Muon Detector Milestones<br />

• 24/32 Endcap Big Wheel sectors done<br />

– Installation in pit starts in Oct<br />

– Small Wheel assembly starts in Oct<br />

• 7/12 TGC1C sectors installed in pit - finish by Sept<br />

• Muon barrel installation ~ 55% complete<br />

– hardest chambers have been installed.<br />

• Barrel toroid cooling<br />

• Barrel MDTs have been readout in cosmic tests<br />

– rate of bottom sector ~ 40 Hz<br />

– combined running with Tilcal and RPC trigger done<br />

• Beam pipe closes 30-Aug-07<br />

<strong>Harvard</strong> DoE Site Visit – 21 August 2006 George Brandenburg – Page 17