102.00 24.48 105.00 25.20<br />

99.00 26.14 102.00 26.93 105.00 27.72<br />

460.12 469.70 479.28<br />

0.53 0.53 0.52<br />

9.58 9.58 9.58<br />

4.65 4.60 4.56<br />

51.14 52.21 53.27<br />

0.16 0.15 0.15


POWER & ENERGY GENERATION IN TABLE 7.6<br />

50% MEAN YEAR (1980-81)<br />

Net Head = 160.00 mtr<br />

Eff. = 0.92<br />

Restricted Restrict Restrict<br />

<strong>Power</strong> Energy <strong>Power</strong> Energy <strong>Power</strong> Energy<br />

MW GWH MW GWH MW GWH<br />

108 111 114<br />

108.00 25.92 111.00 26.64 114.00 27.36<br />

108.00 25.92 111.00 26.64 114.00 27.36<br />

108.00 25.92 111.00 26.64 114.00 27.36<br />

108.00 25.92 111.00 26.64 114.00 27.36<br />

108.00 25.92 111.00 26.64 114.00 27.36<br />

108.00 28.51 111.00 29.30 114.00 30.10<br />

108.00 25.92 111.00 26.64 114.00 27.36<br />

108.00 25.92 111.00 26.64 114.00 27.36<br />

108.00 28.51 111.00 29.30 114.00 30.10<br />

108.00 25.92 111.00 26.64 114.00 27.36<br />

94.05 22.57 94.05 22.57 94.05 22.57<br />

65.55 15.73 65.55 15.73 65.55 15.73<br />

51.30 12.31 51.30 12.31 51.30 12.31<br />

33.25 7.98 33.25 7.98 33.25 7.98<br />

26.60 7.02 26.60 7.02 26.60 7.02<br />

19.95 4.79 19.95 4.79 19.95 4.79<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

17.10 4.10 17.10 4.10 17.10 4.10<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

15.20 4.01 15.20 4.01 15.20 4.01<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

15.20 3.65 15.20 3.65 15.20 3.65<br />

14.25 3.76 14.25 3.76 14.25 3.76<br />

14.25 3.42 14.25 3.42 14.25 3.42<br />

15.20 3.65 15.20 3.65 15.20 3.65<br />

17.10 3.28 17.10 3.28 17.10 3.28<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

17.10 4.51 17.10 4.51 17.10 4.51<br />

18.05 4.33 18.05 4.33 18.05 4.33<br />

24.70 5.93 24.70 5.93 24.70 5.93<br />

35.15 8.44 35.15 8.44 35.15 8.44<br />

108.00 25.92 111.00 26.64 114.00 27.36<br />

108.00 25.92 111.00 26.64 114.00 27.36<br />

108.00 28.51 111.00 29.30 114.00 30.10<br />

488.85 498.43 508.00<br />

0.52 0.51 0.51<br />

9.58 9.58 9.58<br />

4.53 4.49 4.46<br />

54.34 55.40 56.47<br />

0.14 0.14 0.14


POWER & ENERGY GENERATION IN TABLE 7.6<br />

50% MEAN YEAR (1980-81)<br />

Net Head = 160.00 mtr<br />

Eff. = 0.92<br />

Restricted Restrict Restrict<br />

<strong>Power</strong> Energy <strong>Power</strong> Energy <strong>Power</strong> Energy<br />

MW GWH MW GWH MW GWH<br />

117 120 123<br />

117.00 28.08 120.00 28.80 123.00 29.52<br />

117.00 28.08 120.00 28.80 123.00 29.52<br />

117.00 28.08 120.00 28.80 123.00 29.52<br />

117.00 28.08 120.00 28.80 123.00 29.52<br />

117.00 28.08 120.00 28.80 123.00 29.52<br />

117.00 30.89 120.00 31.68 123.00 32.47<br />

117.00 28.08 120.00 28.80 123.00 29.52<br />

117.00 28.08 120.00 28.80 123.00 29.52<br />

117.00 30.89 120.00 31.68 123.00 32.47<br />

117.00 28.08 120.00 28.80 123.00 29.52<br />

94.05 22.57 94.05 22.57 94.05 22.57<br />

65.55 15.73 65.55 15.73 65.55 15.73<br />

51.30 12.31 51.30 12.31 51.30 12.31<br />

33.25 7.98 33.25 7.98 33.25 7.98<br />

26.60 7.02 26.60 7.02 26.60 7.02<br />

19.95 4.79 19.95 4.79 19.95 4.79<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

17.10 4.10 17.10 4.10 17.10 4.10<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

15.20 4.01 15.20 4.01 15.20 4.01<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

15.20 3.65 15.20 3.65 15.20 3.65<br />

14.25 3.76 14.25 3.76 14.25 3.76<br />

14.25 3.42 14.25 3.42 14.25 3.42<br />

15.20 3.65 15.20 3.65 15.20 3.65<br />

17.10 3.28 17.10 3.28 17.10 3.28<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

17.10 4.51 17.10 4.51 17.10 4.51<br />

18.05 4.33 18.05 4.33 18.05 4.33<br />

24.70 5.93 24.70 5.93 24.70 5.93<br />

35.15 8.44 35.15 8.44 35.15 8.44<br />

117.00 28.08 120.00 28.80 123.00 29.52<br />

117.00 28.08 120.00 28.80 123.00 29.52<br />

117.00 30.89 120.00 31.68 123.00 32.47<br />

517.58 527.16 536.73<br />

0.50 0.50 0.50<br />

9.58 9.58 9.58<br />

4.42 4.39 4.36<br />

57.53 58.59 59.66<br />

0.13 0.13 0.13


POWER & ENERGY GENERATION IN TABLE 7.6<br />

50% MEAN YEAR (1980-81)<br />

Net Head = 160.00 mtr<br />

Eff. = 0.92<br />

Restricted Restrict Restrict<br />

<strong>Power</strong> Energy <strong>Power</strong> Energy <strong>Power</strong> Energy<br />

MW GWH MW GWH MW GWH<br />

126 129 132<br />

126.00 30.24 129.00 30.96 132.00 31.68<br />

126.00 30.24 129.00 30.96 132.00 31.68<br />

126.00 30.24 129.00 30.96 132.00 31.68<br />

126.00 30.24 129.00 30.96 132.00 31.68<br />

126.00 30.24 129.00 30.96 132.00 31.68<br />

126.00 33.26 129.00 34.06 132.00 34.85<br />

126.00 30.24 129.00 30.96 132.00 31.68<br />

126.00 30.24 129.00 30.96 132.00 31.68<br />

126.00 33.26 129.00 34.06 132.00 34.85<br />

126.00 30.24 129.00 30.96 132.00 31.68<br />

94.05 22.57 94.05 22.57 94.05 22.57<br />

65.55 15.73 65.55 15.73 65.55 15.73<br />

51.30 12.31 51.30 12.31 51.30 12.31<br />

33.25 7.98 33.25 7.98 33.25 7.98<br />

26.60 7.02 26.60 7.02 26.60 7.02<br />

19.95 4.79 19.95 4.79 19.95 4.79<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

17.10 4.10 17.10 4.10 17.10 4.10<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

15.20 4.01 15.20 4.01 15.20 4.01<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

15.20 3.65 15.20 3.65 15.20 3.65<br />

14.25 3.76 14.25 3.76 14.25 3.76<br />

14.25 3.42 14.25 3.42 14.25 3.42<br />

15.20 3.65 15.20 3.65 15.20 3.65<br />

17.10 3.28 17.10 3.28 17.10 3.28<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

17.10 4.51 17.10 4.51 17.10 4.51<br />

18.05 4.33 18.05 4.33 18.05 4.33<br />

24.70 5.93 24.70 5.93 24.70 5.93<br />

35.15 8.44 35.15 8.44 35.15 8.44<br />

124.45 29.87 124.45 29.87 124.45 29.87<br />

126.00 30.24 129.00 30.96 132.00 31.68<br />

126.00 33.26 129.00 34.06 132.00 34.85<br />

545.94 554.79 563.65<br />

0.49 0.49 0.49<br />

9.20 8.86 8.86<br />

4.33 4.30 4.27<br />

60.68 61.67 62.65<br />

0.12 0.12 0.12


POWER & ENERGY GENERATION IN TABLE 7.6<br />

50% MEAN YEAR (1980-81)<br />

Net Head = 160.00 mtr<br />

Eff. = 0.92<br />

Restricted Restrict Restrict<br />

<strong>Power</strong> Energy <strong>Power</strong> Energy <strong>Power</strong> Energy<br />

MW GWH MW GWH MW GWH<br />

135 138 141<br />

135.00 32.40 138.00 33.12 141.00 33.84<br />

135.00 32.40 138.00 33.12 141.00 33.84<br />

135.00 32.40 138.00 33.12 141.00 33.84<br />

135.00 32.40 138.00 33.12 141.00 33.84<br />

135.00 32.40 138.00 33.12 141.00 33.84<br />

135.00 35.64 138.00 36.43 141.00 37.22<br />

135.00 32.40 138.00 33.12 141.00 33.84<br />

135.00 32.40 138.00 33.12 141.00 33.84<br />

135.00 35.64 138.00 36.43 141.00 37.22<br />

135.00 32.40 138.00 33.12 141.00 33.84<br />

94.05 22.57 94.05 22.57 94.05 22.57<br />

65.55 15.73 65.55 15.73 65.55 15.73<br />

51.30 12.31 51.30 12.31 51.30 12.31<br />

33.25 7.98 33.25 7.98 33.25 7.98<br />

26.60 7.02 26.60 7.02 26.60 7.02<br />

19.95 4.79 19.95 4.79 19.95 4.79<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

17.10 4.10 17.10 4.10 17.10 4.10<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

15.20 4.01 15.20 4.01 15.20 4.01<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

15.20 3.65 15.20 3.65 15.20 3.65<br />

14.25 3.76 14.25 3.76 14.25 3.76<br />

14.25 3.42 14.25 3.42 14.25 3.42<br />

15.20 3.65 15.20 3.65 15.20 3.65<br />

17.10 3.28 17.10 3.28 17.10 3.28<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

17.10 4.51 17.10 4.51 17.10 4.51<br />

18.05 4.33 18.05 4.33 18.05 4.33<br />

24.70 5.93 24.70 5.93 24.70 5.93<br />

35.15 8.44 35.15 8.44 35.15 8.44<br />

124.45 29.87 124.45 29.87 124.45 29.87<br />

135.00 32.40 138.00 33.12 141.00 33.84<br />

135.00 35.64 138.00 36.43 141.00 37.22<br />

572.50 581.36 590.22<br />

0.48 0.48 0.48<br />

8.86 8.86 8.86<br />

4.24 4.21 4.19<br />

63.63 64.62 65.60<br />

0.12 0.11 0.11


POWER & ENERGY GENERATION IN TABLE 7.6<br />

50% MEAN YEAR (1980-81)<br />

Net Head = 160.00 mtr<br />

Eff. = 0.92<br />

Restricted Restrict Restrict<br />

<strong>Power</strong> Energy <strong>Power</strong> Energy <strong>Power</strong> Energy<br />

MW GWH MW GWH MW GWH<br />

144 147 150<br />

144.00 34.56 147.00 35.28 150.00 36.00<br />

144.00 34.56 147.00 35.28 150.00 36.00<br />

144.00 34.56 147.00 35.28 150.00 36.00<br />

144.00 34.56 147.00 35.28 150.00 36.00<br />

144.00 34.56 147.00 35.28 150.00 36.00<br />

144.00 38.02 147.00 38.81 150.00 39.60<br />

144.00 34.56 147.00 35.28 150.00 36.00<br />

144.00 34.56 147.00 35.28 150.00 36.00<br />

144.00 38.02 147.00 38.81 150.00 39.60<br />

144.00 34.56 147.00 35.28 149.15 35.80<br />

94.05 22.57 94.05 22.57 94.05 22.57<br />

65.55 15.73 65.55 15.73 65.55 15.73<br />

51.30 12.31 51.30 12.31 51.30 12.31<br />

33.25 7.98 33.25 7.98 33.25 7.98<br />

26.60 7.02 26.60 7.02 26.60 7.02<br />

19.95 4.79 19.95 4.79 19.95 4.79<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

17.10 4.10 17.10 4.10 17.10 4.10<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

15.20 4.01 15.20 4.01 15.20 4.01<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

15.20 3.65 15.20 3.65 15.20 3.65<br />

14.25 3.76 14.25 3.76 14.25 3.76<br />

14.25 3.42 14.25 3.42 14.25 3.42<br />

15.20 3.65 15.20 3.65 15.20 3.65<br />

17.10 3.28 17.10 3.28 17.10 3.28<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

17.10 4.51 17.10 4.51 17.10 4.51<br />

18.05 4.33 18.05 4.33 18.05 4.33<br />

24.70 5.93 24.70 5.93 24.70 5.93<br />

35.15 8.44 35.15 8.44 35.15 8.44<br />

124.45 29.87 124.45 29.87 124.45 29.87<br />

144.00 34.56 147.00 35.28 150.00 36.00<br />

144.00 38.02 147.00 38.81 150.00 39.60<br />

599.07 607.93 616.58<br />

0.47 0.47 0.47<br />

8.86 8.86 8.65<br />

4.16 4.14 4.11<br />

66.59 67.57 68.53<br />

0.11 0.11 0.10


POWER & ENERGY GENERATION IN TABLE 7.6<br />

50% MEAN YEAR (1980-81)<br />

Net Head = 160.00 mtr<br />

Eff. = 0.92<br />

Restricted Restrict Restrict<br />

<strong>Power</strong> Energy <strong>Power</strong> Energy <strong>Power</strong> Energy<br />

MW GWH MW GWH MW GWH<br />

153 156 159<br />

153.00 36.72 156.00 37.44 159.00 38.16<br />

153.00 36.72 156.00 37.44 159.00 38.16<br />

153.00 36.72 156.00 37.44 159.00 38.16<br />

153.00 36.72 156.00 37.44 159.00 38.16<br />

153.00 36.72 156.00 37.44 159.00 38.16<br />

153.00 40.39 156.00 41.18 159.00 41.98<br />

153.00 36.72 156.00 37.44 159.00 38.16<br />

153.00 36.72 156.00 37.44 159.00 38.16<br />

153.00 40.39 156.00 41.18 159.00 41.98<br />

149.15 35.80 149.15 35.80 149.15 35.80<br />

94.05 22.57 94.05 22.57 94.05 22.57<br />

65.55 15.73 65.55 15.73 65.55 15.73<br />

51.30 12.31 51.30 12.31 51.30 12.31<br />

33.25 7.98 33.25 7.98 33.25 7.98<br />

26.60 7.02 26.60 7.02 26.60 7.02<br />

19.95 4.79 19.95 4.79 19.95 4.79<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

19.00 4.56 19.00 4.56 19.00 4.56<br />

17.10 4.10 17.10 4.10 17.10 4.10<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

15.20 4.01 15.20 4.01 15.20 4.01<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

15.20 3.65 15.20 3.65 15.20 3.65<br />

14.25 3.76 14.25 3.76 14.25 3.76<br />

14.25 3.42 14.25 3.42 14.25 3.42<br />

15.20 3.65 15.20 3.65 15.20 3.65<br />

17.10 3.28 17.10 3.28 17.10 3.28<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

16.15 3.88 16.15 3.88 16.15 3.88<br />

17.10 4.51 17.10 4.51 17.10 4.51<br />

18.05 4.33 18.05 4.33 18.05 4.33<br />

24.70 5.93 24.70 5.93 24.70 5.93<br />

35.15 8.44 35.15 8.44 35.15 8.44<br />

124.45 29.87 124.45 29.87 124.45 29.87<br />

153.00 36.72 156.00 37.44 157.70 37.85<br />

153.00 40.39 156.00 41.18 159.00 41.98<br />

624.72 632.85 640.68<br />

0.47 0.46 0.46<br />

8.14 8.14 7.82<br />

4.08 4.06 4.03<br />

69.44 70.34 71.21<br />

0.10 0.10 0.10


CHHATRU HYDRO- ELECTRIC PROJECT TABLE-7.7<br />

50% Dep. <strong>Power</strong> Energy Energy<br />

Discharges MW GWH GWH<br />

MONTH PERIOD 1980-81 108 at 95%m/c Availability<br />

I 132.89 108.00 25.92 25.92<br />

JUN II 154.60 108.00 25.92 24.62<br />

III 219.73 108.00 25.92 24.62<br />

I 231.57 108.00 25.92 24.62<br />

JUL II 223.68 108.00 25.92 24.62<br />

III 205.91 108.00 28.51 27.09<br />

I 223.02 108.00 25.92 24.62<br />

AUG II 146.71 108.00 25.92 24.62<br />

III 165.13 108.00 28.51 27.09<br />

I 103.29 108.00 25.92 24.62<br />

SEP II 65.13 94.05 22.57 21.44<br />

III 45.39 65.55 15.73 15.73<br />

I 35.52 51.30 12.31 12.31<br />

OCT II 23.03 33.25 7.98 7.98<br />

III 18.42 26.60 7.02 7.02<br />

I 13.82 19.95 4.79 4.79<br />

NOV II 13.16 19.00 4.56 4.56<br />

III 13.16 19.00 4.56 4.56<br />

I 11.84 17.10 4.10 4.10<br />

DEC II 11.18 16.15 3.88 3.88<br />

III 10.53 15.20 4.01 4.01<br />

I 11.18 16.15 3.88 3.88<br />

JAN II 10.53 15.20 3.65 3.65<br />

III 9.87 14.25 3.76 3.76<br />

I 9.87 14.25 3.42 3.42<br />

FEB II 10.53 15.20 3.65 3.65<br />

III 11.84 17.10 3.28 3.28<br />

I 11.18 16.15 3.88 3.88<br />

MAR II 11.18 16.15 3.88 3.88<br />

III 11.84 17.10 4.51 4.51<br />

I 12.50 18.05 4.33 4.33<br />

APR II 17.10 24.70 5.93 5.93<br />

III 24.34 35.15 8.44 8.44<br />

I 86.18 108.00 25.92 25.92<br />

MAY II 109.21 108.00 25.92 25.92<br />

III 128.28 108.00 28.51 28.51<br />

TOTAL ENERGY= 488.85 475.80<br />

GWH GWH


CHHATRU HYDRO- ELECTRIC PROJECT<br />

SUMMARY TABLE 7.10<br />

50% MEAN YEAR<br />

Installed Cap. Total Energy Inc. Increase Gwh/ Mw PLF PLF<br />

Mw Gwh Gwh Total Year Dec. - Feb.<br />

78 389.24 0.00 4.99 0.57 0.20<br />

81 399.54 10.30 4.93 0.56 0.19<br />

84 409.83 10.30 4.88 0.56 0.19<br />

87 420.13 10.30 4.83 0.55 0.18<br />

90 430.42 10.30 4.78 0.55 0.17<br />

93 440.72 10.30 4.74 0.54 0.17<br />

96 450.55 9.83 4.69 0.54 0.16<br />

99 460.12 9.58 4.65 0.53 0.16<br />

102 469.70 9.58 4.60 0.53 0.15<br />

105 479.28 9.58 4.56 0.52 0.15<br />

108 488.85 9.58 4.53 0.52 0.14<br />

111 498.43 9.58 4.49 0.51 0.14<br />

114 508.00 9.58 4.46 0.51 0.14<br />

117 517.58 9.58 4.42 0.50 0.13<br />

120 527.16 9.58 4.39 0.50 0.13<br />

123 536.73 9.58 4.36 0.50 0.13<br />

126 545.94 9.20 4.33 0.49 0.12<br />

129 554.79 8.86 4.30 0.49 0.12<br />

132 563.65 8.86 4.27 0.49 0.12<br />

135 572.50 8.86 4.24 0.48 0.12<br />

138 581.36 8.86 4.21 0.48 0.11<br />

141 590.22 8.86 4.19 0.48 0.11<br />

144 599.07 8.86 4.16 0.47 0.11<br />

147 607.93 8.86 4.14 0.47 0.11<br />

150 616.58 8.65 4.11 0.47 0.10<br />

153 624.72 8.14 4.08 0.47 0.10<br />

156 632.85 8.14 4.06 0.46 0.10<br />

159 640.68 7.82 4.03 0.46 0.10


DISCH. IN CUMECS<br />

400.00<br />

300.00<br />

200.00<br />

100.00<br />

0.00<br />

0.00<br />

CHHATRU HEP FLOW DURATION CURVE(OVER-ALL)<br />

10.00<br />

20.00<br />

30.00<br />

40.00<br />

50.00<br />

60.00<br />

% OCCURR.<br />

70.00<br />

80.00<br />

90.00<br />

100.00<br />

PLATE 5.1<br />

%Cumm.occ. Disch.(m3/sec)<br />

0.31 300.00<br />

10.49 200.00<br />

19.03 150.00<br />

28.40 100.00<br />

29.53 90.00<br />

31.38 80.00<br />

32.92 70.00<br />

34.88 60.00<br />

37.04 50.00<br />

41.26 40.00<br />

46.50 30.00<br />

51.23 25.00<br />

59.67 20.00<br />

72.53 15.00<br />

91.56 10.00<br />

100.00 5.00<br />

90% Dep. Discharge = 10.41 cumecs<br />

50% Dep. Discharge = 26.30 cumecs<br />

Design discharge <strong>of</strong> 75 Cumec 32.15 % availability


DISCH.(CUMECS)<br />

40<br />

35<br />

30<br />

25<br />

20<br />

15<br />

10<br />

5<br />

0<br />

0.00<br />

CHHATRU HEP FLOW DURATION CURVE (LEAN SEASON)<br />

10.00<br />

20.00<br />

30.00<br />

40.00<br />

50.00<br />

60.00<br />

% OCCURR.<br />

70.00<br />

80.00<br />

90.00<br />

100.00<br />

PLATE 5.2<br />

Series1<br />

%Cumm.occ. Disch.<br />

2.06 35<br />

2.47 30<br />

4.94 25<br />

13.58 20<br />

32.92 15<br />

74.49 10<br />

100.00 5<br />

90% Dep. Discharge = 6.96 Cumecs<br />

50% Dep. Discharge = 12.95 Cumecs


TEN DAILY AVERAGE DISCHARGE DATA OF RIVER CHANDRA AT GHOUSA<br />

Year Period 1973-74 1974-75 1975-76 1976-77 1977-78 1978-79 1979-80<br />

I 279 98 196 208 135 237 101<br />

June II 464 163 271 163 93 215 205<br />

III 402 110 306 139 281 411 403<br />

I 383 154 228 269 370 443 359<br />

July II 403 289 403 352 347 369 431<br />

III 330 238 278 372 294 360 346<br />

I 323 262 329 262 349 368 386<br />

Aug. II 229 222 357 233 249 289 322<br />

III 266 205 236 184 221 259 236<br />

I 217 136 183 156 189 126 213<br />

Sept. II 198 100 127 84 109 105 112<br />

III 136 66 80 69 71 83 51<br />

I 48 35 61 49 50 56 48<br />

Oct. II 31 27 51 31 34 44 39<br />

III 26 22 33 23 29 38 34<br />

I 22 18 23 21 26 28 31<br />

Nov. II 19 17 20 19 22 25 27<br />

III 18 16 18 17 21 25 26<br />

I 18 15 16 16 20 23 25<br />

Dec. II 17 13 14 14 17 22 23<br />

III 17 14 13 13 15 22 23<br />

I 16 14 12 12 13 22 20<br />

Jan. II 14 14 12 11 15 19 19<br />

III 17 12 11 9 14 18 18<br />

I 14 14 12 13 13 20 23<br />

Feb. II 17 14 8 12 12 18 20<br />

III 15 14 10 12 18 16 22<br />

I 14 11 12 12 12 17 20<br />

March II 15 12 11 12 12 22 22<br />

III 19 16 10 17 15 28 24<br />

I 21 18 10 20 16 31 26<br />

April II 26 25 16 19 26 38 29<br />

III 43 35 40 24 33 63 32<br />

I 66 51 57 24 102 88 66<br />

May II 57 111 88 36 159 77 90<br />

III 64 143 122 88 181 76 122<br />

TEN DAILY AVERAGE DISCHARGE DATA OF RIVER CHENAB AT UDAIPUR<br />

Month Period 1973-74 1974-75 1975-76 1976-77 1977-78 1978-79 1979-80<br />

I 195 361 477 258 456 197<br />

June II 318 558 351 184 424 401<br />

III 203 651 287 633 845 806<br />

I 299 513 574 828 904 736<br />

July II 636 887 721 754 700 927


III 504 618 755 601 700 698<br />

I 524 731 569 724 725 817<br />

Aug. II 430 856 518 501 619 666<br />

III 417 535 381 468 528 437<br />

I 293 718 326 396 253 423<br />

Sept. II 205 288 178 226 221 216<br />

III 144 177 159 151 164 130<br />

I 82 148 118 109 121 127<br />

Oct. II 67 121 70 80 96 108<br />

III 55 79 56 69 79 91<br />

I 46 58 52 57 59 83<br />

Nov. II 40 49 44 49 49 70<br />

III 36 42 37 44 44 65<br />

I 36 39 34 38 40 59<br />

Dec. II 35 33 31 35 38 57<br />

III 35 32 31 33 35 57<br />

I 24 32 33 30 32 41 57<br />

Jan. II 22 31 33 29 33 42 56<br />

III 23 26 32 155 32 40 52<br />

I 21 27 31 33 32 39 58<br />

Feb. II 23 31 25 27 27 38 57<br />

III 21 32 28 26 32 - 54<br />

I 23 30 31 28 31 - 51<br />

March II 23 31 29 29 31 - 51<br />

III 35 31 28 37 36 - 51<br />

I 42 38 34 40 38 - 58<br />

April II 53 54 42 39 66 91 71<br />

III 75 71 101 47 82 144 95<br />

I 137 108 131 50 197 179 155<br />

May II 106 228 189 75 290 163 182<br />

III 125 277 276 168 336 145 240


AL (in cu.M/Sec.) FROM 1973-74 Nov.2000.<br />

1980-81 1981-82 1982-83 1983-84 1984-85 1985-86 1986-87 1987-88 1988-89<br />

202 151 122 133 256 186 95 165 155<br />

235 152 232 148 248 220 228 170 199<br />

334 315 213 219 299 255 391 224 392<br />

352 277 283 269 289 294 331 386 393<br />

340 357 314 224 220 340 382 414 375<br />

313 376 353 337 267 271 417 451 378<br />

339 324 379 397 300 286 374 359 328<br />

223 296 335 358 321 283 338 335 333<br />

251 216 247 354 262 250 228 345 238<br />

157 169 163 288 166 200 207 259 198<br />

99 94 151 202 121 112 105 168 167<br />

69 86 115 108 60 81 80 129 168<br />

54 47 80 76 37 65 49 74 79<br />

35 39 70 51 38 42 37 52 57<br />

28 25 39 33 37 34 27 45 48<br />

21 23 26 27 34 29 23 43 43<br />

20 20 25 25 31 22 23 40 39<br />

20 18 22 23 26 21 20 37 37<br />

18 17 18 20 25 20 19 29 31<br />

17 15 15 19 34 18 19 24 29<br />

16 14 14 18 23 16 18 20 25<br />

17 14 15 19 19 15 19 19 23<br />

16 14 15 19 18 15 19 18 20<br />

15 12 15 18 17 15 20 17 19<br />

15 13 14 17 15 15 19 17 18<br />

16 14 14 17 18 14 18 17 17<br />

18 13 14 16 18 14 17 16 15<br />

17 15 18 16 21 14 18 17 17<br />

17 15 20 18 22 14 17 24 17<br />

18 14 18 19 23 15 17 34 18<br />

19 16 18 20 24 16 18 28 18<br />

26 17 18 20 29 18 19 54 20<br />

37 25 21 26 45 21 44 97 21<br />

131 49 37 45 56 45 64 94 25<br />

166 44 56 74 71 121 55 118 51<br />

195 76 83 125 159 69 74 122 132<br />

(in cu.M/Sec.) FROM Jan.1973-74 May.2001.<br />

1980-81 1981-82 1982-83 1983-84 1984-85 1985-86 1986-87 1987-88 1988-89<br />

395 292 320 264 615 379 207 330 420<br />

481 311 537 310 555 469 499 383 535<br />

696 738 519 555 643 511 810 546 958<br />

731 582 582 497 576 579 685 717 950<br />

762 779 705 350 437 666 797 709 811


635 818 903 725 556 535 819 863 920<br />

750 694 861 903 598 585 697 624 710<br />

423 628 664 686 639 564 648 577 704<br />

473 467 425 697 536 520 482 631 493<br />

301 370 338 597 362 392 424 532 416<br />

213 221 339 406 239 240 197 352 306<br />

165 211 136 195 112 165 181 273 274<br />

150 125 84 142 78 127 109 132 170<br />

116 108 71 99 65 80 78 100 132<br />

95 92 63 62 60 63 64 80 98<br />

84 76 53 50 48 54 53 78 85<br />

77 57 48 48 43 49 49 75 75<br />

72 53 44 44 41 46 45 71 64<br />

68 49 42 42 38 41 40 68 57<br />

67 45 42 39 37 38 37 64 52<br />

65 44 39 36 36 36 34 62 47<br />

65 36 31 35 36 37 34 57 39<br />

62 35 29 35 34 35 33 55 36<br />

65 33 28 32 31 34 32 52 36<br />

59 36 27 30 31 34 31 51 34<br />

64 35 26 28 30 34 36 49 35<br />

64 37 24 22 31 35 38 48 32<br />

61 37 26 33 33 35 42 57 33<br />

60 37 30 33 31 49 52 77 34<br />

65 38 32 36 36 35 54 70 43<br />

70 45 44 42 36 37 65 100 36<br />

100 56 45 51 42 65 82 143 40<br />

149 80 45 69 63 103 102 187 44<br />

304 138 100 128 93 143 110 243 51<br />

321 109 173 180 120 245 111 350 73<br />

405 179 167 353 386 170 156 377 181


1989-90 1990-91 1991-92 1992-93 1993-94 1994-95 1995-96 1996-97 1997-98<br />

292 176 213 90 156 215 156 169 67<br />

215 174 301 205 220 220 328 299 174<br />

257 449 352 263 260 311 273 351 230<br />

240 402 448 202 289 379 415 263 257<br />

356 285 433 299 326 402 365 290 319<br />

456 284 397 332 192 362 262 323 344<br />

209 335 326 247 245 329 254 345 272<br />

290 283 253 236 184 265 256 343 249<br />

266 266 247 248 204 370 237 249 216<br />

133 200 226 212 163 195 263 186 161<br />

126 148 178 104 190 140 181 120 161<br />

106 112 103 67 75 74 117 103 121<br />

64 69 72 60 58 63 78 77 67<br />

43 53 54 49 45 46 59 60 50<br />

37 42 44 44 34 38 45 52 44<br />

33 38 38 34 30 38 36 46 41<br />

30 37 30 28 25 36 32 44 38<br />

27 34 26 25 23 34 31 41 36<br />

28 27 23 24 23 33 32 40 34<br />

26 23 21 23 22 31 25 39 33<br />

24 21 20 23 20 30 25 37 32<br />

24 19 19 21 19 29 25 36 30<br />

23 19 19 20 18 27 25 34 30<br />

23 17 18 19 17 24 26 32 29<br />

22 16 18 18 17 23 22 34 27<br />

23 14 18 17 17 23 23 34 27<br />

22 14 17 18 17 24 21 33 30<br />

23 12 18 18 19 24 23 33 30<br />

25 16 19 19 21 26 23 34 31<br />

26 17 18 19 23 27 27 39 32<br />

26 20 19 21 23 28 27 37 34<br />

28 18 23 23 28 29 27 39 37<br />

33 30 29 31 33 28 29 39 40<br />

62 61 34 50 52 32 33 43 46<br />

140 97 48 45 58 90 31 43 53<br />

184 90 70 85 150 105 74 52 154<br />

1989-90 1990-91 1991-92 1992-93 1993-94 1994-95 1995-96 1996-97 1997-98<br />

497 503 589 490 305 388 409 253 251<br />

445 459 775 700 471 362 831 542 211<br />

530 989 826 909 458 996 589 703 362<br />

501 886 905 825 648 954 776 140 344<br />

694 721 975 864 650 758 837 298 524


992 634 1025 950 451 747 677 312 561<br />

525 820 820 816 496 753 548 216 569<br />

639 582 487 631 398 612 658 182 604<br />

569 590 510 650 469 653 605 163 523<br />

314 424 473 472 356 511 452 407 437<br />

326 215 415 218 246 220 276 366 294<br />

257 125 234 163 200 129 204 295 169<br />

175 88 163 136 130 117 170 187 95<br />

131 72 125 104 108 96 145 158 57<br />

101 64 96 89 80 73 167 132 59<br />

90 58 88 82 77 73 100 85 62<br />

85 43 82 80 80 70 74 69 62<br />

81 31 78 75 74 67 61 62 57<br />

78 39 72 68 68 64 59 67 53<br />

70 37 68 61 67 60 56 64 50<br />

64 38 63 56 56 60 53 62 54<br />

61 34 56 48 50 63 56 60 48<br />

56 29 54 46 48 63 58 57 47<br />

53 29 54 44 44 61 56 57 45<br />

50 38 59 41 46 60 58 60 42<br />

47 28 54 41 45 63 63 59 43<br />

44 30 52 41 53 62 61 67 46<br />

43 31 52 45 44 60 65 85 56<br />

43 45 61 44 53 63 62 106 58<br />

49 69 72 42 64 64 30 96 76<br />

50 98 73 42 68 69 80 67 86<br />

59 136 84 50 69 77 98 64 114<br />

82 162 110 74 88 88 111 72 172<br />

133 178 152 118 115 97 125 78 202<br />

348 220 233 124 134 101 131 54 244<br />

545 246 326 168 194 128 121 109 398


1998-99 1999-2000 2000-01<br />

221 147 130<br />

175 278 187<br />

286 384 245<br />

485 429 236<br />

520 435 248<br />

453 344 292<br />

442 371 278<br />

426 293 248<br />

351 321 263<br />

296 240 200<br />

227 221 135<br />

128 197 92<br />

105 118 58<br />

75 72 53<br />

69 67 50<br />

66 67 51<br />

57 66 45<br />

45 61 41<br />

40 59<br />

38 57<br />

36 57<br />

35 43<br />

34 42<br />

32 41<br />

31 55<br />

30 55<br />

29 46<br />

30 50<br />

30 46<br />

33 43<br />

34 42<br />

40 42<br />

124 45<br />

164 86<br />

193 197<br />

218 187<br />

1998-99 1999-2000 2000-01<br />

466 273 290<br />

333 590 451<br />

717 777 675<br />

968 1032 655<br />

815 908 725


610 712 944<br />

708 881 674<br />

709 588 670<br />

564 591 641<br />

504 470 500<br />

322 427 336<br />

264 319 207<br />

152 202 166<br />

132 121 143<br />

110 109 135<br />

91 96 130<br />

81 85 104<br />

70 72 91<br />

61 66 85<br />

55 63 83<br />

48 61 80<br />

49 53 77<br />

47 49 67<br />

45 49 71<br />

57 48 65<br />

58 46 65<br />

55 48 65<br />

55 47 66<br />

55 47 71<br />

60 52 75<br />

72 69 72<br />

118 97 86<br />

281 117 98<br />

255 193 152<br />

360 411 257<br />

397 430 293


Table-5.3(1)<br />

REGRESSION ANALYSIS BETWEEN DISCHARGES OF TANDI AND GHOUSAL JUNE- JULY<br />

TANDI GHOUSAL DEVIATION FROM MEAN<br />

D/SITE D/SITE X Y X^2 X*Y<br />

YEAR MONTH Qx Qy LOG x LOG y LOGx-LOGX' LOGy-LOGy'<br />

(Cumecs) (Cumecs)<br />

I 54.28 98.00 1.7346 1.9912 -0.3652 -0.3987 0.1334 0.1456<br />

1974 JUN II 85.59 163.00 1.9324 2.2122 -0.1674 -0.1777 0.0280 0.0298<br />

III 57.44 110.00 1.7592 2.0414 -0.3406 -0.3485 0.1160 0.1187<br />

I 92.61 154.00 1.9667 2.1875 -0.1332 -0.2024 0.0177 0.0270<br />

JUL II 163.53 289.00 2.2136 2.4609 0.1138 0.0710 0.0129 0.0081<br />

III 136.12 238.00 2.1339 2.3766 0.0341 -0.0133 0.0012 -0.0005<br />

I 86.44 196.00 1.9367 2.2923 -0.1631 -0.0977 0.0266 0.0159<br />

1975 JUN II 127.51 271.00 2.1055 2.4330 0.0057 0.0430 0.0000 0.0002<br />

III 162.02 306.00 2.2096 2.4857 0.1098 0.0958 0.0120 0.0105<br />

I 132.00 228.00 2.1206 2.3579 0.0208 -0.0320 0.0004 -0.0007<br />

JUL II 210.91 403.00 2.3241 2.6053 0.2243 0.2154 0.0503 0.0483<br />

III 151.52 278.00 2.1805 2.4440 0.0807 0.0541 0.0065 0.0044<br />

I 109.18 208.00 2.0381 2.3181 -0.0617 -0.0719 0.0038 0.0044<br />

1976 JUN II 84.79 163.00 1.9283 2.2122 -0.1715 -0.1777 0.0294 0.0305<br />

III 63.81 139.00 1.8049 2.1430 -0.2949 -0.2469 0.0870 0.0728<br />

I 146.59 269.00 2.1661 2.4298 0.0663 0.0398 0.0044 0.0026<br />

JUL II 208.80 352.00 2.3197 2.5465 0.2199 0.1566 0.0484 0.0344<br />

III 208.87 372.00 2.3199 2.5705 0.2201 0.1806 0.0484 0.0397<br />

I 61.59 135.00 1.7895 2.1303 -0.3103 -0.2596 0.0963 0.0806<br />

1977 JUN II 48.04 93.00 1.6816 1.9685 -0.4182 -0.4214 0.1749 0.1763<br />

III 155.71 281.00 2.1923 2.4487 0.0925 0.0588 0.0086 0.0054<br />

I 209.09 370.00 2.3203 2.5682 0.2205 0.1783 0.0486 0.0393<br />

JUL II 185.87 347.00 2.2692 2.5403 0.1694 0.1504 0.0287 0.0255<br />

III 156.26 294.00 2.1938 2.4683 0.0940 0.0784 0.0088 0.0074<br />

I 116.06 237.00 2.0647 2.3747 -0.0351 -0.0152 0.0012 0.0005<br />

1978 JUN II 97.95 215.00 1.9910 2.3324 -0.1088 -0.0575 0.0118 0.0063<br />

III 229.03 411.00 2.3599 2.6138 0.2601 0.2239 0.0676 0.0582<br />

I 204.43 443.00 2.3105 2.6464 0.2107 0.2565 0.0444 0.0540<br />

JUL II 171.15 369.00 2.2334 2.5670 0.1336 0.1771 0.0178 0.0237<br />

III 176.99 360.00 2.2479 2.5563 0.1481 0.1664 0.0219 0.0246<br />

I 40.70 101.00 1.6096 2.0043 -0.4902 -0.3856 0.2403 0.1890<br />

1979 JUN II 90.39 205.00 1.9561 2.3118 -0.1437 -0.0782 0.0206 0.0112<br />

III 194.47 403.00 2.2889 2.6053 0.1890 0.2154 0.0357 0.0407<br />

I 182.98 359.00 2.2624 2.5551 0.1626 0.1652 0.0264 0.0269<br />

JUL II 229.97 431.00 2.3617 2.6345 0.2619 0.2446 0.0686 0.0640<br />

III 173.08 346.00 2.2382 2.5391 0.1384 0.1492 0.0192 0.0206<br />

I 99.89 202.00 1.9995 2.3054 -0.1003 -0.0846 0.0101 0.0085<br />

1980 JUN II 121.45 235.00 2.0844 2.3711 -0.0154 -0.0189 0.0002 0.0003<br />

III 173.78 334.00 2.2400 2.5237 0.1402 0.1338 0.0197 0.0188<br />

I 184.27 352.00 2.2655 2.5465 0.1656 0.1566 0.0274 0.0259<br />

JUL II 184.29 340.00 2.2655 2.5315 0.1657 0.1416 0.0275 0.0235<br />

III 161.10 313.00 2.2071 2.4955 0.1073 0.1056 0.0115 0.0113<br />

I 70.07 151.00 1.8455 2.1790 -0.2543 -0.2109 0.0647 0.0536<br />

1981 JUN II 77.57 152.00 1.8897 2.1818 -0.2101 -0.2081 0.0442 0.0437<br />

III 186.01 315.00 2.2695 2.4983 0.1697 0.1084 0.0288 0.0184<br />

I 141.26 277.00 2.1500 2.4425 0.0502 0.0526 0.0025 0.0026<br />

JUL II 169.95 357.00 2.2303 2.5527 0.1305 0.1627 0.0170 0.0212<br />

III 196.92 376.00 2.2943 2.5752 0.1945 0.1853 0.0378 0.0360<br />

I 60.53 122.00 1.7820 2.0864 -0.3178 -0.3036 0.1010 0.0965<br />

1982 JUN II 100.83 232.00 2.0036 2.3655 -0.0962 -0.0244 0.0093 0.0024<br />

III 115.64 213.00 2.0631 2.3284 -0.0367 -0.0615 0.0013 0.0023<br />

I 156.48 283.00 2.1945 2.4518 0.0946 0.0619 0.0090 0.0059<br />

JUL II 150.71 314.00 2.1781 2.4969 0.0783 0.1070 0.0061 0.0084<br />

III 186.55 353.00 2.2708 2.5478 0.1710 0.1579 0.0292 0.0270<br />

I 71.20 133.00 1.8525 2.1239 -0.2473 -0.2661 0.0612 0.0658<br />

1983 JUN II 83.29 148.00 1.9206 2.1703 -0.1792 -0.2197 0.0321 0.0394<br />

III 108.14 219.00 2.0340 2.3404 -0.0658 -0.0495 0.0043 0.0033<br />

I 133.41 269.00 2.1252 2.4298 0.0254 0.0398 0.0006 0.0010<br />

JUL II 89.79 224.00 1.9532 2.3502 -0.1466 -0.0397 0.0215 0.0058<br />

III 201.52 337.00 2.3043 2.5276 0.2045 0.1377 0.0418 0.0282<br />

G.TOTAL 125.99 143.40 0.00 0.00 2.18 2.00<br />

NO. OF PERIOD 60 LOG x' LOG y'<br />

AVERAGE<br />

Co-efficient <strong>of</strong> Corelation<br />

2.0998 2.3899<br />

b = SIGMA X*Y = 0.9168<br />

SIGMA X^2


REGRESSION ANALYSIS BETWEEN DISCHARGES OF TANDI AND GHOUSAL AUG.- SEPT.<br />

TANDI GHOUSAL DEVIATION FROM MEAN<br />

D/SITE D/SITE X Y X^2 X*Y<br />

YEAR MONTH Qx Qy LOG x LOG y LOGx-LOGX' LOGy-LOGy'<br />

(Cumecs) (Cumecs)<br />

I 140.96 262.00 2.1491 2.4183 0.1890 0.1610 0.0357 0.0304<br />

1974 AUG II 108.22 222.00 2.0343 2.3464 0.0742 0.0890 0.0055 0.0066<br />

III 106.99 205.00 2.0293 2.3118 0.0693 0.0544 0.0048 0.0038<br />

I 75.23 136.00 1.8764 2.1335 -0.0837 -0.1238 0.0070 0.0104<br />

SEPT II 60.48 100.00 1.7816 2.0000 -0.1785 -0.2573 0.0318 0.0459<br />

III 41.41 66.00 1.6171 1.8195 -0.3430 -0.4378 0.1176 0.1501<br />

I 182.62 329.00 2.2615 2.5172 0.3015 0.2599 0.0909 0.0784<br />

1975 AUG II 218.79 357.00 2.3400 2.5527 0.3800 0.2954 0.1444 0.1122<br />

III 134.86 236.00 2.1299 2.3729 0.1698 0.1156 0.0288 0.0196<br />

I 101.37 183.00 2.0059 2.2625 0.0458 0.0051 0.0021 0.0002<br />

SEPT II 73.70 127.00 1.8675 2.1038 -0.0926 -0.1535 0.0086 0.0142<br />

III 44.74 80.00 1.6507 1.9031 -0.3094 -0.3542 0.0957 0.1096<br />

I 146.32 262.00 2.1653 2.4183 0.2052 0.1610 0.0421 0.0330<br />

1976 AUG II 127.47 233.00 2.1054 2.3674 0.1453 0.1100 0.0211 0.0160<br />

III 98.12 184.00 1.9918 2.2648 0.0317 0.0075 0.0010 0.0002<br />

I 84.73 156.00 1.9280 2.1931 -0.0320 -0.0642 0.0010 0.0021<br />

SEPT II 54.96 84.00 1.7400 1.9243 -0.2200 -0.3330 0.0484 0.0733<br />

III 44.35 69.00 1.6469 1.8388 -0.3132 -0.4185 0.0981 0.1310<br />

I 181.88 349.00 2.2598 2.5428 0.2997 0.2855 0.0898 0.0856<br />

1977 AUG II 119 249.00 2.0755 2.3962 0.1155 0.1389 0.0133 0.0160<br />

III 109.56 221.00 2.0397 2.3444 0.0796 0.0871 0.0063 0.0069<br />

I 92.03 189.00 1.9639 2.2765 0.0039 0.0192 0.0000 0.0001<br />

SEPT II 61.94 109.00 1.7920 2.0374 -0.1681 -0.2199 0.0283 0.0370<br />

III 43.63 71.00 1.6398 1.8513 -0.3203 -0.4061 0.1026 0.1300<br />

I 182.35 368.00 2.2609 2.5658 0.3008 0.3085 0.0905 0.0928<br />

1978 AUG II 146.17 289.00 2.1649 2.4609 0.2048 0.2036 0.0419 0.0417<br />

III 119.00 259.00 2.0755 2.4133 0.1155 0.1560 0.0133 0.0180<br />

I 60.00 126.00 1.7782 2.1004 -0.1819 -0.1569 0.0331 0.0285<br />

SEPT II 37.98 105.00 1.5796 2.0212 -0.3805 -0.2361 0.1448 0.0898<br />

III 53.28 83.00 1.7266 1.9191 -0.2335 -0.3382 0.0545 0.0790<br />

I 188.89 386.00 2.2762 2.5866 0.3161 0.3293 0.0999 0.1041<br />

1979 AUG II 156.29 322.00 2.1939 2.5079 0.2339 0.2505 0.0547 0.0586<br />

III 99.16 236.00 1.9963 2.3729 0.0363 0.1156 0.0013 0.0042<br />

I 98.36 213.00 1.9928 2.3284 0.0328 0.0711 0.0011 0.0023<br />

SEPT II 52.16 112.00 1.7173 2.0492 -0.2427 -0.2081 0.0589 0.0505<br />

III 23.60 51.00 1.3729 1.7076 -0.5872 -0.5497 0.3447 0.3228<br />

I 176.94 339.00 2.2478 2.5302 0.2878 0.2729 0.0828 0.0785<br />

1980 AUG II 95.18 223.00 1.9785 2.3483 0.0185 0.0910 0.0003 0.0017<br />

III 105.30 251.00 2.0224 2.3997 0.0624 0.1424 0.0039 0.0089<br />

I 68.52 157.00 1.8358 2.1959 -0.1242 -0.0614 0.0154 0.0076<br />

SEPT II 45.10 99.00 1.6542 1.9956 -0.3059 -0.2617 0.0936 0.0800<br />

III 30.36 69.00 1.4823 1.8388 -0.4778 -0.4185 0.2283 0.1999<br />

I 163.37 324.00 2.2132 2.5105 0.2531 0.2532 0.0641 0.0641<br />

1981 AUG II 145.32 296.00 2.1623 2.4713 0.2023 0.2140 0.0409 0.0433<br />

III 87.76 216.00 1.9433 2.3345 -0.0168 0.0771 0.0003 -0.0013<br />

I 81.66 169.00 1.9120 2.2279 -0.0481 -0.0294 0.0023 0.0014<br />

SEPT II 47.39 94.00 1.6757 1.9731 -0.2844 -0.2842 0.0809 0.0808<br />

III 39.77 86.00 1.5996 1.9345 -0.3605 -0.3228 0.1300 0.1164<br />

I 199.82 379.00 2.3006 2.5786 0.3406 0.3213 0.1160 0.1094<br />

1982 AUG II 151.72 335.00 2.1810 2.5250 0.2210 0.2677 0.0488 0.0592<br />

III 97.35 247.00 1.9883 2.3927 0.0283 0.1354 0.0008 0.0038<br />

I 88.49 163.00 1.9469 2.2122 -0.0132 -0.0451 0.0002 0.0006<br />

SEPT II 68.20 151.00 1.8338 2.1790 -0.1263 -0.0783 0.0159 0.0099<br />

III 37.19 115.00 1.5704 2.0607 -0.3896 -0.1966 0.1518 0.0766<br />

I 246.85 397.00 2.3924 2.5988 0.4324 0.3415 0.1869 0.1476<br />

1983 AUG II 188.24 358.00 2.2747 2.5539 0.3146 0.2966 0.0990 0.0933<br />

III 185.17 354.00 2.2676 2.5490 0.3075 0.2917 0.0946 0.0897<br />

I 149.26 288.00 2.1739 2.4594 0.2139 0.2021 0.0457 0.0432<br />

SEPT II 97.29 202.00 1.9881 2.3054 0.0280 0.0480 0.0008 0.0013<br />

III 53.98 108.00 1.7322 2.0334 -0.2278 -0.2239 0.0519 0.0510<br />

G.TOTAL 117.60 135.44 0.00 0.00 3.52 3.37<br />

NO. OF PERIOD 60 LOG x' LOG y'<br />

AVERAGE 1.9601 2.2573<br />

Co-efficient <strong>of</strong> Corelation<br />

b = SIGMA X*Y = 0.9583<br />

SIGMA X^2<br />

Table-5.3(2)


Table-5.3(3)<br />

REGRESSION ANALYSIS BETWEEN DISCHARGES OF TANDI AND GHOUSAL ( NON-MONSOON PERIOD)<br />

TANDI GHOUSAL DEVIATION FROM MEAN<br />

D/SITE D/SITE X Y X^2 X*Y<br />

YEAR MONTH Qx Qy LOG x LOG y LOGx-LOGX' LOGy-LOGy'<br />

(Cumecs) (Cumecs)<br />

I 24.62 35.00 1.3913 1.5441 0.2877 0.1687 0.0828 0.0485<br />

1974-75 OCT II 21.58 27.00 1.3341 1.4314 0.2305 0.0560 0.0531 0.0129<br />

III 17.31 22.00 1.2383 1.3424 0.1347 -0.0329 0.0181 -0.0044<br />

I 14.92 18.00 1.1738 1.2553 0.0702 -0.1201 0.0049 -0.0084<br />

NOV II 18.83 17.00 1.2749 1.2304 0.1713 -0.1449 0.0293 -0.0248<br />

III 11.45 16.00 1.0588 1.2041 -0.0448 -0.1712 0.0020 0.0077<br />

I 10.69 15.00 1.0290 1.1761 -0.0746 -0.1992 0.0056 0.0149<br />

DEC II 10.43 13.00 1.0183 1.1139 -0.0853 -0.2614 0.0073 0.0223<br />

III 10.42 14.00 1.0179 1.1461 -0.0857 -0.2292 0.0073 0.0196<br />

I 8.38 14.00 0.9232 1.1461 -0.1803 -0.2292 0.0325 0.0413<br />

JAN II 8.07 14.00 0.9069 1.1461 -0.1967 -0.2292 0.0387 0.0451<br />

III 7.60 12.00 0.8808 1.0792 -0.2228 -0.2961 0.0496 0.0660<br />

I 8.19 14.00 0.9133 1.1461 -0.1903 -0.2292 0.0362 0.0436<br />

FEB II 7.59 14.00 0.8802 1.1461 -0.2233 -0.2292 0.0499 0.0512<br />

III 9.12 14.00 0.9600 1.1461 -0.1436 -0.2292 0.0206 0.0329<br />

I 7.30 11.00 0.8633 1.0414 -0.2403 -0.3339 0.0577 0.0802<br />

MAR II 6.43 12.00 0.8082 1.0792 -0.2954 -0.2961 0.0872 0.0875<br />

III 7.26 16.00 0.8609 1.2041 -0.2427 -0.1712 0.0589 0.0415<br />

I 8.42 18.00 0.9253 1.2553 -0.1783 -0.1201 0.0318 0.0214<br />

APR II 10.38 25.00 1.0162 1.3979 -0.0874 0.0226 0.0076 -0.0020<br />

III 13.70 35.00 1.1367 1.5441 0.0331 0.1687 0.0011 0.0056<br />

I 23.16 51.00 1.3647 1.7076 0.2612 0.3322 0.0682 0.0868<br />

MAY II 47.15 111.00 1.6735 2.0453 0.5699 0.6700 0.3248 0.3818<br />

III 62.11 143.00 1.7932 2.1553 0.6896 0.7800 0.4755 0.5379<br />

I 36.47 61.00 1.5619 1.7853 0.4583 0.4100 0.2101 0.1879<br />

1975-76 OCT II 30.99 51.00 1.4912 1.7076 0.3876 0.3322 0.1503 0.1288<br />

III 21.50 33.00 1.3324 1.5185 0.2289 0.1432 0.0524 0.0328<br />

I 16.53 23.00 1.2183 1.3617 0.1147 -0.0136 0.0132 -0.0016<br />

NOV II 14.42 20.00 1.1590 1.3010 0.0554 -0.0743 0.0031 -0.0041<br />

III 13.23 18.00 1.1216 1.2553 0.0180 -0.1201 0.0003 -0.0022<br />

I 13.32 16.00 1.1245 1.2041 0.0209 -0.1712 0.0004 -0.0036<br />

DEC II 12.02 14.00 1.0799 1.1461 -0.0237 -0.2292 0.0006 0.0054<br />

III 11.75 13.00 1.0700 1.1139 -0.0336 -0.2614 0.0011 0.0088<br />

I 12.16 12.00 1.0849 1.0792 -0.0187 -0.2961 0.0003 0.0055<br />

JAN II 11.46 12.00 1.0592 1.0792 -0.0444 -0.2961 0.0020 0.0131<br />

III 10.84 11.00 1.0350 1.0414 -0.0686 -0.3339 0.0047 0.0229<br />

I 10.41 12.00 1.0175 1.0792 -0.0861 -0.2961 0.0074 0.0255<br />

FEB II 10.21 8.00 1.0090 0.9031 -0.0946 -0.4722 0.0089 0.0447<br />

III 10.03 10.00 1.0013 1.0000 -0.1023 -0.3753 0.0105 0.0384<br />

I 10.49 12.00 1.0208 1.0792 -0.0828 -0.2961 0.0069 0.0245<br />

MAR II 10.10 11.00 1.0043 1.0414 -0.0993 -0.3339 0.0099 0.0331<br />

III 10.13 10.00 1.0056 1.0000 -0.0980 -0.3753 0.0096 0.0368<br />

I 10.08 10.00 1.0035 1.0000 -0.1001 -0.3753 0.0100 0.0376<br />

APR II 10.91 16.00 1.0378 1.2041 -0.0658 -0.1712 0.0043 0.0113<br />

III 20.08 40.00 1.3028 1.6021 0.1992 0.2267 0.0397 0.0452<br />

I 26.13 57.00 1.4171 1.7559 0.3136 0.3805 0.0983 0.1193<br />

MAY II 39.74 88.00 1.5992 1.9445 0.4956 0.5692 0.2457 0.2821<br />

III 62.72 122.00 1.7974 2.0864 0.6938 0.7110 0.4814 0.4933<br />

I 31.29 49.00 1.4954 1.6902 0.3918 0.3149 0.1535 0.1234<br />

1976-77 OCT II 20.19 31.00 1.3051 1.4914 0.2015 0.1160 0.0406 0.0234<br />

III 16.71 23.00 1.2230 1.3617 0.1194 -0.0136 0.0143 -0.0016<br />

I 14.45 21.00 1.1599 1.3222 0.0563 -0.0531 0.0032 -0.0030<br />

NOV II 13.17 19.00 1.1196 1.2788 0.0160 -0.0966 0.0003 -0.0015<br />

III 11.95 17.00 1.0774 1.2304 -0.0262 -0.1449 0.0007 0.0038<br />

I 10.40 16.00 1.0170 1.2041 -0.0866 -0.1712 0.0075 0.0148<br />

DEC II 9.24 14.00 0.9657 1.1461 -0.1379 -0.2292 0.0190 0.0316<br />

III 8.93 13.00 0.9509 1.1139 -0.1527 -0.2614 0.0233 0.0399<br />

I 8.07 12.00 0.9069 1.0792 -0.1967 -0.2961 0.0387 0.0583<br />

JAN II 7.97 11.00 0.9015 1.0414 -0.2021 -0.3339 0.0409 0.0675<br />

III 7.18 9.00 0.8561 0.9542 -0.2475 -0.4211 0.0612 0.1042<br />

I 9.47 13.00 0.9763 1.1139 -0.1272 -0.2614 0.0162 0.0333<br />

FEB II 7.22 12.00 0.8585 1.0792 -0.2451 -0.2961 0.0600 0.0726<br />

III 7.26 12.00 0.8609 1.0792 -0.2427 -0.2961 0.0589 0.0719<br />

I 7.12 12.00 0.8525 1.0792 -0.2511 -0.2961 0.0631 0.0744<br />

MAR II 7.33 12.00 0.8651 1.0792 -0.2385 -0.2961 0.0569 0.0706<br />

III 9.05 17.00 0.9566 1.2304 -0.1469 -0.1449 0.0216 0.0213<br />

I 9.91 20.00 0.9961 1.3010 -0.1075 -0.0743 0.0116 0.0080<br />

APR II 9.31 19.00 0.9689 1.2788 -0.1346 -0.0966 0.0181 0.0130<br />

III 10.28 24.00 1.0120 1.3802 -0.0916 0.0049 0.0084 -0.0004<br />

I 11.33 24.00 1.0542 1.3802 -0.0494 0.0049 0.0024 -0.0002<br />

MAY II 15.18 36.00 1.1813 1.5563 0.0777 0.1810 0.0060 0.0141<br />

III 36.42 88.00 1.5613 1.9445 0.4578 0.5692 0.2095 0.2605<br />

I 30.11 50.00 1.4787 1.6990 0.3751 0.3236 0.1407 0.1214<br />

1977-78 OCT II 23.55 34.00 1.3720 1.5315 0.2684 0.1562 0.0720 0.0419


Table-5.3(4)<br />

TANDI GHOUSAL DEVIATION FROM MEAN<br />

D/SITE D/SITE X Y X^2 X*Y<br />

YEAR MONTH Qx Qy LOG x LOG y LOGx-LOGX' LOGy-LOGy'<br />

(Cumecs) (Cumecs)<br />

III 18.45 29.00 1.2660 1.4624 0.1624 0.0871 0.0264 0.0141<br />

I 15.74 26.00 1.1970 1.4150 0.0934 0.0396 0.0087 0.0037<br />

NOV II 14.3 22.00 1.1553 1.3424 0.0517 -0.0329 0.0027 -0.0017<br />

III 13.85 21.00 1.1414 1.3222 0.0379 -0.0531 0.0014 -0.0020<br />

I 12.17 20.00 1.0853 1.3010 -0.0183 -0.0743 0.0003 0.0014<br />

DEC II 10.86 17.00 1.0358 1.2304 -0.0678 -0.1449 0.0046 0.0098<br />

III 10.35 15.00 1.0149 1.1761 -0.0886 -0.1992 0.0079 0.0177<br />

I 9.94 13.00 0.9974 1.1139 -0.1062 -0.2614 0.0113 0.0278<br />

JAN II 11.57 15.00 1.0633 1.1761 -0.0403 -0.1992 0.0016 0.0080<br />

III 10.35 14.00 1.0149 1.1461 -0.0886 -0.2292 0.0079 0.0203<br />

I 9.16 13.00 0.9619 1.1139 -0.1417 -0.2614 0.0201 0.0370<br />

FEB II 10.57 12.00 1.0241 1.0792 -0.0795 -0.2961 0.0063 0.0235<br />

III 9.02 18.00 0.9552 1.2553 -0.1484 -0.1201 0.0220 0.0178<br />

I 8.6 12.00 0.9345 1.0792 -0.1691 -0.2961 0.0286 0.0501<br />

MAR II 8.1 12.00 0.9085 1.0792 -0.1951 -0.2961 0.0381 0.0578<br />

III 8.41 15.00 0.9248 1.1761 -0.1788 -0.1992 0.0320 0.0356<br />

I 9.1 16.00 0.9590 1.2041 -0.1445 -0.1712 0.0209 0.0247<br />

APR II 14.41 26.00 1.1587 1.4150 0.0551 0.0396 0.0030 0.0022<br />

III 19.48 33.00 1.2896 1.5185 0.1860 0.1432 0.0346 0.0266<br />

I 44.66 102.00 1.6499 2.0086 0.5463 0.6333 0.2985 0.3460<br />

MAY II 70.87 159.00 1.8505 2.2014 0.7469 0.8261 0.5578 0.6170<br />

III 86.93 181.00 1.9392 2.2577 0.8356 0.8824 0.6982 0.7373<br />

I 24.94 56.00 1.3969 1.7482 0.2933 0.3729 0.0860 0.1094<br />

1978-79 OCT II 17.61 44.00 1.2458 1.6435 0.1422 0.2681 0.0202 0.0381<br />

III 21.49 38.00 1.3322 1.5798 0.2286 0.2045 0.0523 0.0467<br />

I 12.26 28.00 1.0885 1.4472 -0.0151 0.0718 0.0002 -0.0011<br />

NOV II 10.70 25.00 1.0294 1.3979 -0.0742 0.0226 0.0055 -0.0017<br />

III 11.17 25.00 1.0481 1.3979 -0.0555 0.0226 0.0031 -0.0013<br />

I 10.02 23.00 1.0009 1.3617 -0.1027 -0.0136 0.0106 0.0014<br />

DEC II 9.29 22.00 0.9680 1.3424 -0.1356 -0.0329 0.0184 0.0045<br />

III 9.17 22.00 0.9624 1.3424 -0.1412 -0.0329 0.0199 0.0046<br />

I 8.52 22.00 0.9304 1.3424 -0.1731 -0.0329 0.0300 0.0057<br />

JAN II 7.92 19.00 0.8987 1.2788 -0.2049 -0.0966 0.0420 0.0198<br />

III 8.07 18.00 0.9069 1.2553 -0.1967 -0.1201 0.0387 0.0236<br />

I 7.86 20.00 0.8954 1.3010 -0.2082 -0.0743 0.0433 0.0155<br />

FEB II 7.12 18.00 0.8525 1.2553 -0.2511 -0.1201 0.0631 0.0301<br />

III 9.41 16.00 0.9736 1.2041 -0.1300 -0.1712 0.0169 0.0223<br />

I 8.35 17.00 0.9217 1.2304 -0.1819 -0.1449 0.0331 0.0264<br />

MAR II 18.35 22.00 1.2636 1.3424 0.1600 -0.0329 0.0256 -0.0053<br />

III 28.50 28.00 1.4548 1.4472 0.3513 0.0718 0.1234 0.0252<br />

I 20.00 31.00 1.3010 1.4914 0.1974 0.1160 0.0390 0.0229<br />

APR II 16.00 38.00 1.2041 1.5798 0.1005 0.2045 0.0101 0.0206<br />

III 25.02 63.00 1.3983 1.7993 0.2947 0.4240 0.0868 0.1250<br />

I 30.02 88.00 1.4774 1.9445 0.3738 0.5692 0.1397 0.2128<br />

MAY II 25.58 77.00 1.4079 1.8865 0.3043 0.5112 0.0926 0.1556<br />

III 24.78 76.00 1.3941 1.8808 0.2905 0.5055 0.0844 0.1469<br />

I 20.72 48.00 1.3164 1.6812 0.2128 0.3059 0.0453 0.0651<br />

1979-80 OCT II 17.94 39.00 1.2538 1.5911 0.1502 0.2157 0.0226 0.0324<br />

III 14.83 34.00 1.1711 1.5315 0.0676 0.1562 0.0046 0.0105<br />

I 13.23 31.00 1.1216 1.4914 0.0180 0.1160 0.0003 0.0021<br />

NOV II 10.74 27.00 1.0310 1.4314 -0.0726 0.0560 0.0053 -0.0041<br />

III 10.24 26.00 1.0103 1.4150 -0.0933 0.0396 0.0087 -0.0037<br />

I 9.74 25.00 0.9886 1.3979 -0.1150 0.0226 0.0132 -0.0026<br />

DEC II 8.93 23.00 0.9509 1.3617 -0.1527 -0.0136 0.0233 0.0021<br />

III 8.86 23.00 0.9474 1.3617 -0.1562 -0.0136 0.0244 0.0021<br />

I 7.68 20.00 0.8854 1.3010 -0.2182 -0.0743 0.0476 0.0162<br />

JAN II 7.76 19.00 0.8899 1.2788 -0.2137 -0.0966 0.0457 0.0206<br />

III 6.08 18.00 0.7839 1.2553 -0.3197 -0.1201 0.1022 0.0384<br />

I 6.54 23.00 0.8156 1.3617 -0.2880 -0.0136 0.0829 0.0039<br />

FEB II 6.83 20.00 0.8344 1.3010 -0.2692 -0.0743 0.0725 0.0200<br />

III 6.79 22.00 0.8319 1.3424 -0.2717 -0.0329 0.0738 0.0089<br />

I 5.5 20.00 0.7404 1.3010 -0.3632 -0.0743 0.1319 0.0270<br />

MAR II 5.55 22.00 0.7443 1.3424 -0.3593 -0.0329 0.1291 0.0118<br />

III 6.63 24.00 0.8215 1.3802 -0.2821 0.0049 0.0796 -0.0014<br />

I 7.9 26.00 0.8976 1.4150 -0.2060 0.0396 0.0424 -0.0082<br />

APR II 9.03 29.00 0.9557 1.4624 -0.1479 0.0871 0.0219 -0.0129<br />

III 10.98 32.00 1.0406 1.5051 -0.0630 0.1298 0.0040 -0.0082<br />

I 25.76 66.00 1.4109 1.8195 0.3074 0.4442 0.0945 0.1365<br />

MAY II 33.09 90.00 1.5197 1.9542 0.4161 0.5789 0.1731 0.2409<br />

III 55.23 122.00 1.7422 2.0864 0.6386 0.7110 0.4078 0.4541


Table-5.3(5)<br />

TANDI GHOUSAL DEVIATION FROM MEAN<br />

D/SITE D/SITE X Y X^2 X*Y<br />

YEAR MONTH Qx Qy LOG x LOG y LOGx-LOGX' LOGy-LOGy'<br />

(Cumecs) (Cumecs)<br />

I 30.26 54.00 1.4809 1.7324 0.3773 0.3571 0.1423 0.1347<br />

1980-81 OCT II 21.63 35.00 1.3351 1.5441 0.2315 0.1687 0.0536 0.0391<br />

III 17.26 28.00 1.2370 1.4472 0.1335 0.0718 0.0178 0.0096<br />

I 12.35 21.00 1.0917 1.3222 -0.0119 -0.0531 0.0001 0.0006<br />

NOV II 9.02 20.00 0.9552 1.3010 -0.1484 -0.0743 0.0220 0.0110<br />

III 8.62 20.00 0.9355 1.3010 -0.1681 -0.0743 0.0283 0.0125<br />

I 8.16 18.00 0.9117 1.2553 -0.1919 -0.1201 0.0368 0.0230<br />

DEC II 7.82 17.00 0.8932 1.2304 -0.2104 -0.1449 0.0443 0.0305<br />

III 7.64 16.00 0.8831 1.2041 -0.2205 -0.1712 0.0486 0.0378<br />

I 7.71 17.00 0.8871 1.2304 -0.2165 -0.1449 0.0469 0.0314<br />

JAN II 7.35 16.00 0.8663 1.2041 -0.2373 -0.1712 0.0563 0.0406<br />

III 7.36 15.00 0.8669 1.1761 -0.2367 -0.1992 0.0560 0.0472<br />

I 7.46 15.00 0.8727 1.1761 -0.2308 -0.1992 0.0533 0.0460<br />

FEB II 7.07 16.00 0.8494 1.2041 -0.2542 -0.1712 0.0646 0.0435<br />

III 6.76 18.00 0.8299 1.2553 -0.2736 -0.1201 0.0749 0.0329<br />

I 6.76 17.00 0.8299 1.2304 -0.2736 -0.1449 0.0749 0.0396<br />

MAR II 6.60 17.00 0.8195 1.2304 -0.2840 -0.1449 0.0807 0.0412<br />

III 6.80 18.00 0.8325 1.2553 -0.2711 -0.1201 0.0735 0.0325<br />

I 7.44 19.00 0.8716 1.2788 -0.2320 -0.0966 0.0538 0.0224<br />

APR II 9.34 26.00 0.9703 1.4150 -0.1332 0.0396 0.0178 -0.0053<br />

III 33.52 37.00 1.5253 1.5682 0.4217 0.1929 0.1778 0.0813<br />

I 70.93 131.00 1.8508 2.1173 0.7472 0.7419 0.5584 0.5544<br />

MAY II 77.63 166.00 1.8900 2.2201 0.7864 0.8448 0.6185 0.6644<br />

III 92.76 195.00 1.9674 2.2900 0.8638 0.9147 0.7461 0.7901<br />

I 15.05 47.00 1.1775 1.6721 0.0739 0.2968 0.0055 0.0219<br />

1981-82 OCT II 12.80 39.00 1.1072 1.5911 0.0036 0.2157 0.0000 0.0008<br />

III 12.24 25.00 1.0878 1.3979 -0.0158 0.0226 0.0002 -0.0004<br />

I 10.72 23.00 1.0302 1.3617 -0.0734 -0.0136 0.0054 0.0010<br />

NOV II 8.67 20.00 0.9380 1.3010 -0.1656 -0.0743 0.0274 0.0123<br />

III 7.31 18.00 0.8639 1.2553 -0.2397 -0.1201 0.0574 0.0288<br />

I 6.42 17.00 0.8075 1.2304 -0.2961 -0.1449 0.0876 0.0429<br />

DEC II 5.94 15.00 0.7738 1.1761 -0.3298 -0.1992 0.1088 0.0657<br />

III 5.72 14.00 0.7574 1.1461 -0.3462 -0.2292 0.1198 0.0793<br />

I 8.34 14.00 0.9212 1.1461 -0.1824 -0.2292 0.0333 0.0418<br />

JAN II 8.20 14.00 0.9138 1.1461 -0.1898 -0.2292 0.0360 0.0435<br />

III 9.41 12.00 0.9736 1.0792 -0.1300 -0.2961 0.0169 0.0385<br />

I 9.32 13.00 0.9694 1.1139 -0.1342 -0.2614 0.0180 0.0351<br />

FEB II 8.70 14.00 0.9395 1.1461 -0.1641 -0.2292 0.0269 0.0376<br />

III 8.76 13.00 0.9425 1.1139 -0.1611 -0.2614 0.0259 0.0421<br />

I 8.37 15.00 0.9227 1.1761 -0.1809 -0.1992 0.0327 0.0360<br />

MAR II 7.92 15.00 0.8987 1.1761 -0.2049 -0.1992 0.0420 0.0408<br />

III 8.09 14.00 0.9079 1.1461 -0.1956 -0.2292 0.0383 0.0448<br />

I 8.50 16.00 0.9294 1.2041 -0.1742 -0.1712 0.0303 0.0298<br />

APR II 9.13 17.00 0.9605 1.2304 -0.1431 -0.1449 0.0205 0.0207<br />

III 11.40 25.00 1.0569 1.3979 -0.0467 0.0226 0.0022 -0.0011<br />

I 21.96 49.00 1.3416 1.6902 0.2380 0.3149 0.0567 0.0750<br />

MAY II 20.11 44.00 1.3034 1.6435 0.1998 0.2681 0.0399 0.0536<br />

III 30.79 76.00 1.4884 1.8808 0.3848 0.5055 0.1481 0.1945<br />

I 20.84 80.00 1.3189 1.9031 0.2153 0.5278 0.0464 0.1136<br />

1982-83 OCT II 18.58 70.00 1.2690 1.8451 0.1655 0.4698 0.0274 0.0777<br />

III 16.79 39.00 1.2251 1.5911 0.1215 0.2157 0.0148 0.0262<br />

I 15.31 26.00 1.1850 1.4150 0.0814 0.0396 0.0066 0.0032<br />

NOV II 13.77 25.00 1.1389 1.3979 0.0353 0.0226 0.0012 0.0008<br />

III 12.27 22.00 1.0888 1.3424 -0.0147 -0.0329 0.0002 0.0005<br />

I 11.40 18.00 1.0569 1.2553 -0.0467 -0.1201 0.0022 0.0056<br />

DEC II 10.54 15.00 1.0228 1.1761 -0.0807 -0.1992 0.0065 0.0161<br />

III 12.22 14.00 1.0871 1.1461 -0.0165 -0.2292 0.0003 0.0038<br />

I 7.36 15.00 0.8667 1.1761 -0.2369 -0.1992 0.0561 0.0472<br />

JAN II 7.40 15.00 0.8692 1.1761 -0.2344 -0.1992 0.0549 0.0467<br />

III 7.62 15.00 0.8820 1.1761 -0.2216 -0.1992 0.0491 0.0442<br />

I 7.39 14.00 0.8686 1.1461 -0.2349 -0.2292 0.0552 0.0538<br />

FEB II 7.20 14.00 0.8573 1.1461 -0.2463 -0.2292 0.0606 0.0564<br />

III 7.45 14.00 0.8722 1.1461 -0.2314 -0.2292 0.0536 0.0530<br />

I 11.99 18.00 1.0788 1.2553 -0.0248 -0.1201 0.0006 0.0030<br />

MAR II 12.42 20.00 1.0941 1.3010 -0.0095 -0.0743 0.0001 0.0007<br />

III 11.44 18.00 1.0584 1.2553 -0.0452 -0.1201 0.0020 0.0054<br />

I 11.41 18.00 1.0573 1.2553 -0.0463 -0.1201 0.0021 0.0056<br />

APR II 10.28 18.00 1.0120 1.2553 -0.0916 -0.1201 0.0084 0.0110<br />

III 12.42 21.00 1.0941 1.3222 -0.0095 -0.0531 0.0001 0.0005<br />

I 20.45 37.00 1.3107 1.5682 0.2071 0.1929 0.0429 0.0399<br />

MAY II 35.11 56.00 1.5454 1.7482 0.4418 0.3729 0.1952 0.1647<br />

III 56.24 83.00 1.7500 1.9191 0.6465 0.5438 0.4179 0.3515


Table-5.3(6)<br />

TANDI GHOUSAL DEVIATION FROM MEAN<br />

D/SITE D/SITE X Y X^2 X*Y<br />

YEAR MONTH Qx Qy LOG x LOG y LOGx-LOGX' LOGy-LOGy'<br />

(Cumecs) (Cumecs)<br />

1983-84 I 45.51 76.00 1.6581 1.8808 0.5545 0.5055 0.3075 0.2803<br />

OCT II 27.07 51.00 1.4325 1.7076 0.3289 0.3322 0.1082 0.1093<br />

III 17.04 33.00 1.2315 1.5185 0.1279 0.1432 0.0164 0.0183<br />

I 12.42 27.00 1.0941 1.4314 -0.0095 0.0560 0.0001 -0.0005<br />

NOV II 11.67 25.00 1.0671 1.3979 -0.0365 0.0226 0.0013 -0.0008<br />

III 11.10 23.00 1.0453 1.3617 -0.0583 -0.0136 0.0034 0.0008<br />

I 10.40 20.00 1.0168 1.3010 -0.0868 -0.0743 0.0075 0.0064<br />

DEC II 9.55 19.00 0.9801 1.2788 -0.1234 -0.0966 0.0152 0.0119<br />

III 3.42 18.00 0.5340 1.2553 -0.5696 -0.1201 0.3244 0.0684<br />

I 11.03 19.00 1.0426 1.2788 -0.0610 -0.0966 0.0037 0.0059<br />

JAN II 10.59 19.00 1.0249 1.2788 -0.0787 -0.0966 0.0062 0.0076<br />

III 10.06 18.00 1.0026 1.2553 -0.1010 -0.1201 0.0102 0.0121<br />

I 9.62 17.00 0.9829 1.2304 -0.1206 -0.1449 0.0146 0.0175<br />

FEB II 9.07 17.00 0.9576 1.2304 -0.1460 -0.1449 0.0213 0.0211<br />

III 8.73 16.00 0.9410 1.2041 -0.1626 -0.1712 0.0264 0.0278<br />

I 9.65 16.00 0.9845 1.2041 -0.1191 -0.1712 0.0142 0.0204<br />

MAR II 11.19 18.00 1.0488 1.2553 -0.0548 -0.1201 0.0030 0.0066<br />

III 11.48 19.00 1.0599 1.2788 -0.0436 -0.0966 0.0019 0.0042<br />

I 11.91 20.00 1.0759 1.3010 -0.0277 -0.0743 0.0008 0.0021<br />

APR II 10.85 20.00 1.0354 1.3010 -0.0682 -0.0743 0.0046 0.0051<br />

III 15.00 26.00 1.1761 1.4150 0.0725 0.0396 0.0053 0.0029<br />

I 28.03 45.00 1.4476 1.6532 0.3440 0.2779 0.1184 0.0956<br />

MAY II 33.90 74.00 1.5302 1.8692 0.4266 0.4939 0.1820 0.2107<br />

III 72.58 125.00 1.8608 2.0969 0.7572 0.7216 0.5734 0.5464<br />

G.TOTAL 264.86 330.08 0.00 0.00 15.65 14.99<br />

NO. OF PERIOD 240 LOG x' LOG y'<br />

AVERAGE<br />

Co-efficient <strong>of</strong> Corelation<br />

1.1036 1.3753<br />

b = SIGMA X*Y = 0.9580<br />

SIGMA X^2


REGRESSION ANALYSIS BETWEEN DISCHARGES OF TANDI PLUS GHOUSAL AND UDAIPUR JUNE- JULY<br />

UDAIPUR TDI.+GSL DEVIATION FROM MEAN<br />

D/SITE D/SITE X Y X^2 X*Y<br />

YEAR MONTH Qx Qy LOG x LOG y LOGx-LOGX' LOGy-LOGy'<br />

(Cumecs) (Cumecs)<br />

I 195.00 152.28 2.2900 2.1826 -0.4193 -0.3874 0.1758 0.1625<br />

1974 JUN II 318.00 248.59 2.5024 2.3955 -0.2069 -0.1746 0.0428 0.0361<br />

III 203.00 167.44 2.3075 2.2239 -0.4018 -0.3462 0.1615 0.1391<br />

I 299.00 246.61 2.4757 2.3920 -0.2337 -0.1781 0.0546 0.0416<br />

JUL II 636.00 452.53 2.8035 2.6556 0.0941 0.0856 0.0089 0.0081<br />

III 504.00 374.12 2.7024 2.5730 -0.0069 0.0029 0.0000 0.0000<br />

I 361.00 282.44 2.5575 2.4509 -0.1518 -0.1192 0.0231 0.0181<br />

1975 JUN II 558.00 398.51 2.7466 2.6004 0.0373 0.0304 0.0014 0.0011<br />

III 651.00 468.02 2.8136 2.6703 0.1042 0.1002 0.0109 0.0104<br />

I 513.00 360.00 2.7101 2.5563 0.0008 -0.0138 0.0000 0.0000<br />

JUL II 887.00 613.91 2.9479 2.7881 0.2386 0.2180 0.0569 0.0520<br />

III 618.00 429.52 2.7910 2.6330 0.0816 0.0629 0.0067 0.0051<br />

I 477.00 317.18 2.6785 2.5013 -0.0308 -0.0688 0.0010 0.0021<br />

1976 JUN II 351.00 247.79 2.5453 2.3941 -0.1640 -0.1760 0.0269 0.0289<br />

III 287.00 202.81 2.4579 2.3071 -0.2515 -0.2630 0.0632 0.0661<br />

I 574.00 415.59 2.7589 2.6187 0.0496 0.0486 0.0025 0.0024<br />

JUL II 721.00 560.80 2.8579 2.7488 0.1486 0.1787 0.0221 0.0266<br />

III 755.00 580.87 2.8779 2.7641 0.1686 0.1940 0.0284 0.0327<br />

I 258.00 196.59 2.4116 2.2936 -0.2977 -0.2765 0.0886 0.0823<br />

1977 JUN II 184.00 141.04 2.2648 2.1493 -0.4445 -0.4207 0.1976 0.1870<br />

III 633.00 436.71 2.8014 2.6402 0.0921 0.0701 0.0085 0.0065<br />

I 828.00 579.09 2.9180 2.7627 0.2087 0.1927 0.0435 0.0402<br />

JUL II 754.00 532.87 2.8774 2.7266 0.1680 0.1565 0.0282 0.0263<br />

III 601.00 450.26 2.7789 2.6535 0.0695 0.0834 0.0048 0.0058<br />

I 456.00 353.06 2.6590 2.5478 -0.0504 -0.0222 0.0025 0.0011<br />

1978 JUN II 424.00 312.95 2.6274 2.4955 -0.0820 -0.0746 0.0067 0.0061<br />

III 845.00 640.03 2.9269 2.8062 0.2175 0.2361 0.0473 0.0514<br />

I 904.00 647.43 2.9562 2.8112 0.2468 0.2411 0.0609 0.0595<br />

JUL II 700.00 540.15 2.8451 2.7325 0.1358 0.1624 0.0184 0.0221<br />

III 700.00 536.99 2.8451 2.7300 0.1358 0.1599 0.0184 0.0217<br />

I 197.00 141.70 2.2945 2.1514 -0.4149 -0.4187 0.1721 0.1737<br />

1979 JUN II 401.00 295.39 2.6031 2.4704 -0.1062 -0.0997 0.0113 0.0106<br />

III 806.00 597.47 2.9063 2.7763 0.1970 0.2062 0.0388 0.0406<br />

I 736.00 541.98 2.8669 2.7340 0.1575 0.1639 0.0248 0.0258<br />

JUL II 927.00 660.97 2.9671 2.8202 0.2577 0.2501 0.0664 0.0645<br />

III 698.00 519.08 2.8439 2.7152 0.1345 0.1451 0.0181 0.0195<br />

I 395.00 301.89 2.5966 2.4798 -0.1127 -0.0902 0.0127 0.0102<br />

1980 JUN II 481.00 356.45 2.6821 2.5520 -0.0272 -0.0181 0.0007 0.0005<br />

III 696.00 507.78 2.8426 2.7057 0.1333 0.1356 0.0178 0.0181<br />

I 731.00 536.27 2.8639 2.7294 0.1546 0.1593 0.0239 0.0246<br />

JUL II 762.00 524.29 2.8820 2.7196 0.1726 0.1495 0.0298 0.0258<br />

III 635.00 474.10 2.8028 2.6759 0.0934 0.1058 0.0087 0.0099<br />

I 292.00 221.07 2.4654 2.3445 -0.2440 -0.2256 0.0595 0.0550<br />

1981 JUN II 311.00 229.57 2.4928 2.3609 -0.2166 -0.2092 0.0469 0.0453<br />

III 738.00 501.01 2.8681 2.6998 0.1587 0.1298 0.0252 0.0206<br />

I 582.00 418.26 2.7649 2.6214 0.0556 0.0514 0.0031 0.0029<br />

JUL II 779.00 526.95 2.8915 2.7218 0.1822 0.1517 0.0332 0.0276<br />

III 818.00 572.92 2.9128 2.7581 0.2034 0.1880 0.0414 0.0382<br />

I 320.00 182.53 2.5051 2.2613 -0.2042 -0.3088 0.0417 0.0630<br />

1982 JUN II 537.00 332.83 2.7300 2.5222 0.0206 -0.0479 0.0004 -0.0010<br />

III 519.00 328.64 2.7152 2.5167 0.0058 -0.0534 0.0000 -0.0003<br />

I 582.00 439.48 2.7649 2.6429 0.0556 0.0729 0.0031 0.0040<br />

JUL II 705.00 464.71 2.8482 2.6672 0.1388 0.0971 0.0193 0.0135<br />

III 903.00 539.55 2.9557 2.7320 0.2463 0.1619 0.0607 0.0399<br />

I 264.00 204.20 2.4216 2.3101 -0.2877 -0.2600 0.0828 0.0748<br />

1983 JUN II 310.00 231.29 2.4914 2.3642 -0.2180 -0.2059 0.0475 0.0449<br />

III 555.00 327.14 2.7443 2.5147 0.0349 -0.0554 0.0012 -0.0019<br />

I 497.00 402.41 2.6964 2.6047 -0.0130 0.0346 0.0002 -0.0004<br />

JUL II 350.00 313.79 2.5441 2.4966 -0.1653 -0.0734 0.0273 0.0121<br />

III 725.00 538.52 2.8603 2.7312 0.1510 0.1611 0.0228 0.0243<br />

G.TOTAL 162.56 154.21 0.00 0.00 2.15 2.03<br />

NO. OF PERIOD 60 LOG x' LOG y'<br />

AVERAGE 2.7093 2.5701<br />

Co-efficient <strong>of</strong> Corelation<br />

b = SIGMA X*Y = 0.9422<br />

SIGMA X^2<br />

Table-5.4(1)


REGRESSION ANALYSIS BETWEEN DISCHARGES OF TANDI PLUS GHOUSAL AND UDAIPUR AUG.- SEPT<br />

UDAIPUR TDI.+GSL DEVIATION FROM MEAN<br />

D/SITE D/SITE X Y X^2 X*Y<br />

YEAR MONTH Qx Qy LOG x LOG y LOGx-LOGX' LOGy-LOGy'<br />

(Cumecs) (Cumecs)<br />

I 524.00 402.96 2.7193 2.6053 0.1394 0.1697 0.0194 0.0237<br />

1974 AUG II 430.00 330.22 2.6335 2.5188 0.0535 0.0832 0.0029 0.0045<br />

III 417.00 311.99 2.6201 2.4941 0.0402 0.0586 0.0016 0.0024<br />

I 293.00 211.23 2.4669 2.3248 -0.1131 -0.1108 0.0128 0.0125<br />

SEPT II 205.00 160.48 2.3118 2.2054 -0.2682 -0.2302 0.0719 0.0617<br />

III 144.00 107.41 2.1584 2.0310 -0.4216 -0.4045 0.1777 0.1705<br />

I 731.00 511.62 2.8639 2.7089 0.2840 0.2734 0.0806 0.0776<br />

1975 AUG II 856.00 575.79 2.9325 2.7603 0.3525 0.3247 0.1243 0.1145<br />

III 535.00 370.86 2.7284 2.5692 0.1484 0.1336 0.0220 0.0198<br />

I 718.00 284.37 2.8561 2.4539 0.2762 0.0183 0.0763 0.0051<br />

SEPT II 288.00 200.70 2.4594 2.3025 -0.1205 -0.1330 0.0145 0.0160<br />

III 177.00 124.74 2.2480 2.0960 -0.3320 -0.3396 0.1102 0.1127<br />

I 569.00 408.32 2.7551 2.6110 0.1752 0.1754 0.0307 0.0307<br />

1976 AUG II 518.00 360.47 2.7143 2.5569 0.1344 0.1213 0.0181 0.0163<br />

III 381.00 282.12 2.5809 2.4504 0.0010 0.0148 0.0000 0.0000<br />

I 326.00 240.73 2.5132 2.3815 -0.0667 -0.0541 0.0045 0.0036<br />

SEPT II 178.00 138.96 2.2504 2.1429 -0.3295 -0.2927 0.1086 0.0964<br />

III 159.00 113.35 2.2014 2.0544 -0.3785 -0.3812 0.1433 0.1443<br />

I 724.00 530.88 2.8597 2.7250 0.2798 0.2894 0.0783 0.0810<br />

1977 AUG II 501.00 368.00 2.6998 2.5658 0.1199 0.1303 0.0144 0.0156<br />

III 468.00 330.56 2.6702 2.5193 0.0903 0.0837 0.0082 0.0076<br />

I 396.00 281.03 2.5977 2.4488 0.0178 0.0132 0.0003 0.0002<br />

SEPT II 226.00 170.94 2.3541 2.2328 -0.2258 -0.2027 0.0510 0.0458<br />

III 151.00 114.63 2.1790 2.0593 -0.4010 -0.3763 0.1608 0.1509<br />

I 725.00 550.35 2.8603 2.7406 0.2804 0.3050 0.0786 0.0855<br />

1978 AUG II 619.00 435.17 2.7917 2.6387 0.2118 0.2031 0.0448 0.0430<br />

III 528.00 378.00 2.7226 2.5775 0.1427 0.1419 0.0204 0.0202<br />

I 253.00 186.00 2.4031 2.2695 -0.1768 -0.1661 0.0313 0.0294<br />

SEPT II 221.00 142.98 2.3444 2.1553 -0.2355 -0.2803 0.0555 0.0660<br />

III 164.00 136.28 2.2148 2.1344 -0.3651 -0.3012 0.1333 0.1100<br />

I 817.00 574.89 2.9122 2.7596 0.3323 0.3240 0.1104 0.1077<br />

1979 AUG II 666.00 478.29 2.8235 2.6797 0.2435 0.2441 0.0593 0.0594<br />

III 437.00 335.16 2.6405 2.5253 0.0605 0.0897 0.0037 0.0054<br />

I 423.00 311.36 2.6263 2.4933 0.0464 0.0577 0.0022 0.0027<br />

SEPT II 216.00 164.16 2.3345 2.2153 -0.2455 -0.2203 0.0603 0.0541<br />

III 130.00 74.60 2.1139 1.8727 -0.4660 -0.5629 0.2172 0.2623<br />

I 750.00 515.94 2.8751 2.7126 0.2951 0.2770 0.0871 0.0818<br />

1980 AUG II 423.00 318.18 2.6263 2.5027 0.0464 0.0671 0.0022 0.0031<br />

III 473.00 356.30 2.6749 2.5518 0.0949 0.1162 0.0090 0.0110<br />

I 301.00 225.52 2.4786 2.3532 -0.1014 -0.0824 0.0103 0.0084<br />

SEPT II 213.00 144.10 2.3284 2.1587 -0.2516 -0.2769 0.0633 0.0697<br />

III 165.00 99.36 2.2175 1.9972 -0.3625 -0.4384 0.1314 0.1589<br />

I 694.00 487.37 2.8414 2.6879 0.2614 0.2523 0.0683 0.0659<br />

1981 AUG II 628.00 441.32 2.7980 2.6448 0.2180 0.2092 0.0475 0.0456<br />

III 467.00 303.76 2.6693 2.4825 0.0894 0.0469 0.0080 0.0042<br />

I 370.00 250.66 2.5682 2.3991 -0.0117 -0.0365 0.0001 0.0004<br />

SEPT II 221.00 141.39 2.3444 2.1504 -0.2355 -0.2852 0.0555 0.0672<br />

III 211.00 125.77 2.3243 2.0996 -0.2557 -0.3360 0.0654 0.0859<br />

I 861.00 578.82 2.9350 2.7625 0.3551 0.3270 0.1261 0.1161<br />

1982 AUG II 664.00 486.72 2.8222 2.6873 0.2422 0.2517 0.0587 0.0610<br />

III 425.00 344.35 2.6284 2.5370 0.0485 0.1014 0.0023 0.0049<br />

I 338.00 251.49 2.5289 2.4005 -0.0510 -0.0351 0.0026 0.0018<br />

SEPT II 339.00 219.20 2.5302 2.3408 -0.0497 -0.0947 0.0025 0.0047<br />

III 136.00 152.19 2.1335 2.1824 -0.4464 -0.2532 0.1993 0.1130<br />

I 903.00 643.85 2.9557 2.8088 0.3757 0.3732 0.1412 0.1402<br />

1983 AUG II 686.00 546.24 2.8363 2.7374 0.2564 0.3018 0.0657 0.0774<br />

III 697.00 539.17 2.8432 2.7317 0.2633 0.2961 0.0693 0.0780<br />

I 597.00 437.26 2.7760 2.6407 0.1960 0.2052 0.0384 0.0402<br />

SEPT II 406.00 299.29 2.6085 2.4761 0.0286 0.0405 0.0008 0.0012<br />

III 195.00 161.98 2.2900 2.2095 -0.2899 -0.2261 0.0840 0.0656<br />

G.TOTAL 154.80 146.14 0.00 0.00 3.49 3.37<br />

NO. OF PERIOD 60 LOG x' LOG y'<br />

AVERAGE 2.5799 2.4356<br />

Co-efficient <strong>of</strong> Corelation<br />

b = SIGMA X*Y = 0.9648<br />

SIGMA X^2<br />

Table-5.4(2)


REGRESSION ANALYSIS BETWEEN DISCHARGES OF TANDI PLUS GHOUSAL AND UDAIPUR ( N-MON )<br />

UDAIPUR TDI.+GSL DEVIATION FROM MEAN<br />

D/SITE D/SITE X Y X^2 X*Y<br />

YEAR MONTH Qx Qy LOG x LOG y LOGx-LOGX' LOGy-LOGy'<br />

(Cumecs) (Cumecs)<br />

I 82.00 59.62 1.9138 1.7754 0.1598 0.2095 0.0256 0.0335<br />

1974-75 OCT II 67.00 48.58 1.8261 1.6865 0.0721 0.1206 0.0052 0.0087<br />

III 55.00 39.31 1.7404 1.5945 -0.0136 0.0287 0.0002 -0.0004<br />

I 46.00 32.92 1.6628 1.5175 -0.0912 -0.0484 0.0083 0.0044<br />

NOV II 40.00 35.83 1.6021 1.5542 -0.1519 -0.0116 0.0231 0.0018<br />

III 36.00 27.45 1.5563 1.4385 -0.1977 -0.1273 0.0391 0.0252<br />

I 36.00 25.69 1.5563 1.4098 -0.1977 -0.1561 0.0391 0.0309<br />

DEC II 35.00 23.43 1.5441 1.3698 -0.2099 -0.1961 0.0441 0.0412<br />

III 35.00 24.42 1.5441 1.3877 -0.2099 -0.1781 0.0441 0.0374<br />

I 32.00 22.38 1.5051 1.3499 -0.2488 -0.2160 0.0619 0.0537<br />

JAN II 31.00 22.07 1.4914 1.3438 -0.2626 -0.2220 0.0690 0.0583<br />

III 26.00 19.60 1.4150 1.2923 -0.3390 -0.2736 0.1149 0.0927<br />

I 27.00 22.19 1.4314 1.3462 -0.3226 -0.2197 0.1041 0.0709<br />

FEB II 31.00 21.59 1.4914 1.3343 -0.2626 -0.2316 0.0690 0.0608<br />

III 32.00 23.12 1.5051 1.3640 -0.2488 -0.2019 0.0619 0.0502<br />

I 30.00 18.30 1.4771 1.2625 -0.2768 -0.3034 0.0766 0.0840<br />

MAR II 31.00 18.43 1.4914 1.2655 -0.2626 -0.3003 0.0690 0.0789<br />

III 31.00 23.26 1.4914 1.3666 -0.2626 -0.1992 0.0690 0.0523<br />

I 38.00 26.42 1.5798 1.4219 -0.1742 -0.1439 0.0303 0.0251<br />

APR II 54.00 35.38 1.7324 1.5488 -0.0216 -0.0171 0.0005 0.0004<br />

III 71.00 48.70 1.8513 1.6875 0.0973 0.1217 0.0095 0.0118<br />

I 108.00 74.16 2.0334 1.8702 0.2795 0.3043 0.0781 0.0850<br />

MAY II 228.00 158.15 2.3579 2.1991 0.6040 0.6332 0.3648 0.3824<br />

III 277.00 205.11 2.4425 2.3120 0.6885 0.7461 0.4740 0.5137<br />

I 148.00 97.47 2.1703 1.9889 0.4163 0.4230 0.1733 0.1761<br />

1975-76 OCT II 121.00 81.99 2.0828 1.9138 0.3288 0.3479 0.1081 0.1144<br />

III 79.00 54.50 1.8976 1.7364 0.1437 0.1706 0.0206 0.0245<br />

I 58.00 39.53 1.7634 1.5969 0.0095 0.0311 0.0001 0.0003<br />

NOV II 49.00 34.42 1.6902 1.5368 -0.0638 -0.0290 0.0041 0.0019<br />

III 42.00 31.23 1.6232 1.4946 -0.1307 -0.0713 0.0171 0.0093<br />

I 39.00 29.32 1.5911 1.4672 -0.1629 -0.0987 0.0265 0.0161<br />

DEC II 33.00 26.02 1.5185 1.4153 -0.2355 -0.1505 0.0554 0.0354<br />

III 32.00 24.75 1.5051 1.3936 -0.2488 -0.1723 0.0619 0.0429<br />

I 33.00 24.16 1.5185 1.3831 -0.2355 -0.1827 0.0554 0.0430<br />

JAN II 33.00 23.46 1.5185 1.3703 -0.2355 -0.1955 0.0554 0.0460<br />

III 32.00 21.84 1.5051 1.3393 -0.2488 -0.2266 0.0619 0.0564<br />

I 31.00 22.41 1.4914 1.3504 -0.2626 -0.2154 0.0690 0.0566<br />

FEB II 25.00 18.21 1.3979 1.2603 -0.3560 -0.3055 0.1268 0.1088<br />

III 28.00 20.03 1.4472 1.3017 -0.3068 -0.2642 0.0941 0.0810<br />

I 31.00 22.49 1.4914 1.3520 -0.2626 -0.2139 0.0690 0.0562<br />

MAR II 29.00 21.10 1.4624 1.3243 -0.2916 -0.2416 0.0850 0.0704<br />

III 28.00 20.13 1.4472 1.3038 -0.3068 -0.2620 0.0941 0.0804<br />

I 34.00 20.08 1.5315 1.3028 -0.2225 -0.2631 0.0495 0.0585<br />

APR II 42.00 26.91 1.6232 1.4299 -0.1307 -0.1359 0.0171 0.0178<br />

III 101.00 60.08 2.0043 1.7787 0.2504 0.2129 0.0627 0.0533<br />

I 131.00 83.13 2.1173 1.9198 0.3633 0.3539 0.1320 0.1286<br />

MAY II 189.00 127.74 2.2765 2.1063 0.5225 0.5405 0.2730 0.2824<br />

III 276.00 184.72 2.4409 2.2665 0.6869 0.7007 0.4719 0.4813<br />

I 118.00 80.29 2.0719 1.9047 0.3179 0.3388 0.1011 0.1077<br />

1976-77 OCT II 70.00 51.19 1.8451 1.7092 0.0911 0.1433 0.0083 0.0131<br />

III 56.00 39.71 1.7482 1.5989 -0.0058 0.0331 0.0000 -0.0002<br />

I 52.00 35.45 1.7160 1.5496 -0.0380 -0.0162 0.0014 0.0006<br />

NOV II 44.00 32.17 1.6435 1.5075 -0.1105 -0.0584 0.0122 0.0065<br />

III 37.00 28.95 1.5682 1.4616 -0.1858 -0.1042 0.0345 0.0194<br />

I 34.00 26.40 1.5315 1.4216 -0.2225 -0.1442 0.0495 0.0321<br />

DEC II 31.00 23.24 1.4914 1.3662 -0.2626 -0.1996 0.0690 0.0524<br />

III 31.00 21.93 1.4914 1.3410 -0.2626 -0.2248 0.0690 0.0590<br />

I 30.00 20.07 1.4771 1.3025 -0.2768 -0.2633 0.0766 0.0729<br />

JAN II 29.00 18.97 1.4624 1.2781 -0.2916 -0.2878 0.0850 0.0839<br />

III 155.00 16.18 2.1903 1.2090 0.4364 -0.3569 0.1904 -0.1557<br />

I 33.00 22.47 1.5185 1.3516 -0.2355 -0.2142 0.0554 0.0504<br />

FEB II 27.00 19.22 1.4314 1.2838 -0.3226 -0.2821 0.1041 0.0910<br />

III 26.00 19.26 1.4150 1.2847 -0.3390 -0.2812 0.1149 0.0953<br />

I 28.00 19.12 1.4472 1.2815 -0.3068 -0.2844 0.0941 0.0872<br />

MAR II 29.00 19.33 1.4624 1.2862 -0.2916 -0.2796 0.0850 0.0815<br />

III 37.00 26.05 1.5682 1.4158 -0.1858 -0.1500 0.0345 0.0279<br />

I 40.00 29.91 1.6021 1.4758 -0.1519 -0.0900 0.0231 0.0137<br />

APR II 39.00 28.31 1.5911 1.4519 -0.1629 -0.1139 0.0265 0.0186<br />

III 47.00 34.28 1.6721 1.5350 -0.0819 -0.0308 0.0067 0.0025<br />

I 50.00 35.33 1.6990 1.5481 -0.0550 -0.0177 0.0030 0.0010<br />

MAY II 75.00 51.18 1.8751 1.7091 0.1211 0.1433 0.0147 0.0173<br />

III 168.00 124.42 2.2253 2.0949 0.4713 0.5290 0.2222 0.2494<br />

Table-5.4(3)


UDAIPUR TDI.+GSL DEVIATION FROM MEAN<br />

D/SITE D/SITE X Y X^2 X*Y<br />

YEAR MONTH Qx Qy LOG x LOG y LOGx-LOGX' LOGy-LOGy'<br />

(Cumecs) (Cumecs)<br />

I 109.00 80.11 2.0374 1.9037 0.2835 0.3378 0.0803 0.0958<br />

1977-78 OCT II 80.00 57.55 1.9031 1.7600 0.1491 0.1942 0.0222 0.0290<br />

III 69.00 47.45 1.8388 1.6762 0.0849 0.1104 0.0072 0.0094<br />

I 57.00 41.74 1.7559 1.6206 0.0019 0.0547 0.0000 0.0001<br />

NOV II 49.00 36.30 1.6902 1.5599 -0.0638 -0.0059 0.0041 0.0004<br />

III 44.00 34.85 1.6435 1.5422 -0.1105 -0.0236 0.0122 0.0026<br />

I 38.00 32.17 1.5798 1.5075 -0.1742 -0.0584 0.0303 0.0102<br />

DEC II 35.00 27.86 1.5441 1.4450 -0.2099 -0.1209 0.0441 0.0254<br />

III 33.00 25.35 1.5185 1.4040 -0.2355 -0.1619 0.0554 0.0381<br />

I 32.00 22.94 1.5051 1.3606 -0.2488 -0.2053 0.0619 0.0511<br />

JAN II 33.00 26.57 1.5185 1.4244 -0.2355 -0.1415 0.0554 0.0333<br />

III 32.00 24.35 1.5051 1.3865 -0.2488 -0.1793 0.0619 0.0446<br />

I 32.00 22.16 1.5051 1.3456 -0.2488 -0.2203 0.0619 0.0548<br />

FEB II 27.00 22.57 1.4314 1.3535 -0.3226 -0.2123 0.1041 0.0685<br />

III 32.00 27.02 1.5051 1.4317 -0.2488 -0.1342 0.0619 0.0334<br />

I 31.00 20.60 1.4914 1.3139 -0.2626 -0.2520 0.0690 0.0662<br />

MAR II 31.00 20.10 1.4914 1.3032 -0.2626 -0.2626 0.0690 0.0690<br />

III 36.00 23.41 1.5563 1.3694 -0.1977 -0.1964 0.0391 0.0388<br />

I 38.00 25.10 1.5798 1.3997 -0.1742 -0.1662 0.0303 0.0289<br />

APR II 66.00 40.41 1.8195 1.6065 0.0656 0.0406 0.0043 0.0027<br />

III 82.00 52.48 1.9138 1.7200 0.1598 0.1541 0.0256 0.0246<br />

I 197.00 146.66 2.2945 2.1663 0.5405 0.6005 0.2921 0.3246<br />

MAY II 290.00 229.87 2.4624 2.3615 0.7084 0.7956 0.5019 0.5637<br />

III 336.00 267.93 2.5263 2.4280 0.7724 0.8622 0.5966 0.6659<br />

I 121.00 80.94 2.0828 1.9082 0.3288 0.3423 0.1081 0.1126<br />

1978-79 OCT II 96.00 61.61 1.9823 1.7897 0.2283 0.2238 0.0521 0.0511<br />

III 79.00 59.49 1.8976 1.7744 0.1437 0.2086 0.0206 0.0300<br />

I 59.00 40.26 1.7709 1.6049 0.0169 0.0390 0.0003 0.0007<br />

NOV II 49.00 35.70 1.6902 1.5527 -0.0638 -0.0132 0.0041 0.0008<br />

III 44.00 36.17 1.6435 1.5583 -0.1105 -0.0075 0.0122 0.0008<br />

I 40.00 33.02 1.6021 1.5188 -0.1519 -0.0471 0.0231 0.0071<br />

DEC II 38.00 31.29 1.5798 1.4954 -0.1742 -0.0704 0.0303 0.0123<br />

III 35.00 31.17 1.5441 1.4937 -0.2099 -0.0721 0.0441 0.0151<br />

I 41.00 30.52 1.6128 1.4846 -0.1412 -0.0813 0.0199 0.0115<br />

JAN II 42.00 26.92 1.6232 1.4301 -0.1307 -0.1358 0.0171 0.0177<br />

III 40.00 26.07 1.6021 1.4161 -0.1519 -0.1497 0.0231 0.0227<br />

I 39.00 27.86 1.5911 1.4450 -0.1629 -0.1209 0.0265 0.0197<br />

FEB II 38.00 25.12 1.5798 1.4000 -0.1742 -0.1658 0.0303 0.0289<br />

III 35.00 25.41 1.5441 1.4050 -0.2099 -0.1608 0.0441 0.0338<br />

I 41.00 25.35 1.6128 1.4040 -0.1412 -0.1619 0.0199 0.0229<br />

MAR II 40.00 40.35 1.6021 1.6058 -0.1519 0.0400 0.0231 -0.0061<br />

III 45.00 56.50 1.6532 1.7520 -0.1008 0.1862 0.0102 -0.0188<br />

I 64.00 51.00 1.8062 1.7076 0.0522 0.1417 0.0027 0.0074<br />

APR II 91.00 54.00 1.9590 1.7324 0.2051 0.1665 0.0421 0.0342<br />

III 144.00 88.02 2.1584 1.9446 0.4044 0.3787 0.1635 0.1532<br />

I 179.00 118.02 2.2529 2.0720 0.4989 0.5061 0.2489 0.2525<br />

MAY II 163.00 102.58 2.2122 2.0111 0.4582 0.4452 0.2100 0.2040<br />

III 145.00 100.78 2.1614 2.0034 0.4074 0.4375 0.1660 0.1783<br />

I 127.00 68.72 2.1038 1.8371 0.3498 0.2712 0.1224 0.0949<br />

1979-80 OCT II 108.00 56.94 2.0334 1.7554 0.2795 0.1896 0.0781 0.0530<br />

III 91.00 48.83 1.9590 1.6887 0.2051 0.1228 0.0421 0.0252<br />

I 83.00 44.23 1.9191 1.6457 0.1651 0.0799 0.0273 0.0132<br />

NOV II 70.00 37.74 1.8451 1.5768 0.0911 0.0110 0.0083 0.0010<br />

III 65.00 36.24 1.8129 1.5592 0.0589 -0.0067 0.0035 -0.0004<br />

I 59.00 34.74 1.7709 1.5408 0.0169 -0.0250 0.0003 -0.0004<br />

DEC II 57.00 31.93 1.7559 1.5042 0.0019 -0.0616 0.0000 -0.0001<br />

III 57.00 31.86 1.7559 1.5032 0.0019 -0.0626 0.0000 -0.0001<br />

I 57.00 27.68 1.7559 1.4422 0.0019 -0.1237 0.0000 -0.0002<br />

JAN II 56.00 26.76 1.7482 1.4275 -0.0058 -0.1384 0.0000 0.0008<br />

III 52.00 24.08 1.7160 1.3817 -0.0380 -0.1842 0.0014 0.0070<br />

I 58.00 29.54 1.7634 1.4704 0.0095 -0.0954 0.0001 -0.0009<br />

FEB II 57.00 26.83 1.7559 1.4286 0.0019 -0.1372 0.0000 -0.0003<br />

III 54.00 28.79 1.7324 1.4592 -0.0216 -0.1066 0.0005 0.0023<br />

I 51.00 25.50 1.7076 1.4065 -0.0464 -0.1593 0.0022 0.0074<br />

MAR II 51.00 27.55 1.7076 1.4401 -0.0464 -0.1257 0.0022 0.0058<br />

III 51.00 30.63 1.7076 1.4861 -0.0464 -0.0797 0.0022 0.0037<br />

I 58.00 33.90 1.7634 1.5302 0.0095 -0.0356 0.0001 -0.0003<br />

APR II 71.00 38.03 1.8513 1.5801 0.0973 0.0143 0.0095 0.0014<br />

III 95.00 42.98 1.9777 1.6333 0.2238 0.0674 0.0501 0.0151<br />

I 155.00 91.76 2.1903 1.9627 0.4364 0.3968 0.1904 0.1732<br />

MAY II 182.00 123.09 2.2601 2.0902 0.5061 0.5244 0.2561 0.2654<br />

III 240.00 177.23 2.3802 2.2485 0.6262 0.6827 0.3922 0.4275<br />

Table-5.4(4)


UDAIPUR TDI.+GSL DEVIATION FROM MEAN<br />

D/SITE D/SITE X Y X^2 X*Y<br />

YEAR MONTH Qx Qy LOG x LOG y LOGx-LOGX' LOGy-LOGy'<br />

(Cumecs) (Cumecs)<br />

I 150.00 84.26 2.1761 1.9256 0.4221 0.3598 0.1782 0.1519<br />

1980-81 OCT II 116.00 56.63 2.0645 1.7530 0.3105 0.1872 0.0964 0.0581<br />

III 95.00 45.26 1.9777 1.6557 0.2238 0.0899 0.0501 0.0201<br />

I 84.00 33.35 1.9243 1.5231 0.1703 -0.0427 0.0290 -0.0073<br />

NOV II 77.00 29.02 1.8865 1.4627 0.1325 -0.1031 0.0176 -0.0137<br />

III 72.00 28.62 1.8573 1.4567 0.1034 -0.1092 0.0107 -0.0113<br />

I 68.00 26.16 1.8325 1.4176 0.0785 -0.1482 0.0062 -0.0116<br />

DEC II 67.00 24.82 1.8261 1.3948 0.0721 -0.1710 0.0052 -0.0123<br />

III 65.00 23.64 1.8129 1.3736 0.0589 -0.1922 0.0035 -0.0113<br />

I 65.00 24.71 1.8129 1.3929 0.0589 -0.1730 0.0035 -0.0102<br />

JAN II 62.00 23.35 1.7924 1.3683 0.0384 -0.1976 0.0015 -0.0076<br />

III 65.00 22.36 1.8129 1.3495 0.0589 -0.2164 0.0035 -0.0128<br />

I 59.00 22.46 1.7709 1.3514 0.0169 -0.2144 0.0003 -0.0036<br />

FEB II 64.00 23.07 1.8062 1.3630 0.0522 -0.2028 0.0027 -0.0106<br />

III 64.00 24.76 1.8062 1.3938 0.0522 -0.1721 0.0027 -0.0090<br />

I 61.00 23.76 1.7853 1.3758 0.0314 -0.1900 0.0010 -0.0060<br />

MAR II 60.00 23.60 1.7782 1.3729 0.0242 -0.1929 0.0006 -0.0047<br />

III 65.00 24.80 1.8129 1.3945 0.0589 -0.1714 0.0035 -0.0101<br />

I 70.00 26.44 1.8451 1.4223 0.0911 -0.1436 0.0083 -0.0131<br />

APR II 100.00 35.34 2.0000 1.5483 0.2460 -0.0176 0.0605 -0.0043<br />

III 149.00 70.52 2.1732 1.8483 0.4192 0.2825 0.1757 0.1184<br />

I 304.00 201.93 2.4829 2.3052 0.7289 0.7394 0.5313 0.5389<br />

MAY II 321.00 243.63 2.5065 2.3867 0.7525 0.8209 0.5663 0.6177<br />

III 405.00 287.76 2.6075 2.4590 0.8535 0.8932 0.7284 0.7623<br />

I 125.00 62.05 2.0969 1.7927 0.3429 0.2269 0.1176 0.0778<br />

1981-82 OCT II 108.00 51.80 2.0334 1.7143 0.2795 0.1485 0.0781 0.0415<br />

III 92.00 37.24 1.9638 1.5710 0.2098 0.0052 0.0440 0.0011<br />

I 76.00 33.72 1.8808 1.5279 0.1268 -0.0380 0.0161 -0.0048<br />

NOV II 57.00 28.67 1.7559 1.4574 0.0019 -0.1084 0.0000 -0.0002<br />

III 53.00 25.31 1.7243 1.4033 -0.0297 -0.1626 0.0009 0.0048<br />

I 49.00 23.42 1.6902 1.3696 -0.0638 -0.1963 0.0041 0.0125<br />

DEC II 45.00 20.94 1.6532 1.3210 -0.1008 -0.2449 0.0102 0.0247<br />

III 44.00 19.72 1.6435 1.2949 -0.1105 -0.2709 0.0122 0.0299<br />

I 36.00 22.34 1.5563 1.3491 -0.1977 -0.2168 0.0391 0.0428<br />

JAN II 35.00 22.20 1.5441 1.3464 -0.2099 -0.2195 0.0441 0.0461<br />

III 33.00 21.41 1.5185 1.3306 -0.2355 -0.2352 0.0554 0.0554<br />

I 36.00 22.32 1.5563 1.3487 -0.1977 -0.2171 0.0391 0.0429<br />

FEB II 35.00 22.70 1.5441 1.3560 -0.2099 -0.2098 0.0441 0.0440<br />

III 37.00 21.76 1.5682 1.3377 -0.1858 -0.2282 0.0345 0.0424<br />

I 37.00 23.37 1.5682 1.3687 -0.1858 -0.1972 0.0345 0.0366<br />

MAR II 37.00 22.92 1.5682 1.3602 -0.1858 -0.2056 0.0345 0.0382<br />

III 38.00 22.09 1.5798 1.3442 -0.1742 -0.2216 0.0303 0.0386<br />

I 45.00 24.50 1.6532 1.3892 -0.1008 -0.1767 0.0102 0.0178<br />

APR II 56.00 26.13 1.7482 1.4171 -0.0058 -0.1487 0.0000 0.0009<br />

III 80.00 36.40 1.9031 1.5611 0.1491 -0.0047 0.0222 -0.0007<br />

I 138.00 70.96 2.1399 1.8510 0.3859 0.2852 0.1489 0.1101<br />

MAY II 109.00 64.11 2.0374 1.8069 0.2835 0.2411 0.0803 0.0683<br />

III 179.00 106.79 2.2529 2.0285 0.4989 0.4627 0.2489 0.2308<br />

I 84.00 100.84 1.9243 2.0036 0.1703 0.4378 0.0290 0.0746<br />

1982-83 OCT II 71.00 88.58 1.8513 1.9473 0.0973 0.3815 0.0095 0.0371<br />

III 63.00 55.79 1.7993 1.7466 0.0454 0.1807 0.0021 0.0082<br />

I 53.00 41.31 1.7243 1.6161 -0.0297 0.0502 0.0009 -0.0015<br />

NOV II 48.00 38.77 1.6812 1.5885 -0.0727 0.0227 0.0053 -0.0016<br />

III 44.00 34.27 1.6435 1.5349 -0.1105 -0.0309 0.0122 0.0034<br />

I 42.00 29.40 1.6232 1.4683 -0.1307 -0.0975 0.0171 0.0127<br />

DEC II 42.00 25.54 1.6232 1.4072 -0.1307 -0.1586 0.0171 0.0207<br />

III 39.00 26.22 1.5911 1.4186 -0.1629 -0.1472 0.0265 0.0240<br />

I 31.00 22.36 1.4914 1.3494 -0.2626 -0.2164 0.0690 0.0568<br />

JAN II 29.00 22.40 1.4624 1.3502 -0.2916 -0.2156 0.0850 0.0629<br />

III 28.00 22.62 1.4472 1.3545 -0.3068 -0.2114 0.0941 0.0648<br />

I 27.00 21.39 1.4314 1.3302 -0.3226 -0.2356 0.1041 0.0760<br />

FEB II 26.00 21.20 1.4150 1.3263 -0.3390 -0.2395 0.1149 0.0812<br />

III 24.00 21.45 1.3802 1.3314 -0.3738 -0.2344 0.1397 0.0876<br />

I 26.00 29.99 1.4150 1.4770 -0.3390 -0.0889 0.1149 0.0301<br />

MAR II 30.00 32.42 1.4771 1.5108 -0.2768 -0.0550 0.0766 0.0152<br />

III 32.00 29.44 1.5051 1.4689 -0.2488 -0.0969 0.0619 0.0241<br />

I 44.00 29.41 1.6435 1.4685 -0.1105 -0.0973 0.0122 0.0108<br />

APR II 45.00 28.28 1.6532 1.4515 -0.1008 -0.1144 0.0102 0.0115<br />

III 45.00 33.42 1.6532 1.5240 -0.1008 -0.0418 0.0102 0.0042<br />

I 100.00 57.45 2.0000 1.7593 0.2460 0.1934 0.0605 0.0476<br />

MAY II 173.00 91.11 2.2380 1.9596 0.4841 0.3937 0.2343 0.1906<br />

III 167.00 139.24 2.2227 2.1438 0.4687 0.5779 0.2197 0.2709<br />

1983-84 I 142.00 121.51 2.1523 2.0846 0.3983 0.5188 0.1587 0.2066<br />

OCT II 99.00 78.07 1.9956 1.8925 0.2417 0.3266 0.0584 0.0789<br />

III 62.00 50.04 1.7924 1.6993 0.0384 0.1335 0.0015 0.0051<br />

I 50.00 39.42 1.6990 1.5957 -0.0550 0.0299 0.0030 -0.0016<br />

NOV II 48.00 36.67 1.6812 1.5643 -0.0727 -0.0015 0.0053 0.0001<br />

III 44.00 34.10 1.6435 1.5328 -0.1105 -0.0331 0.0122 0.0037<br />

Table-5.4(5)


UDAIPUR TDI.+GSL DEVIATION FROM MEAN<br />

D/SITE D/SITE X Y X^2 X*Y<br />

YEAR MONTH Qx Qy LOG x LOG y LOGx-LOGX' LOGy-LOGy'<br />

(Cumecs) (Cumecs)<br />

I 42.00 30.40 1.6232 1.4828 -0.1307 -0.0830 0.0171 0.0109<br />

DEC II 39.00 28.55 1.5911 1.4557 -0.1629 -0.1102 0.0265 0.0180<br />

Table-5.4(6)


UDAIPUR TDI.+GSL DEVIATION FROM MEAN<br />

D/SITE D/SITE X Y X^2 X*Y<br />

YEAR MONTH Qx Qy LOG x LOG y LOGx-LOGX' LOGy-LOGy'<br />

(Cumecs) (Cumecs)<br />

III 36.00 21.42 1.5563 1.3308 -0.1977 -0.2350 0.0391 0.0465<br />

I 35.00 30.03 1.5441 1.4776 -0.2099 -0.0883 0.0441 0.0185<br />

JAN II 35.00 29.59 1.5441 1.4711 -0.2099 -0.0947 0.0441 0.0199<br />

III 32.00 28.06 1.5051 1.4481 -0.2488 -0.1178 0.0619 0.0293<br />

I 30.00 26.62 1.4771 1.4251 -0.2768 -0.1407 0.0766 0.0390<br />

FEB II 28.00 26.07 1.4472 1.4161 -0.3068 -0.1497 0.0941 0.0459<br />

III 22.00 24.73 1.3424 1.3932 -0.4115 -0.1726 0.1694 0.0710<br />

I 33.00 25.65 1.5185 1.4091 -0.2355 -0.1568 0.0554 0.0369<br />

MAR II 33.00 29.19 1.5185 1.4652 -0.2355 -0.1006 0.0554 0.0237<br />

III 36.00 30.48 1.5563 1.4840 -0.1977 -0.0818 0.0391 0.0162<br />

I 42.00 31.91 1.6232 1.5039 -0.1307 -0.0619 0.0171 0.0081<br />

APR II 51.00 30.85 1.7076 1.4893 -0.0464 -0.0766 0.0022 0.0036<br />

III 69.00 41.00 1.8388 1.6128 0.0849 0.0469 0.0072 0.0040<br />

I 128.00 73.03 2.1072 1.8635 0.3532 0.2977 0.1248 0.1051<br />

MAY II 180.00 107.90 2.2553 2.0330 0.5013 0.4672 0.2513 0.2342<br />

III 353.00 197.58 2.5478 2.2957 0.7938 0.7299 0.6301 0.5794<br />

G.TOTAL 420.95 375.80 0.00 0.00 17.53 15.36<br />

NO. OF PERIOD 240 LOG x' LOG y'<br />

AVERAGE 1.7540 1.5658<br />

Co-efficient <strong>of</strong> Corelation<br />

b = SIGMA X*Y = 0.8766<br />

SIGMA X^2<br />

Table-5.4(7)


Discharge in Cumecdays<br />

120000<br />

100000<br />

80000<br />

60000<br />

40000<br />

20000<br />

Graph showing the trend lines <strong>of</strong> two series blocks<br />

<strong>of</strong> annual discharge <strong>of</strong> river Chenab at Udaipur<br />

0<br />

19<br />

74-<br />

75<br />

19<br />

76-<br />

77<br />

19<br />

78-<br />

79<br />

19<br />

80-<br />

81<br />

19<br />

82-<br />

83<br />

19<br />

84-<br />

85<br />

19<br />

86-<br />

87<br />

19<br />

88-<br />

89<br />

19<br />

90-<br />

91<br />

19<br />

92-<br />

93<br />

19<br />

94-<br />

95<br />

19<br />

96-<br />

97<br />

combined s2 s1 Linear (combined) Linear (s2) Linear (s1)<br />

19<br />

98-<br />

99<br />

20<br />

00-<br />

01

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!