PROJECT DURATION:<br />
• Analysis-18 Hrs.<br />
• Design – 10Hrs.<br />
• Development –26Hrs<br />
• Testing – 5Hrs<br />
• Documentation -11hrs<br />
Analysis<br />
Design Development Testing Documentation<br />
20 21 22 23 24 25 26 27 28 29 1 2 3 4 5 6 7 8 9 10 11 12<br />
Each phase has completed as shown by the lines.<br />
The team would meet after every 6 working days and evaluate their progress. Detailed progress<br />
plan to be drawn to access progress of the project.<br />
As it can be noticed that there are overlapping of process this is kept because certain process can<br />
go hand in hand with other processes.