26.10.2014 Views

Leighton News - Leighton Holdings

Leighton News - Leighton Holdings

Leighton News - Leighton Holdings

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Logistical challenges overcome<br />

on Hong Kong railway<br />

It’s not an easy task to build six kilometres of new railway<br />

when you are allowed on site for only two hours a day.<br />

That was the dilemma facing the team which<br />

is now completing <strong>Leighton</strong> Asia’s HK$260<br />

million ($65 million) contract for Hong<br />

Kong’s MTR Corporation.<br />

Works under the contract comprised the<br />

design, manufacture, supply, delivery,<br />

installation, testing and commissioning for<br />

the trackwork, overhead line system and<br />

noise barriers for the Tung Chung Line<br />

between Olympic and the Lai King South<br />

tunnel portal.<br />

The problem was that the work area was<br />

immediately adjacent to the very busy Lantau<br />

and Airport Railway, and <strong>Leighton</strong>’s teams<br />

were only allowed to work on site in nontraffic<br />

hours – effectively from 2 am to 4 am.<br />

Project manager Chris Blair said that, to take<br />

maximum advantage of the restricted work<br />

hours, his team prioritised and arranged the<br />

activities to optimise what could be achieved<br />

in the daytime.<br />

“Working at night required strict noise<br />

mitigation measures, such as using quiet<br />

plant and working behind acoustic blankets<br />

and acoustic enclosures,” he said.<br />

“Because of the risk of tools and equipment<br />

being left on the adjacent rail lines (creating<br />

the potential for a train disaster), a checklist<br />

system was initiated to ensure that absolutely<br />

everything was removed from the site before<br />

trains started operating again after 4 am.”<br />

Included in the contract was the erection of<br />

about 6.5 kilometres of noise barriers along<br />

the existing railway, along a nearby highway<br />

viaduct and also along the new track. Their<br />

design was also a challenging task.<br />

The alignment of the existing railway and<br />

viaduct moves upward and curves in some<br />

sections. Therefore, few of the noise panels<br />

were of a standard size and shape, and many<br />

detailed design and fabrication drawings had<br />

to be prepared before they could be<br />

produced. For safety reasons, to minimise<br />

the noise impact and to reduce the number<br />

of lifting activities required, the noise<br />

barriers were pre-assembled and then lifted<br />

into place.<br />

Material procurement was also a logistically<br />

difficult task. <strong>Leighton</strong> sourced materials<br />

from more than 200 overseas suppliers.<br />

Efficient coordination was required to<br />

ensure that the materials were delivered<br />

when needed.<br />

Despite these limitations, all physical works<br />

were completed in mid-February, allowing<br />

the energisation of the overhead line system<br />

to take place about two months ahead<br />

of schedule.<br />

Chris Blair said that a feature of the contract<br />

was the partnership agreement between<br />

<strong>Leighton</strong>, MTR and other track stakeholders.<br />

“We all pledged to work together in a<br />

collaborative and safe manner, and find a<br />

balanced and harmonious way to complete<br />

the project,” he said.<br />

Cooperation and coordination was also<br />

required with contractors working on the<br />

West Rail project, which interfaces with<br />

<strong>Leighton</strong>’s site. <<br />

<strong>Leighton</strong>’s team prioritised activities to<br />

optimise what could be achieved during<br />

daylight hours.<br />

page 7

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!