Memorandum of Capacity<br />

allocation <strong>between</strong> <strong>Baltic</strong> TSOs<br />

• Signed on 22nd of April<br />

‣ Starting January 1st 2011 – implicit auctions <strong>between</strong><br />

NPS price areas in <strong>Baltic</strong>'s<br />

CONGESTION<br />

MANAGEMENT in <strong>Baltic</strong>s<br />

‣30th of June NPS has to announce the new price areas<br />

opening<br />

‣Estonian experience: political decision (legislation), ITsystems,<br />

Agreements, NPS conditions<br />

‣ Starting January 1st 2011 - cross-border capacity<br />

optimization with 3rd countries, implemented by NPS<br />

(today the method on Estonian – Latvian border)<br />

Ingrid Arus<br />

Manager of Electricity Markets<br />

Department


CM <strong>between</strong> Estonia-Latvia<br />

New capacity allocation principles:<br />

‣ 01.04.2010 – 31.12.2010<br />

‣Bilateral trade: explicit auction; nomination D-2<br />

‣PEX Trade: capacity optimization method; D-1<br />

‣ Starting 01.01.2011<br />

‣If there are price areas in Latvia and in Lithuania: Implicit<br />

auction: managed by NPS


Estlink 1<br />

• Cable in commercial use until 2013, when it will be bought out by<br />

transmission network operators<br />

NPS <strong>Baltic</strong> project was launched in November 2007 in order for<br />

Elering and Fingrid to rent or buy a part of or the entire cable for<br />

allocation on NPS<br />

• Aim:<br />

‣ A base for a joint <strong>Baltic</strong> and Nordic energy market<br />

‣ A price area at the southern end of the Estlink 1 cable<br />

‣ More efficient use of the Estlink 1 cable<br />

‣ A more reliable market price for electricity<br />

THE STATUS TODAY:<br />

Estlink 1 cable rented by Elering and Fingrid:<br />

EE – FI: 262.5 MW<br />

FI – EE: 252.7 MW<br />

Capacity is allocated by NPS.


Capacity Optimization method<br />

Cross-border<br />

capacity limits<br />

for PX Trade<br />

(XB max)<br />

NPS SESAM<br />

Cross-border bids<br />

(NPS)<br />

All cross-border import and export bids<br />

are accepted for spot-price calculation<br />

Bids to PX Trade<br />

Imp < XB max (import)<br />

Exp < XB max (export)<br />

YES<br />

Bid- cutting until<br />

Imp = XB max (import) and<br />

Exp = XB max (export)<br />

Accepted cross-border bids<br />

for spot-price calculation<br />

NO


Explicit auction<br />

• First auction for 21st week: capacities 60 MW from Estonia to Latvia<br />

and 70 MW from Latvia to Estonia<br />

‣ 5 participants<br />

‣ Results: sold both directions: E-L: price 3,10 EUR/MW; L-E: price: 0,15<br />

EUR/MW; bottleneck income: 33 012 EUR<br />

• Participants: have to register in Auction office<br />

‣ Completed and signed Registration Form<br />

• Weekly<br />

‣ Friday: capacity MW<br />

‣ Tuesday:<br />

‣ deadline (12:00 CET) for bids (capacity, price) encrypted, protected<br />

document: explicit@elering.ee<br />

‣ 12:00 – 13:00 (CET) passwords<br />

‣ results: aimed before 14:00 (CET), but in any case before 17:00 (CET)<br />

‣ Nomination: D-2 planning phase


Implicit auction <strong>between</strong> price areas<br />

managed by NPS (starting 2011)<br />

NPS BEMIP project:<br />

‣ Kick-off meeting 02.2010<br />

‣ Goal:<br />

‣ Expanding the NPS market area<br />

‣ to all <strong>Baltic</strong> countries<br />

‣ Intra-day market<br />

‣ New price area should be opened when<br />

conditions are ready for market opening.<br />

‣ Decision by local TSO and NPS<br />

Implicit auction <strong>between</strong> price areas<br />

managed by NPS<br />

‣ NPS Estonia<br />

‣ NPS Latvia<br />

‣ NPS Lithuania<br />

<strong>Baltic</strong> TSOs among the owners of NPS


Memorandum of Capacity<br />

allocation <strong>between</strong> <strong>Baltic</strong> TSOs<br />

• Signed on 22nd of April<br />

‣ Starting January 1st 2011 – implicit auctions <strong>between</strong><br />

NPS price areas in <strong>Baltic</strong>'s<br />

‣30th of June NPS has to announce the new price areas<br />

opening<br />

‣Estonian experience: political decision (legislation), ITsystems,<br />

Agreements, NPS conditions<br />

‣ Starting January 1st 2011 - cross-border capacity<br />

optimization with 3rd countries, implemented by NPS<br />

(today the method on Estonian – Latvian border)


<strong>Congestion</strong> <strong>Management</strong><br />

on Latvia – Lithuania border<br />

Until 1 st January, 2011 the capacity optimisation method will be<br />

used if there is congestion <strong>between</strong> Lithuania and Latvia for<br />

the agreed ATC value. Agreed ATC will be used only for<br />

electricity trade organised by Baltpool (Lithuanian Power<br />

Exchange).<br />

From 1 st January, 2011 Implicit auction: managed by NPS


<strong>Congestion</strong> <strong>Management</strong><br />

on Belarus – Lithuania border<br />

Until 1 st January, 2011 the capacity optimisation method will be<br />

used for ATC agreed <strong>between</strong> TSOs and performed by Baltpool<br />

(Lithuanian Power Exchange). The methodology for setting<br />

ATC on Lithuania and Belarus border is based on N-1 principle<br />

supported by emergency reserve maintained in Lithuanian<br />

power system.<br />

From 1 st January, 2011 common market based cross border<br />

capacity optimization method for trade with 3rd countries<br />

must be applied and implemented by NPS.


<strong>Congestion</strong> <strong>Management</strong><br />

on Latvia – Lithuania and Lithuania-Belarus border<br />

today<br />

All bids to<br />

sell or to<br />

buy from<br />

customers<br />

SESAM<br />

Cross<br />

border<br />

bids/offers<br />

PX<br />

Im


Conclusions<br />

<strong>Congestion</strong> <strong>Management</strong><br />

in <strong>Baltic</strong> <strong>states</strong> from 1 st of January 2011<br />

Market based congestion management method (implicit auction)<br />

must be started <strong>between</strong> the <strong>Baltic</strong> price areas and managed by NPS.<br />

Common market based cross border capacity optimization<br />

method for trade with 3rd countries must be applied and implemented<br />

by NPS.


To Do List, Capacity<br />

Rules:<br />

Common NTC and ATC calculations rules<br />

Russian transit Rules (Kaliningrad, Belarus)<br />

Common trade principles with third countries<br />

Common outage planning<br />

Agreements:<br />

General Agreement concerning temporary transmission service<br />

Counter Trade agreement<br />

PEX service agreement and open supply for PEX<br />

Service agreement on congestion income<br />

Data publication agreement