01.11.2014 Views

Managing Risks - Department of Public Works and Services

Managing Risks - Department of Public Works and Services

Managing Risks - Department of Public Works and Services

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

<strong>Managing</strong> Risk During<br />

Pre-Tender Stages<br />

Project Management Conference<br />

Yellowknife, N.T.<br />

November 17-19, 2009<br />

© Helmut K. Johannsen, P.Eng., C.Arb.<br />

Partner, Fasken Martineau DuMoulin LLP


Introduction<br />

Some general principles <strong>of</strong> risk management<br />

General Comments on Project Development<br />

Process<br />

Procurement Strategies<br />

Procurement Process Issues<br />

<strong>Managing</strong> risks < closing time<br />

Some key contract risk issues<br />

<strong>Managing</strong> risks < award<br />

Project example<br />

Practice tip<br />

2


Some General Principles<br />

<strong>Managing</strong> pre-tender risks means identifying<br />

<strong>and</strong> addressing in advance:<br />

General project development risks (e.g. l<strong>and</strong>,<br />

finance <strong>and</strong> regulatory approval issues)<br />

Procurement process risks (e.g. non-compliant<br />

proposals/tenders)<br />

Contract performance risks (after contract award)<br />

No “one size fits all” approach<br />

In preparing procurement documents or in<br />

deciding whether to bid, must underst<strong>and</strong><br />

proposed risk allocation <strong>and</strong> contractual risk<br />

transfer after contract award<br />

3


Some General Principles (cont’d)<br />

Every project is different<br />

Size <strong>and</strong> complexity<br />

Mix <strong>of</strong> new construction/expansion/renovation<br />

Single project or staged construction/ turnover<br />

Schedule/budget pressures<br />

Number <strong>of</strong> construction/operation interfaces<br />

Financeability issues <strong>and</strong> constraints<br />

Effort required to identify <strong>and</strong> manage risks not<br />

always dependent on project size or value<br />

4


Some General Principles (cont’d)<br />

2007-2008 Market Conditions:<br />

Contractors, consultants <strong>and</strong> suppliers had<br />

surplus <strong>of</strong> work<br />

No time or willingness to review significant non-st<strong>and</strong>ard<br />

contract terms at time <strong>of</strong> tender<br />

No desire or need to tender on a project that appears<br />

aggressively or unfairly weighted in favour <strong>of</strong> owner<br />

2009 Market Conditions:<br />

Receiverships, projects “on hold”, shortage <strong>of</strong><br />

work<br />

But contractors, consultants <strong>and</strong> suppliers are<br />

now more knowledgeable than before about risks<br />

<strong>and</strong> thus risk averse<br />

5


Some General Principles (cont’d)<br />

Risk must be acceptable to lenders or<br />

financing may not be available<br />

Risk analyses/assessments by lenders will<br />

likely differ substantially from that <strong>of</strong><br />

government party/private sector party<br />

Parties may apply probabilistic approach to risks<br />

(especially for cumulative risks)<br />

Lenders may not use same probabilistic approach<br />

<strong>and</strong>/or may look to “worst case scenarios”<br />

Best strategy for financeability may not be<br />

best strategy for design <strong>and</strong> construction!<br />

6


Some General Principles (cont’d)<br />

<strong>Risks</strong> must be understood before they can be<br />

allocated<br />

Risk management is a formal process that<br />

enables identification, assessment, planning<br />

<strong>and</strong> management <strong>of</strong> risks<br />

Risk management is necessary in each<br />

phase <strong>of</strong> a project:<br />

Pre-tender phase<br />

Tender phase to contract award<br />

Post contract award/implementation phase<br />

Identify – mitigate – control risks<br />

7


Some General Principles (cont’d)<br />

Basic risk management strategy:<br />

Avoid risk – eliminate uncertainty<br />

Accept risk<br />

Transfer risk<br />

Mitigate risk<br />

Implement risk management strategy through<br />

Proper planning<br />

Clear, concise & consistent contract & specs<br />

Comprehensive, integrated insurance program<br />

Performance security: bonds (with riders?), bank<br />

guarantees, letters <strong>of</strong> credit, “good” parent<br />

company guarantees, etc.<br />

8


Some General Principles (cont’d)<br />

In theory, “risks should be borne by the party<br />

best able to h<strong>and</strong>le <strong>and</strong> manage the risk”<br />

Distinction between:<br />

“h<strong>and</strong>ling <strong>and</strong> managing” the risk; <strong>and</strong><br />

willingness or ability to bear consequences if <strong>and</strong><br />

when risk materializes<br />

This distinction <strong>of</strong>ten over-rides the general theory<br />

Optimum risk allocation is not maximum<br />

transfer <strong>of</strong> all risks<br />

Owners <strong>of</strong>ten fail to underst<strong>and</strong> <strong>and</strong> take into<br />

account that general contractors pass/push<br />

risks down<br />

9


Some General Principles (cont’d)<br />

Risk matrix is critical risk management tool<br />

Should a risk matrix be included in<br />

procurement documents/contracts?<br />

Often misleading in defining true risk allocation<br />

Beware <strong>of</strong> reliance on risk matrix as<br />

substitute for detailed risk review<br />

Contract language can contain subtle differences<br />

from risk allocation assumed from matrix<br />

Matrix may conflict with contractual terms or fail to<br />

fails to clearly identify retained risks (e.g. if<br />

contract liability caps exceeded)<br />

10


Some General Principles (cont’d)<br />

No “one size fits all” approach<br />

Risk allocation <strong>and</strong> contractual risk transfer<br />

depend on many things, including:<br />

Nature <strong>of</strong> contractual relationship<br />

Market conditions<br />

Each party’s ability <strong>and</strong> willingness to:<br />

accept a risk<br />

manage a risk<br />

insure against the risk<br />

A contract simply records final contractual risk<br />

allocation <strong>and</strong> transfer as agreed to by parties<br />

11


Some General Principles (cont’d)<br />

<strong>Risks</strong> <strong>of</strong>ten allocated to more than 1 person<br />

E.g. subsurface risk<br />

Owner allocates to contractor, who allocates to<br />

subcontractor<br />

But – contractor <strong>and</strong> subcontractor may have<br />

liability caps <strong>and</strong>/or exculpatory provisions that<br />

leave owner with some residual risk<br />

E.g. “insured risks”<br />

When risks transferred to insurers, there may be<br />

limits <strong>of</strong> liability, specific exclusions <strong>and</strong> gaps in<br />

coverage so residual risk remains to be borne by a<br />

party to the construction contract<br />

12


Project Development Process<br />

Often involves “Three Tracks”<br />

I: Environmental/Regulatory Process<br />

II: Industry Competition/Procurement Process<br />

III: Owner’s Other Commitments/Obligations<br />

Each track has its own risks, <strong>and</strong> these can<br />

impact other tracks as well, including through:<br />

Schedule<br />

Additional obligations/liabilities<br />

Project viability<br />

Alternative Development Strategies<br />

Run tracks sequentially<br />

Running tracks concurrently<br />

13


Project Development Process (cont’d)<br />

Example <strong>of</strong> Concurrent Tracks<br />

DESIGN -- EVALUATE -- BUILD<br />

TRACK I - Environmental / Regulatory<br />

<strong>Public</strong>, First Nations & other consultations<br />

Environmental approvals, regulatory licenses<br />

TRACK II - Industry D-B Competition<br />

Base Concept EOIs Proposal Competition<br />

Final Evaluation<br />

D-B Contract<br />

engin. & constr.<br />

shortlist<br />

technical & legal requirements<br />

feasibility & viability<br />

award & build<br />

TRACK III - Owner’s Commitment<br />

Planning, infrastructure works, power sales,<br />

facilitation agreements, modeling, financing<br />

DEVELOPMENT<br />

PHASE<br />

CONSTRUCTION<br />

PHASE<br />

14


Project Development Process (cont’d)<br />

Track I: Environmental/Regulatory<br />

Owner working with the public <strong>and</strong> government<br />

Objective: regulatory approvals necessary for<br />

project to proceed<br />

Track II: Industry Competition/Procurement<br />

Process<br />

Owner working with industry engineers, architects<br />

<strong>and</strong> contractors<br />

Objective: quality/cost optimized project & viable<br />

construction contract<br />

15


Project Development Process (cont’d)<br />

Track III: Owner’s Commitments<br />

Owner satisfying itself that all other requirements<br />

for project to proceed have been met <strong>and</strong><br />

obtained, including rights to l<strong>and</strong>s, temporary work<br />

spaces, other infrastructure that may be required<br />

(e.g. access, utilities, etc.), financing, internal<br />

board approvals, etc.<br />

Objective: project facilitating financial <strong>and</strong> physical<br />

resources, sales arrangements, <strong>and</strong> other legal<br />

agreements as necessary<br />

16


Project Development Process (cont’d)<br />

Environmental/Regulatory <strong>Risks</strong><br />

Early identification <strong>of</strong> required Permits, Licences<br />

<strong>and</strong> Approvals is essential<br />

Does the Project require Environmental<br />

Assessment? French Translations for CEAA?<br />

Scope <strong>of</strong> Assessment?<br />

How to deal with design-build & P3 processes?<br />

To mitigate risks must anticipate<br />

environmental issues during review process<br />

E.g. Project which had significant environmental<br />

issues re sturgeon<br />

Complex Computational Fluid Dynamics Model<br />

performed to assess flow patterns in spawning areas<br />

Inclusion <strong>of</strong> “sturgeon exclusion screens”.<br />

17


Project Development Process (cont’d)<br />

Procurement Process <strong>Risks</strong><br />

Request for Expressions <strong>of</strong> Interest (REOI)<br />

Pre-qualification Process (RFQ)<br />

Request for Proposals (RFP)<br />

Request for Tenders (RFT)<br />

Poor processes <strong>and</strong>/or poor risk allocation may be<br />

obstacles to finding pool <strong>of</strong> interested <strong>and</strong><br />

qualified bidders<br />

Consider doing market research before finalizing<br />

processes for major projects<br />

18


Project Development Process (cont’d)<br />

Owner’s Commitments/Obligations <strong>Risks</strong><br />

Property rights – Permanent <strong>and</strong> Temporary<br />

title, rights-<strong>of</strong>-way, easements, access, crane overswing<br />

agreements, etc.<br />

Other Agreements<br />

E.g. Tenant Leases, Licences to Occupy, Energy Sales<br />

Agreements, etc.<br />

Internal board approvals<br />

Other approvals<br />

Municipal Council, Government Ministry, Treasury<br />

Board, Risk Management Branch, etc.<br />

Project Labour Agreements<br />

19


Project Development Process (cont’d)<br />

Owner’s Commitments/Obligations <strong>Risks</strong><br />

(cont’d)<br />

Municipal/Regional District requirements<br />

Development Permit/Building Permit process<br />

Development Cost Charges<br />

Municipal/regional infrastructure improvement<br />

requirements as conditions <strong>of</strong> development<br />

20


Project Development Process (cont’d)<br />

To identify, manage <strong>and</strong> mitigate risks, all<br />

risks should be in a Project Risk Register<br />

Project Risk Register must be constantly<br />

reviewed <strong>and</strong> updated as time passes to<br />

reflect changes<br />

If risks not identified, difficult to manage them<br />

through the procurement documents<br />

21


Procurement Strategy<br />

Identify general procurement constraints<br />

Stakeholder requirements/constraints<br />

Regulatory/environmental permitting<br />

<strong>and</strong> approval processes <strong>and</strong> requirements<br />

First Nation issues<br />

Requirements for public invitation or private<br />

invitation<br />

<strong>Public</strong> owner or private owner<br />

Pre-qualification/short-listing<br />

Competitive tendering/proposals vs. sole source<br />

Contracting model <strong>and</strong> pricing model<br />

22


Procurement Strategy (cont’d)<br />

Select contract model that best reflects<br />

desired risk allocation through a walk down<br />

“Acronym Alley”:<br />

PO: Purchase Order<br />

D-B-B: Design-Bid-Build or “Traditional”<br />

D-B: Design-Build or Design-Construct<br />

EPC: Engineer-Procure-Construct<br />

EPCM: Engineer-Procure-Construct-Manage<br />

AC: Alliance Contract<br />

BOT: Build-Operate-Transfer<br />

BOOT: Build-Own-Operate-Transfer<br />

BLT: Build-Lease-Transfer<br />

FDBOM: Finance-Design-Build-Operate-Maintain<br />

PPP: <strong>Public</strong> Private Partnership (P3)<br />

23


Procurement Strategy (cont’d)<br />

Select pricing model that best reflects desired<br />

risk allocation:<br />

Stipulated Price/Lump Sum<br />

Unit Price<br />

Cost Plus<br />

Fixed Fee<br />

GMP<br />

Target Price<br />

Combination <strong>of</strong> above<br />

Note that pricing model/strategy largely<br />

independent <strong>of</strong> contracting model/strategy<br />

24


Risk Transfer<br />

Shifting the risk<br />

CONTRACT TYPE<br />

OWNER<br />

RISK<br />

CONTRACTOR<br />

Management Contracts<br />

Construction Management<br />

Traditional Unit Price<br />

Bill <strong>of</strong> Approximate Quantity<br />

Traditional Lump Sum<br />

Fixed Price / GMP<br />

Design <strong>and</strong> Build<br />

Complete “Package”<br />

Private Finance Initiative<br />

P3 or DBFO<br />

25


Design-Bid-Build or “Traditional”<br />

Method <strong>of</strong> project delivery in which an owner:<br />

contracts directly with a consultant to prepare the<br />

detailed design, drawings <strong>and</strong> specifications for<br />

the project; <strong>and</strong><br />

subsequently contracts directly with a contractor to<br />

construct the project to the owner’s design,<br />

drawings <strong>and</strong> specifications.<br />

The construction contract is typically (not<br />

always) administered by the owner’s<br />

consultant<br />

26


EPCM vs. Design-Bid-Build Approach<br />

Method <strong>of</strong> project delivery in which an owner<br />

contracts with another party (typically an<br />

engineer) to:<br />

provide design, drawings <strong>and</strong> specifications;<br />

procure equipment <strong>and</strong> construction by entering<br />

into contracts as agent for the owner with<br />

suppliers <strong>and</strong> contractors, or prepare contracts<br />

directly for owner’s signature; <strong>and</strong><br />

administer <strong>and</strong> manage the equipment <strong>and</strong><br />

construction contracts on behalf <strong>of</strong> the owner.<br />

27


Design–Bid–Build or “Traditional”<br />

OWNER’’S<br />

CONSULTANT<br />

PREPARE<br />

DESIGN<br />

OWNER<br />

ADMINISTER<br />

CONTRACT<br />

$<br />

CONSTRUCTION OF<br />

OWNER’S DESIGN<br />

CONTRACTOR<br />

Trade Contractor<br />

Supplier<br />

Trade Contractor<br />

D/B Contractor<br />

28


Summary <strong>of</strong> Design-Bid-Build<br />

Some Advantages<br />

Well understood<br />

Single design contract<br />

<strong>and</strong> single construction<br />

contract<br />

Often fixed price<br />

GC at risk for<br />

Price<br />

Schedule<br />

Quality<br />

OH&S<br />

Single bonds<br />

Predictable<br />

St<strong>and</strong>ard form contracts<br />

Some Disadvantages<br />

Difficult to fast track<br />

Quality <strong>and</strong> completeness <strong>of</strong><br />

documents critical<br />

Design<br />

Specifications<br />

Drawings<br />

Contract<br />

Change Orders expensive<br />

(delays <strong>and</strong> extras)<br />

Market dependent<br />

Ill-suited for renovations &<br />

expansions<br />

29


Construction Management (CM not “at risk”)<br />

OWNER’’S<br />

CONSULTANT<br />

PREPARE<br />

DESIGN<br />

OWNER<br />

$<br />

CONSTRUCTION OF<br />

OWNER’S DESIGN<br />

CONSTRUCTION<br />

MANAGER<br />

Trade Contractor<br />

Supplier<br />

Trade Contractor<br />

D/B Contractor<br />

30


Construction Management (CM not “at risk”)<br />

Some Advantages<br />

Fast track friendly with<br />

“just in time” design<br />

Flexible start <strong>and</strong> stop<br />

Experienced CM assists<br />

management <strong>of</strong> design/<br />

construction interfaces<br />

High Owner/Consultant<br />

dem<strong>and</strong>s<br />

Owner can weigh<br />

trade/supplier pricing<br />

against risk transfer<br />

Some Disadvantages<br />

Multiple<br />

contracts/Interfaces/bonds<br />

Cost, schedule, quality, OH&S<br />

at Owner’s risk<br />

Performance risk with Owner<br />

Difficult to control cost<br />

Requires experienced owner<br />

knowledgeable <strong>of</strong> risks<br />

Lack <strong>of</strong> project definition prior<br />

to contract award<br />

Patchwork quilt <strong>of</strong> bonds<br />

31


Construction Management (CM “at risk”)<br />

OWNER’’S<br />

CONSULTANT<br />

PREPARE<br />

DESIGN<br />

OWNER<br />

$<br />

CONSTRUCTION OF<br />

OWNER’S DESIGN<br />

CONSTRUCTION<br />

MANAGER<br />

$<br />

TRANSITION FROM CONSTRUCTION MANAGER<br />

TO GENERAL CONTRACTOR<br />

CONTRACTOR<br />

Trade Contractor<br />

Supplier<br />

Trade Contractor<br />

D/B Contractor<br />

32


Construction Management (CM “at risk”)<br />

Some Advantages<br />

“One Contract”<br />

Fast track friendly with<br />

“just in time” design<br />

Flexible start <strong>and</strong> stop<br />

Experienced CM assists<br />

management <strong>of</strong> design/<br />

construction interfaces<br />

Owner can weigh<br />

trade/supplier pricing<br />

against risk transfer<br />

OH&S at CM’s risk<br />

Some Disadvantages<br />

Risk <strong>of</strong> changes<br />

Late design<br />

Cost, schedule, quality at<br />

Owner’s risk<br />

Performance risk can still be<br />

with Owner<br />

Difficult to control cost<br />

Requires experienced owner<br />

knowledgeable <strong>of</strong> risks<br />

Lack <strong>of</strong> project definition prior<br />

to contract award<br />

Patchwork quilt <strong>of</strong> bonds<br />

33


Construction Management - General<br />

Regardless <strong>of</strong> “at risk” or “not at risk”, must<br />

clarify <strong>and</strong> then control:<br />

Contract Team (bait <strong>and</strong> switch, departures)<br />

Contract Fee<br />

Disbursements (internal, from affiliates, markups)<br />

Own Forces work<br />

Sharing risk <strong>of</strong> savings <strong>and</strong> over-runs<br />

Construction Management:<br />

Theoretically superior - but theory not always reality<br />

Often becomes “cost plus” in reality regardless <strong>of</strong><br />

pricing structure<br />

34


Design-Build / Design & Construct<br />

Owner contracts with design-build contractor<br />

to design <strong>and</strong> construct a project<br />

Design-build contractor is responsible for<br />

design, procurement <strong>and</strong> construction<br />

Owner or owner’s consultant administers the<br />

design-build contract<br />

Variations<br />

Owner’s requirements can be prepared by owner,<br />

owner’s consultant or design-build contractor<br />

May be for entire project or only for specific parts<br />

<strong>of</strong> a project (e.g. “water to wire”, turbine genset for<br />

cogeneration or wind power, recovery boiler for a<br />

pulp mill, etc.)<br />

35


Engineer-Procure-Construct (EPC)<br />

Method <strong>of</strong> project delivery in which an owner<br />

contracts with another party (EPC contractor)<br />

to:<br />

engineer;<br />

procure; <strong>and</strong><br />

construct<br />

project to meet owner’s statement <strong>of</strong> requirements.<br />

Some publications use Engineer-Procure-<br />

Construct-Install (“EPCI”)<br />

Most publications/authors define EPC as<br />

“similar to Design-Build”<br />

36


Turnkey<br />

The “turnkey” arrangement, (also known as the “package<br />

deal”, “design <strong>and</strong> build”, “clé-en-main” or “design <strong>and</strong><br />

construct”) places the duty to design <strong>and</strong> construct solely<br />

on the contractor. There is no accepted definition for<br />

each <strong>of</strong> these terms in the construction field. The term<br />

“turnkey” tends to mean the most extreme form <strong>of</strong> placing<br />

design <strong>and</strong> construction responsibility on the contractor,<br />

such that after completion the employer need only turn the<br />

key to commence operation <strong>of</strong> the constructed facility.<br />

Notwithst<strong>and</strong>ing this, the term “turnkey” will be used here<br />

to describe the more general global arrangement <strong>of</strong><br />

placing both design <strong>and</strong> construction responsibilities on<br />

one contractor” (emphasis added)<br />

From Text “Underst<strong>and</strong>ing <strong>and</strong> Negotiating Turnkey Contracts”, by<br />

Joseph A. Huse (Freshfields), Sweet & Maxwell 1997<br />

37


Build-Operate-Transfer<br />

Method <strong>of</strong> project delivery in which a private<br />

company is given a concession to finance,<br />

design, build <strong>and</strong> operate a facility<br />

(powerplant, airport, toll road, etc.) normally<br />

built <strong>and</strong> operated by the government. At the<br />

end <strong>of</strong> the concession period, ownership<br />

<strong>and</strong>/or operation <strong>of</strong> the facility is transferred<br />

to the government. Variants include BOO (no<br />

transfer back), BOOT, DBFO, FDBOM, etc.<br />

38


P3/ D-B / EPC / Turnkey Common Themes<br />

Performance obligations<br />

Quality <strong>of</strong> overall product, performance <strong>of</strong> plant,<br />

modules <strong>and</strong> equipment<br />

Output - in terms <strong>of</strong> overall production/output<br />

Schedule completion<br />

Financing entities (banks, bond investors,<br />

etc.) <strong>of</strong>ten insist on underlying D-B contract<br />

for P3 <strong>and</strong> IPP projects<br />

Significant exposure <strong>of</strong> D-B contractor to<br />

damages<br />

Many risks normally borne by owner assigned<br />

to D-B contractor<br />

39


Design–Build Relationship (Theory)<br />

OWNER’S<br />

CONSULTANT<br />

ADMINISTER<br />

CONTRACT(?)<br />

PERFORMANCE<br />

SPECIFICATIONS<br />

$<br />

OWNER<br />

DESIGN-BUILD<br />

CONTRACTOR<br />

DESIGN TO PERFORMANCE SPECIFICATIONS,<br />

PROCURE AND CONSTRUCT<br />

LABOUR<br />

SPECIALTY<br />

SUBCONTRACTORS<br />

MATERIALS<br />

AND SUPPLIES<br />

Note: Design-Build Contractor assumed to be a single integrated firm<br />

40


Design–Build Relationship (Typical)<br />

OWNER’S<br />

CONSULTANT<br />

ADMINISTER<br />

CONTRACT(?)<br />

PERFORMANCE<br />

SPECIFICATIONS<br />

$<br />

OWNER<br />

DESIGN-BUILD<br />

CONTRACTOR<br />

DESIGN TO PERFORMANCE SPECIFICATIONS,<br />

PROCURE AND CONSTRUCT<br />

DESIGN<br />

CONSULTANTS<br />

SUBCONTRACTORS<br />

EQUIPMENT<br />

SUPPLIERS<br />

Note:<br />

Design-Build Contractor is typically a joint venture,<br />

consortium, special-purpose vehicle, etc.<br />

41


Some Advantages <strong>of</strong> Design-Build<br />

Single point responsibility<br />

Opportunity for innovation <strong>and</strong> faster project delivery<br />

Efficiency (design & construction expertise together)<br />

Fitness for purpose<br />

No real alternative for proprietary technology<br />

Fewer changes <strong>and</strong> implementation simplified<br />

Reduction <strong>of</strong> claims (or number <strong>of</strong> claims)<br />

Increased flexibility to address changed conditions<br />

Reduced administrative burden for owner<br />

Cost savings <strong>and</strong> more certainty <strong>of</strong> final price<br />

Improved risk management for owner<br />

Greater ability to evaluate contractors on factors<br />

other than cost<br />

42


Some Disadvantages <strong>of</strong> Design-Build<br />

Loss <strong>of</strong> control <strong>and</strong> reduced owner involvement in<br />

design<br />

Cost <strong>of</strong> tendering (to all parties)<br />

Difficulty/time comparing different designs<br />

Cost <strong>of</strong> risks <strong>and</strong> contingencies<br />

Danger <strong>of</strong> Design-Build becoming Build-Design<br />

Environmental/regulatory processes<br />

Limited pool <strong>of</strong> qualified Design-Builders<br />

QA/QC largely in contractor’s h<strong>and</strong>s<br />

Disputes tend to be larger <strong>and</strong> more complex<br />

Management <strong>of</strong> long term risks<br />

Some lack <strong>of</strong> project definition prior to contract award<br />

43


Some Owner Considerations D-B-B/D-B<br />

Design-Bid-Build<br />

Multiple projects to spread<br />

risks<br />

High risk tolerance<br />

High return on investment<br />

Internal resources <strong>and</strong><br />

expertise<br />

Complex environmental/<br />

regulatory permitting<br />

Owner can select “best”<br />

engineer & contractor<br />

independently<br />

Design-Build<br />

Single-point responsibility<br />

“One-<strong>of</strong>f” project<br />

Low risk tolerance<br />

Marginal project<br />

No internal resources<br />

Owner has limited<br />

expertise<br />

Need for proprietary<br />

technology<br />

Need for overall<br />

Performance Guarantees<br />

44


Some Contractor Considerations D-B-B/D-B<br />

Design-Bid-Build<br />

Civil contractor with no<br />

design-build expertise<br />

No design-build track record<br />

No historical relationships<br />

with engineers & suppliers<br />

Low risk tolerance<br />

Limited resources for<br />

pursuit costs<br />

Design-Build<br />

Specialty supplier/<br />

contractor<br />

Integrated design-build<br />

contractor<br />

Design-build track record<br />

Proprietary designs/<br />

technologies<br />

Substantial resources for<br />

pursuit costs<br />

Better control <strong>of</strong> destiny if<br />

it controls architect/<br />

engineer<br />

45


P3 Relationship<br />

(Typical for Infrastructure)<br />

GOVERNMENT<br />

PUBLIC<br />

ENTITY<br />

(“”OWNER”)<br />

BOND HOLDERS<br />

SENIOR<br />

DEBT<br />

EQUITY<br />

EQUITY<br />

$ FUNDING<br />

DIVIDENDS<br />

P3 CONTRACTOR<br />

(Private Partner SPV)<br />

$ FUNDING<br />

INTEREST &<br />

PRINCIPAL<br />

BANKS/BONDS/INVESTORS<br />

$<br />

DESIGN BUILD<br />

CONTRACTOR<br />

O & M SERVICE<br />

PROVIDER<br />

DESIGN<br />

CONSULTANTS<br />

SUBCONTRACTORS<br />

EQUIPMENT<br />

SUPPLIERS<br />

Note:<br />

P3 Contractor is typically special-purpose vehicle (to be formed)<br />

46


<strong>Public</strong>-Private-Partnerships (cont’d)<br />

No universal definition <strong>of</strong> P3<br />

P3s cover a wide range <strong>of</strong> projects,<br />

depending on asset ownership, risk sharing,<br />

financing <strong>and</strong> operation<br />

CCPPP includes as P3 examples: Design-<br />

Build; O&M Contract; Design-Build-Finance-<br />

Operate; Operation Licence (e.g. IT projects);<br />

Finance Only (e.g. bond issue for project)<br />

Current economic climate creates challenges<br />

for some P3 projects that involve large risk<br />

transfer <strong>and</strong> significant financing<br />

requirements.<br />

47


Summary <strong>of</strong> Contracting Models<br />

No universally accepted industry definitions<br />

for D-B-B, D-B, Design-Construct, EPC,<br />

EPCM, Turnkey, P3, etc. in terms <strong>of</strong> specific<br />

scope <strong>of</strong> work or risk allocation<br />

Use <strong>and</strong> Abuse <strong>of</strong> St<strong>and</strong>ard Forms<br />

“Adapting” st<strong>and</strong>ard form contracts to applications<br />

other than those for which they were intended<br />

Key Points:<br />

It is contractual risk allocation, not title <strong>of</strong> contract,<br />

that is determinative <strong>and</strong> must be reviewed with<br />

care<br />

In practice, terms <strong>of</strong>ten used loosely so it is always<br />

prudent to clarify terminology before<br />

misunderst<strong>and</strong>ings arise<br />

48


Procurement Process Issues<br />

Disputes over validity <strong>and</strong> enforceability <strong>of</strong><br />

tenders is a thriving business for lawyers<br />

Knowledge <strong>of</strong> current tendering law is critical<br />

RFPs vs. RFQs vs. Request for Bid<br />

Failure to properly address tendering law<br />

issues in the invitation to tender <strong>and</strong><br />

instructions to tenderers can:<br />

Expose owner/tendering authority to liability<br />

Expose consultant who prepared tender<br />

documents to liability<br />

Disrupt <strong>and</strong> delay entire project<br />

Feed the families <strong>of</strong> many lawyers<br />

49


Procurement Process Issues (cont’d)<br />

Threshold Issue: Use Request for Tenders or RFP?<br />

Want m<strong>and</strong>atory use <strong>of</strong> same contract/performance<br />

requirements?<br />

Allow departures from contract requirements?<br />

In tender/proposal?<br />

In negotiations following identification <strong>of</strong> highest-ranked<br />

submission?<br />

Want submissions to be fixed price & irrevocable?<br />

Want “bid security”? If so, what kind, for what purpose <strong>and</strong><br />

how will it be enforced?<br />

Will there be Fairness Monitor/Process Monitor?<br />

Willing <strong>and</strong> able to entertain bilateral meetings <strong>and</strong><br />

change commercial terms prior to closing?<br />

50


Procurement Process Issues (cont’d)<br />

Request for Tenders<br />

Tendering process to which tendering law applies<br />

Contract “A” <strong>and</strong> Contract “B”<br />

Contract “A” imposes obligations on Owner<br />

Limits<br />

Flexibility<br />

Discretion<br />

Negotiations<br />

51


Procurement Process Issues (cont’d)<br />

Request for Proposals<br />

Solicitation <strong>of</strong> interest (“invitation to treat”)<br />

Very flexible<br />

Limited obligations created (other than those<br />

under the terms <strong>of</strong> the RFP)<br />

Generally leads to negotiations<br />

Negotiation risk high after selection <strong>of</strong> preferred<br />

proponent<br />

52


Procurement Process Issues (cont’d)<br />

Use <strong>of</strong> term “RFP” or “Request for Tenders”<br />

is not conclusive <strong>and</strong> courts consider:<br />

Are terms “tender”, “bid”, “bidder” etc. used<br />

anywhere in documents, correspondence, etc.?<br />

Are proposals required to be “Irrevocable”<br />

Are proposals required to give fixed price?<br />

Are proposals required to conform to contract <strong>and</strong><br />

specifications issued by owner without exception?<br />

Do tender documents refer to “award” <strong>of</strong> contract?<br />

53


Procurement Process Issues (cont’d)<br />

What are ramifications on process <strong>of</strong>:<br />

“Short-listing” entities that do not exist until<br />

contract awarded?<br />

Changes in composition <strong>of</strong> proponent teams?<br />

Changes in internal contractual structure from that<br />

on which proponent was short-listed?<br />

Are you evaluating the entities named, or<br />

really their parent companies through<br />

consolidated financial information?<br />

Should procurement process allow designbuild<br />

teams flexibility to change<br />

members/arrangements?<br />

54


Procurement Process Issues (cont’d)<br />

Bid bonds & consent <strong>of</strong> surety<br />

Questionable security or value in other than<br />

traditional tendering situation<br />

Perhaps useful for use as pre-qualification tool<br />

Competition/Participation Agreements:<br />

Contractual commitment by proponent to submit<br />

conforming proposal, backed by appropriate<br />

proposal security (e.g. L/C)<br />

Contractual commitment by owner to pay<br />

honorarium (if applicable)<br />

Addresses owner entitlement to use ideas/designs<br />

<strong>of</strong> unsuccessful proponents<br />

55


Procurement Process Issues (cont’d)<br />

Regardless <strong>of</strong> RFP or Request for Tenders,<br />

minimize amendments to process/tender<br />

documents<br />

If substantial deficiencies/conflicts in design <strong>and</strong><br />

specs become evident, consider canceling tender<br />

call<br />

Beware <strong>of</strong> using question/answer series or RFI<br />

responses to avoid amending documents<br />

Dangerous to bind them into contract!<br />

56


Procurement Process Issues (cont’d)<br />

Alternates <strong>and</strong> Alternative Proposals<br />

Consider whether alternates permitted<br />

Evaluating alternates within base proposal<br />

Evaluating alternative proposals<br />

Defining winning criteria - Base Proposal or<br />

Alternate Proposal<br />

Opportunity for others to match alternates<br />

Negotiation<br />

Governed/limited by RFP/Request for Tenders<br />

Bid shopping vs. negotiation<br />

Sequential vs concurrent negotiations<br />

57


Procurement Process Issues (cont’d)<br />

Health Care Developers Inc. v. Newfoundl<strong>and</strong><br />

(1995) N.J. No. 48 (S.C.T.D.<br />

RFP to developers for design-build-lease <strong>of</strong> clinics<br />

“Invitation to Tender” advertisement & RFP<br />

documents used mixed language<br />

Held: Tender Call, particularly because ad<br />

required <strong>of</strong>fers be irrevocable<br />

58


Procurement Process Issues (cont’d)<br />

Khoury Real Estate <strong>Services</strong> Ltd. v. Canada<br />

(Minister <strong>of</strong> <strong>Public</strong> <strong>Works</strong>) (1996) 33 C.L.R.(2d) 294<br />

(Fed.T.D.).<br />

RFP to provide modern <strong>of</strong>fice space in Fredericton for<br />

Federal Government<br />

No overall st<strong>and</strong>ard <strong>of</strong> evaluation in RFP<br />

Khoury applied for basis <strong>of</strong> scoring <strong>of</strong> its proposal<br />

Held: Tendering rules apply. Owner must demonstrate it<br />

acted fairly <strong>and</strong> disclose evaluation/scoring <strong>of</strong> proposal<br />

59


Procurement Process Issues (cont’d)<br />

Cable Assembly Systems Ltd. V. Dufferin-Peel<br />

Roman Catholic Separate School Board (2000) O.J. No.<br />

577 (Ont. SC)<br />

RFP issued for cable plant & ethernet hubs in 88 elementary<br />

schools & contemplated negotiation<br />

Board met with 3 lowest proponents <strong>and</strong> then awarded to<br />

other than Cable<br />

Held: Board had duty to be fair to all “bidders” <strong>and</strong> to act in<br />

good faith<br />

Held: Cable was treated fairly as RFP did not limit<br />

negotiations to preferred proposal<br />

60


Summary - Procurement Process Issues<br />

Tendering Law can extend to RFP<br />

Court looks to substance not “style”<br />

Duty <strong>of</strong> fairness may apply<br />

Law applicable to tenders may or may not<br />

apply depending on terms <strong>of</strong> RFP<br />

Practice Tip: Draft RFP as true RFP but<br />

then treat it as if it will be held to be a<br />

Request for Tenders<br />

61


<strong>Managing</strong> <strong>Risks</strong> < Bid Closing<br />

Leading edge/bleeding edge<br />

New technology? Pushing the envelope?<br />

New application? European vs. N.A. practices?<br />

History <strong>of</strong> comparable work? Bridges vs. schools?<br />

Contract value > 150% <strong>of</strong> previous largest contract<br />

No substitution for knowledge <strong>and</strong><br />

experience<br />

Of consultants<br />

Of contractors/subcontractors/suppliers<br />

Of lawyers <strong>and</strong> other advisors<br />

People experience vs. corporate experience<br />

62


<strong>Managing</strong> <strong>Risks</strong> < Bid Closing (cont’d)<br />

Schedule – Political or Real?<br />

Allow sufficient time for preparation <strong>of</strong> bids<br />

Allow sufficient time for performance <strong>of</strong> work<br />

Consider environmental, noise & other restrictions<br />

Set contract completion date in advance <strong>of</strong><br />

required completion date<br />

Especially where occupancy/revenue generation is<br />

critical<br />

Provide some flexibility in subsequent contracts<br />

that are dependent upon completion<br />

E.g. leases, purchase contracts, production commitments<br />

3 years to plan <strong>and</strong> design but only 30 days to<br />

tender <strong>and</strong> then 3 months to construct!<br />

63


<strong>Managing</strong> <strong>Risks</strong> < Bid Closing (cont’d)<br />

Manage risks by appropriate pricing:<br />

Use a mixture <strong>of</strong> lump sums, unit prices, cash<br />

allowances, etc.<br />

Obtain fixed price for part <strong>of</strong> the scope <strong>of</strong> work,<br />

with cash allowance for other parts that are<br />

incomplete or may require large contingencies<br />

Bid Form/Price Breakdowns<br />

Allow for unbalanced bids?<br />

Influence on evaluation if broken down poorly?<br />

Quantity variations?<br />

Manage risks by “Early contractor<br />

involvement”?<br />

64


<strong>Managing</strong> <strong>Risks</strong> < Bid Closing (cont’d)<br />

Specifications/Drawings/Construction<br />

Avoid incomplete drawings <strong>and</strong> specifications<br />

Coordinate to ensure free <strong>of</strong> internal conflicts<br />

Recurring problem: 6” pipe in 4” wall syndrome<br />

Ensure consistency <strong>of</strong> terms <strong>and</strong> terminology<br />

Someone must be responsible for coordination<br />

Too little time <strong>and</strong> <strong>of</strong>ten too little money increases<br />

risks:<br />

Use <strong>of</strong> inappropriate precedents<br />

Too much cut <strong>and</strong> paste without conforming end product<br />

Avoid reliance on “Design Intent” to cover errors &<br />

omissions in drawings <strong>and</strong> specifications<br />

65


<strong>Managing</strong> <strong>Risks</strong> < Bid Closing (cont’d)<br />

Subsurface Conditions<br />

No such thing as too much geotechnical<br />

investigation prior to tendering<br />

Consider joint geotechnical program during<br />

tendering to manage the risk <strong>and</strong> reduce<br />

contingencies regardless <strong>of</strong> who bears the risk<br />

Consider risk sharing specific items<br />

E.g. where slope stability or potential presence <strong>of</strong> rock is<br />

an issue, perhaps:<br />

Contractor bears first portion <strong>of</strong> additional costs<br />

Owner <strong>and</strong> Contractor share next level <strong>of</strong> costs<br />

Owner (or Contractor) bears remainder<br />

66


<strong>Managing</strong> <strong>Risks</strong> < Bid Closing (cont’d)<br />

Subsurface Conditions (cont’d)<br />

Opportunity <strong>and</strong> time for investigation<br />

Risk allocation/management<br />

Baseline geotechnical report?<br />

Field investigations funded by owner during proposal<br />

competition?<br />

Issues re disclosure <strong>of</strong> field investigations by other<br />

proponents to owner/successful bidder<br />

Failure to disclose information can change initial<br />

assumed risk allocation<br />

67


<strong>Managing</strong> <strong>Risks</strong> < Bid Closing (cont’d)<br />

Labour<br />

Assess open shop/union shop issues<br />

Addressing <strong>and</strong> managing labour issues is critical,<br />

especially for out <strong>of</strong> province contractors<br />

Availability <strong>of</strong> skilled labour<br />

Keeping the labour force when competition arises from<br />

other projects <strong>of</strong>fering overtime/longer hours<br />

If longer work week/overtime required to keep existing<br />

force or attract more labour, who pays?<br />

If not available, is this force majeure?<br />

68


<strong>Managing</strong> <strong>Risks</strong> < Bid Closing (cont’d)<br />

Change Order Process<br />

Contracts must have workable processes for<br />

changes<br />

Colautti Construction v. City <strong>of</strong> Ottawa (1984),<br />

46 O.R. 2d 46 (Ont. C.A.) (emphasis added):<br />

“There is no doubt that this contract, drawn as it was to protect<br />

taxpayers, attempted to limit the liability <strong>of</strong> the City to such an<br />

extent that one would expect that not even the ordered rotation <strong>of</strong><br />

the seasons could be reasonably anticipated by the Contractor.<br />

The problem with contracts such as these is that they are so<br />

rigid <strong>and</strong> so restricting that the parties tend to amend them by<br />

their actions during the course <strong>of</strong> the contract. That was the<br />

situation in this case. There were several significant changes <strong>and</strong><br />

additions as to the work ordered by the City during the contract.<br />

None <strong>of</strong> these were in writing. All but the items in dispute in this<br />

case were paid for by the City.”<br />

69


<strong>Managing</strong> <strong>Risks</strong> < Bid Closing (cont’d)<br />

Owner <strong>and</strong> Contractor must both consider<br />

some additional key contractual risk issues,<br />

including:<br />

Performance Guarantees<br />

Performance Specifications<br />

Liquidated Damages<br />

Consequential Damages<br />

70


Performance Guarantees<br />

Heart <strong>of</strong> the contract but <strong>of</strong>ten poorly drafted<br />

Especially true in industrial contracts<br />

Close collaboration required between lawyers<br />

<strong>and</strong> consultants<br />

Rarely can consultants or lawyers working alone<br />

draft clear <strong>and</strong> enforceable performance<br />

guarantees<br />

Enforceability dependent on quality <strong>and</strong><br />

completeness <strong>of</strong> drafting<br />

71


Performance Guarantees (cont’d)<br />

Focus on inputs <strong>and</strong> outputs<br />

If inputs not to spec, are outputs guaranteed?<br />

Two levels <strong>of</strong> Performance Guarantees<br />

Performance <strong>of</strong> Facility as a whole<br />

Performance <strong>of</strong> individual components,<br />

equipment, subsystems <strong>and</strong> systems<br />

Keep the distinction clear throughout the<br />

documents!<br />

72


Performance Guarantees (cont’d)<br />

Key questions for performance guarantees<br />

What is guaranteed<br />

Performance tests<br />

Who develops them <strong>and</strong> when?<br />

When are tests performed?<br />

Who performs tests?<br />

How are measurements taken? Frequency? Number?<br />

Use average <strong>of</strong> all or discard highest <strong>and</strong> lowest?<br />

Consequences if tests stopped or fail?<br />

Due to shortages/problems attributed to owner<br />

Due to deficiencies/problems in equipment<br />

73


Performance Specifications<br />

Often not well drafted<br />

Often fail to address “Big Picture”<br />

Establish logical structure <strong>and</strong> simplified<br />

section referencing<br />

For each component part <strong>of</strong> project, identify<br />

overall performance requirement separately from<br />

detailed requirements<br />

Use consistent numbering format throughout!<br />

Only specify details where critical to Owner<br />

Detailed specifications can undermine<br />

performance specifications <strong>and</strong> enforceability <strong>of</strong><br />

performance guarantees<br />

74


Performance Specifications (cont’d)<br />

Use <strong>of</strong> general reference “st<strong>and</strong>ards”<br />

“St<strong>and</strong>ard Industry Practice”, “Prudent Utility<br />

Practice” <strong>and</strong> other “Motherhood Provisions”.<br />

<strong>Public</strong> Utility vs. IPP<br />

“Current Practice”<br />

Define what you mean<br />

References to Codes <strong>and</strong> St<strong>and</strong>ards<br />

Some codes contain discretionary items or require<br />

contract to specify certain requirements.<br />

Application <strong>of</strong> Code where items not specified.<br />

Additional load factors or capacity reductions for<br />

codes <strong>and</strong> st<strong>and</strong>ards<br />

75


Liquidated Damages<br />

Liquidated Damages vs. Penalties<br />

Two edged-sword – represent the maximum<br />

amount recoverable if the event to which they<br />

are tied occurs<br />

Sample Contract Definition:<br />

“Liquidated Damages” are not a penalty but represent the<br />

amount(s) agreed to be paid by the Contractor to the Owner<br />

as the result <strong>of</strong> the happening <strong>of</strong> a specified event, which<br />

amount(s) the parties have agreed to be not a penalty but to<br />

represent a genuine <strong>and</strong> reasonable pre-estimate <strong>of</strong> the<br />

damages that the Owner will suffer as a result <strong>of</strong> the<br />

happening <strong>of</strong> the specified event, <strong>and</strong> which the parties have<br />

agreed in advance would be difficult or impossible to quantify<br />

upon the happening <strong>of</strong> the specified event.”<br />

Relief from forfeiture<br />

76


Consequential Damages<br />

“Neither party shall be liable to the other for<br />

special, indirect, consequential or punitive<br />

damages resulting from or arising out <strong>of</strong> this<br />

Contract, including without limiting the<br />

generality <strong>of</strong> the foregoing any loss or<br />

damage resulting from loss <strong>of</strong> use, revenue,<br />

pr<strong>of</strong>it or opportunity…”<br />

Often inconsistent with Liquidated Damages<br />

No universal definition <strong>of</strong> “consequential<br />

damages”!<br />

In the absence <strong>of</strong> a universal definition, difficult to<br />

assess exposure/risk to parties<br />

77


<strong>Managing</strong> <strong>Risks</strong> < Award<br />

Harmonize Contract Documents prior to<br />

contract execution<br />

Ensure precedents within documents have been<br />

properly adapted/modified to suit contract<br />

Applies to specifications as well as<br />

commercial/legal parts <strong>of</strong> contract<br />

Integrate results <strong>of</strong> bid clarifications <strong>and</strong><br />

negotiations<br />

Exclude “Extraneous” Material<br />

Q&As<br />

Pre-Tender Minutes <strong>of</strong> Meeting<br />

78


<strong>Managing</strong> <strong>Risks</strong> < Award (cont’d)<br />

Include or Exclude Contractor’s Proposal?<br />

Should proposal be merged with<br />

Performance Specifications?<br />

Including proposal in contract:<br />

Contractor’s perspective/hope:<br />

qualifies & defines/limits<br />

scope/responsibility<br />

Owner’s perspective/hope:<br />

exp<strong>and</strong>s scope/responsibility<br />

Often forms basis <strong>of</strong> disputes <strong>and</strong> claims, <strong>and</strong><br />

raises issues <strong>of</strong> liability/responsibility<br />

79


<strong>Managing</strong> <strong>Risks</strong> < Award (cont’d)<br />

Letters <strong>of</strong> Intent <strong>and</strong> Limited Authorization to<br />

Proceed<br />

What is the “Intent”?<br />

Award <strong>of</strong> contract?<br />

Or merely intention to negotiate? Exclusivity?<br />

“Agreements to agree” generally not<br />

enforceable at law<br />

Letters <strong>of</strong> Intent can be binding or nonbinding,<br />

depending on terms<br />

80


Project Example: Roadwork<br />

Custom D-B-B contract over budget<br />

Project broken down into components by<br />

contract type:<br />

Logging<br />

Clearing <strong>and</strong> grubbing<br />

Fencing<br />

Relocation <strong>of</strong> watermain <strong>and</strong> service connections<br />

Relocation <strong>of</strong> hydro, telephone, etc.<br />

Provision <strong>of</strong> alternate access for local residences<br />

New roadworks<br />

Lighting <strong>and</strong> traffic control<br />

New specifications based on st<strong>and</strong>ard form<br />

MoT <strong>and</strong> municipal specs<br />

81


Project Example: Roadwork (cont’d)<br />

Result:<br />

Potential for disaster averted as major survey<br />

error discovered during performance <strong>of</strong> the work<br />

Re-packaging provided opportunities for local<br />

specialized <strong>and</strong> First Nations contractors <strong>and</strong> thus<br />

more competition<br />

Project completed within schedule<br />

Net savings <strong>of</strong> more than 40% over original price<br />

in single D-B-B contract<br />

Potential for claims mitigated by contracting<br />

strategy<br />

82


Practice Tip<br />

Three R’s for identifying <strong>and</strong> managing risks<br />

Read the tender documents carefully <strong>and</strong><br />

thoroughly after properly identifying, assessing,<br />

planning <strong>and</strong> managing the risks, <strong>and</strong> before<br />

issuing them for tender / submitting tender<br />

Read the complete contract carefully <strong>and</strong><br />

thoroughly before executing the contract<br />

Read the contract carefully <strong>and</strong> thoroughly<br />

whenever a dispute arises <strong>and</strong> then comply with<br />

the contract regarding notice periods, etc.<br />

Scanning is not reading!<br />

83


Questions?<br />

Helmut K. Johannsen, P.Eng., C.Arb.<br />

604 631 4819<br />

hjohannsen@fasken.com<br />

DM_Van#7461943v1

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!