Critical Path Method Schedule (CPM)<br />
Weaknesses<br />
• CPM does not readily discern nor identify the distinction<br />
between “hard” logic links and “s<strong>of</strong>t” logic links. S<strong>of</strong>t logic<br />
can be used to distort and/or hide available flexibility (float)<br />
within the construction program<br />
• CPM does not readily graphically portray potential “conflict”<br />
between trade crews, work area & locations within the<br />
construction sequence.<br />
• With CPM there are many ways to write the logic <strong>of</strong> the project,<br />
and unfortunately can prove to be self-serving for whoever<br />
creates the schedule.<br />