CHENNAI METRO CHENNAI RAIL NEWS METRO LETTER RAIL NEWS LETTER<br />

Volume-II<br />

Issue-12<br />

<strong>December</strong> <strong>2012</strong><br />

Dr.Sudhir Krishna, IAS<br />

Secretary<br />

Ministry of Urban Development<br />

Government of India &<br />

Chairman, <strong>CMRL</strong><br />

Thiru K.Rajaraman, IAS<br />

Managing Director<br />

Thiru S.Krishnamoorthy, IRAS<br />

Chief General Manager<br />

( Public Relations )<br />

CHENNAI METRO RAIL LIMITED<br />

“Harini Towers”<br />

No.7, Conran Smith Road,<br />

Gopalapuram,<br />

CHENNAI-600 086.<br />

PH: 044-28430020<br />

FAX: 044-28351401<br />

Tunnelling work in progress at Washermenpet Station<br />

Progress of Underground Highlights as on 31-12-12<br />

1. 1 st TBM has completed 300m from<br />

Nehru Park towards Egmore. 2 nd TBM has completed<br />

85m drive.<br />

2. Two TBMs launched from Washermenpet towards<br />

Mannadi. 1 st TBM has completed 245m drive and<br />

2 nd TBM has completed 35m drive.<br />

3. TBM assembly in progress at Saidapet & Shenoy<br />

Nagar. TBM launch in progress at May Day Park &<br />

Shenoy Nagar.<br />

4. Preparation for top slab construction at<br />

Washermenpet, High Court, Shenoy Nagar, Anna<br />

Nagar Tower and Thirumangalam stations &<br />

concourse slab construction at Egmore shaft in<br />

progress.<br />

5. 3 rd level excavation and preparation for base slab<br />

construction in progress in Nehru Park.<br />

6. Diaphragm wall work in progress at Thirumangalam<br />

ramp area.<br />

7. Stage 2 traffic management plan implemented at<br />

Chamiers Road.<br />

8. Excavation of shaft and first level strutting in<br />

progress at Government Estate.<br />

Roof Slab Work in progress at High<br />

Court Station Site<br />

Diaphragm Wall work in progress at<br />

Mannadi Station Site<br />

Rebar Work in progress at<br />

Teynampet Station Site<br />

Website:<br />

www.<strong>chennai</strong><strong>metro</strong><strong>rail</strong>.gov.in<br />

Email:<br />

<strong>chennai</strong><strong>metro</strong><strong>rail</strong>@gmail.com<br />

Lowering and Assembling of TBM at Saidapet.


<strong>CMRL</strong> celebrates 5 th Foundation Day<br />

Chennai Metro Rail Limited celebrated its 5 th<br />

Foundation day on 31-12-12.<br />

CGM (PF) and CGM (C) addressed the gathering<br />

.All CGMs, GMs and GC officials along with<br />

other staff and officials of <strong>CMRL</strong> participated in<br />

the celebrations. The Vote of Thanks was given by<br />

Advisor (HR) of <strong>CMRL</strong>.<br />

―“Failure<br />

will never<br />

overtake<br />

me if<br />

my<br />

determinati<br />

on to<br />

succeed<br />

is<br />

strong<br />

enough.‖<br />

Og Mandino<br />

Caption describing picture<br />

or graphic.<br />

Track works in progress<br />

Total Length of Track-plinth concreting done between<br />

Vadapalani and Koyambedu station is 5350 Tr.mtr and from<br />

Sidco to Vadapalani is 2650 Tr.mtr. A total of 8000 Tr.mtr track<br />

laying has been completed.<br />

World Aids Day Celebrated<br />

L&T SUCG JV at Chennai Metro Underground Package observed<br />

World Aids Day, on Dec – 1 st <strong>2012</strong>, with series of activities comprise<br />

taking of AIDS pledge by all staff and workmen. Guest lecture was<br />

delivered by Dr.K.N.S.Varadhan (TNSACS) Tamil Nadu State Aids<br />

Control Society. A programme was conducted at Workmen colony for<br />

highlighting the modes of HIV/AIDS Transmission and Importance<br />

on the usage of Condoms . Pamphlets, Condoms and Sweets were distributed<br />

to all the employees and the program concluded with the<br />

screening of short films on HIV/AIDS. The participation was very<br />

good and feed back was encouraging.<br />

Workshop on Design & Construction of Earthing, Bonding & Lightning Protection<br />

System for Under Ground Stations & Tunnels .<br />

A workshop on Design & Construction of Earthing, Bonding & Lightning Protection<br />

System for Under Ground Stations & Tunnels was held at <strong>CMRL</strong> office on 13/12/12.<br />

The workshop had a detailed discussion on how Earthing is done for Electrical and Lightning<br />

protection in Underground Metro Rail Stations.<br />

There was an interaction among the UG Mechanical, Electrical – Plumbing Division of <strong>CMRL</strong><br />

and Siemens Power on how techniques were adopted for the execution of Earthing , Bonding<br />

& Lightning Protection system for the UG Metro Stations.<br />

Several members from <strong>CMRL</strong>,GC and all Contractors of the Underground Packages participated<br />

in this Workshop and shared their views in regard to the Earthing Systems in UG stations.<br />

Several Topics were discussed during the Workshop viz.,<br />

1. Interface point on Earthing system between Power Supply Contractor &<br />

Underground Civil contractor.<br />

2. Earthing System – Standards and References<br />

3. Clean Earthing , Neutral Earthing<br />

4. Lightning Protection System<br />

Page 2<br />

Chennai Metro Rail <strong>Newsletter</strong>


Progress of Depot work as on 31-12-<strong>2012</strong><br />

VIADUCT PARAPET ERECTION IN<br />

PROGRESS AT KOYAMBEDU<br />

ROLLING STOCK TRUSS<br />

ERECTION IN PROGRESS<br />

Sl. No. Description Unit Total quantity Quantity<br />

executed<br />

1 Earth filling Cum 3,16,000 255000<br />

2 Installation of Prefabricated Vertical RMT 26,00,000 26,23,325<br />

Drain (PVD)<br />

3 Surcharge filling Cum 4,22,354 3,13,000<br />

4 Admn building (work pile)600mm,<br />

Completed<br />

Admin building roofslab & beam<br />

(GF&FF,SF and TF)<br />

5 Admn building pile cap, infrashed pile No. 514 460<br />

cap and rolling stock pile cap and<br />

stabling shed pile cap<br />

6 Infrastructure shed, stabling shed rolling<br />

stock and workshop 500 mm , Viaduct<br />

and ramp area 1000 mm, Viaduct<br />

pile cap, Viaduct pier and pier cap<br />

Completed<br />

7 Viaduct segment precast slab erection No 76 72<br />

8 Viaduct parapet wall casting,<br />

Completed<br />

Substation I&II&III RCC footing.,<br />

Substation Roof beam & slab<br />

9 Compound wall precast footing casting No 1124 555<br />

10 Compound wall precast column casting No 1124 470<br />

11 Compound wall precast wall panel No 1124 610<br />

casting (TOP)<br />

12 Infrashed truss fabrication No 10 8<br />

“Nothing<br />

will ever<br />

be<br />

attempted<br />

if all<br />

possible<br />

objections<br />

must<br />

be<br />

overcome”<br />

Dr. Johnson<br />

Volume-II<br />

Issue-12<br />

Page 3


Progress of civil works in Elevated Sections<br />

Progress from Koyambedu to Ashok Nagar<br />

as on 31st <strong>December</strong> <strong>2012</strong><br />

Item<br />

Total Nos<br />

Completed<br />

Nos<br />

Piles 1171 1118<br />

Pile caps 267 257<br />

Piers 288 246<br />

Work in progress near OTA<br />

station<br />

“Opportunities<br />

are usually<br />

disguised<br />

as hard work<br />

so most<br />

people<br />

don't<br />

recognize<br />

them.”<br />

Ann Landers<br />

Caption describing picture<br />

or graphic.<br />

Page 4<br />

Pier Arm 13 13<br />

Spans Erected 185 155<br />

Portal Beam 40 34<br />

Progress from Ashok Nagar to<br />

St.Thomas Mount as on 31st <strong>December</strong> , <strong>2012</strong><br />

Item<br />

Total<br />

Nos<br />

Progress from Little Mount to O T A<br />

as on 31st <strong>December</strong> <strong>2012</strong><br />

Completed<br />

Nos<br />

Piles 348 348<br />

Pile caps 89 89<br />

Open foundations 87 83<br />

Piers 176 158<br />

Spans Erected 131 89<br />

Completed<br />

Item Total Nos<br />

Nos<br />

Piles 398 284<br />

Pile caps 100 54<br />

Open foundations 169 130<br />

Piers 271 184<br />

Spans Erected 80 51<br />

Progress from OTA to Chennai Airport as on<br />

31st <strong>December</strong> <strong>2012</strong><br />

Total Completed<br />

Item<br />

Nos Nos<br />

Open foundation 128 30<br />

Pier 128 22<br />

Cut and Cover 340m 85m<br />

ramp excavation<br />

Raft slab 340m 76m<br />

U-Sec (excavation) 520m 40m<br />

Work in progress at<br />

Alandur Station<br />

Work in progress at Sidco<br />

Work in progress at<br />

CMBT station.<br />

Chennai Metro Rail <strong>Newsletter</strong>


Progress of works in Under Ground Sections<br />

Name of Work<br />

UAA 01<br />

Design and construction<br />

of under ground stations<br />

and associated tunnels<br />

at W ashermenpet,<br />

Mannadi, High Court,<br />

Chennai Central and<br />

Egmore and May Day<br />

Park<br />

UAA 02<br />

Design and construction<br />

of under ground stations<br />

and associated tunnels<br />

at Government Estate,<br />

LIC Building and<br />

Thousand Lights<br />

UAA 03<br />

Design and construction<br />

of under ground stations<br />

a n d a s s o c i a t e d<br />

t u n n e l s a t<br />

New Gemini, Teynampet,<br />

Chamiers Road<br />

and Saidapet.<br />

UAA 04<br />

Design and construction<br />

of under ground stations<br />

and associated tunnels<br />

at Nehru Park, Kilpauk<br />

Medical College and<br />

Pachaiappa’s College.<br />

UAA 05<br />

Design and construction<br />

of under ground stations<br />

and associated tunnels<br />

at Shenoy Nagar, Anna<br />

Nagar East, Anna Nagar<br />

Tower and Thirumangalam<br />

Status<br />

All the diaphragm wall work completed in Washermenpet; Base<br />

slab for 120m length completed; 15 Plunge columns completed;<br />

Washermenpet main station box Roof slab 105m completed<br />

TBM 01&02 drive from Washermenpet to Mannadi in progress.<br />

1 st TBM has completed 245m drive and 2 nd TBM has completed<br />

35m drive.<br />

98 Diaphragm wall panels completed, 2 Plunge columns completed<br />

at Mannadi station.<br />

96 Diaphragm wall panels completed, 8 Plunge columns completed.<br />

Roof slab excavation of 60m completed and PCC 50m<br />

completed at High Court station.<br />

45 entrance Diaphragm wall panels and 51 main Diaphragm<br />

wall panels completed at Chennai Central station.<br />

All Diaphragm wall panels, excavation, base slab completed at<br />

May Day Park; 3 rd TBM launch towards Chennai Central in progress<br />

in May Day Park.<br />

99 Diaphragm wall panels completed, 1 Plunge column completed<br />

at Egmore station. Receiving shaft (L&T) roof slab completed;<br />

Excavation to concourse slab in progress in shaft area.<br />

77 Diaphragm wall panels completed at Government Estate<br />

station; Excavation for TBM receiving shaft commenced and is in<br />

progress.<br />

49 Diaphragm wall panels completed at LIC.<br />

18 Diaphragm wall panels completed at Thousand Lights station.<br />

Commissioning of TBM in progress at May Day Park.<br />

Initial drive of TBM commenced at May Day Park<br />

60 Diaphragm wall panels completed at Gemini station.<br />

34 Diaphragm wall panels completed at Teynampet Station.<br />

38 Diaphragm wall panels completed at Chamiers road Station.<br />

74 Diaphragm wall panels completed at Saidapet Station;<br />

Excavation for TBM receiving shaft commenced and is in progress.<br />

138 m of base slab and 44 m of roof slab completed at Saidapet<br />

Ramp.<br />

Lowering and assembly of TBM S701 and S702 started at<br />

Saidapet shaft.<br />

115 m roof slab and 107 m concourse slab casted; Preparation<br />

for base slab casting in progress.<br />

TBM-01&02 drives from Nehru Park to Egmore in progress; 1 st<br />

TBM completed 300m drive; 2 nd TBM completed 85m drive.<br />

104 Diaphragm wall panels and 20 plunge columns completed<br />

at KMC; 44m roof slab constructed in KMC. 3 panels completed in<br />

Entry/Exit structures.<br />

83 Diaphragm wall panels and 12 plunge columns completed;<br />

65m roof slab constructed at Pachaiyappas College station; 34<br />

Diaphragm walls completed in entry/exit structures.<br />

All 154 Diaphragm wall panels completed and base slab<br />

casted for 130m length in Shenoy Nagar; TBM 1 assembly<br />

in progress; 5 plunge columns completed; 20m roof slab<br />

casted; Further excavation and rebar work for roof slab in<br />

progress.<br />

100 Diaphragm wall panels completed at Anna Nagar East<br />

station; Plunge column work commenced.<br />

52 Diaphragm wall panels completed at Anna Nagar<br />

Tower station; 13 plunge columns completed; Top down<br />

excavation in progress; Rebar work in progress for roof slab.<br />

54 Diaphragm wall panels completed at Thirumangalam<br />

station; 17 plunge columns completed; 20m roof slab (North<br />

side half) completed; Further excavation in progress; Rebar<br />

work in progress for next 20m roof slab.<br />

12 Diaphragm wall panels completed in Thirumangalam<br />

ramp area<br />

WORK IN PROGRESS AT<br />

PACHAIYAPPA’S STATION<br />

TUNNELLING IN PRO-<br />

GRESS FROM NEHRU PARK<br />

TO EGMORE.<br />

WORK IN PROGRESS AT<br />

SHENOY NAGAR STATION<br />

BASE SLAB REINFORCEMENT<br />

WORK IN PROGRESS AT<br />

SAIDAPET RAMP<br />

STRUT FIXING AND EXCAVA-<br />

TION WORK IN PROGRESS AT<br />

ANNA NAGAR TOWER STATION<br />

"If you focus<br />

on the<br />

obstacles,<br />

then you<br />

give them<br />

more<br />

power.<br />

Instead<br />

focus on<br />

your<br />

purpose, on<br />

your most<br />

authentic<br />

and<br />

fundamental<br />

intentions.”<br />

-Ralph Marstan<br />

Volume-II<br />

Issue-12<br />

Page 5


Rolling Stock progress as on 31st <strong>December</strong> <strong>2012</strong><br />

In-process inspection of Manufacturing of third<br />

train is started<br />

View of the first car body shell under manufacture<br />

in Alstom, Sricity, India<br />

Progress in manufacturing of train<br />

Production activity of the first train is in the final phase with fitment of most of<br />

the equipments on the 4 <strong>rail</strong>cars after completion of electrical wiring, fixation of<br />

panels and stage level tests. As per the test schedule given by Alstom, car level<br />

tests will start in the first week of <strong>December</strong> <strong>2012</strong> followed by 4 car train level test<br />

in January 2013 and February 2013. Accordingly, the car level tests have started by<br />

the first week of <strong>December</strong> <strong>2012</strong> which was witnessed by the Engineers from GC<br />

and <strong>CMRL</strong> stationed in Sao Polo, Brazil. The tests are progressing well. During the<br />

three months period from <strong>December</strong> <strong>2012</strong> to February 2013, it is planned to conduct<br />

thorough checks and all static type tests on the first train before clearance.<br />

The quality of the first train will set the standard for manufacturing of all subsequent<br />

rakes.<br />

The first train will be packed and shipped to Chennai<br />

on completion of static type tests subject to clearance<br />

by <strong>CMRL</strong>/GC.<br />

All the major equipments fitted into the train are<br />

checked for quality separately prior to fitment at their<br />

manufacturer’s place which is witnessed by <strong>CMRL</strong>/<br />

GC officials. Accordingly, First Article Inspection and<br />

type tests of most of them were completed in November<br />

<strong>2012</strong>. Production of the second and third trains has started and is in<br />

various stages of production. Equipments and panels are fitted on the car shell<br />

which is expected to finish in another one month, which will be followed by car<br />

level tests. Production of the third train has also started with sub-assemblies and<br />

car body shell production was started in October-12 and is progressing Transfer<br />

of Technology and Progress in in production of trains in India<br />

Construction of Car Body shell at Alstom Factory in sricity - CBS shop is completed<br />

and continuous production is planned to start by March 2013. Other<br />

shops for train manufacturing, like fitting shop, bogie shop, and testing shop is<br />

under construction, all of which will complete the construction by March 2013.<br />

Regarding transfer of technology, the activities of new factory in Sri City are still progressing up to date. Specific<br />

jigs dispatched from Alstom Brazil for carshell erection workstation arrived in Sri City. About training,<br />

training for carbody shell sub-assembly workstations has been concluded and training for fitting activities has<br />

been started.<br />

INTERCONNECTION OF 700 MM WATER PIPELINE FOR METRO RAIL UG STATION<br />

Interconnection of 700 mm dia water pipeline (transmitting water from Kilpauk<br />

water works to Triplicane head works) were carried out for Central Metro<br />

UG station. This is a special type of work involving welding joint at one end<br />

and flange joint at the other end. This type of joint is being carried out for the<br />

1 st time for <strong>CMRL</strong> diversion work. Normally this type of work takes 2 days.<br />

Because of the availability of sophisticated equipments like hydra Crane,<br />

<strong>CMRL</strong> was able to complete this work in 10 hrs.<br />

First train- Ceiling installed in car<br />

Interior view of the car under construction<br />

for 1 st train<br />

Page 6<br />

Chennai Metro Rail <strong>Newsletter</strong>


Progress of Elevated Station Works<br />

Arumbakkam<br />

Vadapalni<br />

S. No Description Total nos Completed Total nos Completed<br />

1 Pile 234 234 173 153<br />

2 Pile cap 61 61 52 39<br />

3 Stub column COMPLETED 70 42<br />

4 Plinth beam at street level (rmt) 530 420<br />

5 Column up to concourse level<br />

70 40<br />

(1 st lift)<br />

6 Column up to concourse level<br />

70 30<br />

(2 st lift)<br />

7 Column up to platform level 52 42 NA NA<br />

8 Concourse floor slab 1676 1510 NA NA<br />

9 Platform slab 1750 NA NA NA<br />

Koyambedu &CMBT<br />

All Structural works have been completed.<br />

Block works is in progress<br />

Work in progress at<br />

Koyambedu<br />

Work in progress at<br />

ST Mount station<br />

Sidco<br />

Alandur<br />

S. Description Total completed<br />

Total completed<br />

No<br />

nos<br />

nos<br />

1 Footings 41 36 123 123<br />

2 Stub column 56 49 165 154<br />

3 Plinth beam at street 350 285 1700 1673<br />

level (rmt)<br />

4 Column up to<br />

58 27 124 118<br />

intermediate level<br />

5 Intermediate roof slab<br />

COMPLETED<br />

(Sqm)<br />

6 Column above intermediate<br />

56 7 96 53<br />

floor level.<br />

7. Intermediate level slab Completed 1620 1420<br />

8. I Girder Erection 48 48<br />

9. Concourse Slab 1175 190 Na Na<br />

S.<br />

No<br />

Viaduct works -<br />

Description<br />

Vadapalani S T Mount<br />

Total<br />

nos<br />

Total<br />

nos<br />

completed<br />

Completed<br />

1 Pile COMPLETED NA NA<br />

2 Pile Cap AND NA NA<br />

3 Pier<br />

HANDED<br />

7 6<br />

OVER TO<br />

4 Pier Cap 7 4<br />

OTHER<br />

5 I Griders<br />

240 117<br />

WORKS<br />

(Casting)<br />

6 Fly Over Pile 132 43 NA NA<br />

7 Deck slab concrete<br />

46 43 NA NA<br />

8 Footings NA NA 11 11<br />

S.<br />

No<br />

Description<br />

Total<br />

nos<br />

Completed<br />

Total<br />

nos<br />

Completed Total<br />

nos<br />

Completed Total<br />

nos<br />

Completed Total<br />

nos<br />

Completed<br />

1 Pile 77 77 NA NA NA NA NA NA NA NA NA NA<br />

2 Pile cap 16 16 56 53 NA NA NA NA NA NA NA NA<br />

3 Stub column 51 29 76 66 56 28 74 73 264 180 43 15<br />

Volume-II<br />

Issue-12<br />

Page 7<br />

Total<br />

nos<br />

Completed<br />

4 Plinth beam at street 525 405 800 394 625 226 1037 825 3800 2500 NA NA<br />

level (rmt)<br />

5 Footings 12 17 63 53 48 20 52 51 221 177 43 12<br />

6 Column above tie 34 30 94 37 53 32 82 78 255 170 NA NA<br />

beam<br />

7. Concourse level slab 850 530 2237 1350 1990 610 2750 2600 7048 3750 NA NA<br />

8. Intermediate Slab NA NA NA NA NA NA NA NA 3000 3000 NA NA<br />

9. Portal Pier up to<br />

MRTS concourse slab<br />

NA– Not Applicable<br />

Little Mount Guindy OTA Ashok Nagar S T Mount Meenambakkam<br />

NA NA NA NA NA NA NA NA 52 17 NA NA


Awareness Programme conducted during <strong>December</strong> <strong>2012</strong><br />

Girija Apartments Owners; Welfare Association—Vadapalani<br />

Jain Eiffel Gardens Flat Owners’<br />

Welfare Assoiation—Vadapalani<br />

Purva Jade Residential Apartments—Arcot Road<br />

Villivakkam Panchayat Elementary School—Villivakkam<br />

Pallavapuram Higher Secondary<br />

School—Pallavaram<br />

Compensatory tree planting as on<br />

31-12-<strong>2012</strong><br />

Kesari Higher Secondary School— T Nagar<br />

Year Target In so far<br />

NOV<br />

2011-12 15,000 - 10,726<br />

(JVS)<br />

<strong>2012</strong>-13<br />

(JVS)<br />

15,000 7938 10,931<br />

<strong>2012</strong>-13<br />

(TNFD)<br />

8200 6800 15000<br />

Editor : Thiru S.Krishnamoorthy, IRAS<br />

Sub-Editors : Thiru K.Elanthiraiyan.<br />

Selvi R. Shruti Shambavi<br />

Published by Chennai Metro Rail Limited.<br />

Please address all correspondence to: The Editor, Chennai Metro Rail News Letter,<br />

Chennai Metro Rail Limited, “Harini Towers”, No.7, Conran Smith Road,<br />

Gopalapuram, Chennai-600 086.<br />

Email: <strong>chennai</strong><strong>metro</strong><strong>rail</strong>@gmail.com