Development time-line (estimates)<br />
Conceptual Design Review July 2003<br />
Preliminary Design Review Early 2004<br />
Critical Design Review Mid 2004<br />
Complete instrument tests Late 2005<br />
Delivery to telescope December 2005<br />
The dates in this timeline are current estimates, and assume no interruption in <strong>the</strong><br />
development cycle. Final delivery to telescope will not occur be<strong>for</strong>e delivery of SCUBA-<br />
2 and <strong>the</strong> associated optics.<br />
SCUBA-2 FTS <strong>Requirements</strong>, version 1.0<br />
Page 8 of 8