ID Task Name Start Finish Predecessors<br />

1 PARTA to Submit <strong>the</strong> TIGER Grant Application Tue 9/15/09 Tue 9/15/09<br />

<strong>Kent</strong> <strong>Central</strong> <strong>Gateway</strong><br />

Anticipated Construction Schedule<br />

(Pending <strong>Funding</strong> Availability)<br />

Quart 4th Quarte 1st Quart 2nd Quart 3rd Quart 4th Quarte 1st Quart 2nd Quart 3rd Quart 4th Quarte 1st Quarte 2nd Quart 3rd Quart 4th Quarte 1st Quart<br />

u e Oct o e Jan e MarApr a Jun Jul u e Oct o e Jan e MarApr a Jun Jul u e Oct o e Jan e MarApr a Jun Jul u e Oct o e Jan e Mar<br />

9/15<br />

2 TIGER Grant Selection Process (Feb. 17, 2010 is <strong>the</strong> latest<br />

award notification date. However, assume notification will be<br />

received earlier in order to meet <strong>the</strong> President's ARRA goals.)<br />

Tue 9/15/09 Mon 1/18/10 1<br />

3 Complete Remaining ROW Acquisitions Utilizing Already<br />

Encumbered Funds (<strong>for</strong> Construction Contract No.2)<br />

Tue 9/15/09 Mon 8/30/10 1<br />

4 Begin Preparing Final Bid Documents. Two (2) Sets of Bid<br />

Documents will be Prepared - One <strong>for</strong> Utility and City Road<br />

Modifications, <strong>the</strong> O<strong>the</strong>r <strong>for</strong> <strong>the</strong> Construction of <strong>the</strong> MMC<br />

(Portions of this Work will Utilize Already Encumbered Funds)<br />

Tue 9/15/09 Mon 3/29/10 1<br />

5 Milestone: PARTA Receives Notice of TIGER Grant<br />

Award<br />

Mon 1/18/10 Mon 1/18/10 2<br />

1/18<br />

6 Execute Private Development Partnership Contracts and<br />

Agreements<br />

Tue 1/19/10 Mon 4/12/10 5<br />

7 Advertise Contract No. 1: Utility and Road Modifications Tue 3/30/10 Mon 5/10/10 5,4<br />

8 Contractor Selection <strong>for</strong> Contract No. 1 Tue 5/11/10 Mon 5/17/10 7<br />

9 Complete Contract No. 1: Construction of Utility and City<br />

Roadway Modifications<br />

Mon 5/31/10 Mon 8/1/11<br />

10 Milestone: Begin Construction <strong>for</strong> Contract Group 1 Mon 5/31/10 Mon 5/31/10 8FS+10 days<br />

5/31<br />

11 Set up Roadway/Pedestrian Maintenance-of-Traffic Tue 6/1/10 Mon 6/7/10 10<br />

12 Remove Existing Pavements and Sidewalks (Demo) Tue 6/8/10 Mon 7/5/10 11<br />

13 Construct and Install Required Drainage Features Tue 7/6/10 Mon 8/30/10 12<br />

14 Relocate Existing Overhead Utilities Tue 6/8/10 Mon 11/22/10 11<br />

15 Complete Grading Work Tue 6/8/10 Mon 11/22/10 11<br />

16 Construct New Pavements, Curbs, and Pedestrian<br />

Sidewalks (<strong>for</strong> continuation of <strong>the</strong> Esplanade)<br />

Tue 6/8/10 Mon 6/6/11 11<br />

17 Install Lighting Tue 6/7/11 Mon 7/4/11 16<br />

Project: Construction Schedule_Updat<br />

Date: Tue 9/15/09<br />

Task<br />

Split<br />

Progress<br />

Milestone<br />

Summary<br />

Project Summary<br />

External Tasks<br />

External Milestone<br />

Deadline<br />

Page 1