Annual Report <strong>2010</strong>-<strong>2011</strong><br />

Venture structuring. The said project is under planning stage. Preliminary activities for land<br />

acquisition is in progress. Matter taken up with WRD for requirement 40 MM 3 water for this<br />

project. For grant of long term coal linkages, follow up is going on with Ministry of Coal, CEA.<br />

9. Coal based Thermal Power Project near Manora (Tal. Tiroda, Dist. Gondia) (2 x 660 MW):<br />

The said project is under planning stage. Preliminary activities for land acquisition is in progress.<br />

WRD has informed its inability to meet the water requirement of 40 MM 3 water for this project<br />

from proposed barrage on Wainganga river near Mendhri (Khairi). For grant of long term coal<br />

linkages, follow up is going on with Ministry of Coal, CEA.<br />

10. Coal based Thermal Power Project in Mendki (Tal. Brahmapuri, Dist. Chandrapur)<br />

<strong>Mahagenco</strong> has proposed to go in for installation of 2x660 MW Units in Mendki by way of Joint<br />

Venture structuring. The said project is under planning stage. Preliminary activities for land<br />

acquisition is in progress. Matter taken up with WRD for the requirement of 40 MM 3 water for<br />

this project. For grant of long term coal linkages, follow up is going on with Ministry of Coal,<br />

CEA.<br />

SUBSIDIARIES AND JOINT VENTURES<br />

Mahaguj Collieries Ltd.- The company is a joint venture between your company and Gujarat State Electricity<br />

Co Ltd. for captive mining of coal blocks at Machchakata. The Company has appointed Mine Developer cum<br />

Operator for executing the project. The vital preliminary activities like acquisition of land, various Govt<br />

clearances has been started. The Govt. of Orrissa has granted approval for acquisition of land for the project.<br />

Coal Mining Service Agreement between MDO i.e M/s Adani Enterprises Ltd and Mahaguj Collieries Ltd for<br />

30 MTPA coal has been signed on 6th May <strong>2010</strong>.<br />

Considering the availability of coal reserves the Ministry of Coal has directed to increase the Mine capacity of<br />

Machchakata coal block from 30 MTPA to 50 MTPA. Accordingly Board of Mahaguj Collieries Ltd has<br />

approved increase in capacity of Mines from 30 MTPA to 50 MTPA.<br />

Maharashtra State Power Generation Co. Ltd.<br />

Dhule Thermal Power Co. Ltd.- This company has been incorporated to implement various Thermal Power<br />

Projects as green field project under case-2 as per the guidelines of Ministry of Power, Government of India.<br />

During the year there was no activity in this company.<br />

UCM Coal Company Ltd. – The UCM coal Company Ltd is a JV company between your company and<br />

Uttarpradesh Rajya Vidyut Uttpadan Nigam Ltd. (UPRVUNL) and Chattisgarh Mineral Development Corporation<br />

(CMDC) to share the output of Coal to be generated from Chendipada and Chendipada II coal blocks.<br />

INITIATIVES TAKEN FOR NON COVENTIONAL ENERGY RESOURCES (SOLAR BASED POWER<br />

PLANT)<br />

Chandrapur 1 MW Solar PV Power Projects: In line with the guidelines issued in Jan 2008 by Ministry of<br />

new and Renewable Energy (MNRE), Govt. of India, <strong>Mahagenco</strong> has set up 1 MW Solar PV power project at<br />

Chandrapur in the premises of Chandrapur Super Thermal Power Station. The project is commissioned on 9th<br />

April <strong>2010</strong> and it is feeding electricity to the grid. <strong>Mahagenco</strong> is receiving generation Based Incentive (GBI)<br />

for this project from NMRE. This is first grid connected solar project in Maharashtra and second in India.<br />