29.04.2014 Views

appendix c occupational health and safety - sanral

appendix c occupational health and safety - sanral

appendix c occupational health and safety - sanral

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Scaffolding Supervisor (Construction Regulation 14)<br />

Stacking & Storage Supervisor (Construction Regulation 26)<br />

Structures Supervisor (Construction Regulation 9)<br />

Suspended Platform Supervisor (Construction Regulation 15)<br />

Tunnelling Supervisor (Construction Regulation 13)<br />

Vessels under Pressure Supervisor<br />

(Vessels under Pressure<br />

Regulations)<br />

Working on/next to Water Supervisor (Construction Regulation 24)<br />

Welding Supervisor (General Safety Regulation 9)<br />

In addition SANRAL requires that a Traffic Safety Officer be appointed (see COLTO Section 1500).<br />

The above appointments shall be in writing <strong>and</strong> the responsibilities clearly stated together with the<br />

period for which the appointment is made. This information shall be communicated <strong>and</strong> agreed with<br />

the appointees. Notice of appointments shall be submitted to SANRAL. All changes shall also be<br />

communicated to SANRAL.<br />

The Principal Contractor shall, furthermore, provide SANRAL with an organogram of all Contractors<br />

that he/she has appointed or intends to appoint <strong>and</strong> keep this list updated <strong>and</strong> prominently displayed<br />

on site. Where necessary, or when instructed by an inspector of the Department of Labour, the<br />

Principal Contractor shall appoint a competent Construction Safety Officer.<br />

2.3.3 Designation of OH&S Representatives (Section 17 of the OH&S Act)<br />

Where the Principal Contractor employs more than 20 (twenty) persons (including the employees of<br />

other Contractors (sub-contractors) he has to appoint 1 (one) OH&S representatives for every 50<br />

(fifty) employees or part thereof. General Administrative Regulation 6 requires that the appointment<br />

or election <strong>and</strong> subsequent designation of the OH&S representatives be conducted in consultation<br />

with employee representatives or employees. (Section 17 of the Act <strong>and</strong> General Administrative<br />

Regulation 6 & 7). OH&S representatives shall be designated in writing <strong>and</strong> the designation shall<br />

include the area of responsibility of the person <strong>and</strong> term of the designation.<br />

2.3.4. Duties <strong>and</strong> Functions of the OH&S Representatives (Section 18 of the OH&S Act)<br />

The Principal Contractor shall ensure that the designated OH&S representatives conduct continuous<br />

monitoring <strong>and</strong> regular inspections of their respective areas of responsibility using a checklist <strong>and</strong><br />

report thereon to the Principal Contractor. OH&S representatives shall be included in accident or<br />

incident investigations. OH&S representatives shall attend all OH&S committee meetings.<br />

2.3.5. Appointment of OH&S Committee (Sections 19 <strong>and</strong> 20 of the OH&S Act)<br />

The Principal Contractor shall establish an OH&S committee, which shall meet as specified in the<br />

Regulations.<br />

2.4. Administrative Controls <strong>and</strong> the Occupational Health & Safety File<br />

2.4.1. The OH&S File (Construction Regulation 5 (7))<br />

As required by Construction Regulation 5(7), the Principal Contractor <strong>and</strong> other Contractors shall<br />

each keep an OH&S file on site. The following list is not exhaustive <strong>and</strong> shall only be used as a<br />

guide:<br />

• Notification of construction work (Construction Regulation 3)<br />

• Latest copy of OH&S Act (General Administrative Regulation 4)<br />

• Proof of registration <strong>and</strong> good st<strong>and</strong>ing with COID Insurer (Construction Regulation 4(g))<br />

• OH&S plan agreed with the Client including the underpinning risk assessment/s <strong>and</strong> method<br />

statements (Construction regulation 5(1))<br />

• Copies of OH&S committee <strong>and</strong> other relevant minutes<br />

• Designs/drawings (Construction Regulation 5(8))<br />

• A list of Contractors (sub-contractors) including copies of the agreements between the<br />

parties <strong>and</strong> the type of work being done by each Contractor (Construction Regulation 9)<br />

• Appointment/designation forms as per paragraphs 2.1.1 <strong>and</strong> 2.1.2.<br />

• Registers as follows:<br />

# 377437-v1

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!