Document Title: SCUBA2 Polarimeter Risk Assessment ... - JACH
Document Title: SCUBA2 Polarimeter Risk Assessment ... - JACH
Document Title: SCUBA2 Polarimeter Risk Assessment ... - JACH
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
SCUBA-2 <strong>Polarimeter</strong> Project Office<br />
Université de Montréal<br />
Département de physique<br />
B. P. 6128, Succ. Centre-ville<br />
Montréal, Québec<br />
Canada H3C 3J7<br />
Tel: 1-514-343-5816<br />
Fax: 1-514-343-2071<br />
Email: bastien@astro.umontreal.ca<br />
WWW: http://www.astro.umontreal.ca/to_come...<br />
<strong>Document</strong> <strong>Title</strong>:<br />
<strong>SCUBA2</strong> <strong>Polarimeter</strong><br />
<strong>Risk</strong> <strong>Assessment</strong><br />
<strong>Document</strong> Number: SC2/POL/PM500/002<br />
Issue: Version 1.1<br />
Date: 17 th November 2004<br />
<strong>Document</strong><br />
Prepared By:<br />
<strong>Document</strong><br />
Approved By:<br />
<strong>Document</strong><br />
Released By:<br />
Janos Molnar<br />
PLM Project Manager<br />
Pierre Bastien<br />
Project Scientist<br />
Janos Molnar<br />
<strong>SCUBA2</strong> Canadian<br />
Project Manager<br />
Signature and Date: 17 th Nov. 2004<br />
Signature and Date: 17 th Nov. 2004<br />
Signature and Date: 17 th Nov. 2004<br />
The information contained in this document is strictly confidential and is intended for the addressee only.<br />
The unauthorised use, disclosure, copying, alteration or distribution of this document is strictly prohibited and may be unlawful.<br />
SCUBA-2 POL <strong>Risk</strong> <strong>Assessment</strong>, version 1.1 Page 1 of 11
Change Record<br />
Issue Date Section(s) Affected Description of Change/Change<br />
Request Reference/Remarks<br />
0.1 09/10/03 Initial document<br />
0.2 14/10/03 <strong>Risk</strong>s 2, 3 and 5 Additional information added in<br />
preparation for the CoDR<br />
1.1 17/11/04 All changes, additions are shown<br />
in italics<br />
Renamed document, updated for<br />
the PDR<br />
SCUBA-2 POL <strong>Risk</strong> <strong>Assessment</strong>, version 1.1 Page 2 of 11
Introduction<br />
The <strong>Polarimeter</strong> for SCUBA-2 (POL-2) is a medium-risk, high-reward project.<br />
The POL-2 development project has a limited and fixed budget and a much reduced<br />
development cycle due to the late approval of POL-2 by the JCMT Board of Directors as<br />
an essential auxiliary instrument for SCUBA-2. The additional risk, posed by this fact is<br />
still considered manageable by the POL-2 Team.<br />
The Process<br />
After the initial review of the instrument requirements projects typically start with a high<br />
level of risk that is then reduced by the implementation of mitigation steps within the<br />
project plan, changing the requirements or developing a better understanding of the<br />
engineering/programmatic challenges.<br />
To help manage risk the project management team has adopted the standard UK ATC<br />
risk management strategy which:<br />
a) identifies the key risks in the project<br />
b) assigns a hazard (severity) level to each risk on a scale of 1 to 5 (5 is very high<br />
severity and would be terminal to the project if it occurred - infinite schedule<br />
delay).<br />
c) assigns a probability of occurrence of the risk (0 to 4) (5 is > 50% probability), 1<br />
d) multiplies the two numbers to come up with the risk level (Impact)<br />
e) tracks, with regular updates, all risks with a level of 6 or higher (9 is regarded as<br />
high risk)<br />
f) assigns cost and schedule impact to all tracked risks<br />
g) puts in place risk mitigation steps designed to bring the risk down to the<br />
acceptable level, estimates the risk level after the implemented steps and forecasts<br />
the date when the risk will reach the acceptable level and is eliminated<br />
Although Université de Montréal has accumulated significant experience in building<br />
polarimeters, it is possible that with the selected mode of operation some difficult<br />
technical problem might yet be uncovered that would put the delivery date too far back or<br />
require large amounts of new funds to overcome. The risks applicable to the <strong>Polarimeter</strong><br />
will be tracked separately and are described in the following tables.<br />
1 If probability of occurrence is higher, than 0.5, the risk will be treated as certainty and be part of the development plan<br />
SCUBA-2 POL <strong>Risk</strong> <strong>Assessment</strong>, version 1.1 Page 3 of 11
<strong>Risk</strong> Number POL/1 Status Live<br />
Date Logged October 2003 Date Cleared<br />
On Critical Path Yes WBS Ref. No. x.x<br />
Owner<br />
Mike Fich, Gary Davis<br />
Original <strong>Risk</strong> Factor Prob: 5 Severity: 5 Impact (P*I) = 25 Cat = High<br />
Mitigated <strong>Risk</strong> Factor Prob: 1 Severity: 5 Impact = 5 Cat = Medium<br />
Updated Mitigated <strong>Risk</strong> Factor Prob: .5 Severity: 5 Impact = 2.5 Cat = Low<br />
as of Nov.19th<br />
Date when risk is forecast to<br />
be passed:<br />
Apr.2004 -> Apr.2005<br />
Description of risk:<br />
Additional Canadian funding will not be available to complete SCUBA-2 development in its original<br />
configuration, so available funds allocated to <strong>Polarimeter</strong> development will be redirected<br />
Impact on project cost, schedule or quality if risk realised without mitigation:<br />
<strong>Polarimeter</strong> won’t be developed for SCUBA-2<br />
A potential for achieving the best polarimetry in sub-millimetre range won’t be realized for the JCMT user<br />
community<br />
Schedule Delay: none<br />
Cost:<br />
none<br />
Mitigation action:<br />
1. Secure additional funding through OIT<br />
2. Secure additional funding through inviting new partners and or private donations<br />
Hence the re-assessment is that the Probability and Impact have been reduced by 80%.<br />
November 19 th 2004 update:<br />
a. The JCMT Board of directors deemed the polarimeter an essential auxiliary instrumentfor SCUBA-2,<br />
which means that its development won’t be halted to redirect funding to support other SCUBA-2<br />
specific work.<br />
b. Negotiations are ongoing to extend the lifecycle of JCMT, which would open up opportunities for<br />
additional funding by new potential SCUBA-2 users<br />
Hence the probability of discontinued funding for the polarimeter development alone is further reduced.<br />
Impact on project cost, schedule or quality if risk realised with mitigation action:<br />
<strong>Polarimeter</strong> won’t be developed for SCUBA-2<br />
A potential for achieving the best polarimetry in sub-millimetre range won’t be realized for the JCMT user<br />
community<br />
Schedule Delay:<br />
Cost:<br />
none<br />
none<br />
SCUBA-2 POL <strong>Risk</strong> <strong>Assessment</strong>, version 1.1 Page 4 of 11
<strong>Risk</strong> Number POL/2 Status Live<br />
Date Logged October 2003 Date Cleared<br />
On Critical Path Yes WBS Ref. No. x.x<br />
Owner<br />
PB, JM<br />
Original <strong>Risk</strong> Factor Prob: 3 Severity: 3 Impact (P*I) = 9 Cat = High<br />
Mitigated <strong>Risk</strong> Factor Prob: 1 Severity: 3 Impact = 3 Cat = Medium<br />
Updated Mitigated <strong>Risk</strong> Factor Prob: .5 Severity: 3 Impact = 1.5 Cat = Low<br />
as of Nov.19th<br />
Date when risk is forecast to<br />
be passed:<br />
September 2005 -> April 2005<br />
Description of risk:<br />
Manufacture of the sapphire wave-plate by QMC Instruments Co., Cardiff gets significantly delayed<br />
Impact on project cost, schedule or quality if risk realised without mitigation:<br />
Potential for delays in testing of the wave-plate and eventually delivery of the polarimeter.<br />
Schedule Delay: tbd<br />
Cost:<br />
$US 10,000/month<br />
Mitigation action:<br />
1. Keep in close contact with supplier and adjust internal deliveries to minimise impact<br />
2. Explore alternative supplier<br />
3. Use a monochromatic halfwave plate centered in the middle of the 850 µm bandpass. This<br />
would allow a less efficient use of the instrument in one band only. A manufacturer for<br />
that monochromatic wave plate would still be required.<br />
Hence the re-assessment is that the Probability has been reduced by 67%.<br />
November 19 th 2004 update:<br />
QMC signed off on the project plan, which shows the delivery of wave-plate in April 2005<br />
Hence the risk of late wave-plate delivery is further reduced<br />
Impact on project cost, schedule or quality if risk realised with mitigation action:<br />
Schedule Delay:
<strong>Risk</strong> Number POL/3 Status Live<br />
Date Logged October 2003 Date Cleared<br />
On Critical Path Yes WBS Ref. No. x.x<br />
Owner<br />
PB<br />
Original <strong>Risk</strong> Factor Prob: 5 Severity: 1 Impact = 5 Cat = Medium<br />
Mitigated <strong>Risk</strong> Factor Prob: 2 Severity: 1 Impact = 2 Cat = Low<br />
Updated Mitigated <strong>Risk</strong> Factor Prob: 4 Severity: 1 Impact = 4 Cat = Medium<br />
as of Nov.19th<br />
Date when risk is forecast to<br />
be passed:<br />
April 2004 -> May 2005<br />
Description of risk:<br />
Full potential of <strong>SCUBA2</strong> polarimetry is not utilised due to excessive loss through the sapphire wave-plate at<br />
ambient temperature at 450 µm<br />
Impact on project cost, schedule or quality if risk realised without mitigation:<br />
Lost sensitivity<br />
Schedule Delay: none<br />
Cost:<br />
none<br />
Mitigation action:<br />
1. Build polarimeter’s own cryostat<br />
Hence the re-assessment is that the probability has been reduced by 60%<br />
November 19 th 2004 update:<br />
Preliminary research by UWC indicated that putting the wave-plate into its own cryostat is not helping so<br />
the probability of this happening has increased, but its severity has been reduced<br />
There is additional research going on at UWC, which if successful, might eliminate the loss problem<br />
altogether<br />
Hence the risk of excessive loss at 450µm has gone up.<br />
Impact on project cost, schedule or quality if risk realised with mitigation action:<br />
Schedule Delay:<br />
Cost:<br />
none<br />
$US 75,000 -> none<br />
SCUBA-2 POL <strong>Risk</strong> <strong>Assessment</strong>, version 1.1 Page 6 of 11
<strong>Risk</strong> Number POL/4 Status Live<br />
Date Logged October 2003 Date Cleared November 04<br />
On Critical Path Yes WBS Ref. No. x.x<br />
Owner<br />
PB<br />
Original <strong>Risk</strong> Factor Prob: 3 Severity: 2 Impact = 6 Cat = High<br />
Mitigated <strong>Risk</strong> Factor Prob: 1 Severity: 2 Impact = 4 Cat = Low<br />
Updated Mitigated <strong>Risk</strong> Factor Prob: 0 Severity: 1 Impact = 0 Cat = 0<br />
as of Nov.19th<br />
Date when risk is forecast to<br />
be passed:<br />
April 2004<br />
Description of risk:<br />
Not getting all the technical information about the mechanical mounting of the polarization module –<br />
information coordinated by ATC<br />
Impact on project cost, schedule or quality if risk realised without mitigation:<br />
Late information will lead to delays in the project<br />
Incomplete information may result in redesign<br />
Schedule Delay: 3 months<br />
Cost: $US 30,000<br />
Mitigation action:<br />
1. Establish close working relationship with ATC and UWC Mechanical Design group<br />
2. Get <strong>Polarimeter</strong> Design Reviewed and accepted by ATC and UWC Mechanical Design<br />
group<br />
3. Establish process by which any mechanical design change to the optics and cryostat has to<br />
be acknowledged by the <strong>Polarimeter</strong> design prime<br />
Hence the re-assessment is that the probability has been reduced by 67%<br />
November 19 th 2004 update:<br />
We have gotten sufficient information on the available to us space for the polarimeter. We are not quite<br />
pleased with the allocated space envelop, which by itself introduces new risks, but at least has eliminated<br />
this one.<br />
Hence the risk of late design information has been eliminated.<br />
Impact on project cost, schedule or quality if risk realised with mitigation action:<br />
Schedule Delay: 1.0 months -> 0<br />
Cost: $US 10,000 -> 0<br />
SCUBA-2 POL <strong>Risk</strong> <strong>Assessment</strong>, version 1.1 Page 7 of 11
<strong>Risk</strong> Number POL/5 Status Live<br />
Date Logged October 2003 Date Cleared<br />
On Critical Path Yes WBS Ref. No. x.x<br />
Owner<br />
PB<br />
Original <strong>Risk</strong> Factor Prob: 3 Severity: 3 Impact = 9 Cat = High<br />
Mitigated <strong>Risk</strong> Factor Prob: 3 Severity: 1 Impact = 3 Cat = low<br />
Updated Mitigated <strong>Risk</strong> Factor Prob: 2 Severity: 1 Impact = 2 Cat = low<br />
as of Nov.19th<br />
Date when risk is forecast to<br />
be passed:<br />
May 2005<br />
Description of risk:<br />
Getting all the technical information for running the polarization module in step with the rest of SCUBA-2 on<br />
time<br />
Impact on project cost, schedule or quality if risk realised without mitigation:<br />
Delay in the project<br />
Schedule Delay: tbd<br />
Cost:<br />
$US10,000/month<br />
Mitigation actions:<br />
By ensuring that the position of the wave plate (from the encoder) is recorded in the header of each individual<br />
image will guarantee that the polarization module will run in step with the rest of SCUBA-2<br />
Hence the re-assessment is that the probability remains significant, but the severity has been reduced to a<br />
minimal level<br />
November 19 th 2004 update:<br />
We have gotten sufficient information on the available to us space for the polarimeter. We are not quite<br />
pleased with the allocated space envelo, which by itself introduces new risks, but at least has eliminated<br />
this one.<br />
Hence the risk of late design information has been eliminated.<br />
Impact on project cost, schedule or quality if risk realised with mitigation action:<br />
Schedule Delay: none<br />
Cost: $0<br />
SCUBA-2 POL <strong>Risk</strong> <strong>Assessment</strong>, version 1.1 Page 8 of 11
<strong>Risk</strong> Number POL/6 Status Live<br />
Date Logged June 2003 Date Cleared<br />
On Critical Path Yes WBS Ref. No. n/a<br />
Owners<br />
PB<br />
Original <strong>Risk</strong> Factor Prob: 2 Severity: 3 Impact = 6 Cat = High<br />
Mitigated <strong>Risk</strong> Factor Prob: 1 Severity: 2 Impact = 2 Cat = Low<br />
Date when risk is forecast to<br />
be passed:<br />
December 2005<br />
Description of risk:<br />
Critical support staff leaves the project<br />
Impact on project cost, schedule or quality if risk realised without mitigation:<br />
Design complexity requires significant learning curve for new staff to get up to speed.<br />
Worst case scenario would be if critical staff left at the start of module test and system integration<br />
Schedule Delay: 3 months<br />
Cost: $US 30,000<br />
Mitigation action:<br />
1. Create stable and rewarding work environment.<br />
2. Minimise work overload and eliminate burn-out.<br />
3. Demand detailed and clear design documentation at every stage of the design<br />
4. Store all design information in clearly structured and easy to use secure database<br />
Impact on project cost, schedule or quality if risk realised with mitigation action:<br />
Schedule Delay: 1 month<br />
Cost: $US 10,000<br />
SCUBA-2 POL <strong>Risk</strong> <strong>Assessment</strong>, version 1.1 Page 9 of 11
<strong>Risk</strong> Number POL/7 Status Live<br />
Date Logged November 2004 Date Cleared<br />
On Critical Path Yes WBS Ref. No. n/a<br />
Owners<br />
PB<br />
Original <strong>Risk</strong> Factor Prob: 4 Severity: 2 Impact = 8 Cat = High<br />
Mitigated <strong>Risk</strong> Factor Prob: 1 Severity: 2 Impact = 2 Cat = Low<br />
Date when risk is forecast to be<br />
passed:<br />
May 2005<br />
Description of risk:<br />
Unexpected change in wave-plate position (relative to cryostat window) requires more complex mechanical<br />
design if we want to maintain the maximum possible efficiency for polarimetry.<br />
Impact on project cost, schedule or quality if risk realised without mitigation:<br />
Full potential and efficiency of SCUBA-2 <strong>Polarimeter</strong> won’t be achieved<br />
Schedule Delay: 0<br />
Cost: 0<br />
Mitigation action:<br />
1. Develop more elaborate mechanical mounting of the waveplate.<br />
2. Hire experienced mechanical design contractor to develop reliable and safe mounting mechanism.<br />
3. Search for larger sized wave-plate<br />
4. Search for alternative wave-plate implementation<br />
Impact on project cost, schedule or quality if risk realised with mitigation action:<br />
Schedule Delay: 1 month<br />
Cost: $US 10,000<br />
SCUBA-2 POL <strong>Risk</strong> <strong>Assessment</strong>, version 1.1 Page 10 of 11
<strong>Risk</strong> Number POL/8 Status Live<br />
Date Logged November 2004 Date Cleared<br />
On Critical Path Yes WBS Ref. No. n/a<br />
Owners<br />
PB<br />
Original <strong>Risk</strong> Factor Prob: 4 Severity: 2 Impact = 8 Cat = High<br />
Mitigated <strong>Risk</strong> Factor Prob: 2 Severity: 2 Impact = 4 Cat = Medium<br />
Date when risk is forecast to be<br />
passed:<br />
May 2005<br />
Description of risk:<br />
Attainable observing modes (due to mechanical, control or computational limitations) don’t allow maximum<br />
possible efficiency for polarimetry.<br />
Impact on project cost, schedule or quality if risk realised without mitigation:<br />
Full potential and efficiency of SCUBA-2 <strong>Polarimeter</strong> won’t be achieved<br />
Schedule Delay: 0<br />
Cost: 0<br />
Mitigation action:<br />
1. Develop option of POL-2 providing RTS signal for the SCUBA-2 and telescope control complex.<br />
2. Enhance existing or develop new data processing algorithms for polarimetry.<br />
3. Accept unavoidable limitations<br />
Impact on project cost, schedule or quality if risk realised with mitigation action:<br />
SCUBA-2 <strong>Polarimeter</strong> performance and efficiency will be closer to their full potential at the price of<br />
Schedule Delay: 2 month<br />
Cost: $US 20,000<br />
SCUBA-2 POL <strong>Risk</strong> <strong>Assessment</strong>, version 1.1 Page 11 of 11