Species Act. The rehabilitation would have included construction of overflow flumes suitable for<br />
steelhead smolt passage and modification of the outlet structures on one or both Arroyo Leon<br />
Ponds (Johnson Ranch or Giusti) so that they could quickly drain prior to significant forecasted<br />
storm events. The rehabilitation process would have developed operational guidelines and/or<br />
structural improvements to minimize negative impacts while restoring functional rearing habitat.<br />
It would have also secured permits from the California Department of Fish and Game and the<br />
National Marine Fisheries Service to resume operation of the ponds in a manner that would<br />
provide steelhead rearing and would not significantly interfere with fish passage.<br />
This project was rejected by both the California Department of Fish and Game and the National<br />
Marine Fisheries Service. There were a number of agency concerns that could not be overcome<br />
within the constraints of the site and regulatory requirements.<br />
Identified Priority Projects 90 October, 2008