<strong>Uttar</strong> <strong>Gujarat</strong> <strong>Vij</strong> <strong>Company</strong> <strong>Limited</strong><br />
Truing up for FY 2010-11<br />
and Determination of Tariff for FY 2012-13<br />
It is further submitted that variation in power purchase expenses due to variation in<br />
the cost and quantum is an uncontrollable factor. Accordingly, any gain or loss, on<br />
this account is to be entirely passed on to the consumers. However, the increase or<br />
reduction in quantum of power purchase and power purchase expense due to<br />
reduction in distribution loss is a controllable factor; which would result in gain or loss<br />
under MYT Regulations and is dealt accordingly.<br />
Commission’s Analysis<br />
The Commission has examined the actual quantum of power purchase and the<br />
power purchase cost during the year FY 2010-11, based on the actual energy sales<br />
and the distribution losses submitted by UGVCL. The sales and the quantum of<br />
power purchase and the power purchase cost are as per the audited annual<br />
accounts for the FY 2010-11. The power purchase cost, as per the audited annual<br />
accounts for FY 2010-11, is Rs. 4317.55 Crore as shown in the Table below:<br />
Table 4.8: Power purchase cost as per the audited annual accounts for FY 2010-11<br />
(Rs. Crore)<br />
Sl.<br />
Particulars<br />
Amount<br />
No.<br />
1 Power Purchase from GUVNL 4905.75<br />
2 Power Purchase from others (Wind) 15.66<br />
3 UI Import 26.44<br />
4 Total Power Purchase 4947.85<br />
5 Power sold to GUVNL 410.62<br />
6 UI Export 219.68<br />
7 Net Power Purchase cost 4317.55<br />
The Commission considers the net power purchase cost of Rs. 4317.55 Crore<br />
as per the audited annual accounts.<br />
Table 4.9: Power purchase cost approved by the Commission for truing up for FY<br />
2010-11<br />
Particulars<br />
FY 2010-11<br />
(Approved in<br />
Tariff Order)<br />
FY 2010-11<br />
(submitted in<br />
Truing up)<br />
(Rs. Crore)<br />
FY 2010-11<br />
(Approved in<br />
True up)<br />
Total Power Purchase cost 3755.56 4317.55 4317.55<br />
<strong>Gujarat</strong> Electricity Regulatory Commission Page 34<br />
June 2012