Federal-Aid Design<br />
Process Overview<br />
Gregg Wilhelm<br />
<strong>MoDOT</strong> Local Programs Design Engineer
Local Programs Design Staff<br />
St. Louis District<br />
Gregg Wilhelm, Local Program Design Engineer (314) 453‐1832;<br />
Gregory.Wilhelm@modot.mo.gov<br />
Area of responsibility: St. Louis City<br />
Laura Ellen, District Design Liaison ‐ (314) 275‐1542;<br />
Laura.Ellen@modot.mo.gov<br />
Area of responsibility: North St. Louis County and St. Charles<br />
County<br />
Tom McCloskey, District Design Liaison ‐ (314) 453‐1831;<br />
Thomas.McCloskey@modot.mo.gov<br />
Area of responsibility: Franklin County and Jefferson County<br />
Jim Schmidt, District Design Liaison ‐ (314) 453‐5082;<br />
James.Schmidt@modot.mo.gov<br />
Area of responsibility: Southwest St. Louis County
•LPA Manual online at:<br />
http://www.modot.mo.gov/business/lpa/lpamanual.htm<br />
• <strong>MoDOT</strong> approval needed before starting reimbursable work
Person in responsible charge<br />
Person in responsible charge:<br />
• must be a full time employee of<br />
the LPA<br />
• cannot be a consultant hired by<br />
the LPA<br />
• is the person accountable for the<br />
project
LPA Basic Training
Conflict of Interest<br />
Consultants and TIP applications<br />
•If prepared without getting fairly paid, consultant cannot be<br />
considered for selection for the design contract.<br />
•If prepared with getting fairly paid, all project documents must be<br />
made available to all interested firms.
Conflict of Interest<br />
Consultants and Request For Qualifications<br />
•If consultant helps develop RFQ, regardless of payment, they<br />
WILL NOT be eligible for the next phase of the project.<br />
• Figure 136.4.13 – nine page Q&A on consultant services
Project Programming<br />
•Federal Project Number<br />
assigned<br />
•Environmental review<br />
conducted<br />
•<strong>MoDOT</strong> will notify LPA of<br />
environmental approvals<br />
needed
Federal-Aid Program Agreements<br />
• Agreements for each<br />
funding type<br />
• Outlines funding amount,<br />
type, and responsibilities<br />
• Enabling ordinance<br />
required for cities,<br />
1 st class counties<br />
• Per ordinance, only<br />
certain personnel can<br />
sign agreement
Engineering Selection Process<br />
Request for Qualifications (RFQ)<br />
• Must submit to <strong>MoDOT</strong> for review/approval<br />
• Recommend sample shown on <strong>MoDOT</strong> website<br />
• Scope must be consistent with project’s TIP<br />
application<br />
• Will be reviewed for a DBE goal<br />
• Must be posted on <strong>MoDOT</strong>’s website at least 14 days
Engineering Selection Process
Engineering Selection Process<br />
Qualification Based Selection (QBS)<br />
• Must select most qualified firm<br />
using criteria in RFQ<br />
• Price CANNOT be a factor in<br />
selection<br />
• Negotiate price after most<br />
qualified firm selected<br />
• Firm must be on <strong>MoDOT</strong> preapproved<br />
list
Engineering Selection Process<br />
Engineering Services Contract (ESC)<br />
• Must use standard contract in<br />
manual<br />
• Contract scope can include<br />
design and construction<br />
inspection costs<br />
• Work cannot begin until<br />
<strong>MoDOT</strong> approves contract
Preliminary Design<br />
If want to use own design staff, must first receive<br />
<strong>MoDOT</strong> and FHWA approval<br />
Design preliminary plans in accordance with:<br />
• Applicable design guidelines<br />
• ADA<br />
• MUTCD<br />
Submit all environmental clearances obtained<br />
thus far
<strong>MoDOT</strong> will review:<br />
Preliminary Design<br />
• Scope – is it consistent with TIP application?<br />
• Eligibility - to ensure plans meet intent of program<br />
• Utility impacts - to help ensure no delays will occur<br />
• Environmental - to ensure all applicable clearances are<br />
in progress/obtained<br />
• Impacts to any <strong>MoDOT</strong> route.
Right of Way<br />
•Submit RW plans after prelim.<br />
plans are approved<br />
•Easements = right of way<br />
Can’t start acquiring until:<br />
•Environmental approvals (CE and<br />
106) are acquired<br />
•RW plans are approved<br />
•Acquisition (A-date) date request is<br />
approved<br />
•Plans and A-date request can be<br />
submitted together
Utilities<br />
Must notify <strong>MoDOT</strong><br />
when any utility will be<br />
impacted<br />
Utility relocations:<br />
• If owned by LPA, must<br />
submit estimate<br />
• If not owned by LPA,<br />
must submit<br />
agreement with utility<br />
company
Utilities<br />
Want federal reimbursement for relocation work?<br />
• 106 and CE approval must first be approved<br />
• Submit estimate or executed agreement to <strong>MoDOT</strong><br />
• Work cannot begin until after <strong>MoDOT</strong> approves
Supplemental Agreements<br />
(SA) to ESCs<br />
• Must notify <strong>MoDOT</strong> of the need for an SA<br />
• <strong>MoDOT</strong> will review to ensure it is necessary<br />
and scope is within original RFQ scope<br />
• <strong>MoDOT</strong> will give verbal notice to proceed<br />
• Still need to strive to meet original DBE goal<br />
• Cannot submit invoices for SA until after FHWA<br />
approves
‐<br />
Final Plans, Specifications and<br />
Estimates (PSE)<br />
<strong>MoDOT</strong> will review to check:<br />
•Scope<br />
•ADA compliance<br />
•Eligibility<br />
•TIP to ensure project is listed in correct fiscal year<br />
• Impact to <strong>MoDOT</strong> route<br />
• and…..
Final Plans, Specifications and<br />
Estimates (PSE)<br />
<strong>MoDOT</strong> will review to check:<br />
• Bid proposal to ensure all federal requirements are<br />
included (number all pages in proposal please)<br />
• Ensure construction engineering (CE) is performed by<br />
qualified personnel.<br />
• Type of work so DBE goal can be assigned<br />
• RW is clear<br />
• Environmental clearances
PSE Checklist – Fig 136.9.1
Bid Proposal Boilerplate<br />
Figure 136.9.3
ADA Requirements<br />
- <strong>MoDOT</strong> reviews – now only performed if on <strong>MoDOT</strong> route<br />
- ADA Checklist – Figure 136.9.4<br />
- ADA Certification – Figure 136.9.12<br />
- ADA JSP – LPA Website
Job Special Provisions
Final Plans, Specifications<br />
and Estimates (PSE)<br />
Construction Engineering (CE)<br />
- If want federal reimbursement, must request now<br />
- Can be done by consultant or by Local Forces
Construction Authorization<br />
(Authority to Advertise for Bids)<br />
<strong>MoDOT</strong> will issue formal approval letter<br />
LPA advertises for bid and ensures:<br />
• DBE Goal included in bid documents<br />
• Ad is placed on <strong>MoDOT</strong>’s website and local newspaper<br />
• Ad is in paper in vicinity of project<br />
• Is advertised once for 21 days prior to bid opening
Bid Opening & Award<br />
• LPA publicly opens bids<br />
• Requests <strong>MoDOT</strong> to concur<br />
with award<br />
• Must award to lowest<br />
responsive, responsible<br />
bidder<br />
• Award request and bid info<br />
emailed to <strong>MoDOT</strong> Central<br />
Office
Reimbursement Requests for<br />
Consultant Work<br />
• LPA must submit for reimbursable work<br />
• Reimbursement for actual costs incurred<br />
• Must use sample invoice in Manual<br />
• Must include supporting documentation<br />
• Submit regularly as work progresses<br />
• Reimbursement occurs 2-4 weeks after submittal
Figure 136.4.17 – Sample Invoice for<br />
Consultant Work