<strong>Performance</strong> Goals<br />
1. Plan an AO Mobilization Prototype Exercise for FY 2006.<br />
Was the goal achieved? No. The exercise was postponed until FY 2009.<br />
Results: Planning activities are scheduled to begin in FY 2006.<br />
Discussion:<br />
It was noted in last year’s report that a reassessment of the Agency’s<br />
business rules was conducted and the planning was suspended until<br />
the results could be assessed. The results have now been finalized and<br />
the extent to which the business rules have changed requires a new<br />
iteration of many of the Agency’s major procedural manuals which<br />
includes much of the software dealing with induction processing. As<br />
a consequence, it has been decided not to limit the parameters of the<br />
next exercise to reestablishing an Area Office, but to build an exercise<br />
that will encompass the activities of the entire delivery system.<br />
The plans for the exercise will entail designing a total mobilization<br />
exercise that will be tailored to evaluate the SSS’ mandates for a<br />
mobilization of any type. The sheer size and detail of the exercise will<br />
take approximately 18 months to produce. The final product will be<br />
played in the field in FY 2009.<br />
12<br />
FISCAL YEAR 2005 PERFORMANCE AND ACCOUNTABILITY REPORT - SELECTIVE SERVICE SYSTEM