PeopleSoft <strong>Upgrade</strong>s<br />

The Big Picture and the Little Details<br />

Presented by: CedarCrestone Managed Services


Topics<br />

‣ <strong>Upgrade</strong> <strong>Overview</strong><br />

Terminology<br />

Initial Pass<br />

Test Moves<br />

Go-Live<br />

‣ Infrastructure<br />

Environments<br />

Backups<br />

Refreshes<br />

‣ Additional Considerations<br />

Development & Migration Strategy<br />

PeopleSoft Apply to Release (Applications Fixes)<br />

PeopleTools Freeze<br />

‣ Q & A


<strong>Upgrade</strong> <strong>Overview</strong> – Terminology<br />

‣ C2 – Chapter 2: Pre-<strong>Upgrade</strong> Functional Setup<br />

‣ C6 – Chapter 6: Post-<strong>Upgrade</strong> Functional Setup<br />

‣ IP – Initial Pass<br />

‣ TM – Test Move<br />

‣ GL – Go Live<br />

‣ SRC DB – Source DB for upgraded tools definitions<br />

‣ TGT DB – Target DB; the upgrade database


<strong>Upgrade</strong> <strong>Overview</strong> – Initial Pass<br />

‣ Plan, Build, Execute<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

Plan the upgrade<br />

Install the software<br />

Pre-upgrade functional setup/audits (C2)<br />

Technical upgrade – upgrade PeopleTools<br />

Generate and review compare reports<br />

Complete technical upgrade – Deliver TST<br />

Post-upgrade functional setup (C6)<br />

Patch/Fix<br />

Deliver DEV environment<br />

Create & maintain Go Live task list**<br />

** Post-IP ongoing activity


<strong>Upgrade</strong> <strong>Overview</strong> – Test Moves<br />

‣ Test the planned Go-Live processes<br />

Subset of Initial Pass processes<br />

Plan the <strong>Upgrade</strong><br />

Install the Software<br />

Functional setup and data audits (subset)<br />

Technical upgrade (subset)<br />

Run and Review Compare Reports<br />

Complete technical upgrade (subset)<br />

Complete functional setup (subset)<br />

Continue Testing<br />

• Unit, System, Parallel<br />

Continue to maintain Go-Live task list


<strong>Upgrade</strong> <strong>Overview</strong> – Go Live<br />

‣ Final Move to Production<br />

Back up production<br />

<strong>Upgrade</strong> Production in place ** - OR -<br />

Create copy of production on new release<br />

production box **<br />

Run same subset of processes as test moves<br />

Apply go-live checklist tasks<br />

Final user verification test<br />

Communicate to user base<br />

New Release Live in Production<br />

** which method to use to be determined later


Initial Pass – A Picture (Part 1)<br />

UPG DB<br />

OldRel Demo DB<br />

UPG DB<br />

NewRel Uprader<br />

DMU DB<br />

1. Execute PreUpg Functional tasks<br />

on UPG<br />

2. Full DB Compare UPG to oldrel<br />

DMO – creates UPGCUST Project<br />

3. If UPG LastUpdOprID <br />

PPLSOFT, assumes customization<br />

4. Remove all non-custom objects<br />

from UPGCUST project<br />

5. UPGCUST Project Compare from UPG to<br />

NewRel <strong>Upgrade</strong>r DMU DB<br />

6. Generate compare reports<br />

7. Review compare reports; select ‘custom’<br />

objects to bring forward into 9.2<br />

8. <strong>Upgrade</strong>r copies custom objects from UPG to<br />

DMU<br />

9. Export all newrel DMU tools objects + the<br />

custom objects pushed from UPG to DMU;<br />

then import those into UPG<br />

10. Now, UPG is upgraded with 9.2 object<br />

definitions<br />

11. Complete technical upgrade on UPG (SQL<br />

Builds, Data Conversion, etc)


Initial Pass – A Picture (Part 2)<br />

NewRel Client<br />

DEMO DB<br />

UPG DB<br />

NewRel TST DB<br />

P/F team begins applying<br />

MP’s and bundles to 9.2<br />

DEM toward end of IP<br />

12. DB Copy UPG to TST<br />

13. Complete Post-<strong>Upgrade</strong><br />

Functional Tasks in TST<br />

14. P/F applies MP’s & Bundles<br />

in TST after Post-<strong>Upgrade</strong><br />

Functional Tasks<br />

15. After P/F is complete, DB<br />

Copy TST to DEV<br />

NewRel DEV DB


Test Moves – A Picture<br />

TST<br />

Test Env<br />

UPG<br />

TST is<br />

refreshed<br />

from UPG<br />

after each<br />

TM<br />

Test Moves<br />

COP2-n<br />

Export <strong>Upgrade</strong>d<br />

Tools Objects<br />

from TST<br />

MVPRD.dat<br />

TST is SRC DB<br />

for TM1 -<br />

GoLive


Go-Live – A Picture<br />

New Rlse<br />

PRD<br />

TM3<br />

MVPRD.dat<br />

1. Backup oldrel PRD & either copy to what will be<br />

NewRel PRD or <strong>Upgrade</strong> in Place<br />

2. Complete pre-upgrade functional tasks in PRD<br />

3. Import tools objects to PRD<br />

4. Complete Technical <strong>Upgrade</strong> on PRD<br />

5. Complete post-upgrade functional tasks & final<br />

testing/validation<br />

6. Communication – System is live on 9.2


Infrastructure<br />

‣ Environments<br />

‣ Backups<br />

‣ Refreshes


Infrastructure - Environments<br />

‣ Old Release Environment (UPG)<br />

<br />

<br />

Required to run pre-upgrade functional tasks<br />

All services (app/batch/web) running on NT/Terminal Server<br />

‣ New Release Environments<br />

<br />

<br />

<br />

<br />

<br />

Demo (DEM), Development (DEV), Test (TST)<br />

Each has its own codeline for migration testing<br />

Unix-based App/Batch Server + NT Batch Server<br />

Crystal and NVisions run on NT Batch Server; normally all<br />

other code runs from UNIX (COBOL, AppEngine, SQR)<br />

App Engines and SQR can run from either NT or UNIX<br />

schedulers with UNIX being the preferred server. COBOL is<br />

only executable on UNIX.<br />

New Release Production codeline is created from<br />

copy of Test


Infrastructure - Backups<br />

‣ Cold Backups<br />

Initial Pass<br />

• After Pre-<strong>Upgrade</strong> functional setup<br />

• After tools upgrade<br />

• After UPGCUST Compare<br />

• After <strong>Upgrade</strong> copy<br />

• Before Data Conversion<br />

• After Data Conversion<br />

• After completing initial pass


Infrastructure - Backups<br />

‣ Cold Backups<br />

Test Moves<br />

• After Pre-<strong>Upgrade</strong> functional setup<br />

• Before Data Conversion<br />

• After Data Conversion (eliminated by TM3)<br />

• Before application fix scripts (eliminated by TM3)<br />

• After completing test move<br />

‣ Hot Backups<br />

DEV & TST - weekly


Infrastructure – Refreshes<br />

‣ Refresh UPG from CurRel PRD each pass<br />

‣ Build DEV from TST after Initial Pass**<br />

‣ Refresh TST from UPG after each TM pass<br />

** To preserve ongoing development work, DEV is created from TST after IP and is<br />

NOT refreshed thereafter


Additional Considerations<br />

‣ Development and Migration Strategy<br />

‣ PeopleSoft Apply to Release (Application)<br />

Fixes<br />

‣ PeopleTools Freeze


Additional Considerations<br />

Development & Migration Strategy<br />

‣ Reapply mods/new<br />

development<br />

• Online & Batch<br />

‣ Unit Testing<br />

• Pages work;<br />

retrieve data<br />

• SQR’s run<br />

DEV<br />

Development<br />

By TM3: DEV = TST<br />

capture all reapp in final test move<br />

(all reapp, online & batch, complete by<br />

TM3)<br />

1-Project Compare & Copy<br />

Move reapps to test env<br />

UPG<br />

NOTE: Migrations to TST<br />

are frozen from the start<br />

to the end of each TM pass<br />

Refresh<br />

TST<br />

User Test<br />

2 - MVPRD.dat<br />

3-Run Test Move then<br />

refresh Test DB<br />

2 - As changes are signed off on<br />

in TST – incorporate them into<br />

the next test move cycle


Additional Considerations<br />

Apply to Release (Application) Fixes<br />

CMS will apply the most current maintenance pack and<br />

all subsequently posted bundles for the new release<br />

after the Initial Pass.<br />

• CMS Patch Fix standards are to apply all available<br />

fixes, both Maintenance Packs and Bundles.<br />

CMS will keep the upgrade environments<br />

(DEM/DEV/TST) in sync with any Regulatory updates<br />

that are applied to the current production environment.<br />

This includes tax updates and any pre/post requisites<br />

only.


Additional Considerations<br />

Apply to Release (Application) Fixes Cont’d<br />

After the Initial Pass, fixes will be applied on an asneeded<br />

basis and only fixes required to fix showstopper<br />

issues will be applied.<br />

No fixes should be applied after the final test move;<br />

database objects should not change before Go-Live.


Additional Considerations<br />

PeopleTools Freeze<br />

PeopleTools must be ‘frozen’ – e.g. halt<br />

peopletools object changes in production - as<br />

soon as the first cut of production is taken<br />

Any Tools change in current release production<br />

after the Initial Pass copy of production will not<br />

‘carry forward’ in future Test Moves<br />

Dual development is required if Tools freeze is not<br />

possible in current release production<br />

• Changes made to production must also be made to<br />

the new release DEV/TST environments


Additional Considerations<br />

PeopleTools Freeze – Cont’d<br />

<br />

<br />

Queries, Trees and Security<br />

• Queries, Trees and Security are considered PeopleTools objects.<br />

• Changes to these objects should be frozen after first COP is<br />

taken for initial pass.<br />

• Changes to these objects in production must be manually<br />

updated to the new release database.<br />

• Option to capture these objects:<br />

• Queries & Trees – add’l fee-based service offering to capture these<br />

as part of one or more test move passes<br />

• Security – UpgLab offers a free (mini) or a fee-based service (more<br />

robust) to capture security changes during one or more test move<br />

passes<br />

Query Access Group Trees<br />

• Custom records will be dropped from PS delivered Query Access<br />

Group Trees<br />

• Recommendation: Place all custom records on a custom query<br />

access group tree


Questions?


The End<br />

Let the <strong>Upgrade</strong> Begin!