South Gordon Sanitary Trunk Pre-Design<br />
CONCEPTUAL ROUTING REPORT - ROUTING OPTION #2<br />
Class 'C' Construction Cost Estimate<br />
ITEM DESCRIPTION UNIT<br />
UNIT PRICE QUANTITY AMOUNT<br />
Section 01535 - Temporary Facilities<br />
1535.1 Dewatering for excavations lin.m. $ 150.00 3,750 $ 562,500<br />
Section 01561 - Environmental Protection<br />
1561.1 Environmental protection and compensation L.S. $ 50,000<br />
Section 01570 - Traffic Regulation<br />
1570.1 Traffic management week $ 3,500.00 60 $ 210,000<br />
Section 02070 - Sitework Demolition and Removal<br />
2070.1<br />
Remove and dispose <strong>of</strong> sanitary sewer pipe, regardless <strong>of</strong> diameter or<br />
depth<br />
lin.m. $ 100.00 293 $ 29,300<br />
2070.2 Remove and dispose <strong>of</strong> manholes each $ 900.00 2 $ 1,800<br />
Section 02223 - Excavating, Trenching and Backfilling<br />
2223.1 Common excavation, <strong>of</strong>fsite disposal cu. m $ 14.00 78,250 $ 1,095,500<br />
2223.2<br />
Removal and replacement <strong>of</strong> unsuitable trench backfill with import<br />
material<br />
cu. m $ 30.00 47,400 $ 1,422,000<br />
Section 02233 - Granular Base<br />
2233.1 Granular base, 25 mm minus crushed gravel<br />
75mm thickness (roadway) sq. m $ 6.00 31,786 $ 190,700<br />
Section 02234 - Granular Subbase<br />
2234.1 Granular subbase, 75mm minus crushed gravel<br />
535mm thickness sq. m $ 25.00 31,786 $ 794,700<br />
Section 02512 - Hot Mix Asphalt Concrete Paving<br />
2512.1 Asphalt lower course, 60 mm sq. m $ 13.00 34,036 $ 442,500<br />
2512.2 Asphalt surface course, 40mm sq. m $ 9.00 34,036 $ 306,300<br />
Section 02550 - Asphalt Removal<br />
2550.1 Sawcut, remove and dispose asphalt paving (all thicknesses) sq.m $ 4.00 34,036 $ 136,100<br />
Section 02666 - Waterworks<br />
2666.1 Remove and replace perpendicular AC watermain each $ 1,000.00 5 $ 5,000<br />
U:\Projects_KEL\0467\0384\01\D-Drafting-Design-Analysis\D3-Models-Spreadsheets\Spreadsheets\2009-10-09 South Gordon <strong>Conceptual</strong> <strong>Routing</strong> <strong>Report</strong> Schedule <strong>of</strong> Quantities.xls