Federal-Aid Design<br />

Process Overview<br />

Gregg Wilhelm<br />

<strong>MoDOT</strong> Local Programs Design Engineer


Local Programs Design Staff<br />

St. Louis District<br />

Gregg Wilhelm, Local Program Design Engineer (314) 453‐1832;<br />

Gregory.Wilhelm@modot.mo.gov<br />

Area of responsibility: St. Louis City<br />

Laura Ellen, District Design Liaison ‐ (314) 275‐1542;<br />

Laura.Ellen@modot.mo.gov<br />

Area of responsibility: North St. Louis County and St. Charles<br />

County<br />

Tom McCloskey, District Design Liaison ‐ (314) 453‐1831;<br />

Thomas.McCloskey@modot.mo.gov<br />

Area of responsibility: Franklin County and Jefferson County<br />

Jim Schmidt, District Design Liaison ‐ (314) 453‐5082;<br />

James.Schmidt@modot.mo.gov<br />

Area of responsibility: Southwest St. Louis County


•LPA Manual online at:<br />

http://www.modot.mo.gov/business/lpa/lpamanual.htm<br />

• <strong>MoDOT</strong> approval needed before starting reimbursable work


Person in responsible charge<br />

Person in responsible charge:<br />

• must be a full time employee of<br />

the LPA<br />

• cannot be a consultant hired by<br />

the LPA<br />

• is the person accountable for the<br />

project


LPA Basic Training


Conflict of Interest<br />

Consultants and TIP applications<br />

•If prepared without getting fairly paid, consultant cannot be<br />

considered for selection for the design contract.<br />

•If prepared with getting fairly paid, all project documents must be<br />

made available to all interested firms.


Conflict of Interest<br />

Consultants and Request For Qualifications<br />

•If consultant helps develop RFQ, regardless of payment, they<br />

WILL NOT be eligible for the next phase of the project.<br />

• Figure 136.4.13 – nine page Q&A on consultant services


Project Programming<br />

•Federal Project Number<br />

assigned<br />

•Environmental review<br />

conducted<br />

•<strong>MoDOT</strong> will notify LPA of<br />

environmental approvals<br />

needed


Federal-Aid Program Agreements<br />

• Agreements for each<br />

funding type<br />

• Outlines funding amount,<br />

type, and responsibilities<br />

• Enabling ordinance<br />

required for cities,<br />

1 st class counties<br />

• Per ordinance, only<br />

certain personnel can<br />

sign agreement


Engineering Selection Process<br />

Request for Qualifications (RFQ)<br />

• Must submit to <strong>MoDOT</strong> for review/approval<br />

• Recommend sample shown on <strong>MoDOT</strong> website<br />

• Scope must be consistent with project’s TIP<br />

application<br />

• Will be reviewed for a DBE goal<br />

• Must be posted on <strong>MoDOT</strong>’s website at least 14 days


Engineering Selection Process


Engineering Selection Process<br />

Qualification Based Selection (QBS)<br />

• Must select most qualified firm<br />

using criteria in RFQ<br />

• Price CANNOT be a factor in<br />

selection<br />

• Negotiate price after most<br />

qualified firm selected<br />

• Firm must be on <strong>MoDOT</strong> preapproved<br />

list


Engineering Selection Process<br />

Engineering Services Contract (ESC)<br />

• Must use standard contract in<br />

manual<br />

• Contract scope can include<br />

design and construction<br />

inspection costs<br />

• Work cannot begin until<br />

<strong>MoDOT</strong> approves contract


Preliminary Design<br />

If want to use own design staff, must first receive<br />

<strong>MoDOT</strong> and FHWA approval<br />

Design preliminary plans in accordance with:<br />

• Applicable design guidelines<br />

• ADA<br />

• MUTCD<br />

Submit all environmental clearances obtained<br />

thus far


<strong>MoDOT</strong> will review:<br />

Preliminary Design<br />

• Scope – is it consistent with TIP application?<br />

• Eligibility - to ensure plans meet intent of program<br />

• Utility impacts - to help ensure no delays will occur<br />

• Environmental - to ensure all applicable clearances are<br />

in progress/obtained<br />

• Impacts to any <strong>MoDOT</strong> route.


Right of Way<br />

•Submit RW plans after prelim.<br />

plans are approved<br />

•Easements = right of way<br />

Can’t start acquiring until:<br />

•Environmental approvals (CE and<br />

106) are acquired<br />

•RW plans are approved<br />

•Acquisition (A-date) date request is<br />

approved<br />

•Plans and A-date request can be<br />

submitted together


Utilities<br />

Must notify <strong>MoDOT</strong><br />

when any utility will be<br />

impacted<br />

Utility relocations:<br />

• If owned by LPA, must<br />

submit estimate<br />

• If not owned by LPA,<br />

must submit<br />

agreement with utility<br />

company


Utilities<br />

Want federal reimbursement for relocation work?<br />

• 106 and CE approval must first be approved<br />

• Submit estimate or executed agreement to <strong>MoDOT</strong><br />

• Work cannot begin until after <strong>MoDOT</strong> approves


Supplemental Agreements<br />

(SA) to ESCs<br />

• Must notify <strong>MoDOT</strong> of the need for an SA<br />

• <strong>MoDOT</strong> will review to ensure it is necessary<br />

and scope is within original RFQ scope<br />

• <strong>MoDOT</strong> will give verbal notice to proceed<br />

• Still need to strive to meet original DBE goal<br />

• Cannot submit invoices for SA until after FHWA<br />

approves


‐<br />

Final Plans, Specifications and<br />

Estimates (PSE)<br />

<strong>MoDOT</strong> will review to check:<br />

•Scope<br />

•ADA compliance<br />

•Eligibility<br />

•TIP to ensure project is listed in correct fiscal year<br />

• Impact to <strong>MoDOT</strong> route<br />

• and…..


Final Plans, Specifications and<br />

Estimates (PSE)<br />

<strong>MoDOT</strong> will review to check:<br />

• Bid proposal to ensure all federal requirements are<br />

included (number all pages in proposal please)<br />

• Ensure construction engineering (CE) is performed by<br />

qualified personnel.<br />

• Type of work so DBE goal can be assigned<br />

• RW is clear<br />

• Environmental clearances


PSE Checklist – Fig 136.9.1


Bid Proposal Boilerplate<br />

Figure 136.9.3


ADA Requirements<br />

- <strong>MoDOT</strong> reviews – now only performed if on <strong>MoDOT</strong> route<br />

- ADA Checklist – Figure 136.9.4<br />

- ADA Certification – Figure 136.9.12<br />

- ADA JSP – LPA Website


Job Special Provisions


Final Plans, Specifications<br />

and Estimates (PSE)<br />

Construction Engineering (CE)<br />

- If want federal reimbursement, must request now<br />

- Can be done by consultant or by Local Forces


Construction Authorization<br />

(Authority to Advertise for Bids)<br />

<strong>MoDOT</strong> will issue formal approval letter<br />

LPA advertises for bid and ensures:<br />

• DBE Goal included in bid documents<br />

• Ad is placed on <strong>MoDOT</strong>’s website and local newspaper<br />

• Ad is in paper in vicinity of project<br />

• Is advertised once for 21 days prior to bid opening


Bid Opening & Award<br />

• LPA publicly opens bids<br />

• Requests <strong>MoDOT</strong> to concur<br />

with award<br />

• Must award to lowest<br />

responsive, responsible<br />

bidder<br />

• Award request and bid info<br />

emailed to <strong>MoDOT</strong> Central<br />

Office


Reimbursement Requests for<br />

Consultant Work<br />

• LPA must submit for reimbursable work<br />

• Reimbursement for actual costs incurred<br />

• Must use sample invoice in Manual<br />

• Must include supporting documentation<br />

• Submit regularly as work progresses<br />

• Reimbursement occurs 2-4 weeks after submittal