Future Projects (13940 MW):<br />
1. Uran Gas Based Combined Cycle Power Plant (CCPP) (1220 MW) - Block-I : 406 MW, Block-<br />
II: 814 MW:<br />
Tender for Lump sum turnkey contract for installation of 1220 MW advance class gas turbine based<br />
CCPP were invited on 28.01.<strong>2011</strong>. Tender sale was from 09.02.<strong>2011</strong> to 24.02.<strong>2011</strong>. Bids received<br />
on 08.07.<strong>2011</strong> and Cover-I opened on the same day. Letter of Award is expected by March 2014<br />
followed by Block II (814 MW) by June 2014.<br />
Land, water and other statutory clearances are available. Tying up of gas for the project is in<br />
progress.<br />
GoM has accorded approval for implementation of 1220 MW Combined Cycle Power Project at<br />
Uran vide Government Resolution no. Project08/ Pra.kra.1246/ Urja-4 dated 02.03.<strong>2010</strong>.<br />
2. Bhusawal TPS Unit 6 (1 x 660 MW):<br />
Land for the project is acquired. Acquisition of land for railway siding is in progress. The order for main<br />
plant is envisaged by May 2012. To this extent, commissioning (COD) is expected by October 2016.<br />
Government of Maharashtra has approved the implementation of this project vide Government resolution<br />
no. Prakalpa-<strong>2010</strong>/ Pra. Kra. 3/Urja-4 dated 05.10.<strong>2010</strong>.<br />
3. Nasik TPS Unit 6 (1 x 660 MW):<br />
It is planned to install one coal based super critical unit of 660 MW capacity at Nasik TPS premises.<br />
4. Paras Thermal Power Project Unit 5 (1 x 660 MW):<br />
The said project is under planning stage.<br />
Maharashtra State Power Generation Co. Ltd.<br />
5. Latur Coal Based Unit 1&2 (2 x 660 MW) or Gas based CCPP Block-I & II (2 x 750 MW):<br />
MSPGCL has signed Memorandum of Understanding with M/s BHEL on 12.08.09 for formation of<br />
Joint Venture Company to set up 2 x 660 MW super critical Power Plant or 1500 MW gas based<br />
combined cycle power plant at Latur. The Joint Venture Agreement with M/s BHEL is signed on<br />
11.11.<strong>2010</strong>. Certificate of incorporation of Latur Power Company ltd. is issued by Registrar of<br />
Companies, Mumbai under the Companies Act on 06.04.<strong>2011</strong>. Further activities for formation of JVC<br />
are in progress.<br />
The activities for land acquisition are in progress. Divisional Commissioner accorded approval for<br />
rates for land required to be acquired.<br />
Action for fuel linkage are in progress with MoC/ MoPNG.<br />
It is envisaged to place the LOA for Main Plant by April 2012. To this extent, the commissioning<br />
(COD) of the project is expected as under:<br />
(i)<br />
Coal based: Unit 1 by April 2016 & Unit 2 by September 2016 or<br />
(ii) Gas based: Block-I by April 2015 and Block-II by June 2015.<br />
9