19.11.2014 Views

Blackburn Wastewater Treatment Plant Upgrade Study

Blackburn Wastewater Treatment Plant Upgrade Study

Blackburn Wastewater Treatment Plant Upgrade Study

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

BLACKBURN WASTEWATER<br />

TREATMENT PLANT UPGRADE STUDY<br />

Prepared for:<br />

The City of Prince George<br />

1100 Patricia Boulerard<br />

Prince George, B.C. V2L 3V9<br />

Prepared by:<br />

Reid Crotitber & Partners Ltd.<br />

Consulting Engineering Worldwide<br />

300 - 4170 StiU Creek Drive<br />

Burnnby, BC<br />

V5C 6C6<br />

Phone: (604) 298-6181<br />

Far: (604) 294-8597<br />

November, 1999<br />

Projwt No. 34918-00 (3)


<strong>Blackburn</strong> <strong>Wastewater</strong> <strong>Treatment</strong> <strong>Plant</strong> <strong>Upgrade</strong> <strong>Study</strong><br />

SECTION<br />

Table of Contents<br />

TITLE PAGE NO .<br />

1 STUDY BACKGROUND AND OBJECTIVES ................................................... 1-1<br />

Introduction .................................................................................................... 1-1<br />

Blackbum WWTP .......................................................................................... 1-2<br />

Lansdowne Road WWTP .............................................................................. 1-3<br />

Collection System .......................................................................................... 1-3<br />

<strong>Upgrade</strong> Options ............................................................................................. 1-4<br />

. .<br />

Ammonia Toxmty Issues .................................................. ............................ 1-4<br />

. .<br />

Population and Flow Projechons .................................................................. 1-5<br />

1.7.1 Outline .......................................................................................... 1-5<br />

1.7.2 Design Populations ...................................................................... 1-5<br />

1.7.3 Design <strong>Wastewater</strong> Flows ............................................................ 1-6<br />

............................................................<br />

1.7.4 Design <strong>Wastewater</strong> Loads 1-8<br />

. 1.7.5 Wet Weather Flow Impacts . 1-8<br />

1.7.6 Wet Weather Flows 1-9<br />

......................................................................<br />

Regulatory Background ............................................................................... 1-10<br />

.........................................<br />

1.8.1 Blackbum WWTP Discharge Permit 1-10<br />

1.8.2 Lansdowne Road WWTP Discharge Pennit 1-10<br />

1.8.3 BC Municipal<br />

.<br />

Sewage<br />

.<br />

Regulations ........................................... 1-11<br />

.....................................................................<br />

1.8.4 Ammonia Toxlclty 1-12<br />

2 VI MITGATION MEASURES ..................................................................................... 2-1<br />

2.1 Introduction ................................................................................................. 2-1<br />

2.2 I/I Reduction Plan .......................................................................................... 2-2<br />

2.2.1 Inflow Reduction ......................................................................... 2-2<br />

2.2.2 Infiltration Reduction ................................................................... 2-2<br />

........................................................................<br />

2.3 Rehabilitation Cost Estimates 2-3<br />

3 AUDIT OF EXISTING FACILITIES ......................................................................... 3-1<br />

3.1 Blackbum <strong>Wastewater</strong> <strong>Treatment</strong> <strong>Plant</strong> ....................................................... 3-1<br />

3.1.1 Outline .......................................................................................... 3-1<br />

3.1.2 Preliminary <strong>Treatment</strong> ................................................................. 3-1<br />

3.1.3 Secondary <strong>Treatment</strong> ................................................................... 3-2<br />

3.1.4 Effluent Disposal ......................................................................... 3-2<br />

3.1.5 Sludge <strong>Treatment</strong> ......................................................................... 3-2<br />

.............................................<br />

3.2 Lansdowne Road <strong>Wastewater</strong> <strong>Treatment</strong> <strong>Plant</strong> 3-2


Table of Contents<br />

SECTION TITLE PAGE KO .<br />

3.2.1 Outline .......................................................................................... 3-2<br />

3.2.2 Preliminary <strong>Treatment</strong> ................................................................. 3-3<br />

3.2.3 Primary <strong>Treatment</strong> .................................................................... 3-3<br />

3.2.4 Secondary <strong>Treatment</strong> ................................................................ 3-3<br />

3.2.5 EMuent Disposal ...................................................................... 3-4<br />

3.2.6 Sludge <strong>Treatment</strong> ......................................................................... 3-4<br />

3.3 Operations Staff ............................................................................................. 3-5<br />

3.4 Concjusion .....................................................................................................<br />

3-5<br />

4 WASTEWATER TREATMENT OPTIONS ........................................................... 4-1<br />

Option 1 ......................................................................................................... 4-1<br />

4.1.1 Outline .............. I: .......................................................................... 4-1<br />

4.1.2 Design Information ...................................................................... 4-2<br />

4.1.3 Cost Estimate ............................................................................... 4-3<br />

Option 2 ......................................................................................................... 4-3<br />

4.2.1 Outline .......................................................................................... 4-3<br />

4.2.2 Design Information ...................................................................... 4-4<br />

4.2.3 Cost Estimate ............................................................................... 4-5<br />

Option 3 ......................................................................................................... 4-6<br />

4.3.1 Outline .......................................................................................... 4-6<br />

4.3.2 Design Information ...................................................................... 4-7<br />

4.3.3 Cost Estimate ............................................................................... 4-7<br />

Option 4 ......................................................................................................... 4-8<br />

4.4.1 Outline .......................................................................................... 4-8<br />

4.4.2 Design information ...................................................................... 4-9<br />

4.4.3 Cost Estimate ............................................................................. 4-10<br />

Option 5 ........................................................... ........................................... 4-10<br />

4.5.1 Outline ........................................................................................ 4-10<br />

4.5.2 Design Information .................................................................... 4-12<br />

4.5.3 Cost Estimate ............................................................................. 4-12<br />

Option 6 ....................................................................................................... 4-13<br />

4.6.1 Outline ........................................................................................ 4-13<br />

4.6.2 Design Information .................................................................... 4-14<br />

4.6.3 Cost Estimate ............................................................................. 4-17<br />

Option 7 ....................................................................................................... 4-18<br />

4.7.1 Outline ........................................................................................ 4-18<br />

4.7.2 Design Information .................................................................... 4-19<br />

4.7.3 Cost Estimate ............................................................................. 4-23<br />

Life Cycle Cost Analysis ............................................................................. 4-24<br />

(ii)


Table of Contents<br />

SECTION TITLE PAGE NO .<br />

5 EVALUATION OF OPTIONS ..................................................................................... 5-1<br />

. .<br />

5.1 Decision Cr~ter~a ............................................................................................ 5-1<br />

5.1.1 Introduction .................................................................................. 5-1<br />

. . 5.1.2 Cost Cnter~a ................................................................................. 5-2<br />

. .<br />

5.1.3 Performance Criter~a .................................................................... 5-2<br />

. .<br />

5.1.4 Operational Cntena ...................................................................... 5-3<br />

5.1.5 Environmental and Aesthetic Criteria .......................................... 5-3<br />

5.2 Evaluation Techniques ................................................................................... 54<br />

5.2.1 Introduction ............................................................................... 54<br />

5.2.2 Weighted Analysis of Evaluation Criteria ................................... 5-5<br />

5.2.3 Pair-Wise Comparison ................................................................. 5-5<br />

5.3 Evaluation Results ..............:...........................................................................<br />

5-6<br />

6 RECOMMENDED OPTION ........................................................................................ 6-1<br />

6.1 Introduction .................................................................................................... 6-1<br />

6.2 Reduced Inflow/Infiltration .......................................................................... 6-1<br />

6.3 Existing Downtown Sewerage System .......................................................... 6-2<br />

6.4 Upgrading Plan ............................................................................................... 6-2<br />

6.5 Option 1 Design Information ......................................................................... 6-3<br />

6.6 Project Staging ............................................................................................... 6-4<br />

6.7 Overall Implementation Program ................................................................... 6-5<br />

APPENDIX A ............................ STANTEC CONSULTING LTD . STUDY CONCLUSIONS<br />

APPENDIX B ...................... ESTIMATED CAPITAL AND 25 YEAR LIFE CYCLE COSTS<br />

APPENDIX C ..............................................<br />

DECISION WORKSHOP . OCTOBER 19. 1999<br />

WORKSHOP NOTES<br />

APPENDIX D .............................................. DECISION WORKSHOP - OCTOBER 19, 1999<br />

RANKING/COMPARISON RESULTS<br />

APPENDIX E ...................................... now CALCULATIONS FOR SEWER UPGRADES


SECTION 1<br />

STUDY BACKGROUND AND OBJECTIVES


SECTION 1.0<br />

STUDY BACKGROUND AND OBJECTIVES<br />

1.1 INTRODUCTION<br />

Integral to the continued growth and development of the City of Prince George is a<br />

reliable sewage collection and treatment system that meets current environmental<br />

standards. Over the years, steady development has taken place in the city central areas<br />

and the Nechako area to the north of the city core. Within the <strong>Blackburn</strong> area, which<br />

is located east of the Fraser River in the east sector of the City, development has been<br />

curtailed due to limited water supply to this area. In addition to the water supply<br />

system, irhastructure is in place for sewage collection and treatment. The City of<br />

Prince George is serviced primarily by one main wastewater treatment facility located<br />

on Lansdowne Road. Outlying subdivisions or sewage collection areas such as the<br />

Blackbum area are serviced by small satellite wastewater treatment facilities.<br />

Until recently, there has been a development moratorium in place in the Blackbum<br />

area due to inadequate water supply. The water supply system has now been upgraded<br />

and the moratorium lifted. It is anticipated that the Blackbum area will experience a<br />

healthy population growth rate and the planned population horizon of 5,000 could be<br />

realized in the next 25 years.<br />

With the anticipated growth and development in the Blackbum area, the City now<br />

wishes to consider the most appropriate and economic option for wastewater<br />

collection/treatment, as well as being in compliance with the new Municipal Sewage<br />

Regulations. The issues that drive the evaluation of options are the capacity of the<br />

existing treatment facility to meet effluent quality criteria; and, the high inflow and<br />

infiltration @'I) peak flows into the collection system that impart hydraulic limitations<br />

both at the Mackus Road pumpstation and at the treatment facility. .<br />

Further to the issues related to the existing sewage collection and treatment system and<br />

the anticipated population growth projections for the Blackbum area, the City of<br />

Prince George commissioned Reid Crowther and Partners Ltd. in September 1999, to<br />

prepare a study to evaluate options on how to manage sewage collected within the<br />

<strong>Blackburn</strong> sewerage area. This report presents these f ndings; identifies and evaluates<br />

options using both economic and non-economic criteria; and recommends an<br />

implementation plan.


Section 1.0 -Project Background and Objectives<br />

The overall aim of this study is to develop a long term plan that incorporates the latest<br />

issues regarding the Blackbum collection, pumping and treatment system, and<br />

establishes whether the City should proceed with upgrading the Blackbum wastewater<br />

treatment facility independently or to consolidate Blackbum sewage flows into the<br />

Lansdowne Road WWTP via connecting purnpinglpipeline infrastructure. Under both<br />

scenarios implementation of appropriate VI reduction measures is required.<br />

A brief summary of the existing wastewater treatment facilities and related issues is<br />

presented in the following sections.<br />

1.2 BLACKBURN WWTP<br />

Construction of the Blackbum wasiewater treatment facility commenced early in 1976<br />

and the facility was commissioned in late 1976 to service a population of 2,500. The<br />

existing facility is comprised of a bar screen, and aerated primary and secondary<br />

lagoons.<br />

The effluent discharge requirements are for BOD5 5 45 mgL, TSS 5 60 mg/L plus a<br />

fecal colifom limit. Any upgrade to the plant would be based on the new Municipal<br />

Sewage Regulations. Presently the Department of Fisheries and Oceans are requesting<br />

an ammonia toxicity limit, which to date has not been required by the Ministry of<br />

Environment, Lands and Parks. This situation may change in the future.<br />

The facility is presently at both its hydraulic and organic design capacities.<br />

Winterlspring thaw conditions and heavy rains contribute high inflow/infiltration peak<br />

wet weather flows (PWWF). Effluent quality is also impacted during the spring to<br />

summer transition as the primary and secondary lagoons warm up. Lagoon


Section 1.0 - Proj~t Background and Objectives<br />

temperatures in the winter drop to between 0°C and 5"C, and in the summer they can<br />

exceed 20°C.<br />

The lagoon aeration equipment is also reaching the end of its design life. The facility<br />

upgrade will be for a population of 5,000, which is equivalent to a 25 year design<br />

horizon.<br />

1.3 LANSDOWNE ROAD WWTP<br />

The Lansdowne Road wastewater treatment facility was recently upgraded to a Year<br />

2026 design horizon with a contributing population of 115,000 and average dry<br />

weather flow of 44.5 Mud. The current contributing population is less than 90,000.<br />

As a result there is adequate design capacity at the plant should the decision be made<br />

to transfer raw sewage flows fiorn the Blackbum sewerage area to Lansdowne Road<br />

WWTP. All potential impacts of transporting flows to the Lansdowne Road WWTP<br />

would, however, need to be considered in detail during this study to ensure viability of<br />

such an option.<br />

1.4 COLLECTION SYSTEM<br />

Most of the construction work on the sewage collection system for the <strong>Blackburn</strong><br />

sewerage area was completed in 1976, and consists of 25 kilometers of both gravity<br />

and forcemain sewers. The pipe network is mostly PVC pipe with some of the larger<br />

diameter pipes being concrete. Soil type in the area is mainly clay in nature with the<br />

pipes laid in sand bedding backfilled with native soils.


Section 1.0 -Project Background and Objectives<br />

The main snowfall in the area occurs from November to April. During winter/spring<br />

thaw conditions, the collection system experiences high IeveIs of UI, raising flow<br />

levels above the capacity of the treatment plant. To determine the nature of the Vi<br />

problem, the City completed a study in June, 1999 to assess the condition of the<br />

pipework, manholes and connections. Manholes that are located in lowlying areas<br />

have been found to be the main contributor of inflow. Snowmelt and water that ponds<br />

around these manholes enters through manhole lids and cracks or deficiencies in the<br />

manhole itself. The City's rehabilitation program will consider the raising of manhole<br />

rims, sealing of manhole lids and the grouting of inner walls. Elimination of cross<br />

connections and repair of sub-standard connection construction that contributes to L'l<br />

will also be part of the rehabilitation work.<br />

1.5 UPGRADE OPTIONS<br />

The principal objective of this study is to examine all issues concerned with the<br />

<strong>Blackburn</strong> sewerage area in order to determine if the City should proceed with<br />

upgradelexpansion of the existing wastewater treatment facility and the Mackus Road<br />

pumpstation; or, transfer raw sewage flows to and consolidate treatment at the<br />

Lansdowne Road WWTP.<br />

For this study, sewer upgrade and treatment expansion options have been identified.<br />

Assessment of the study options includes an appraisal of both economic and noneconomic<br />

criteria. Cost analyses includes full life cycle costing of both capital and<br />

operating/maintenance costs over the planning horizon time-kame of 25 years.<br />

Frequently, the least capital wst can have the highest long-term life-cycle cost. Noneconomic<br />

criteria include environmental impacts, ease of operation, system flexibility<br />

and pubiic/stakeholder preferences.<br />

1.6 AMMONIA TOXICITY ISSUES<br />

There are uncertainties as to whether the upgraded <strong>Blackburn</strong> wastewater treatment<br />

facility will have ammonia toxicity limits placed on the effluent, \vhich is discharged<br />

to the Fraser River. This study takes into account this eventuality.<br />

Ammonia toxicity can place a wastewater treatment emuent in noncompliance with<br />

Fisheries Act requirements. The requirements of the Act are interpreted to mean that<br />

emuents discharged into an aquatic environment should be non-toxic, as measured in<br />

a static bioassay. The Act does not provide for effluent dilution or dispersion to<br />

mitigate toxicity.


Section k .O - Project Background and Objectives<br />

Ammonia limits for effluents discharged to aquatic environments, as published by US<br />

EPA are based on toxicity considerations. These limits can be used to judge the likely<br />

impact of wastewater treatment plant effluents. The EPA limits are approximately<br />

based on the toxicity of ammonia to relevant water species, modified by a safety<br />

factor. Recent modifications of these criteria have been adopted to reflect the findings<br />

of recent studies. These studies note that cold water toxicity is not as severe as<br />

previously found and winter limits need not be as restrictive since more sensitive<br />

juve~le fish are not present during winter months. This study assesses these<br />

considerations.<br />

1.7 POPULATION AND FLOW PROJECTIONS<br />

1.7.1 Outline<br />

Fundamental to a long-term strategic upgrade plan is a thorough assessment of future<br />

population growth, and hence, changes in anticipated wastewater flows. Projections<br />

need to be evaluated in light of the City's Ifl rehabilitation program, Municipal<br />

Sewage Regulations, the availability of adequate water supply and development plans<br />

for the area. The estimated existing serviced popuiation is 1,800. However, not all of<br />

the serviced population is connected to the domestic sewage collection system. The<br />

estimated population CO~eCted to the collection system is 1,500. It is anticipated that<br />

the population growth in this area will be vigorous with steady growth estimated at<br />

approximately 4 percent per annum.<br />

1.7.2 Design Population<br />

The City's estimate for the year ending 1998 is a serviced population of 1,800.<br />

Population growth in the <strong>Blackburn</strong> area over the past 25 years has been slow, due in<br />

part to limited water supply. Water supply to the area has been upgraded and there is<br />

now sufficient capacity to service a fuH development population of 5,000.<br />

With adequate water supply for the Blackbum area, the projected population growth<br />

rate is estimated to be approximately 4 percent, which is greater than the projected<br />

growth rate for the entire City which is 1 percent. Assuming a growth rate of 4.2<br />

percent, the population will increase from 1,800 to 5,000 in 25 years.<br />

Population projections for the <strong>Blackburn</strong> sewage collection area are presented in Table<br />

1.1.


Section 1.0 -Project Background and Objectives<br />

Tablel.1- <strong>Blackburn</strong> Sewage Collection Area<br />

Population Projection<br />

Design <strong>Wastewater</strong> Flows<br />

The flow criteria used in 1976 for the design of the Blackbum WWTP are:<br />

Population 2,500<br />

Per capita contribution, Lkapfd 375<br />

ADWF. m3/d 945<br />

PWWF, m3/d 4,350<br />

The design flow criteria us4 in 1993 to plan the Lansdowne Road WWTP upgrade<br />

and expansion are:<br />

Population 1 15,000<br />

Per capita contribution. L/ca~/d


Section 1.0 -Project Background and Objectives<br />

PWWF, m3/d 11 5,000<br />

Flow records for 1998 for the Blackbum WWTP provide the following information:<br />

Population 1,800<br />

Per capita contribution (calculated), Ucapld 250<br />

ADWF, m31d 450<br />

PWWF, m3/d 4,500<br />

The ADWF flow records for lackb bum indicate a very low per capita contribution. It<br />

is likely that of the estimated 1,800 population within the Blackbum sewage collection<br />

area, not all are connected to the collection system. If it is assumed that approximately<br />

75 percent of the Blackbum population, which is 1,350, is connected to the system, the<br />

calculated per capita contribution is 335 Ucapld. For this study, the per capita<br />

contributory flow is assumed to be 350 Llcapld, which is 10 percent lower than the<br />

design value used for the Lansdowne WWTP. Because of the more rural setting of the<br />

<strong>Blackburn</strong> area; the probable lower use of dishwashershome garburators; smaller<br />

residence size; and, the fact that the sewage pipework is only 25 years old, a 10<br />

percent decrease in per capita contributory flow from 385 to 350 can be rationalized.<br />

The following design flow conditions are assumed for 111 development in the<br />

<strong>Blackburn</strong> area:<br />

Population 5,000<br />

rn Per capita contribution, LJcapld 350<br />

ADWF, m3ld 1,750<br />

The contribution of flow from the Blackbum sewage collection area at full<br />

development in comparison to the design flow capacity of the Lansdowne Road<br />

WWTP is calculated at less than 5 percent.


Section 1.0 - Project Background and Objectives<br />

1.7.4 Design <strong>Wastewater</strong> Loads<br />

The design raw sewage BODs and TSS concentration criteria used in 1993 to plan the<br />

Lansdowne Road WWTP upgrade and expansion is:<br />

These values have been adopted for this study to permit evaluation of various options.<br />

The following design raw sewage BODS and TSS annual loadings are assumed at full<br />

development in the <strong>Blackburn</strong> area:<br />

The design raw sewage BOD5 and TSS a~mualoadings for a design population of<br />

115,000 at the Lansdowne Road WWTP is:<br />

The present 1999 raw sewage BODs and TSS annual loadings at the Lansdowne Road<br />

WWTP is estimated at:<br />

s ,.<br />

!:<br />

I<br />

.-:<br />

:-,.<br />

, .<br />

The proportion of BODs and TSS load h m the <strong>Blackburn</strong> sewage collection area, at<br />

full development in comparison to the design load capacity of the Lansdowne Road<br />

WWTP is calculated at less than 5 percent.<br />

1.7.5 Wet Weather Flow Impacts<br />

One factor that governs the need to expand a wastewater treatment plant is the wet<br />

weather flow component. This component of the flow is dependent on the following:<br />

Type of sewer system (separatefwmbined).<br />

Topography of the Seniced area (piping above or below the water table, possibility<br />

that manhole flooding occurs).<br />

. 1-8<br />

Waorrcrs~~~Gsrn 0r.w -.=.a8<br />

&'<br />

tI*l.W


Section 1.0 -Project Background and Objectives<br />

Physical characteristics of the underground piping (old/new/materials).<br />

rn<br />

Connection policies (roof drain connections, etc.).<br />

Review of wet weather flow mitigation policies and plans is essential. Should a<br />

reduction program prove practicable and cost effective, lower peak flows would occur<br />

after changes are implemented and thereby defer expanding plant infrastructure.<br />

1.7.6 Wet Weather Flows<br />

As detailed in the Stantec Consulting Ltd. report completed June, 1999, VI is a serious<br />

problem in the <strong>Blackburn</strong> sewage collection area and corrective action is required.<br />

The original 1976 design information for the Blackbum treatment facility lists the<br />

following criteria:<br />

rn Contributing population 2,500<br />

ADWF, m3/d 945<br />

In the future, as development exceeds 2,500 population, the facility would be doubled<br />

in capacity to accommodate a population of 5,000 with ADWF doubling, but PWWF<br />

remaining constant.<br />

Based on these design parameters, the lagoon facility would provide an eMuent<br />

quality of BOD6 20 mg/L and TSS< 20 mfl. Monitoring data from the City<br />

indicates that the facility up to now has reliably achieved these two targets and is in<br />

compliance with pennit requirements.<br />

It is important to note that the original design appears to have taken into consideration<br />

not only winter operating conditions, but also identified flow variations due to winter<br />

thaw conditions and spring raidthaw conditions. In the first stage of development,<br />

during wintedspring thaw conditions, because of the layout and locations of manholes<br />

and the coliection pipework, PWWF would be high, amounting to nearly 4.5 times<br />

ADWF, primarily because of inflow due to flooding around manholes adjacent to<br />

natural drainage streams. A second component would be due to infiltration due to wet<br />

ground andtor high groundwater conditions in Iow lying areas. In the second stage of<br />

development, UI would be reduced so that PWWF would remain at 4,350 m3/d and the<br />

PWWFlADWF ratio reduced to approximately 2.5.<br />

. .<br />

1<br />

,& 1 .<br />

- 1-9<br />

H .*mIIrnn>.3C*,,mmId Wnxll m<br />

mmm


Section 1.0 -Project Background and Objectives<br />

Rewrded results for 1999 indicate ADWF at 450 m3/d and PWWF at 4,500 rn3/d. The<br />

PWWF/ADWF ratio is 10:1, which is much greater than the design value of 4.6:l.<br />

The excessive I/I flows consume available capacity of the domestic sewage collection<br />

system as well as the Mackus Road pumpstation. Also because a large component of<br />

the flow is snowmelt, these flows measurably reduce sewage temperatures which<br />

impacts the efficiency of any treatment facility. Without an I/l reduction program in<br />

place, excessive III would limit future development in the Blackbum collection area<br />

because of limits on sewer capacity; and, as well jeopardize the operation of the<br />

treatment facility so that effluent quality is in non-compliance with permit<br />

requirements. The Stantec Consulting Ltd. report identified these issues. The report<br />

concluded that the most wst effective plan was to implement a rehabilitation program<br />

for VI reduction and reammendid as a first step that work be undertaken to seal<br />

manholes to reduce inflow.<br />

1.8 REGULATORY BACKGROUND<br />

1.8.1 <strong>Blackburn</strong> WWTP Discharge Permit<br />

The discharge permit for the <strong>Blackburn</strong> WWTP is covered under Pennit PE-3868. An<br />

amended permit was issued by BC MOELP on March 23, 1992, which requires that<br />

the plant eflluent meet the following not to exceed criteria:<br />

Discharge flow, m3/d 1,375<br />

The effluent quality must not exceed the above maximums based on a monthly<br />

composite sample made up of four grab samples taken over a two-hour period at<br />

maximum flow. The amended permit stipulates that although effluent disinfection is<br />

not required at this time, the existing chlorination facility must be maintained for use<br />

in the event that it is required in the future.<br />

1.8.2 Lansdowne Road WWTP Discharge Permit<br />

The discharge permit for the Landsdowne WWTP is covered under Permit PE-0146.<br />

An amended permit was issued by BC MOELP on March 29, 1996, which requires<br />

that the plant effluent meet the following not to exceed criteria:


Section 1.0 - Project Background and Objectives<br />

Discharge flow, m3/d 45,000<br />

The effluent quality must not exceed the above maximums based on a weekly<br />

composite sample made up of four grab samples taken over a two-hour period at<br />

maximum flow. The permit stipulates that although effluent disinfection is not<br />

required at this time, the existing chlorination and dechlorination facilities must be<br />

maintained for use in the event that faecal coliform contamination of water kom the<br />

College Heights well becomes evident in the future.<br />

1.8.3 BC Municipal Sewage Regulations<br />

The BC MOELP has recently published revised Waste Management Act, Municipal<br />

Sewage Regulation, which may have a future impact on updated permits for both<br />

plants. Any plant upgrade after July 15, 1999 will require an application to be made<br />

under these new regulations, which will impact the collection system, treatment and<br />

the effluent discharge requirements, indicated as follows:<br />

No sanitary sewer overflow (SSO) of less than 1 in 5 year return period will be<br />

allowed after January 1, 2004 unless there has been a liquid waste management<br />

plan (LWMP) where the population is > 10,000, or a study where the population is<br />

< 10,000, to quantify and qualify the SSO.<br />

Similarly for Vi, the maximum day flow should not exceed 2 times ADWF unless<br />

there has been a LWMP or study to address the issues.<br />

The aim will be to reduce the SSO's by 10 percent per year.<br />

Where there will be a treatment plant expansion to accommodate an increase in<br />

flow greater than 20 percent of the previous maximum authorized flow, an<br />

environmental impact study will be required.<br />

Any flow above 2 times ADWF will require primary treatment as a minimum, and<br />

primary and secondary emuent should be combined for discharge.<br />

The receiving water would require careful monitoring with a minimum acceptable<br />

40:l dilution ratio. Appropriate discharge locations would need to be identified<br />

that comply with regulations.<br />

The impact of the new Municipal Sewage Regulation on the future upgrading of the<br />

Blackbum wastewater system infrastructure needs to be considered in detail.


Section 1.0 -Project Background and Objectives<br />

1.8.4 Ammonia Toxicity<br />

In solution, ammonia exists in two forms, ionized ammonium (NH43, and unionized<br />

ammonia w3). Fractionation of these two species depends upon the water pH and<br />

temperature. At higher pH and temperature values, a greater fraction of the effluent<br />

ammonia will exist in he unionized form. It is this unionizd form which is toxic to<br />

aquatic life in relatively low concentrations.<br />

Neither <strong>Blackburn</strong> nor Lansdowne Road WWTPs are required to achieve an effluent<br />

ammonia concentration limit in their respective discharge permits. However, the new<br />

Municipal Sewage Regulation stipulate that the maximum allowable emuent ammonia<br />

concentration at the "end of pipe" must be determined from a back calculation from<br />

the edge of the initial dilution zone. The back calculation must consider the ambient<br />

temperature and pH characteristics of the receiving water and known water quality<br />

guidelines.<br />

Furthermore, the new Municipal Sewage Regulation stipulates that a person must not<br />

discharge effluent, unless "...the discharge passes a 96 hour LC50 bioassay test as<br />

defined by the Environment Canada's Biological Test Method, Reference for<br />

Determining Acute Lethality of Effects of Rainbow Trout (Reference Method EPS<br />

l/RM/13)".<br />

The above stipulation does not apply if "...the discharge is diluted such that at the<br />

outside boundary of the initial dilution zone, the dilution ratio exceeds 100:l and the<br />

discharger demonstrates to the satisfaction of the manager that the discharge does not<br />

adversely affect the receiving environment."<br />

Environment Canada's position is based on Section 36(3) of the Fisheries Act (198%<br />

which states: "No person shall deposit or permit the deposit of a deleterious substance<br />

of any type on water Wuented by fish. Environment Canada chooses to define<br />

deleterious substances in large part by means of the whole effluent- test, is. without<br />

dikution by the receiving water.<br />

In the event that existing <strong>Blackburn</strong> WWTP is upgraded or expanded, consideration<br />

will have to be given to designing the new plant to achieve year round or seasonal<br />

nitrification to reduce or remove the possibility of ammonia toxicity.


APPENDIX D<br />

DECISION WORKSHOP - OCTOBER 19,1999<br />

RANKINGICOMPARISON RESULTS


City of Prince George - Decision Workshop October 19. 1999


City Of Prince George - Decision Workshop Oclober 19, lYnu


City of Prince George - Decision Workshop October 19, 1999<br />

I I L I I I I<br />

OVERALL RESULTS'<br />

I-- --<br />

Wei$atlng . .-<br />

Ciiterin WelgM I 3 --<br />

Financial 3.5 7.0 17.5 15.8<br />

Performance - 2.3 12.8 10.5<br />

Operational 2.4 15.9 13.4 4.9<br />

Emriicnmental 1.7 11.2 4.3 5.2


APPENDIX C<br />

DECISION WORKSHOP - OCTOBER 19,1999<br />

WORKSHOP NOTES


MINUTES OF MEETING<br />

PR~ECT NAME:<br />

<strong>Blackburn</strong> <strong>Wastewater</strong> <strong>Treatment</strong> <strong>Plant</strong> <strong>Upgrade</strong> <strong>Study</strong><br />

LOCATION: PAGE: 10f1<br />

DATE OF October 19, 1999 OATE: November 1,1999<br />

MEETING:<br />

PROJECT NO.: 34918-00 -03<br />

CONTRACT NO.:<br />

PRESENT: Andy Ribul (AR)- City of Prince George - Dave Dyer (DD)- City of Prince George<br />

Norm Gobbi (NG)- City of Prince George - Bany Rabinowitz - RC<br />

Frank Blues (FB)- City of Prince George - LesNemeth -RC<br />

Gary Champagne (GC)- City of Prince George - Andy North - RC<br />

Ritch Girard - MOE<br />

- Stuart Lawrence - L&M Engineering<br />

PURPOSE:<br />

DlSTRlBClTlON TO<br />

ALL ABOVE AND:<br />

WRITTEN BY:<br />

Decision Workshop<br />

Stuart Lawrence<br />

DESCRlmlOPl<br />

Service Area Population - DD stated that the current service area population was<br />

closer to 1,500. BR stated that for the study an aggressive population growth rate<br />

has been assured to reach 5,000 population in 25 years = 4.2% growth.<br />

AR stated that rehabilitation work just started for VI control; 14 manholes done to<br />

date.<br />

FB interested in defaults of NPV's of 5 and 10 year yI rehab programs. LN<br />

handed out tables.<br />

FB asked if cost estimates for downtown sewer upgrades included cost estimates.<br />

LN stated that costs included in Options 1 to 5.<br />

Life cycle costs are all in 1999 dollars. O&M costs are those costs unique to each<br />

option.<br />

FB noted that these are slip problems along river banks, especially near correction<br />

facility. Needs preliminary assessment. Could rule out use of routing? May even<br />

be a problem along highway.<br />

Access to manholes along gravity route (road) could be difficult; 4m + turnarounds<br />

required.<br />

Land acquisition costs not included.<br />

Development potential with gravity main along Hwy 16.<br />

Animonic toxicity not a current issue.<br />

Mackus Rd. PS pumps need to be replaced now. What is correct pump size?<br />

These minutes are in the writer's best interpretation of discussions held<br />

during the meeting. Please inform the writer of any noteworthy omissions or<br />

errors.


APPENDIX B<br />

ESTIMATED CAPITAL AND 25 YEAR LIFE CYCLE<br />

COSTS


<strong>Blackburn</strong> WWTP <strong>Treatment</strong> Options<br />

Option 2 1<br />

Decommission <strong>Blackburn</strong> WWTPmransfer Flows to Lamdowoe Road WWTP<br />

I I I I I


<strong>Blackburn</strong> WWTP <strong>Treatment</strong> Options 1<br />

option 3 1<br />

.Modify <strong>Blackburn</strong> WWTP for Storagflransfer Flows to Lansdowne Road WWTP<br />

I I I I<br />

I<br />

I I I I<br />

Notes:<br />

Annual C&M cost for Blackbum sewage lagoons 1999-2007 is 545,000-$56,571<br />

Annual O&M cost for Blackbum storage lagoons 2008-2024 is $20,000<br />

-<br />

Incremenlal08rM cost for uealing Blackbum wastewater at Lansdowne Road WWTP2008-2024<br />

I I I I I I


Nores.<br />

Annual O&M cost for Blackbum sewage lagoons 1999-2007 is $45,000-$56371<br />

Annual O M cost for <strong>Blackburn</strong> sewage lagoons for PWWFueatmenl2008-2024 is $20.000<br />

Annual O M cmt for pumpstation 2008-2024 is $10,000 1<br />

-<br />

Incrementai 0&M cosl for treating Blackbum wastewater at Lansdowne Road WWTP 2008-2024<br />

I I 1 1 I I


[<strong>Blackburn</strong> ---<br />

WWTP <strong>Treatment</strong> Options 1 -- .- I I<br />

Option 5 1 1<br />

blaintain <strong>Blackburn</strong> WWTP for Flows>2*ADWFmraosfer ElowscZ*ADWF to Lansdowne Road WWTP<br />

I I I I I I<br />

Notes:<br />

Annual O&M oasi for <strong>Blackburn</strong> sewage lagoons 1999-2007 is $45.000-$56,571<br />

Annual O M cosl for <strong>Blackburn</strong> sewage lagoons for PWWF treatment 2008-2024 is $20,000<br />

incremental O&M cost lor treating <strong>Blackburn</strong> wastewater at Lansdowne Road WWTP 2008-2024<br />

I I I I I I


Blackbum WWTP <strong>Treatment</strong> Options<br />

Option 6a<br />

<strong>Upgrade</strong> and Expand <strong>Blackburn</strong> WWTP Lagoodo Nitrification<br />

! I I


<strong>Blackburn</strong> WWTP <strong>Treatment</strong> Options 1<br />

Option 7a<br />

Decommission <strong>Blackburn</strong> WWTP ~ @W~CO~S~NC~<br />

New Mechanical Secondary <strong>Plant</strong>/No Nitri6cation<br />

I I I I I I<br />

Notes: 1 1 1 1<br />

Annual O&M cost lor Blackbum sewage lagoons 1999-2007 is %45.OW$56,5?1<br />

Annual O&M cost for new Blackbum mechanical plant 2008 to 2024 is $129,362-$204,442<br />

I I I I I


APPENDIX A<br />

STANTEC CONSULTING LTD.<br />

STUDY CONCLUSIONS


City of Prince George<br />

<strong>Blackburn</strong> Sanitary Sewer<br />

InfltrationlInflow Studv - 1999<br />

Prepad lor:<br />

City of Prince George<br />

Prepared by:<br />

Stantec Comdtiug Ltd.<br />

June, 1999


5.0 CONCLUSIONS<br />

I<br />

'\<br />

-.<br />

5.1 RESULTS OF STUDY<br />

The study Field investigations included the folfowing works:<br />

instaliing flow muen in nine manholes,<br />

installing peak level indicaturs in six manhoIes,<br />

visd investigations incIuding observing and estimating observed inflow to<br />

selected doles.<br />

visual observations depth bf now titcough selected manholes.<br />

Cornpatisons were made between p ro-h theoretical generated flows at the manholes<br />

equipped with flow mtm, as well as a comparison of observed inflow estimates to the<br />

recorded inflow (recorded flow less theoretical gcncrared flows).<br />

Although estimated observed inflows an only esdmates, it appears that estimated<br />

observed inflows amounted to only approximately 75% of the recorded inflow. The.<br />

additional 25% may be h m manholes which were not open4 or may be from leaking<br />

mains or service connections. The 1991 tefevision camen inspectiom indicate that some<br />

infiltrarion to piping. either crackad or bmken pipes or service connections. was<br />

observed at that time.<br />

Two observed conditions w m<br />

possible mediation activities.<br />

of &gnificaot interest in arsessin~infl~wf~ltration and<br />

On March Zth, bH OKSW was observed to have storm water from a backedvp ditch<br />

flowing dictly into the rim On March 26th. City crews ched out the ditch and<br />

diverted stormwater away from this manhole. Flow mettr No. 7, downsaeam.<br />

immediately recorded a drop in fIow of ;rppmxhtely 400 cu.d&y. This ilfusaatcs<br />

tbat signifiwnf inflow an occur from only a few manhoIes if the rims are below the<br />

bund bl or below stonnwarer kvels. either in ditches, creeks oc standing water<br />

-<br />

during evly spring snowmelt.<br />

On Mmh 25. MH EAK43A exhibited inflow from the cover - the rim was below ground<br />

kvel and had standins W r around ir. On April 9, the sunding water had d-cd to<br />

below the rim of the manhok, however, leakage was observed from the bax of the<br />

ma~~hok. A simh situation was observed at MJi NKSjD, where on March 25, there<br />

was inflow from the rim and bricking and on Aprii 7, there was inflow from the base.<br />

Observations at these NO Imtions indicate that, although the worn inflows appear to<br />

occur during the firsr snow-mlt, iflows also continue 3s the thaws.<br />

I9<br />

c,lyotRinuetCorge<br />

Blrlburn Smiury Sever Infilmhdlnllwr Sm&<br />

,7,".l R m m . llln 19V9


As noted previously, comparisons of recorded flows to theoretical generated flows<br />

indicates that inflowlinfiluation appears to k the result of snowmelt or rainfall events.<br />

and does not occur yqr round. This comparison also indicates that, except for<br />

snowrne1tlr;linfall evenu. then is relatively little year-round infiltration to the <strong>Blackburn</strong><br />

system.<br />

This is important in understanding and mitigating inflowfinfiitration as both<br />

identification of problem arcy and monitoring the results of upgradiing works is<br />

effactiveiy limited to king done during thest events. Si rainfall events occur with on<br />

an irregular basis. the mos effective time ta identify problems and to manitor rtsSs of<br />

uppdiig wiil continue to be during the spring snow-melt period. A comparison of the<br />

1997, 1998 and 1999 snow melt events indicates that sp~g<br />

snow-melt and it's effect on<br />

the Blackbum sewer system can also vary widely so care will need to be taken in<br />

interpreting the results of upgrading activities.<br />

5.2 SUMMARY OF RECOMMENDATIONS FOR<br />

UPGRADING<br />

The recommendations of this study include:<br />

a) upgrading manholes. including repairs to manhole stmcnucs, cappinglxaling of<br />

unused connections and Suds and d i g and waterproofing mahhole~ subject to<br />

being overtopped by srorm wm. See Section 4.1 and 4.3 for derails.<br />

a) upgrading piping, as determined by the 1991 television camera work (if not already<br />

done)<br />

b) thorough cleanins of kouf sscdons of the sanitary sewer system prior to tdevision<br />

came~ins@o& to determine if inflow from broken pi& is occurring, and repair<br />

of any infiltratins piping. See Section 4.4 for details.<br />

C) monitoring of specific areas of the system prior to and during spriag mow melt in<br />

order to limit inflow from avoidable dirch~creck backup. See Section 4.2 for details.<br />

d) plumbing insptcrions to determine if basement sump pumps are insnlled and<br />

connected to the smiwry system.<br />

e) smoke testingto identify mof dr;lim or parking area drains c onnd to the sanirvy<br />

system.


CITY OF PRINCE GEORGE<br />

Forcemain from the existing<br />

<strong>Blackburn</strong> WWTP site to the<br />

high point on Graves Road.<br />

1,720m of 200 rnm dia. forcemain<br />

from the intersection of Mackus<br />

Road and North <strong>Blackburn</strong> Road<br />

to a high point on Highway 16.<br />

3,100rn of 200 mm dia. gravity<br />

sewer main from the end of the<br />

forcemain to the Regional<br />

Correctional Centre tie-in.<br />

100m of 200 rnm dia. sanitary<br />

sewer syphon from the Yellowhead<br />

Bridge to the intersection of 3rd<br />

Ave. and Taylor Drive.<br />

1 Wm of 300 mm dia. gravity sewer<br />

along Taylor Drive to the intersection<br />

with 15th Ave.<br />

180m of 300 rnm dia. gravity sewer<br />

along 15th Ave. from Taylor Drive<br />

to Birch St. Connect to existing<br />

525 mm dia. sewer main.<br />

------ Exist. Sanitary Collection Mains<br />

Prince George<br />

Airport<br />

J<br />

[J I<br />

,yJ<br />

LC'<br />

Blackbum Sanitary Collection Area<br />

I<br />

! City of Prince George<br />

<strong>Blackburn</strong> <strong>Wastewater</strong> <strong>Treatment</strong> <strong>Plant</strong><br />

<strong>Treatment</strong> Options <strong>Study</strong><br />

ENGINEERING LIMITED<br />

RECOMMENDED OPTION - FLOW TRANSFER<br />

Figure 6.1<br />

-


Section 6.0 -Recommended Option<br />

6.3 EXISTING DOWNTOWN SEWERAGE SYSTEM<br />

Flows transferred from the Blackbum catchment will connect into the existing<br />

sanitary sewer mains at the Regional Correctional Centre that ultimately<br />

discharge into the 600rnrn diameter City trunk sanitary sewermain on Taylor<br />

Drive.<br />

The estimated future peak pump flow rate h m the Mackus Road sewage lift<br />

station is 50 Us (4350 m3/d), based on the ultimate 5,000 population. With<br />

successll implementation of III reduction measures this flow rate could be<br />

reduced to 40 Us. The following upgrades are based on the more conservative<br />

50 L/s and should be reviewed at a detailed design stage. The section of<br />

existing 200mm diameter sewer main from the discharge point of the 200mm<br />

diameter syphon, at MH ~ ~ 2to 3 the a intersection of the 525mm diameter<br />

main at Birch Street, will need to be upgraded to a 300mrn diameter pipe at a<br />

minimum grade of 0.3% to handle the future pumped peak flows of<br />

approximately 0.05 m3/s.<br />

The section of gravity sewer main which requires upgrade totals 430 meters in<br />

length.<br />

The wst for this upgrading work (which requires significant road restoration)<br />

at a unit cost of $250 per lineal metre is 430 x 5250 is approximately $107,500.<br />

This cost includes all associated appurtenances, manholes and restoration<br />

costs. Pipe bursting could be considered during the predesign stage as an<br />

alternative to reduce restoration costs.<br />

Flow capacity of existing mains on the Yellowhead Bridge and within the<br />

subdivision on the west side of the Fraser River are listed in Appendix E.<br />

6.4 UPGRADING PLAN<br />

The City's accelerated 3-4 year implementation plan is to decommission the<br />

existing Blackbum WWTP by 2003, and all flows transferred for treatment at<br />

the Lansdowne Road WWTP via a new forcemain and trunk gravity sewer<br />

from the Mackus Road pumpstation. An accelerated III reduction program is<br />

to be initiated and completed to reduce the volume of wastewater being<br />

transferred during wet weather and snowmelt conditions. The existing Mackus<br />

Road pumpstation is to be upgraded and a new, small pumpstation constructed<br />

at the <strong>Blackburn</strong> WWTP site to transfer flows generated in the area adjacent to<br />

the plant to the Mackus Road pumpstation.


Section 6.0 -Recommended Option<br />

Key activities or capital works associated with the upgrading plan are as<br />

follows:<br />

Implement and complete VI reduction program.<br />

Decommission lagmns and rehabilitate site for other use.<br />

<strong>Upgrade</strong> Mackus Road pumpstation to handle projected increasd flows.<br />

Construct trunk gravity sewer and forcemain to transfer all flows from<br />

<strong>Blackburn</strong> sewerage area to Lansdowne Road WWTP.<br />

<strong>Upgrade</strong> downtown sewage collection pipework to handle increased flows<br />

from Slackburn sewerage a&.<br />

Construct sewage purnpstation at Blackbum W P site and construct<br />

connecting forcemain discharging to Mackus Road pumpstation.<br />

6.5 OPTION 1 DESIGN INFORMATION<br />

Population<br />

ADWF, m3/d<br />

PWWF, m3/d<br />

Pipework<br />

Forcemain from intersection of Mackus Road and North<br />

Blackbum Road to a high point on Hwy. 16.<br />

Diameter, mm 200<br />

Length, m 1,720<br />

Gravity sewer main from the end of 200 forcemain to the<br />

Regional Correctional Centre tie-in<br />

Diameter, rnrn 300<br />

Length, m 3,100<br />

Forcemain from the existing <strong>Blackburn</strong> WWTP site to the high<br />

point on Graves Road<br />

Diameter, mm 150<br />

Length, m 1,330<br />

Sanitary sewer syphon connecting to downtown sewage<br />

collection system<br />

Diameter, mm<br />

Length, m


Section 6.0 -Recommended Option<br />

Gravity sewer upgrade, along Taylor Drive, 15" Ave, Ash Street<br />

to Birch Street; connect to 525 diameter sewer.<br />

Diameter, mm<br />

Length, m<br />

Pumpstation<br />

<strong>Upgrade</strong> Mackus Road PS for PWWF capacity of 50 Us; 1<br />

duty/l standby pumps, plus back-up power.<br />

Suppiy and install PS at existing <strong>Blackburn</strong> WWTP site to<br />

service residence along Foreman and Graves Roads; capable of<br />

pumping 5 US; 1 duty11 standby pumps.<br />

Miscellaneous<br />

R&oreflandscape existing Blackbum WWTP site.<br />

6.6 PROJECT STAGING<br />

Stage 1 (2000-2001)<br />

Complete inflow rehabilitation work to reduce flows by 2,170 m3/d.<br />

Complete accelerated 3 year infiltration rehabilitation work to reduce<br />

flows by an additional 1,070 m3/d, using the following techniques:<br />

> Video inspectionkmoke testing of pipelines.<br />

3 Repair MH's.<br />

> Repair leaking pipework.<br />

> Repair private connections.<br />

9 Repair municipal connections.<br />

Stage 2 Predaign Option I (2001)<br />

New forcemain and gravity trunk sewer from Mackus Road PS to<br />

Regional Correctional Centre tie-in.<br />

Downtown sewer work<br />

Mackus Road PS upgrades<br />

New forcemain from Blackbum JWTF site to connect to Mackus Road<br />

PS<br />

Foreman Road PS<br />

<strong>Blackburn</strong> WWTP restorationilandscaping<br />

Stage 3 (2002)<br />

Complete 111 reduction program so that PWWF/ADWF=2.0<br />

6-4<br />

34 ' P%O>ECT~'ZW~~~I~~."JJI~~~~<br />

R-',m> h


Section 6.0 -Recommended Option<br />

Complete detailed design Option 1<br />

Stage 4 (2003)<br />

Complete construction of Option 1<br />

6.7 OVERALL IMPLEMENTATION PROGRAM<br />

An implementation program and capital expenditure plan have been developed<br />

to meet the City's wastewater coHection and treatment needs until 2024. The<br />

plan has been designed to defer capital costs where feasible. A summary of the<br />

overall implementation program and associated capital expenditures is<br />

presented in Table 6.1.<br />

Table 6.1 OveraI1 ~rn~lementation Program<br />

2001 IInfltration mitigation & predesign Option 1<br />

2002 lComplete infiltration mitigation & detailed design Option 1<br />

1 2003 (Complete construction of Option 1


SECTION 6<br />

RECOMMENDED OPTION


SECTION 6.0<br />

RECOMMENDED OPTION<br />

6.1 INTRODUCTION<br />

Both economic and non-economic criteria were used to evaluate each of the<br />

seven upgrarllng options presented in this report. Combining the results of the<br />

Decision Workshop in the evaluation, the recommended upgrading plan for the<br />

<strong>Blackburn</strong> sewerage area is Option 1. Option 1 involves completion of the III<br />

mitigation measures, decommissioning the Blackbum WWTP and pumping all<br />

sewage currently treated at the plant to the Lansdowne Road WWTP. A plan<br />

of the recommended option is presented in Figure 6.1.<br />

This section outlines the basic requirements for the recommended upgrading<br />

plan. For this option, sewerage upgrades are discussed with the aim of<br />

presenting an implementation plan that satisfies the necessary environmental<br />

requirements while at the same time minimizing capital expenditures by<br />

adopting a staged upgrade approach. There are significant capital investments<br />

required to complete yI reduction and transfer <strong>Blackburn</strong> flows to the<br />

Lansdowne Road WWTP. However, by adopting a "just-in-time"<br />

implementation plan, the City should be able to defer required expenditures<br />

until they are absolutely necessary. This approach will also allow the City to<br />

consider the impact of population growth projections for the <strong>Blackburn</strong> area.<br />

6.2 REDUCED INFLOWflNFILTRATION<br />

As detailed in Section 2, there are two possible approaches to completing the<br />

VI rehabilitation program. One is a five year program and the other is a 10<br />

year program. However, the City plans to adopt an accelerated 3 to 4 year<br />

program with the goal of meeting BC Municipal Sewage Regulations for<br />

ADWF and PWWF flow requirements by 2004 and at the same time ensuring<br />

compliance with the discharge permit for the Blackbum WWTP.<br />

Recommended MH repair's will be completed by the end of 2000; as well as<br />

video inspection and smoke testing of pipelines plus complete readily<br />

repairable VI and complete 'off-street' mode to eliminate VI from roof,<br />

perimeter foundation and yard connections.


SECTION 5<br />

EVALUATION OF OPTIONS


SECTION 5.0<br />

EVALUATION OF OPTIONS<br />

5.1. DECISION CRITERIA<br />

5.1.1 Introduction<br />

The purpose of this section is to establish the framework for a Decision<br />

Workshop as part of the Blackbum WWTP treatment options study. Under<br />

consideration are potential options for treating wastewater either at an<br />

upgraded Blackbum WWTP or by transferring the flows to the larger<br />

Lansdowne Road WWTP.<br />

This section presents a process that can assist the decision makers in evaluating<br />

the recommendations for new projects and programs to meet the hture<br />

wastewater treatment requirements of the Blackbum sewage collection area.<br />

The planning framework and model used to evaluate the options and arrive at a<br />

series of conclusions is presented. It must be noted that this process utilizes a<br />

series of tools which, when combined with other criteria, will assist the overall<br />

decision making process.<br />

The following key elements of the project were addressed during the Decision<br />

Workshop held with City staffon October 19, 1999:<br />

A total of 7 potential upgrade options and two sub-options presented for<br />

evaluation using both economic and non-economic criteria.<br />

A decision is required about whether to maintain two separate wastewater<br />

treatment piants or provide one consolidated plant at the Lansdowne Road<br />

WWTP site.<br />

If a consolidated plant at Lansdowne Road is selected as the preferred<br />

option, a decision is required as to the preferred transfer pipeline route and<br />

configuration between the Blackbum sewage collection area and the<br />

Lansdowne Road WWTP.<br />

The issue of ammonia toxicity on the receiving water from a <strong>Blackburn</strong><br />

WWTP discharge needs to be addressed within the workshop process.<br />

In each of the above four elements, the selection of the most appropriate option<br />

is not simply an economic issue. Various economic and non-economic factors<br />

must be taken into consideration. One of the most important elements that<br />

feeds into the decision process is the establishment of the planning criteria


Section 5.0 -Evaluation of Ootions<br />

used by stakeholders to compare options. The planning criteria reflect what is<br />

important to stakeholders when making decisions about wastewater system<br />

upgrade options. Evaluation criteria that were developed through Reid<br />

Crowfher's experience on similar projects elsewhere are presented below. The<br />

list of factors or criteria that form the basis for the comparative evaluation of<br />

the options have been categorized into the following four criteria:<br />

Cost criteria<br />

Technical criteria<br />

Operational criteria<br />

Environmental and aesthetic criteria<br />

Within each category there are many evaluation criteria, however to ensure<br />

that the process is neither too complex nor time consuming, a specific selection<br />

of evaluation criteria have been chosen.<br />

5.1.2 Cost Criteria<br />

Cost criteria relate to short-term and long-term expenditures. Capital costs and<br />

operating and maintenance (O&M) costs are the two major components used in<br />

cost comparisons. Together, these components define the life-cycle cost.<br />

Capital Cost<br />

This cost is a measure of the immediate cost that may be subject to<br />

fmancing. The least risk is attached to this cost; i.e. it will occur regardless<br />

of long-term variations in plant loads, fmancing, etc.<br />

Life-Cycle Cost<br />

Tnis cost is a measure of the total project cost over its design life. It<br />

includes the capital cost, but also incorporates O&M expenditures and the<br />

ultimate salvage value. Life-cycle costs are expressed in "present value"<br />

dollars.<br />

5.1.3 Performance Criteria<br />

Generally, criteria falling within this category are related to the ability of the<br />

facility to meet its objectives consistently. These criteria will be reflected in<br />

the costs; i.e. where a facility is judged less capable of meeting the<br />

performance standards, a greater safety factor will be included in the design.<br />

However, with any facility, there remains some risk that it will not perform up<br />

to expectations. It is this risk that is reflected in the perfomance criteria. The<br />

following are the performance criteria suggested for evaluating alternatives:


Section 5.0 -Evaluation of Options<br />

Reliability and Robustness<br />

The proven ability of the system upgrade to satisfy design objectives or<br />

reguiatory requirements and the ability of the system to operate<br />

successfully under adverse conditions and fluctuating influent<br />

characteristics.<br />

FlexibilitylComplexityISophistication<br />

The ability of the system to be modified or operated in another mode to<br />

meet short-term or long-term requirements and the amount and frequency<br />

of control or operator input that will be required to have the facility/system<br />

be successful in its intended application.<br />

Ease of Construction and Land Requirements<br />

The potential impact on existing operations and/or current land ownership<br />

when new facilities/systemsare built.<br />

5.1.4 Operational Criteria<br />

Operational criteria include those that affect the effort of and acceptance by the<br />

plant's operating and maintenance staff. A system that is difficult to<br />

comprehend or that requires a significant ongoing labour commitment is less<br />

likely to be operated with due diligence. When this occurs, notwithstanding<br />

design intent, a system will not perform to its capabilities. Operational criteria<br />

used in alternative evaluation include the following:<br />

Ease of Operation and Maintenance<br />

The "friendliness" of the system to operator control and the ease with<br />

which equipmentkystems may be removed from service, maintained, and<br />

returned to service. In addition, this criterion should reflect the frequency<br />

and duration of maintenance efforts.<br />

Safety<br />

Although wastewater systems design incorporates the necessxy safety<br />

measures, some facilities are more inherently safe than others. This<br />

criterion is intended to reflect that characteristic.<br />

Stamng<br />

Tne number of operations and maintenance personnel required to operate<br />

the facility.<br />

5.1.5 Environmental and Aesthetic Criteria<br />

Environmental and aesthetic criteria relate to off-site impacts of the<br />

facilityfsystern. Those relating to receiving water quality are extremely<br />

important to the success of this project.


Section 5.0- Evaluation of Options<br />

Effect on Surrounding Area<br />

The potential for degradation of the surrounding area (e.g. the receiving<br />

water quality, or transfer pipeline routes) under normal and upset operating<br />

conditions.<br />

Odonr PotentiallAir Emission<br />

The potential for malodorous gas release from a system under normal and<br />

upset conditions.<br />

VisuaVNoiselTraffic<br />

A measure of the visual obtrusiveness of the system or facility, the<br />

magnitude of noise generation and the amount of buck traffic associated<br />

with the system.<br />

The cost criteria for the various options have been developed within this<br />

document. In cases where there is no significant difference in the life cycle<br />

costs of two options, the decision regarding the preferred option must be based<br />

on the non-economic criteria listed above. During the Decision Workshop, the<br />

key project elements were evaluated using both the economic and noneconomic<br />

criteria by the technical and administrative personnel from the City,<br />

a representative from MOE and key project team members from the Reid<br />

Crowther team.<br />

5.2 EVALUATION TECHNIQUES<br />

5.2.1 Introduction<br />

There are a variety of techniques that can be used to assist decision-makers<br />

with selacting options. The most usefd technique nil1 depend on the nature<br />

and magnitude of the trade-offs identified and the stakeholders involved.<br />

There are a variety of recognized technical methods available, which vaty<br />

considerably in complexity and include:<br />

Holistic assessment<br />

Options are ranked based on structural information, but no formal decision<br />

model. Trade-offs are implicit using this technique which could be<br />

considered to be too judgmental for this project.<br />

Pair-wise comparison<br />

Each of the criteria b m every option is paired with all other options and<br />

individually evaluated or scored based on which perfoms best.


Section 5.0 -Evaluation of Options<br />

Rating and weighting<br />

The criteria are first technically rated and these scores are modified by<br />

assigning a weighting determined from the stakeholders preferences to the<br />

options , to produce a matrix of results.<br />

Multi-attribute trade-off analysis<br />

The most complex technique, best suited to a large number of options and<br />

criteria, but not considered appropriate for this process.<br />

Based on the options requiring evaluation, the planning team has therefore<br />

defmed the following two approaches for assisting in option selection:<br />

5.2.2 Weighted Analysis of Evaluation Criteria<br />

In this technique the ratings are numerical values to be developed on specific<br />

quantitative and qualitative results at the workshop. In the first step,<br />

participants are asked to weight the relative importance of the four criteria, i.e.<br />

cost criteria, technical criteria, operational criteria, and environmentaVaesthetic<br />

criteria, using a total of 10 points, see Form 5.1. In the second step,<br />

participants are asked to weight each of the criteria using a 10-point scale, see<br />

Form 5.2. These two initial steps help to identify the overall level of<br />

importance that participants place on individual criteria. Each option can then<br />

be ranked for each criterion on a score of 1 to 5 (poor to excellent) and then the<br />

weights are applied to the results of the ranking exercise, see Form 5.3.<br />

5.2.3 Pair - Wise Comparison<br />

A oneon-one decision matrix comparison process is utilized to establish the<br />

individual criteria rankings of each of the options, see Form 5.4. Within each<br />

criteria matrix, each option is paired with every other option and evaluated<br />

against each of the criteria. The option that performs best is assigned a value<br />

based on a 'pass - fail' as follows:<br />

if the option is better, a score of 1 is assigned;<br />

if the option is worse, a score of 0 is assigned; and<br />

if the option is no better or no worse, a score of 0.5 is assigned.<br />

By summing up the values for each option, this approach provides an<br />

indication of which option is technically superior. The drawback of this<br />

approach is that it does not take into account the magnitude or extent of the<br />

performance of one option versus another. It also does not take into account


Section 5.0 -Evaluation of Options<br />

part, be addressed by adding the weighting factors to the results and by using<br />

the following approach in parallel.<br />

5.3 EVALUATION RESULTS<br />

Attached as Appendix C and D are the results of the October 19, 1999<br />

Decision Workshop. Attending this workshop were the following individuals:<br />

City of Prince George<br />

Gary Champagne<br />

Andy Zbul<br />

DaveDyer<br />

Frank Blues<br />

Norm Gobbi<br />

MOELP<br />

Ritch Girard<br />

L&M Engineering<br />

Reid Crowther<br />

Bany Rabinowitz<br />

LesNemeth<br />

Andy North<br />

Form 5.1 was completed by each member of the Decision Workshop. A<br />

weighting number for cost, technical, operational and mvironmentaVaesthetic<br />

factors was developed based on the averaged group scores. Cost was weighted<br />

highest followed by operational and technical criteria, with environmental and<br />

aesthetic criteria weighted lowest. Form 5.2 was similarly developed from<br />

individual scores to weight the individual evaluation criteria.<br />

Form 5.3 lists the ranking of each of the options 1 to 7 based on the weighting<br />

numbers developed in Form 5.2. The ranking results for the options indicates<br />

that Option 1 (score 268) and Option 2 (score 286) are the most favoured<br />

options, options 3 to 6 score similarly (in the range 227 to 238), and the least<br />

favoured option is Option 7 (score 175).


Section 5.0 -Evaluation of Options<br />

Subsequent to the ranking results developed in Form 5.3, the participants<br />

completed Form 5.4, by using the pair-wise comparison technique, with the<br />

scores modified by incorporating the weighting results &om Form 5.1. The<br />

overall results were similar to the r;lting/weighting exercise as these results<br />

indicated that the preferred options are Option 1 (score 46.9) and Option 2<br />

(score 44.2), and the least preferred option is Option 7 (score 10.8).<br />

The similarity in the results provides a level of confidence that the decision<br />

techniques are robust. As Options 1 and 2 scored the highest in both<br />

techniques, discussion at the workshop then concentrated on identifying the<br />

preferred option for recommendation. As identified in the earlier sections both<br />

options achieve similar objectives primarily through alternative flow transfer<br />

routes. Consensus at the workshop was that the certainty of the route from<br />

Option 1 was greater than that for Option 2, and the construction of the Option<br />

1 alignment was likely to have more potential to encourage further<br />

development.<br />

The recommendation of the Decision Workshop members based on the ranking<br />

and comparison results is therefore to pursue Option 1.


Section 5.0 -Evaluation of Options<br />

FORM 5.1<br />

Relative Weightings of the Decision Criteria<br />

Groupings to be Used in the Evaluation<br />

Cost Criteria<br />

Technical Criteria<br />

Operational Criteria<br />

Environmental and Aesthetic Criteria<br />

Total 10


Section 5.0 - Evahation of Options<br />

FORM 5.2<br />

Specific Weighting of the Decision Criteria<br />

to be Used in the Evaluation<br />

Cost Criteria (Max = 10)<br />

Ca~ital Cost<br />

Life-Cycle Cost<br />

Technical Criteria I (Max. = 10)<br />

ReliabilityRobustness<br />

Flexibility I complexity /<br />

Sophistication<br />

Ease of Construction j~and<br />

Requirements<br />

I<br />

I<br />

Operational Criteria (Max. = 10)<br />

Ease of Operation and<br />

Maintenance<br />

Safety<br />

Staffing<br />

Environmental and Aesthetic Criteria I (Max. = 10)<br />

Effect on Surrounding Area I I<br />

Visual / Noise I Traffic


Section 5.0 -Evaluation of Options<br />

FORM 5.3<br />

Non-Economic Comparison between Options<br />

I Cost Criteria 1 (Max.=5) 1 (Max. =5) 1<br />

I Capital cost I I I<br />

Life-Cycle Cost<br />

Technical Criteria<br />

(Max- = 5) (Max. = 5)<br />

I<br />

Flexibility I Complexity /<br />

Souhistication<br />

Ease of Construction I Land<br />

Requirements<br />

I Operational Criteria I (Max. = 5) [ (Max. = 5) 1<br />

I<br />

Ease of Operation and<br />

Maintenance<br />

I safety I I I<br />

I Staffing I I I<br />

Environmental and Aesthetic Criteria<br />

Effect on Surrounding Area<br />

Odours/Emissions<br />

Visual / Noise / Trafic<br />

fi<br />

Totals I<br />

(Max. = 5) (Max. = 5)


Section 3.0 - Evaluation of Options<br />

FORM 5.4<br />

Example Pair-Wise Comparison Matrix<br />

I Total<br />

I


SECTION 4<br />

WASTEWATER TREATMENT OPTIONS


SECTION 4.0<br />

BLACKBURN TREATMENT OPTIONS<br />

The following seven options have been identified for upgrading the <strong>Blackburn</strong><br />

sewage collection area and WWTP:<br />

4.1 OPTION 1 - DECOMMISSION EXISTING BLACKBURN WWTP AND<br />

ROUTE ALL FLOW TO LANSDOWNE ROAD WWTP MA<br />

FORCEMAINlGRAVITY SEWER CONNECTION<br />

4.1.1 Outline<br />

In this option the existing sewage lagoons would be decommissioned and all<br />

flows transferred for treatment at the Lansdowne Road WWTP via a new<br />

forcemain and trunk gravity sewer from the Mackus Road pumpstation. A<br />

schematic representation of this option is presented in Figure 4.1. An I/l<br />

reduction program is to be initiated and completed to reduce the volume of<br />

wastewater being transferred during wet weather and snowrnelt conditions.<br />

The existing Mackus Road pumpstation would be upgraded and a new , small<br />

purnpstation would be constructed at the Blackbum WWTP site. It is believed<br />

that he hdowne Road WWTP has sufficient capacity to handle the<br />

projected future hydraulic and BODOSS Ioadings from the Blackbum sewage<br />

collection area.<br />

Key activities or capital works associated with this option are as follows:<br />

Implement and complete I/I reduction program.<br />

Decommission lagoons and rehabilitate site for other use.<br />

<strong>Upgrade</strong> Mackus Road pumpstation to handle projected increased flows.<br />

Construct trunk gravity sewer and/or forcemain to transfer all flows from<br />

Blackbum sewerage area to Lansdowne Road WWTP.<br />

<strong>Upgrade</strong> downtown sewage collection pipework to handle increased flows<br />

from Blackbum sewerage area.<br />

Construct sewage purnpstation at <strong>Blackburn</strong> WWTP site and construct<br />

connecting forcemain discharging to Mackus Road pumpstation.


Initiate 1 reduction program and<br />

complete over 5/10 years;<br />

assess PWWF based on results.<br />

0 Decommission existing <strong>Blackburn</strong><br />

WWTP and restorellandscape site.<br />

a Route all flow to Lansdowne Road<br />

WWTP.<br />

Pipeline route (m n B) from Mackus<br />

Road PS to Correctional<br />

.<br />

Centre tie-in.<br />

Pipeline route ( m .)from new PS at<br />

decommissioned <strong>Blackburn</strong> WWTP<br />

site to Mackus Road PS.<br />

a Assess conditionlcapacity of existing<br />

Mackus Road PS.<br />

e Assess conditionlcapacity of existing<br />

sewage conveyance system through<br />

downtown area.<br />

Assess impact of added sewage flow<br />

on Lansdowne Road WWTP<br />

capacityloperation.<br />

LEGEND:<br />

. - - - - - - Exist. Sanitary Collection Mains<br />

Bbckburn Sanitary Collection Area<br />

City of Prince George<br />

<strong>Wastewater</strong> <strong>Treatment</strong> <strong>Plant</strong><br />

<strong>Treatment</strong> Options <strong>Study</strong><br />

OPTION 1<br />

Figure 4.1


Section 4.0 - Blackbum <strong>Treatment</strong> Options<br />

Key technical issues associated with this option are as follows:<br />

Extent to which the VI reduction program is able to reduce peak wet<br />

weather flows must be evaluated.<br />

City need operate only one wastewater treatment and disposal facility.<br />

Major capital works needed to transfer flows to Lansdowne Road WWTP.<br />

Condition and capacity of the existing Mackus Road pumpstation must be<br />

evaluated.<br />

Details for pipeline routes for transferring Blackbum sewage flows to<br />

Lansdowne Road WWTP must be evaluated.<br />

Impact of added flow on capacityloperation of Lansdowne Road WWTP<br />

needs to be evaluated.<br />

Ammonia toxicity issue addressed at Lansdoume Road WWTP.<br />

4.1.2 Design Information<br />

Population<br />

ADWF, m3/d<br />

PWWF, m31d<br />

Pipework<br />

Forcernain from intersection of Mackus Road and North<br />

<strong>Blackburn</strong> Road to a high point on Hwy. 16.<br />

Diameter, mm<br />

Length, m<br />

Gravity sewer main from the end of 200 diameter forcemain to<br />

the Regional Correctional Centre tie-in<br />

Diameter, rnrn<br />

Length, m<br />

Forcemain from the existing Blackbum WWTP site to the high<br />

point on Graves Road<br />

Diameter, mrn<br />

Length, m<br />

Sanitary sewer syphon from Yellowhead Bridge connecting to<br />

downtown sewage collection system<br />

Diameter, mm<br />

Length, m<br />

Gravity sewer to intersection of isth Ave. and Taylor Drive;<br />

construct new manhole


Section 4.0 - Blackbum <strong>Treatment</strong> Ovtions<br />

Diameter, mrn 300<br />

Length, m 100<br />

Gravity sewer along l5Ih ~ ve. from Taylor Drive to Birch Street;<br />

connect to 525 diameter sewer<br />

Diameter, mm 300<br />

Length, m 180<br />

Pumpstation<br />

<strong>Upgrade</strong> Mackus Road PS for PWWF capacity<br />

Supply and install PS at existing Blackbum WWTP site to<br />

senice residence along Graves and Foreman Roads; capable of<br />

pumping 10 percent of PWWF.<br />

Miscellaneous<br />

Restordlandscape existing Blackbum WWTP site.<br />

4.1.3 Cost Estimate<br />

Pipework<br />

1 5 0 forcemain, S 1 00/m<br />

200 forcernain, $1 8O/m<br />

200 syphon, $200/m<br />

300 gravity sewer<br />

<strong>Blackburn</strong>, $1 60/m<br />

Downtown, $250/m<br />

Pumpstation<br />

Mach Road PS, LS<br />

Foreman Road PS, LS<br />

Miscellaneous<br />

Blackbum WWTP site restoration/lmdscaping, LS<br />

Subtotal<br />

Contingencies (15 percent)<br />

EngineeringIAdministration (20 percent)<br />

GST (3 percent)<br />

TOTAL<br />

4.2 OPTION 2 - DECOMMISSION EXISTING BLACKBURN WVTP AND<br />

ROUTE ALL FLOW TO LANSDOWNE ROAD WWTP VIA GRAVITY<br />

SEWER CONNECTION<br />

4.2.1 Outline<br />

In this option the existing sewage lagoons would be decommissioned and all<br />

flow transferred for treatment at the Lansdowne Road WWTP via a new trunk<br />

gravity sewer. A schematic representation of this option is presented in Figure


Section 4.0 - Blackbum <strong>Treatment</strong> Options<br />

4.2. An UI reduction program is to be initiated and completed to reduce the<br />

volume of wastewater being transfmed during wet weather and snowmelt<br />

conditions. The existing Mackus Road pumpstation would be upgraded. It is<br />

believed that the Lansdowne Road WWTP has sufficient capacity to handle the<br />

projected future hydraulic and BOD5tTSS loadings from the Blackbum sewage<br />

collection area.<br />

Key activities or capital works associated with this option are as follows:<br />

Implement and complete VI reduction program.<br />

Decommission lagoons and rehabilitate site for other use.<br />

<strong>Upgrade</strong> Mackus Road pu&pstation to handle projected increased flows.<br />

Construct trunk gravity sewer to transfer all flows from <strong>Blackburn</strong><br />

sewerage area to Lansdowne Road WWTP.<br />

<strong>Upgrade</strong> downtown sewage collection pipework to handle increased flows<br />

from <strong>Blackburn</strong> sewerage area.<br />

Key technical issues associated with this option are as follows:<br />

Extent to which the If1 reduction program is able to reduce peak wet<br />

weather flows must be evaluated.<br />

City need operate only one wastewater treatment and disposal facility.<br />

Major capital works needed to transfer flows to Lansdowne Road WWTP.<br />

Condition and capacity of the existing Mackus Road pumpstation must be<br />

evaluated.<br />

Details for pipeline routes for transferring <strong>Blackburn</strong> sewage flows to<br />

Lansdowne Road WWTP must be evaluated.<br />

Ammonia toxicity issue addressed at Lansdowne Road WWTP.<br />

4.2.2 Design Information<br />

Population<br />

ADWF, m3/d<br />

PWWF, m3/d


Initiate I11 reduction program and<br />

complete over 5110 year period;<br />

assess PWWF based on results.<br />

Decommission existing Blackbum<br />

WWTP and restorellandscape site.<br />

Route all flow to Lansdowne Road<br />

WWTP.<br />

Pipeline route (a m rn a) from Blackbum<br />

WWTP site to Correctional Centre tie41<br />

Assess conditionlcapacity of existing<br />

Mackus Road PS.<br />

Assess conditionlcapaciiy of existing<br />

sewage conveyance system through<br />

downtown area.<br />

Assess impact of added sewage flow<br />

on Lansdowne Road WWTP<br />

capacityloperation.<br />

LEGEND:<br />

Exist. Sanitary Collection Mains<br />

Blackbum Sanitary Collection Area<br />

City of Prince George<br />

<strong>Blackburn</strong> <strong>Wastewater</strong> <strong>Treatment</strong> <strong>Plant</strong><br />

<strong>Treatment</strong> Options <strong>Study</strong><br />

OPTION 2<br />

Figure 4.2


Section 4.0 - <strong>Blackburn</strong> <strong>Treatment</strong> Options<br />

Pipework<br />

Gravity sewermain from the existing Blackbum WWTP site to<br />

the Regional Correctional Centre tie-in<br />

Diameter, mm<br />

Length, m<br />

Sanitary sewer syphon from Yellowhead Bridge connecting to<br />

downtown sewage collection system<br />

Diameter, mm<br />

Length, m<br />

Gravity sewer to intersection of l5Ih Ave. and Taylor Drive;<br />

construct new manhole<br />

Diameter, mm<br />

Length, m<br />

Gravity sewer along 15" Ave. from Taylor Drive to Birch St.;<br />

connect to 525 diameter sewer<br />

Diameter, mm<br />

Length, m<br />

Pumpstation<br />

<strong>Upgrade</strong> Mackus Road PS for PWWF capacity<br />

Miellaneous<br />

Restoreflandscape existing <strong>Blackburn</strong> WWTP site.<br />

4.23 Cost Estimate<br />

Pipework<br />

200 syphon, $200/m<br />

300 gravity sewer<br />

<strong>Blackburn</strong>, $160/m<br />

Downtown, $250/m<br />

Pumpstation<br />

Mackus Road PS, LS<br />

Miscellaneous<br />

Btackburn M P site restoratiodandscaping, LS<br />

Subtotal<br />

Contingencies (15 percent)<br />

EngineerindAdministration (20 percent)<br />

GST (3 percent)<br />

TOTAL


Section 4.0 - Blackbum <strong>Treatment</strong> Options<br />

4.3 OPTION 3 - USE EXISTING BLACKBURN WWTP FOR<br />

EOUALIZATIONlSTORAGE AND TRANSFER ALL FLOWS TO<br />

4.3.1 Outline<br />

In this option the existing sewage lagoons would be converted to flow<br />

equalization/storage basins, and all flows transferred for treatment at the<br />

Lansdowne Road WWTP. A schematic representation of this option is<br />

presented in Figure 4.3. The principal beneiit of this option is that the peak<br />

flows being transferred from the Blackbum sewage collection area to the<br />

Lansdowne Road WWTP would be attenuated somewhat. An I/I reduction<br />

program is to be initiated and completed to reduce the volume of wastewater<br />

being transferred during wet ieather and snowmelt conditions. Tne existing<br />

Mackus Road pumpstation would be upgraded. It is believed that the<br />

Lansdowne Road WWTP has sufficient capacity to handle the projected future<br />

hydraulic and BODDSS loadings from the <strong>Blackburn</strong> sewage collection area.<br />

Key activities or capital works associated with this option are as follows:<br />

Implement VI reduction program.<br />

Modify lagoons for use as flow equalizationk.torage basins.<br />

<strong>Upgrade</strong> Mackus Road pumpstation to handle projected increased flows.<br />

Construct trunk gravity sewer to transfer all flows fiorn Blackbum<br />

sewerage area to Lansdowne Road WWTP.<br />

<strong>Upgrade</strong> downtown sewage collection system to handle increased flows<br />

from Blackbum sewerage area.<br />

Key technical issues associated with this option are as follows:<br />

Extent to which the LfI reduction program is able to reduce peak wet<br />

weather flows must be evaluated.<br />

City must maintain operation of storage basins; O&M costs of<br />

equalizationktorage basins are only slightly lower than O&M costs for the<br />

existing treatment lagoons.<br />

Major capital works needed to transfer flows to Lansdowne WWTP and<br />

modify lagoons.


Initiate llt reduction program and<br />

complete over 511 0 year period;<br />

assess PWWF based on results.<br />

Modify existing Blackbum WWTP<br />

to operate as storage basins.<br />

Route all flow to Lansdowne Road<br />

WWTP.<br />

Pipeline route (m m m) from <strong>Blackburn</strong><br />

storage basins to Correctional<br />

Centre tie-in.<br />

Assess conditionlcapacity of existing<br />

Mackus Road PS.<br />

Assess conditionlcapacity of existing<br />

sewage conveyance system through<br />

downtown area.<br />

Assess impact of added sewage<br />

flow on Lansdowne Road WWTP<br />

capacityloperation.<br />

I.<br />

I/<br />

I.<br />

li<br />

i I<br />

!<br />

LEGEND:<br />

! ------ Exist. Sanitary Collection Mains<br />

Blackbum Sanitary Collection Area<br />

City of Prince George<br />

<strong>Blackburn</strong> <strong>Wastewater</strong> <strong>Treatment</strong> <strong>Plant</strong><br />

<strong>Treatment</strong> Options <strong>Study</strong><br />

OPTION 3<br />

Figure 4.3


Section 4.0 - Blackbum <strong>Treatment</strong> Options<br />

Condition and capacity of the existing Mackus Road pumpstation must be<br />

evaluated.<br />

Details for pipeline routes for transferring Blackbum sewage flows to<br />

Lansdowne Road WWTP must be evaluated.<br />

Ammonia toxicity issue addressed at Lansdowne Road WWTP.<br />

4.3.2 Design Information<br />

Population<br />

ADWF, m3/d<br />

PWWF, m3/d<br />

Pipework<br />

Gravity sewermain from the existing Blackbum WWTP site to<br />

the Regional Correctional Centre tie-in<br />

Diameter, mm<br />

Length, m<br />

Sanitary sewer syphon from Yellowhead Bridge connecting to<br />

downtown sewage collection system<br />

Diameter, rnrn<br />

Length, m<br />

Gravity sewer to intersection of 15' Ave. and Taylor Drive;<br />

construct new manhole<br />

Diameter, mm<br />

Length, m<br />

Gravity sewer along 1 5 Ave. ~ from Taylor Drive to Birch St.;<br />

connect to 525 diameter sewer<br />

Diameter, rnm<br />

Length, m<br />

Pumpstation<br />

<strong>Upgrade</strong> Mackus Road PS for PWWF capacity<br />

MisceIlaneous<br />

Modifications to Blackbum WWTP to operate as storage basin<br />

4.3.3 Cost Estimate<br />

Pipework<br />

200 syphon, $200/m<br />

300 gravity sewer<br />

Blackbum, $160/m<br />

Downtown, $250/m<br />

Pumpstation<br />

Mackus Road PS, LS


Section 4.0 - <strong>Blackburn</strong> <strong>Treatment</strong> Options<br />

Miscellaneous<br />

Blackbum WWTP modifications to allow lagoons<br />

to operate as storage basins, LS 100,000<br />

Subtotat 1,165,000<br />

Contingencies (1 5 percent)<br />

EngineeringlAdminisWion (20 percent)<br />

GST (3 percent)<br />

TOTAL<br />

4.4 OPTION 4 - TRANSFER ALL FLOW < 2*ADWF TO LANSDOWNE<br />

ROAD WWTP AND USE THE EXISTING BLACKBURN WWTP TO<br />

TREAT FLOWS > 2*ADWF<br />

4.4.1 Outline<br />

In this option all flows up to 2*ADWF would be transferred &om the<br />

<strong>Blackburn</strong> sewage collection area for treatment at the Lansdowne Road<br />

WWTP. The existing sewage lagoons would be used only to treat wet weather<br />

flows > 2*AI)WF. A schematic representation of this option is presented in<br />

Figure 4.4. An It1 reduction program is to be i~tiated and completed to reduce<br />

the volume of wastewater being treated in the lagoons during wet weather and<br />

snowmelt conditions. The existing Mackus Road pumpstation would be<br />

upgraded and a new purnpstation constmcted to handle excess flow<br />

>2*ADWF. It is believed that the Lansdowne Road WWTP has sufficient<br />

capacity to handle the projected future 2*ADWF hydraulic and BODjtTSS<br />

loadings fkom the Blackbum sewage collection area. All wet weather flow ><br />

2*ADWF will be pumped to the existing Blackbum WWTP for treatment.<br />

Key activities or capitat works associated with this option are as follows:<br />

Implement VI reduction program.<br />

<strong>Upgrade</strong> Mackus Road purnpstation to handle project4 increased flows.<br />

All dry weather flows < 2'ADWF are to be pumped to Lansdowne Road<br />

WWTP; all wet weather flows > 2*ADWF are to be pumped to <strong>Blackburn</strong><br />

WWTP.<br />

Construct trunk gravity sewer and/or forcemain to transfer all flows<br />


Initiate Ill reduction program and<br />

complete over 5110 year period;<br />

assess PWWF based on results.<br />

0 Maintain existing <strong>Blackburn</strong> WWTP<br />

for flows > 2(ADWF).<br />

Route Rows s 2(ADWF) to Lansdowne<br />

Road WIKTP.<br />

Pipeline route (<br />

m) from<br />

Mackus Road PS to Correctional<br />

Centre tiein.<br />

Route flow > 2(ADWF) to <strong>Blackburn</strong><br />

WWTP using existing pipeline;<br />

provide primary treatment and<br />

discharge to Fraser River.<br />

Road<br />

Assess conditionlcapacity of existing<br />

Mackus Road PS; provide PS to pump<br />

flows > 2(ADWF) to <strong>Blackburn</strong> WWTP.<br />

Assess conditionlcapacity of existing<br />

sewage conveyance system through<br />

downtown area.<br />

Assess impact of added 2(ADWF)<br />

sewage flow on Lansdowne Road<br />

WWTP capacityloperation.<br />

I<br />

LEGEND:<br />

. - - - - - - Exist. Sanitary Collection Mains<br />

Blackbum Sanitary Collection Area<br />

City of Prince George<br />

Black ;bum <strong>Wastewater</strong> <strong>Treatment</strong> <strong>Plant</strong><br />

<strong>Treatment</strong> Options <strong>Study</strong><br />

OPTION 4<br />

Figure 4.4


Section 4.0 - Blackbm <strong>Treatment</strong> Options<br />

Key technical issues associated with this option are as follows:<br />

Extent to which the I/I reduction program is able to reduce peak wet<br />

weather flows must be evaluated.<br />

City must maintain operation of Blackbum WWTP; O&M costs associated<br />

with lagoon operation will not be significantly lower that for current<br />

operation.<br />

Expansion of the existing lagoons will not be required.<br />

Ammonia toxicity of lagoon emuent needs to be addressed.<br />

Major capital works required to transfer and proportion flows to<br />

Lansdowne Road WWTP and to <strong>Blackburn</strong> WWTP.<br />

Condition and capacity of the existing Mackus Road pumpstation must be<br />

evaluated.<br />

Details for pipeline routes for transferring Blackbum sewage flows to<br />

Lansdowne Road WWTP must be evaluated, as well as, pumping of wet<br />

weather flows to <strong>Blackburn</strong> WWTP.<br />

Ammonia toxicity issue partialIy addressed at Lansdowne Road WWTP for<br />

2*ADWF<br />

4.4.2 Design Information<br />

Population<br />

ADWF, m3/d<br />

PWWF, m3/d<br />

Pipework<br />

Forcemain fiom intersection of Mackus Road and North<br />

Blackbum Road to a high point on Hwy. 16<br />

Diameter, mm 200<br />

Length, m 1,720<br />

Gravity sewermain fiom the end of 200 diameter forcemain to<br />

the Regional Correctional Centre tie-in<br />

Diameter, mm 300<br />

Length, m 3,100<br />

Sanitary sewer syphon from Yellowhead Bridge connecting to<br />

downtown sewage collection system<br />

Diameter, mrn 200<br />

Length, m 100


Section 4.0 - <strong>Blackburn</strong> <strong>Treatment</strong> Options<br />

Gravity sewer to intersection of 15" Ave. and Taylor Drive;<br />

construct new manhole<br />

Diameter, mrn 300<br />

Length, m 100<br />

Gravity sewer along 15' Ave. from Taylor Drive to Birch St.;<br />

connect to 525 diameter sewer<br />

Diameter, mm 300<br />

Length, m 180<br />

Pumpstation<br />

<strong>Upgrade</strong> Mackus Road PS for 2*AD WF capacity<br />

w<br />

Supply and install PS and construct overflow wet well to handle<br />

flows > 2 * m<br />

Miscellaneons<br />

Modifications to existing BIackbwn WWTP to provide primary<br />

treatment for flows > 2*ADWF<br />

4.4.3 Cost Estimate<br />

Pipework<br />

200 forcemain, $180/m<br />

w 200 syphon, $200/m<br />

300 gravity sewer<br />

<strong>Blackburn</strong>, $l6O/m<br />

Downtown, $250/m<br />

Pumpstation<br />

Mackus Road PS, LS<br />

Mackus Road Overflow PS, LS<br />

Miscellaneous<br />

Blackbum WWTP modifications, LS<br />

Subtotal<br />

Contingencies (1 5 percent)<br />

Engineering/Adminishtion (20 percent)<br />

GST (3 percent)<br />

TOTAL<br />

4.5 OPTION 5 - TRANSFER ALL FLOW < 2*ADWF TO LANSDOWNE<br />

ROAD W TP AND USE THE EXISTING BLACKBURN WWTP TO<br />

TREAT FLOWS > 2*ADWF<br />

4.5.1 Outline<br />

In this option all flows up to 2*ADWF would be transferred from the<br />

<strong>Blackburn</strong> sewage collection area for treatment at the Lansdowne Road<br />

WWTP. The existing sewage lagoons would be used only to treat wet weather


Section 4.0 - Blackbum <strong>Treatment</strong> Options<br />

flows > 2*ADWF. A schematic representation of this option is presented in<br />

Figure 4.5. An VI reduction program is to be initiated and completed to reduce<br />

the volume of wastewater being treated in the lagoons during wet weather and<br />

snowmelt conditions. The existing Mackus Road purnpstation would be<br />

upgraded and modifications constructed at the <strong>Blackburn</strong> WWTP to handle<br />

excess flow >2*ADWF. It is believed that the Lansdowne Road WWTP has<br />

sufficient capacity to handle the projected future 2*ADWF hydraulic and<br />

BODOS loadings hm the Blackbum sewage collection area. All wet<br />

weather flow > 2*ADWF will be diverted to the existing Blackbum WWTP<br />

for treatment.<br />

Key activities or capital works associated with this option are as follows:<br />

Implement VI reduction prbgram.<br />

<strong>Upgrade</strong> Mackus Road purnpstation to handle projected increased flows.<br />

Construct trunk gravity sewer to transfer dry weather flow from Blackbum<br />

sewerage area to Lansdowne Road WWTP.<br />

<strong>Upgrade</strong> downtown sewage collection system to handle 2*AD\VF h m<br />

Blackbum sewerage area.<br />

Key technical issues associated with this option are as follows:<br />

Extent to which the I/l reduction program is able to reduce peak wet<br />

weather flows must be evaluated.<br />

City must maintain Blackbum WWTP; O&M costs associated with lagoon<br />

operation will not be significantly lower than for current operation.<br />

0 Expansion of the existing lagoons will not be required.<br />

Ammonia toxicity of lagoon effluent needs to be addressed.<br />

Major capital works needed to transfer flows to Lansdowne Road WWTF'.<br />

0 Condition and capacity of the existing Mackus Road pumpstation must be<br />

evaluated.<br />

Details for pipeline routes for transferring Blackbum sewage flows to<br />

Lansdowne Road WWTP must be evaluated, as well as modifications<br />

required to divert wet weather flows to Blackbum WWTP.<br />

Ammonia toxicity issue partially addressed at Lansdowne Road WWTP.


Initiate Ill reduction program and<br />

complete over 5110 year period;<br />

assess PWWF based on results.<br />

0 Maintain existing <strong>Blackburn</strong> WWTP<br />

for flows > 2(ADWF).<br />

Route all flow to <strong>Blackburn</strong> WWTP<br />

using existing pipeline.<br />

Route flows s 2(ADWF) to Lansdown<br />

Road WWTP for treatment.<br />

Pipeline route (= =) from Blackbun<br />

WWTP to Correctional Centre tie-in.<br />

8 Provide primary treatment for flows<br />

> 2(ADWF) at Blackbum WWTP and<br />

discharge to Fraser River.<br />

Assess conditionlcapacity of existin:<br />

Mackus Road PS.<br />

Assess conditionkapacity of existins<br />

sanitary conveyance system through<br />

downtown area.<br />

Assess impact of added 2(ADWF)<br />

sewage flow on Lansdowne Road<br />

WWTP capacityloperation.<br />

LEGEND:<br />

. - - - - - - Exist. Sanlary Collection Mains<br />

Blackbum Sanitary Collectjon Area


Section 4.0 - Blackbum <strong>Treatment</strong> Options<br />

4.5.2 Design Information<br />

Population<br />

ADWF, m3/d<br />

PWWF, m3/d<br />

Pipework<br />

Gravity sewermain from the existing Blackbum WWTP site to<br />

the Regional Correctional Centre tie-in<br />

Diameter, mm<br />

Length, m<br />

Sanitary sewer syphon connecting to downtown sewage<br />

collection system<br />

Diameter, mm<br />

Length, m<br />

Gravity sewer to intersection of l5Ih Ave. and Taylor Drive;<br />

construct new manhole<br />

Diameter, mm<br />

Length, m<br />

Gravity sewer along 15'~ Ave. hm Taylor Drive to Birch St.;<br />

connect to 525 diameter sewer<br />

Diameter, mm<br />

Length m<br />

Pumpstation<br />

<strong>Upgrade</strong> Mackus Road PS for 2*ADWF capacity<br />

Miscellaneous<br />

4.5.3 Cost Estimate<br />

Modifications to existing Blackbum WWTP to provide primary<br />

tre-ent for flows > 2*ADWF<br />

Pipework<br />

200 syphon, $200/m<br />

300 gravity sewer<br />

Blackbm, $160/m<br />

Downtown, $250/m<br />

Pumpstation<br />

Mackus Road PS, LS<br />

Miscellaneous<br />

Btackburn WWTP modifications, LS<br />

Subtotal<br />

Contingencies (15 percent)<br />

Engineering/ Administration (20 percent)<br />

GST (3 percent)<br />

TOTAL


Section 4.0 - Blackbum <strong>Treatment</strong> Options<br />

4.6 OPTION 6 - UPGRADE AND EXPAND BLACKBURN WWTP TO<br />

TREAT PROJECTED FLOWS AND LOADS<br />

4.6.1 Outline<br />

In this option the existing sewage lagoons would be upgraded and expanded to<br />

handle projected flows and loads from the <strong>Blackburn</strong> sewage collection area,<br />

for an ultimate population of 5,000 persons, and to meet required effluent<br />

standards. The existing treatment system consists of two aerated lagoons,<br />

sized to accommodate a contributing population of 2,500. Expanding the<br />

lagoon system to handle the ultimate population of 5,000 would involve<br />

doubling its present size. The expanded lagoon system will address<br />

conventional treatment requirements for BODs and TSS removal. However,<br />

the lagoon system must also ahress removal of ammonia toxicity. Because of<br />

the winter and early spring weather conditions experienced in the Prince<br />

George area, it is practically impossible to achieve ammonia removal by<br />

nitrification in an aerated lagoon system. The issue of ammonia toxicity<br />

removal would have to be addressed by considering the addition of a tertiary<br />

rotating biological contactor (RBC) process to provide nitrification of the<br />

lagoon emuent. A schematic representation of this option is presented in<br />

Figure 4.6. An VI reduction program is to be implemented to reduce the<br />

volume of wastewater being treated in the lagoons during wet weather and<br />

snowmelt conditions. The existing Mackus Road pumpstation would be<br />

upgraded.<br />

Key activities or capital works associated with this option are as follows:<br />

Implement I/I reduction program.<br />

Rehabilitate existing lagoons.<br />

Double lagoon capacity.<br />

<strong>Upgrade</strong> Mackus Road pumpstation to handle projected increased flows.<br />

Address ammonia toxicity issue by considering the use of a tertiary<br />

nitrifying RBC.<br />

Key technical issues associated with this option are as follows:<br />

Extent to which the VI reduction program will reduce peak wet weather<br />

flows must be evaluated.


CITY OF PRINCE GEORGE<br />

Scale= $:I00<br />

f<br />

Existing Chlorine<br />

Contact Tank<br />

Initiate Ill reduction program and<br />

complete over 5/10 year period;<br />

assess PWWF based on results.<br />

0 <strong>Upgrade</strong> and expand Blackbum<br />

WWTP lagoon facility; provide<br />

treatment capability for ammonia<br />

reduction to address toxicity concerns.<br />

No routing of flow to Lansdowne Road<br />

WWT P.<br />

Assess conditionlcapacity of existing<br />

Mackus Road PS.<br />

Existing<br />

Operations<br />

Building<br />

lsM<br />

ENGINEERING LIMITED<br />

City of Prince George<br />

<strong>Blackburn</strong> <strong>Wastewater</strong> <strong>Treatment</strong> Planl<br />

<strong>Treatment</strong> Options <strong>Study</strong><br />

OPTION 6<br />

Figure 4. t


Section 4.0 - Blackbum <strong>Treatment</strong> Options<br />

* The City must maintain the Blackbum WWTP; O&M costs associated with<br />

expanded lagoon operation will be higher than for current operation.<br />

Additional land area must be identified if further expansion is<br />

contemplated.<br />

Ammonia toxicity of the lagoon effluent needs to be addressed.<br />

Incorporation of a tertiary nitrification stage will significantly increase the<br />

capital and O&M costs of the facility.<br />

The issue of whether nitrification can reliably be achieved in an add-on<br />

RBC process at temperatures below P C needs further investigation.<br />

No transfer of flows and loads, or ammonia toxicity issue to Lansdowne<br />

Road WWTP.<br />

Existing excess capacity at the Lansdowne Road WWTP would not be<br />

utilized.<br />

Condition and capacity of the existing Mackus Road pumpstation must be<br />

evaluated.<br />

4.6.2 Design Information<br />

Population<br />

ADWF, m3/d<br />

P W , m3/d<br />

Stage 1 (existing)<br />

Lagoon l (primary)<br />

Number<br />

Volume, m3<br />

FRT (@ ADWF = 900 m3/d), d<br />

Lagoon 2 (secondary)<br />

Number<br />

Volume, m3<br />

HRT (@ ADWF = 900 m3/d), d<br />

Aeration Blowers<br />

Number<br />

Power, hp<br />

Stage 2 (expanded)<br />

Lagoon 1MlB (primary)<br />

Number<br />

Volume, in3


Section 4.0 - Blackbum <strong>Treatment</strong> Options<br />

HRT (@ ADWF = 1,750 m3/d), d<br />

Lagoon 2N2B (secondary)<br />

Number<br />

Volume, rn3<br />

HRT (@ ADWF = 1,750 m3/d), d<br />

0 Aeration Blowers<br />

Number<br />

Power, hp<br />

Headworks<br />

According to original design data presented on AESL as-built drawing 4102-<br />

01-S-102, the influent works (channels and screens) are adequately sized to<br />

accommodate Stage 2 flows. No major modifications are required in this area.<br />

Aerated Lagoons<br />

The aerated lagoon system will need to be twinned to accommodate the design<br />

ADWF of 1,750 m3/d. Construction work involves the following:<br />

Excavation of two lagoons to the east of the existing two. The dimensions<br />

will be identical to the existing lagoons. The total volume to be excavated<br />

is approximately 23,000 m3. It is assumed some of the excavated material<br />

can be used to extend the berm and no material needs to be imported to<br />

complete construction.<br />

Replacement of both existing 60 hp aeration blowers. Depending on the<br />

mode of operation, the plant presently requires either 1 or both blowers<br />

running; series operation requires 60 hp, and parallel requires 120 hp. Stage<br />

2 requires 150 hp for series and 225 hp for parallel. There is presently<br />

room for three blowers in the existing building. Assuming present<br />

operating practice of no standby capacity during parallel operation is<br />

maintained, three 75 hp (nominal) aeration blowers will be required.<br />

Duplication of the air distribution system (34 "aeration guns" in each<br />

lagoon for a total of 68 new units). If is assumed the air distribution<br />

pipework will be mirrored.<br />

Additional emuent and drain piping will be required to connect the new<br />

lagoons to the chlorine contact chamber. The chlorine contact chamber is<br />

adequate for Stage 2 flows. It is assumed the new emuent pipework will be<br />

of similar configuration to the existing, with approximately 350 m of 300<br />

mm pipe, 2 manholes, and 3 concrete chambers.


Section 4.0 - Blackbum <strong>Treatment</strong> Options<br />

Nitrifying RBCs<br />

The above aerated lagoon system will be unable to produce a nitrified effluent.<br />

Therefore, if ammonia removal is required, a mechanical process such as a<br />

rotating biological contactor (RBC) must be added to treat the lagoon effluent<br />

to reduce the levels of ammonia. The process would be smaller than one<br />

needed to treat raw wastewater, as the organic loads in the lagoon emuent are<br />

significantly reduced.<br />

An RBC consists of a series of discs on which a fixed film of biological<br />

material is grown and maintained. The discs are mounted on a driveshaft,<br />

which rotates the discs through the wastewater. Oxygen is transferred to the<br />

biomass from the atmosphere during the time that the disc is out of the<br />

wastewater.<br />

An RBC can be hydraulically loaded at 0.03 - 0.08 m3/m2/d for combined BOD<br />

removal and nitrification. For separate nitrification, the hydraulic loading can<br />

be increased slightly to 0.04 - 0.10 m3/m2/d. To treat the anticipated ADWF of<br />

1,750 m3/d, approximately 16,700 m2 of media is required.<br />

At wastewater temperatures below 12S°C, the size of the RBC must be<br />

adjusted to achieve the same levels of performance. If the wastewater<br />

temperature is as low as 4OC (lagoon effluent could conceivably be lower in<br />

this climate), the area of the media must be increased by a factor of at least 2.5.<br />

Therefore a total area required to achieve nitrification at 4OC is in the order of<br />

42,000 m2. As the wastewater spends upwards of 20 days in a relatively<br />

shallow lagoon, the temperature of the effluent entering the RBC during the<br />

coldest periods is likely to approach 0°C. The surface area correction curves<br />

for media, below 4OC are quite steep, and it appears impractical to size an R3C<br />

in this temperature range.<br />

Nitrifying RBC<br />

Hydraulic loading rate, m3/m2/d<br />

Temperature correction factor<br />

Surface area, m2<br />

Without temperature correction<br />

With temperature correction<br />

Number<br />

Disc diameter, m


Section 4.0 - Blackbum <strong>Treatment</strong> Options<br />

4.6.3 Cost Estimate<br />

Lagoon System Without RBCYs<br />

Sitework<br />

Excavationberm construction, LS<br />

Manholes/chambers/pipes, LS<br />

Equipment<br />

Headworks, lagoons, chambers, LS<br />

Mechanical<br />

Headworks, lagoons, chambers, LS<br />

ElectricallInstrumeotation<br />

Headworks, lagoons, chambers, LS<br />

MisceUaneous<br />

Pumpstation<br />

Mackus Road PS, LS<br />

Subtotal<br />

Contingencies (15 percent)<br />

Engineering/Administration (20 percent)<br />

GST (3 percent)<br />

Total (without RBC)<br />

Lagoon System with RBC's for Nitrification<br />

The following listing of costs is the extra capital cost requird to include a<br />

nitrifiying R8C process at lagoon effluent temperature of 4OC.<br />

Structural<br />

TanklFRP covers, LS<br />

Equipment<br />

RBC's<br />

Mechanical<br />

Interconnecting pipework, etc.<br />

ElectricallInstrumeotation<br />

RBC motors and controls<br />

Miscellaneous<br />

Subtotal @BC)<br />

Subtotal (Lagoons)<br />

Contingencies (15 percent)<br />

Engineering/Administration (20 percent)<br />

GST (3 percent)<br />

Total (with RBC)


Section 4.0 - Blackbum <strong>Treatment</strong> Options<br />

When compared to the use of lagoons only, the inclusion of nitrifying RBCs<br />

into the process train increases the capital cost of this option by approximately<br />

$1 .O M, or 75 percent.<br />

4.7 OPTION 7 - DECOMMISSION EXISTING BLACKBURN WWTP AND<br />

REPLACE WITH A NEW SECONDARY TREATMENT PLANT<br />

4.7.1 Outline<br />

In this option the existing sewage lagoons would be decommissioned and<br />

replaced with a new secondary wastewater treatment plant with an ultimate<br />

design population of 5,000 persons. It is expected that conventional secondary<br />

treatment technology (either extended aeration, RSCs or SBRs) would be<br />

required. For the purpose -of this analysis, it has been assumed that a<br />

conventional activated sludge process will be used to achieve BODS and TSS<br />

removal. The issue of ammonia toxicity would be addressed by incorporating<br />

year-round nitrification into the process design using an extended aeration<br />

oxidation ditch process. A schematic representation of this option is presented<br />

in Figure 4.7. An yI reduction program is to be implemented to reduce the<br />

volume of wastewater being treated during wet weather and snowmelt<br />

conditions. The existing Mach Road pumpstation would be upgraded.<br />

Key activities or capital works associated with this option are as follows:<br />

Implement VI reduction program.<br />

Decommission Blackbum sewage lagoons and replace with new<br />

mechanical wastewater treatment plant.<br />

<strong>Upgrade</strong> Mackus Road pumpstation to handle projected flows.<br />

Address ammonia toxicity issue by incorporating nitrification into the<br />

process design.<br />

Key technical issues associated with this option are as follows:<br />

Extent to which the I/I reduction program will reduce peak wet weather<br />

flows must be evaluated.<br />

City must maintain the Blackbum WWTP; capital and O&M costs<br />

associated with a new mechanical plant at Blackbum will be significantly<br />

greater than for current lagoon operation.


:ITY Of PRINCE GEORGE<br />

Existing Chlorine<br />

Contact Tank<br />

Initiate UI reduction program and<br />

complete over 5110 year period;<br />

assess PWWF based on results.<br />

0 Decommission exisitng <strong>Blackburn</strong><br />

WWTP and restorellandscape site as<br />

required.<br />

Sludge Storage<br />

I<br />

7 (<br />

T,<br />

Secondary Clarifiers<br />

a Replace lagoon system with new<br />

secondary treatment plant; evaluate<br />

SBR, RBC and extended aeration<br />

process; provide treatment<br />

capability for ammonia reduction to<br />

address toxicity concerns.<br />

No routing of flow to Lansdowne<br />

Road WWTP.<br />

Asses conditionlcapacity of existing<br />

Mackus Road PS.<br />

Anoxic delector<br />

I<br />

,-- Concrete<br />

Ditch<br />

Existing Lagoons<br />

- Existing Operations Building<br />

(clw New Screens, Blowem)<br />

City of Prince George<br />

<strong>Blackburn</strong> <strong>Wastewater</strong> <strong>Treatment</strong> Plan!<br />

<strong>Treatment</strong> Options <strong>Study</strong><br />

ENGINEERING LIMITED<br />

OPTION 7<br />

Figure 4. i


Section 4.0 - <strong>Blackburn</strong> <strong>Treatment</strong> Ootions<br />

Proposed mechanical treatment plant will be more reliable in achieving<br />

nitrification than lagoodRJ3C combination.<br />

The incorporation of nitrification into the process design will significantly<br />

increase capital cost and marginally increase O&M costs.<br />

No transfer of flows and loads, or ammonia toxicity issue to Lansdowne<br />

Road WWTF'.<br />

Existing excess capacity at the Lansdowne Road WWTP would not be<br />

utilized.<br />

Condition and capacity of the existing Mackus Road pumpstation must be<br />

evaluated.<br />

4.7.2 Design Information<br />

Population<br />

ADWF, m3/d<br />

PWWF, m3/d<br />

Preliminary <strong>Treatment</strong><br />

Preliminary treatment removes coarse soli ds from the incoming wz tewater,<br />

which has a deleterious effect on downstream processes (pump clogging,<br />

abrasion, etc). At the very minimum, fme screening is required in front of a<br />

secondary process to remove bulky solids, and other inorganic materials. Grit<br />

removal is sometimes included, but the proposed secondary process (oxidation<br />

ditch) does not absohtely require it.<br />

The existing screening room has three channels: two 600 mm channels (one<br />

equipped with a 75 mm trash rack, one bypass) and a central 450 mm channel<br />

with a cornminutor. A mechanically cleaned screen can be installed into one<br />

of the 600 mm channels.<br />

Number<br />

Opening size, mm<br />

ADWF, Us<br />

Velocity through screen @ ADWF, mfs<br />

Depth of flow, rnm<br />

Width of channel (min), mm


Section 4.0 - Blackbum <strong>Treatment</strong> Options<br />

Secondary <strong>Treatment</strong><br />

Secondary activated sludge processes involve aeration basin(s) and clarifiers.<br />

<strong>Wastewater</strong> enters the basins where it is aerated and mixed with a population<br />

of preconditioned microorganisms. Soluble organic material is removed from<br />

the wastewater by biological oxidation, and the insoluble material is removed<br />

by physical entrapment and adsorption within the floc. This mixture of<br />

microorganisms and organic matter is called mixed liquor suspended solids, or<br />

activated sludge. AAer leaving the aeration basin, the mixed fiquor is<br />

separated into a clear supernatant fraction (secondary effluent) and settled<br />

solids (return activated sludge). The return activated sludge is pumped back to<br />

the aeration basin and mixed with the raw influent to maintain the microbial<br />

population. The solids retentmn time (SRT) or sludge age, is controlled by<br />

daily wasting a fraction of either the mixed liquor or the return activated<br />

sludge. This serves to offset excessive microbial growth in the aeration basin.<br />

Conventional activated sludge processes are designed solely for BOD and TSS<br />

reduction; an hydraulic retention time of only 7 h, and a sludge age of 4 to 7 d<br />

are required for this. If ammonia toxicity in the effluent is an issue, the<br />

retention times must be increased to foster nitrification, which is the<br />

conversion of ammonia to nitrites and nitrates. Organisms, which perform this<br />

reaction generally, grow at a slower rate. This modification is called extended<br />

aeration, and involves doubling the hydraulic and solids retention times. A<br />

small non-aerated compartment known as an anoxic selector is usually<br />

included at the inlet to the aeration tank. This environment favours the growth<br />

of flac-forming organisms over filamentous organisms, which enhance the<br />

settleability of the mixed liquor, which in turn improves the quality of the<br />

secondary effluent. In addition, it reduces some of the nitrates produced in the<br />

nitrification reaction. Nitrates are converted to dissolved nitrogen, which<br />

evolves as nitrogen gas to the atmosphere.<br />

In the event that primary treatment is not included, the secondary treatment<br />

parameters described above would require further increase by a factor of<br />

approximately 1.5 to 2.0. A process flow diagram of the activated sludge<br />

process as it may be applied at this site is described below. Screened<br />

wastewater is combined with return activated sludge and enters an anoxic cell,<br />

which in turn discharges to an oxidation ditch equipped with fine bubble<br />

diffusers and mixers to drive the flow around the circuit. Due to the absence of<br />

primary clarifiers, the oxidation ditch will be sized for a hydraulic retention<br />

time of 24 h to ensure nitrification. The mixed liquor then flows to two<br />

secondary clarifiers, each sized for 50 percent of the total flow. Emuent from


Section 4.0 - <strong>Blackburn</strong> <strong>Treatment</strong> Options<br />

the clarifier discharges directly to the river. The settled sludge is pumped back<br />

to the aeration basins at a rate approximately equal to the influent ADWF.<br />

Excess sludge is wasted from the return activated sludge and diverted to a vault<br />

where it is allowed to settle further. The supernatant from this vault is decanted<br />

back to the plant headworks. Thickened sludge is transported off-site for<br />

disposal.<br />

Non-nitrifying bioreactor<br />

HRT, h<br />

SRT, d<br />

Anoxic cells<br />

Volume (anoxic cell), m3<br />

Power (anoxic cell mixer)!hp<br />

Aerobic cells<br />

Volume (aerobic cell), m3<br />

Plan dimensions, m<br />

SWD,m<br />

MLSS, mglL 2,200<br />

Type of aeration<br />

Blowers<br />

Power (aeration blowers), hp<br />

fine bubble dif!%sers<br />

2<br />

40<br />

Mixers (aerobic cell)<br />

Power (aerobic cell mixers), hp<br />

Waste activated sludge storage<br />

Waste RAS (@ 8,000 ma), m3fd<br />

WAS storage capacity, d<br />

Volume (WAS tank), m3<br />

Plan dimensions, m<br />

SWD,m<br />

WAS tank aerator<br />

Power (tank aerator), hp<br />

Secondary Clarifiers<br />

Secondary clarification is required to remove the bulk of solids !?om the mixed<br />

liquor before final discharge, and to return the separated biological solids to the<br />

bioreactor. The secondary clarifiers will be sid to process 50 percent of<br />

ADWF each at a relatively low overflow rate, thereby allowing one to be taken


Section 4.0 - Blackbum <strong>Treatment</strong> Options<br />

out of senice for maintenance and emergencies while allowing the other to<br />

perform adequately. Only one clarifier would be provided at first; the second<br />

would be installed when flows and populations warrant.<br />

Secondary Clarifier<br />

Clarifiers<br />

Overflow rate, m3/m2/d<br />

Surface area, m2<br />

Diameter, rn<br />

SWD,m<br />

2 (1 now; 1 future)<br />

10<br />

85<br />

10<br />

4.0<br />

RAS Pumps<br />

b p s<br />

Capacity, Lls<br />

TDH,m<br />

Power, hp<br />

Nitrifying Activated Sludge Process<br />

The above activated sludge process will not be able to produce a nitrified<br />

effluent. If nitrification is required, the HRT of &he bioreactor will have to be<br />

increased to approximately 24 h by increasing the volume from 500 m' to<br />

1,700 m3. The ancillary processes included with this option with nitrification<br />

are essentially identical to those described above, i.e. the headworks,<br />

secondary clarifiers, etc. will be the same size. The mechanical components<br />

(mixers, pumps, etc) should be of similar size and quantity. The aeration<br />

system, however, will be larger to meet the oxygen requirements for<br />

nitrification. The blowers will be more powerful and the size of the aeration<br />

diffuser grids will be increased proportionally.<br />

The major cost increase will be in construction costs rather than mechanical<br />

furnishings. The amount of excavation, concrete, and other structural elements<br />

required for the bioreactor will be increased by a factor of at least two.<br />

Nitrifying Bioreactor<br />

HRT,h<br />

SRT,d<br />

Anoxic cells<br />

Volume (anoxic selector cell) m3<br />

Power (anoxic cell mixer), hp<br />

Aerobic cells


Section 4.0 - Blackbum <strong>Treatment</strong> Options<br />

Volume (aerobic cells), m3<br />

Plan dimensions, rn<br />

SWD,m<br />

Type of aeration<br />

Blowem<br />

Power (aeration blower), hp<br />

fine bubble diffusers<br />

2<br />

60<br />

Mixers<br />

Power (mixers), hp<br />

4.7.3 Cost Estimate<br />

Conventional activated sludge plant<br />

Sitework<br />

Excavation, preparation, backfill, etc. LS<br />

Structural<br />

HeadworMlower bldgJsludge vault, LS<br />

Bioreactor, LS<br />

Clarifiers,LS<br />

Equipment<br />

Headworkshlower bldg./sludge vault, LS<br />

Bioreactor, LS<br />

Clarifiers,LS<br />

Mechanical<br />

Headworkshlower bldg./sludge vault, LS<br />

Bioreactor, LS<br />

Clarifiers, LS<br />

ElectricaVInstmmentation<br />

Headworks/blower bldg./sludge vault, LS<br />

Bioreactor, LS<br />

Clarifiers, LS<br />

Miscellaneous, LS<br />

Pumpstation<br />

Makus Road PS, LS<br />

Subtotal<br />

Contingencies (15 percent)<br />

EngineeringtAdministration (20 percent)<br />

GST (3 percent)<br />

Total


Section 4.0 - Blackbum <strong>Treatment</strong> Options<br />

Extended Aeration <strong>Plant</strong><br />

Sitework<br />

Excavation, preparation, backfill, etc., LS<br />

Structural<br />

Headworks/blower bldg./sludge vault, LS<br />

Bioreactor, LS<br />

Clarifiers, LS<br />

Equipment<br />

Headworkshlower bldg.lsludge vault, LS<br />

Bioreactor, LS<br />

Clarifiers, LS<br />

Mechanical<br />

Headworkslblower bldg.ls1udge vault, LS<br />

Bioreactor, LS<br />

Clarifiers,LS<br />

ElectricallInstrumentation<br />

Headworkdblower bldg./sludge vault, LS<br />

Bioreactor, LS<br />

Clarifiers, LS<br />

MisceUaneous, LS<br />

Pumpstation<br />

Makus Road PS, LS<br />

Subtotal<br />

Contingencies (15 percent)<br />

EngineeringtAdministration (20 percent)<br />

GST (3 percent)<br />

Total<br />

When compared to the conventional activated sludge option, the incorporation<br />

of nitrification into the process design increases the capital cost of this option<br />

by over $0.5 M, or approximately 35 percent.<br />

4.8 LIFE CYCLE COST ANALYSIS<br />

Seven basic options were identified in the previous sections as being<br />

appropriate for evaluation. Two of the options, Options 6 and 7, are based on<br />

maintaining full secondary treatment at the Blackbum WWTP site. These two<br />

options have been further subdivided into Options 6a and 6b, and 7a and 7b,<br />

respectively, to address the issue of ammonia toxicity removal. Conceptual<br />

level costing has been developed for each of the options as well as detailed


Section 4.0 - Blackbum <strong>Treatment</strong> Options<br />

descriptions to assist with the decision making process. These seven basic<br />

wastewater treatment andor transfer options and the two sub-options will be<br />

evaluated against both economic and non-economic criteria.<br />

The non-economic analysis is described in Section 5.0, and was completed at<br />

the Decision Workshop held with City staff on October 19, 1999.<br />

The economic analysis is based on preliminary capital cost estimates and<br />

ongoing operating and maintenance (O&M) cost estimates for the above nine<br />

options. Estimates were also made of the approximate timing of the required<br />

capital expenditures. These values were used to generate 25-year life cycle<br />

wst estimates for the nine options using a net present value (NPV) analysis at<br />

a discount rate of 6 percent. :<br />

In all nine options, it was assumed that the major capital expenditure would<br />

occur in 200612007, so that the upgrades would be fully operational when the<br />

existing sewage lagoons at the Blackbum WWTP are at capacity. The existing<br />

lagoons will be operated until that time. Implicit in this assumption is that the<br />

L'I mitigation measures will be successhlly completed in the next five years.<br />

In all options involving the transfer of wastewater from the <strong>Blackburn</strong><br />

colIection area to the Lansdowne Road W P , which are Options 1 to 5, a<br />

small incremental O&M cost allowance was made for treating the additional<br />

wastewater at the Lansdowne Road WWTP. However, no allowance was<br />

made for the fact that this transfer may require & earlier upgrade at<br />

Landsdowe Road WWTP as the <strong>Blackburn</strong> sewage flows are less that 4<br />

percent of the existing capacity at Lansdowne Road WWTP, and the effect of<br />

such a small incremental increase is outside the accuracy of this analysis.<br />

The estimated capital and 25-year life cycle costs for the nine wastewater<br />

treatment options are presentd in Appendix B, and are summarized in Table<br />

4.1 below.<br />

TabIe 4.1: 25-year Life Cycle Costs


Section 4.0 - <strong>Blackburn</strong> <strong>Treatment</strong> Options<br />

Option<br />

7a<br />

7b<br />

Capital Cost<br />

1999<br />

1,785,000<br />

2,315,000<br />

NT'V<br />

Capital Cost<br />

1,155,000<br />

1,495,000<br />

NPV<br />

O&M Costs<br />

1,840,0000<br />

1,840,0000<br />

XPV<br />

Total<br />

2,995,000<br />

3,335,000<br />

The above life cycle cost summary shows that the NeV of Options 1,2, 3,4, 5,<br />

and 6a are all within approximately 20 percent of each other, with Option 2<br />

(decommission Blackbum WWTP and transfer all flows by gravity sewer to<br />

the Lansdowne Road WWTP) having the lowest overall cost. All options<br />

involving the installation of a mechanical secondary treatment plant at the<br />

<strong>Blackburn</strong> site (Options 6b, 7a and 7b) have a significantly higher cost than the<br />

flow transfer options.


SECTION 4<br />

WASTEWATER TREATMENT OPTIONS


SECTION 4.0<br />

BLACKBURN TREATMENT OPTIONS<br />

The following seven options have been identified for upgrading the <strong>Blackburn</strong><br />

sewage collection area and WWTP:<br />

4.1 OPTION 1 - DECOMMISSION EXISTING BLACKBURN WWTP AND<br />

ROUTE ALL FLOW TO LANSDOWNE ROAD WWTP MA<br />

FORCEMAINlGRAVITY SEWER CONNECTION<br />

4.1.1 Outline<br />

In this option the existing sewage lagoons would be decommissioned and all<br />

flows transferred for treatment at the Lansdowne Road WWTP via a new<br />

forcemain and trunk gravity sewer from the Mackus Road pumpstation. A<br />

schematic representation of this option is presented in Figure 4.1. An VI<br />

reduction program is to be initiated and completed to reduce the volume of<br />

wasfewater being transferred during wet weather and snowmelt conditions.<br />

The existing Mackus Road pumpstation would be upgraded and a new, small<br />

pumpstation would be constructed at the Blackbum WWTP site. It is believed<br />

that the Lansdowne Road WWTP has sufficient capacity to handIe the<br />

projected future hydraulic and BODflSS loadings from the Blackbum sewage<br />

collection area.<br />

Key activities or capital works associated with this option are as follows:<br />

Implement and complete I/I reduction program.<br />

Decommission lagoons and rehabilitate site for other use.<br />

<strong>Upgrade</strong> Mackus Road pumpstation to handle projected increased flows.<br />

Construct t ~nk gravity sewer and/or forcemain to transfer all flows from<br />

Blackbum sewerage area to Lansdowne Road WWTP.<br />

<strong>Upgrade</strong> downtown sewage collection pipework to handle increased flows<br />

from Blackbum sewerage area<br />

Construct sewage pumpstation at Blackbum WWTP site and construct<br />

connecting forcemain discharging to Mackus Road pumpstation.


1<br />

Initiate In reduction program and<br />

complete over 5/10 years;<br />

assess PWWF based on results.<br />

0 Decommission existing <strong>Blackburn</strong><br />

WWTP and restorellandscape site.<br />

a Route all flow to Lansdowne Road<br />

Pipeline route (8 8 rn 8) from Mackus<br />

Road PS to Correctional Centre tie-in.<br />

Pipeline route (8 8 rn .)from new PS at<br />

decommissioned <strong>Blackburn</strong> WWTP<br />

site to Mackus Road PS.<br />

a Assess conditionlcapacity of existing<br />

Mackus Road PS.<br />

downtown area.<br />

Assess impact of added sewage flow<br />

on Lansdowne Road WWTP<br />

capacityloperation.<br />

Exist. Sanitary Collection Mains<br />

Blackbum Sanitary Collection Area<br />

City of Prince George<br />

ckburn <strong>Wastewater</strong> <strong>Treatment</strong> <strong>Plant</strong><br />

<strong>Treatment</strong> Options <strong>Study</strong><br />

I


Section 4.0 - <strong>Blackburn</strong> <strong>Treatment</strong> Options<br />

Key technical issues associated with this option are as folIows:<br />

Extent to which the I/i reduction program is able to reduce peak wet<br />

weather flows must be evaluated.<br />

City need operate only one wastewater treatment and disposal facility.<br />

Major capital works needed to transfer flows to Lansdowne Road WWTP.<br />

Condition and capacity of the existing Mackus Road pumpstation must be<br />

evaiuated.<br />

Details for pipeline routes for transferring Blackbum sewage flows to<br />

Lansdowne Road WWTP must be evaluated.<br />

Impact of added flow on capacity/operation of Lansdowne Road WWTP<br />

needs to be evaluated.<br />

Ammonia toxicity issue addressed at Lansdowne Road WWTP.<br />

4.1.2 Design Information<br />

Population<br />

ADWF, m3/d<br />

PWWF, m3/d<br />

Pipework<br />

Forcemain from intersection of Mackus Road and North<br />

<strong>Blackburn</strong> Road to a high point on Hwy. 16.<br />

Diameter, mm<br />

Length, m<br />

Gravity sewer main from the end of 200 diameter forcemain to<br />

the Regional Correctional Centre tie-in<br />

Diameter, mm<br />

Length, m<br />

Forcemain from the existing <strong>Blackburn</strong> WWTP site to the high<br />

point on Graves Road<br />

Diameter, mrn<br />

Length, m<br />

Sanitary sewer syphon from Yellowhead Bridge connecting to<br />

downtown sewage collection system<br />

Diameter, mm<br />

Length, m<br />

Gravity sewer to intersection of l5Ih Ave. and Taylor Drive;<br />

construct new manhole


Section 4.0 - Blackbum <strong>Treatment</strong> O~tions<br />

Diameter, mm 300<br />

Length, m 100<br />

Gravity sewer along 15' Ave. from Taylor Drive to Birch Street;<br />

connect to 525 diameter sewer<br />

Diameter, mrn 300<br />

Length, m 180<br />

Pumpstation<br />

<strong>Upgrade</strong> Mackus Road PS for PWWF capacity<br />

Supply and install PS at existing Blackbum WWTP site to<br />

service residence along Graves and Foreman Roads; capable of<br />

pumping 10 percent of PWWF.<br />

Miscellaneons<br />

Restorellandscape existing Blackbum WWTP site.<br />

4.1.3 Cost Estimate<br />

Pipework<br />

150 forcemain, $100/m<br />

200 forcemain, $1 8Olm<br />

200 syphon, $200/m<br />

300 gravity sewer<br />

<strong>Blackburn</strong>, $160/m<br />

Downtown, S250lm<br />

Pumpstation<br />

Mackus Road PS, LS<br />

Foreman Road PS, LS<br />

Miscellaneous<br />

<strong>Blackburn</strong> WWTP site restorationflandscaping, LS<br />

Subtotal<br />

Contingencies (1 5 percent)<br />

Engineering/Administration (20 percent)<br />

GST (3 percent)<br />

TOTAL<br />

4.2 OPTION 2 - DECOMMISSION EXISTING BLACKBURN WWTP AND<br />

ROUTE ALL FLOW TO LANSDOWNE ROAD \ m P VIA GRAVITY<br />

SEWER CONNECTION<br />

4.2.1 Outline<br />

In this option the existing sewage lagoons would be decommissioned and all<br />

flows transferred for treatment at the Lansdowne Road WWTP via a new trunk<br />

gravity sewer. A schematic representation of this option is presented in Figure


Section 4.0 - Blackbum <strong>Treatment</strong> Options<br />

4.2. An H reduction program is to be initiated and completed to reduce the<br />

volume of wastewater being transferred during wet weather and snowmelt<br />

conditions. The existing Mackus Road pumpstation would be upgraded. It is<br />

believed that the Lansdowne Road WWTP has sufficient capacity to handle the<br />

projected future hydraulic and BOD5/TSS loadings from the Blackbum sewage<br />

collection area.<br />

Key activities or capital works assmiated with this option are as follows:<br />

Implement and complete VI reduction program.<br />

Decommission lagoons and rehabilitate site for other use.<br />

<strong>Upgrade</strong> Mackus Road pdpstation to handle projected increased flows.<br />

Construct trunk gravity sewer to transfer all flours hrn Blackbum<br />

sewerage area to Lansdowne Road WWTP.<br />

<strong>Upgrade</strong> downtown sewage collection pipework to handle increased flows<br />

from Blackbum sewerage area.<br />

Key technical issues associated with this option are as follows:<br />

Extent to which the VI reduction program is able to reduce peak wet<br />

weather flows must be evaluated.<br />

City need operate only one wastewater treatment and disposal facility.<br />

Major capital works needed to transfer flows to Lansdowne Road WWTP.<br />

Condition and capacity of the existing Mackus Road pumpstation must be<br />

evaluated.<br />

Details for pipeline routes for transferring Blackbum sewage flows to<br />

Lansdowne Road WWTP must be evaluated.<br />

Ammonia toxicity issue addressed at Lansdowne Road WWTP.<br />

4.2.2 Design Information<br />

Population<br />

ADWF, m3/d<br />

PWWE, m3/d


'IN - OF PRINCE GEORGE<br />

I<br />

Initiate Ill reduction program and<br />

complete over 5/10 year period;<br />

assess PWWF based on results.<br />

Decommission existing <strong>Blackburn</strong><br />

WWTP and restorellandscape site.<br />

a Route all flow to Lansdowne Road<br />

WWT P.<br />

Pipeline route (m m m) from Blackbum<br />

WWTP site to Correctional Centre tie-in.<br />

Assess conditionlcapacity of existing<br />

Mackus Road PS.<br />

a Assess conditionlcapacity of existing<br />

sewage conveyance system through<br />

downtown area.<br />

. . . . . - -<br />

~rin ~...<br />

, - ..c4 a Assess impact of added sewage flow<br />

citydf" .<br />

cg~- ~ed@e<br />

: / Road<br />

L ---- - . .<br />

on Lansdowne Road WWTP<br />

capacityloperation.<br />

.- ~<br />

..-. - --~<br />

LEGEND:<br />

------ Exist. Sanitary Collection Mains<br />

<strong>Blackburn</strong> Sanitary Collection Area<br />

City of Prince George<br />

ckburn <strong>Wastewater</strong> <strong>Treatment</strong> <strong>Plant</strong><br />

<strong>Treatment</strong> Options <strong>Study</strong><br />

OPTION 2<br />

ENGINEERING LIMITE; Figure 4.2<br />

I


Section 4.0 - Blackbum <strong>Treatment</strong> Options<br />

Pipework<br />

Gravity sewermain fiom the existing <strong>Blackburn</strong> WWTP site to<br />

the Regional Correctional Centre tie-in<br />

Diameter, mm<br />

Length, m<br />

Sanitary sewer syphon from Yellowhead Bridge connecting to<br />

downtown sewage collection system<br />

Diameter, mm<br />

m<br />

Gravity sewer to intersection of 1 5 Ave. ~ ~ and Taylor Drive;<br />

construct new manhole<br />

Diameter, mm<br />

Length, m<br />

Gravity sewer along 15Ih Ave. from Taylor Drive to Birch St.;<br />

connect to 525 diameter s&er<br />

Diameter, mm<br />

ten&, m<br />

Pumpstation<br />

<strong>Upgrade</strong> Mackus Road PS for P WWF capacity<br />

Miscellaneous<br />

Restore/landscape existing Blackbum WWTP site.<br />

4.2.3 Cost Estimate<br />

Pipework<br />

200 syphon, $200/m<br />

300 gravity sewer<br />

Blackbum, $160/m<br />

Downtown, $250/m<br />

Pumpstation<br />

Mach Road PS, LS<br />

Miscellaneous<br />

<strong>Blackburn</strong> WWTP site restorationtlandscaping, LS<br />

Subtotal<br />

Contingencies (1 5 percent)<br />

Engineering/Adrninistration (20 percent)<br />

GST (3 percent)<br />

TOTAL


Section 4.0 - Blackbm <strong>Treatment</strong> Options<br />

4.3 OPTION 3 - USE EXISTING BLACKBURN WWTP FOR<br />

EQUALIZATIONlSTORAGE AND TRANSFER ALL FLOWS TO<br />

LANSDOWNE ROAD WWTP<br />

4.3.1 Outline<br />

In this option the existing sewage lagoons would be converted to flow<br />

equalizationktorage basins, and all flows transferred for treatment at the<br />

Lansdowne Road WWTP. A schematic representation of this option is<br />

presented in Figure 4.3. The principal benefit of this option is that the peak<br />

flows being transferred from the <strong>Blackburn</strong> sewage wllection area to the<br />

Lansdowne Road WWTP would be attenuated somewhat. An VI reduction<br />

program is to be initiated and completed to reduce the volume of wastewater<br />

being transferred during wet weather and snowmelt conditions. The existing<br />

Mackus Road pumpstation would be upgraded. It is believed that the<br />

Lansdowne Road WWTP has sufficient capacity to handle the projected future<br />

hydraulic and BODflSS loadings from the <strong>Blackburn</strong> sewage wllection area.<br />

Key activities or capital works associated with this option are as follows:<br />

Implement L'l reduction program.<br />

0 Modify lagoons for use as flow equalizatiodstorage basins.<br />

0 <strong>Upgrade</strong> Mackus Road pumpstation to handle projected increased flows.<br />

Construct trunk gravity sewer to transfer all flows ihm <strong>Blackburn</strong><br />

sewerage area to Lansdowne Road WWTP.<br />

<strong>Upgrade</strong> downtown sewage collection system to handle increased flows<br />

from <strong>Blackburn</strong> sewerage area.<br />

Key technical issues assmiated with this option are as follows:<br />

Extent to which the I/I reduction program is able to reduce peak wet<br />

weather flows must be evaluated.<br />

City must maintain operation of storage basins; O&M costs of<br />

equalizatiodstorage basins are only slightly lower than O&M costs for the<br />

existing treatment lagoons.<br />

Major capital works needed to transfer flows to Lansdowne WWTP and<br />

modify lagoons.


Initiate Ill reduction program and<br />

complete over 5/10 year period;<br />

assess PWWF based on results.<br />

0 Modify existing <strong>Blackburn</strong> WWTP<br />

to operate as storage basins.<br />

a Route all flow to Lansdowne Road<br />

WWT P.<br />

Pipeline route (m m) from Blackbum<br />

storage basins to Correctional<br />

Centre tiein.<br />

Assess conditionlcapacity of existing<br />

Mackus Road PS.<br />

@ Assess conditionlcapacity of existing<br />

sewage conveyance system through<br />

downtown area.<br />

a Assess impact of added sewage<br />

flow on Lansdowne Road WWTP<br />

/Ti<br />

LEGEND:<br />

------ Exist. Sanitary Collection Mains<br />

Blackbum Sanitary Collection Area<br />

City of Prince George<br />

ckburn <strong>Wastewater</strong> <strong>Treatment</strong> <strong>Plant</strong><br />

<strong>Treatment</strong> Options <strong>Study</strong><br />

I<br />

OPTION 3<br />

Figure 4.3


Section 4.0 - Blackbum <strong>Treatment</strong> Options<br />

Condition and capacity of the existing Mackus Road pumpstation must be<br />

evaluated.<br />

Details for pipeline routes for transfening Blackbum sewage flows to<br />

Lansdowne Road WWTP must be evaluated.<br />

Ammonia toxicity issue addressed at Lansdowne Road WWTP.<br />

43.2 Design Information<br />

Population<br />

ADWF, m3/d<br />

PWWF, m3/d<br />

Pipework<br />

Gravity sewermain hm<br />

the existing Blackbum WWTP site to<br />

the Regional Correctional Centre tie-in<br />

Diameter, mm<br />

Length, m<br />

Sanitary sewer syphon hm Yellowhead Bridge connecting to<br />

downtown sewage collection system<br />

Diameter, mm<br />

Length, m<br />

Gravity sewer to intersection of 15" Ave. and Taylor Drive;<br />

construct new manhole<br />

Diameter, mm<br />

Length, m<br />

Gravity sewer along lSfh ~ ve. from Taylor Drive to Birch St.;<br />

connect to 525 diameter sewer<br />

Diameter, mm<br />

Length, m<br />

Pompstation<br />

<strong>Upgrade</strong>MackusRoadPSforPWWFcapacity<br />

Miscellaneous<br />

Modifications to Blackbum WWTP to operate as storage basin<br />

43.3 Cost Estimate<br />

Pipework<br />

200 syphon, S2OOJm<br />

300 gravity sewer<br />

Blackbum, $160/m<br />

Downtown, S250/m<br />

Pumpstation<br />

Mackus Road PS, LS


Section 4.0 - <strong>Blackburn</strong> <strong>Treatment</strong> Options<br />

Miscellaneous<br />

<strong>Blackburn</strong> WWTP modifications to allow lagoons<br />

to operate as storage basins, LS 100,000<br />

Subtotal 1,165,000<br />

Contingencies (15 percent) 175,000<br />

EngineerindAdministration (20 percent) 235,000<br />

GST (3 percent) 35,000<br />

TOTAL 1,610,000<br />

4.4 OPTION 4 - TRANSFER ALL FLOW < 2*ADWF TO LANSDOWNE<br />

ROAD WWTP AND USE THE EXISTING BLACKBURN WWTP TO<br />

TREAT FLOWS > 2*ADWF<br />

4.4.1 Outline<br />

In this option all flows up to 2*ADW would be transferred &om the<br />

Blackbum sewage collection area for treatment at the Lansdowne Road<br />

WWTP. The existing sewage lagoons would be used only to treat wet weather<br />

flows > 2*ADWF. A schematic representation of this option is presented in<br />

Figure 4.4. An yI reduction program is to be initiated and completed to reduce<br />

the volume of wastewater being treated in the lagoons during wet weather and<br />

snowmelt conditions. The existing Mackus Road pumpstation would be<br />

upgraded and a new pumpstation constructed to handle excess flow<br />

>2*ADWF. It is believed that the Lansdowne Road WWTP has sufficient<br />

capacity to handle the projected future 2*ADWF hydraulic and BODnSS<br />

loadings f7om the <strong>Blackburn</strong> sewage collection area. All wet weather flow ><br />

2*ADWF will be pumped to the existing Blackbum WWTP for treatment.<br />

Key activities or capital works associated with this option are as follows:<br />

Implement III reduction program.<br />

<strong>Upgrade</strong> Mackus Road pumpstation to handle projected increased flows.<br />

Ail dry weather flows < 2*ADWF are to be pumped to Lansdowne Road<br />

WWTP; all wet weather flows > 2*ADWF are to be pumped to <strong>Blackburn</strong><br />

WWTP.<br />

Construct trunk gravity sewer and/or forcemain to transfer all flows<br />


SECTION 3<br />

AUDIT OF EXISTING FACILITIES


SECTION 3.0<br />

AUDIT OF EXISTING FACILITIES<br />

3.1 BLACKBURN WASTEWATER TREATMENT PLANT<br />

The <strong>Blackburn</strong> WWTP is adjacent to Foreman Road and treats wastewater<br />

from the Prince George Airport, Airport Hill, Aitcheson and Blackbum areas.<br />

The plant was constructed in 1976 for a design population of 2,500, and<br />

consists of an inlet works, two aerated lagoons with coarse bubble aeration,<br />

and a chlorination facility. h e plant is presently close to both its design<br />

hydraulic and organic loading capacity. Its hydraulic capacity is often<br />

exceeded during wet weather and winterkpring thaw conditions, which<br />

contribute high levels of III to the wastewater flows. Emuent quality is also<br />

impacted during the spring to summer transition as the lagoons warm up.<br />

Lagoon temperatures in the winter are in the order of 0°C to 5"C, and in the<br />

summer they can exceed 20°C.<br />

At the time of the site visit in September 1999, the lagoon system was<br />

producing an emuent quality of BOD5 < 15 mgiL and TSS < 5 mgL. On<br />

average, the lagoon emuent BODj/TSS concentrations are approximately<br />

20120 mgL, with occasional pmit exceedences during high flows in the<br />

spring. During high flow periods, the plant also regularly exceeds the<br />

maximum allowable daily flow stipulated in the discharge permit.<br />

There are also a number of reported operating problems with the plant. These<br />

include the "freezing" of inlet control valves to the lagoons due to corrosion,<br />

and odour generation during the late spring and early summer. The nearest<br />

houses are approximately 100 m away korn the lagoons. Occasional odour<br />

complaints are received, particularly during the spring breakup when the<br />

lagoon temperature increases, anaerobic biological activity increases and rising<br />

sludge is observed. The operators address the problem by pumping sludge<br />

from the primary lagoon to the secondary lagoon over a 6 week period during<br />

this time.<br />

3.1.2 Preliminary <strong>Treatment</strong><br />

The existing screening room has three influent channels: two 600 mm wide<br />

channels (one equipped with a 75 mm trash rack, one bypass) and a central 450


Section 3.0 -Audit of Existing Facilities<br />

mm wide channel equipped with a cornminutor. The wmminutor is operated<br />

once per day manually, and three times per day automatically. For each of<br />

these cycles, the comminutor is run for approximately 5 minutes.<br />

3.1.3 Secondary <strong>Treatment</strong><br />

The screenedtmacerated wastewater flows by gravity to a series of two unlined<br />

aerated lagoons. The primary lagoon (Lagoon 1) has a volume of<br />

approximately 4,500 m3. The secondary lagoon (Lagoon 2) has a volume of<br />

approximately 14,000 m3. The design mTs of the two lagoons are<br />

approximately 5 days and 15 days, respectively. Both lagoons are equipped<br />

with vertical tube coarse bubble aeration diffusers. The aerators are located in<br />

the centre of Lagoon 1, and in the upstream half of Lagoon 2. The downstream<br />

half of Lagoon 2 serves as a sludge settling zone. Air to the lagoons is<br />

supplied by two 60 hp multistage centrifugal blowers. There is some evidence<br />

of rising sludge and excessive surface foarn/scum in Lagoon 1, and abundant<br />

surface algae growth on the downstream half of Lagoon 2.<br />

3.1.4 Effluent Disposal<br />

The plant is equipped with a chlorine contact tank and chlorination equipment.<br />

However, the City has had an exemption from eMuent chlorination at the plant<br />

since 1983. The outlet of the chlorine contact tank is equipped with a V-notch<br />

weir and Miltronics ultrasonic level sensor, which serve as the principal flow<br />

measuring device. Effluent from the plant flows through a 300 mm diameter<br />

outfall pipe to the Fraser River, where it is discharged just below the river low<br />

water mark.<br />

3.1.5 Sludge <strong>Treatment</strong><br />

The plant is not equipped with sludge removal or handling equipment.<br />

Temporary pumps and piping are used to transfer sludge from -Lagoon 1 to<br />

Lagoon 2 during the spring break-up. Buildup of sludge has not been a<br />

problem during 25 years of operation and consequently removal of sludge from<br />

Lagoon 1 or 2 has not been required.<br />

3.2 LANSDOWNE ROAD WASTEWATER TREATMENT PLANT<br />

3.2.1 Outline<br />

The Lansdowne Road WWTP is the City's main wastewater treatment facility<br />

and treats wastewater from all sewered areas within the City with the exception


Section 3.0 -Audit of exist in^ Facilities<br />

of two industrial subdivisions, Western Acres subdivision and the <strong>Blackburn</strong><br />

area The plant was originally constructed as a high rate activated sludge<br />

process. In 1996, the plant was upgraded to a trickling filter/solids contact<br />

(TFISC) process by the addition of trickling filters and new secondary<br />

clarifiers. The most recent upgrade of the plant was designed for population of<br />

115,000 and an average dry weather flow (ADWF) of 44.5 MLld.<br />

Waste primary and secondary sludge from the plant is stabilized by mesophiIic<br />

anaerobic digestion. The digested sludge is dewatered and stored on the plant<br />

site before being trucked off-site for application to agricultural and forested<br />

land.<br />

At the time of the plant visit in September 1999, the plant was treating about<br />

30 ML/d, which is approximately 67 percent of its design capacity. There are<br />

no reported serious operating or odour problems at the plant.<br />

3.2.2 Preliminary <strong>Treatment</strong><br />

<strong>Wastewater</strong> entering the plant is screened on two 1,500 mm wide Envirex<br />

mechanically raked bar screens. The screens have a bar spacing of 19 mm.<br />

Screenings are removed on a belt conveyor to a pneumatic ejector. Each<br />

screen is followed by a 900 mm parshall flume, and Fisher and Porter<br />

ultrasonic level sensor, which serve as the principal flow measuring devices.<br />

The screened wastewater enters two aerated grit removal chambers (only one<br />

unit is normally in service at a time). The grit and scum is dewatered and<br />

trucked off site for disposal at the Regional sanitary landfill.<br />

3.2.3 Primav <strong>Treatment</strong><br />

The screened degriaed wastewater enters two covered rectangular primary<br />

sedimentation tanks. The tanks are equipped with plastic chain and flight, and<br />

cross collector mechanisms. As well, the tanks are equiped with scum removal<br />

devices. Effluent from the sedimentation tanks is collected through a system<br />

of submerged launders and flows into a wet well.<br />

3.2.4 Secondary <strong>Treatment</strong><br />

Secondary treatment consists of biofilters (trickling filters), a solids contact<br />

tank and two circular secondary clarifiers. Primary eMuent from the wet well<br />

is pumped to a series of headers for distribution over the top of the biofilters by<br />

three (2 duty; 1 standby) 60 hp Flygt pumps located in the main pumpstation.<br />

The biofilter pumps for the pumping of primary effluent to the biofilters are


Section 3.0 -Audit of Existing Facilities<br />

equipped with VFD's, and are controlled to maintain a given water level in the<br />

primary effluent channel. The biofilters are equipped with medium density<br />

Brentwmd crossflow media 6 m deep. Odours emanating from the biofilter<br />

are controlled using a cocurrent ventilation system. Aithough the biofilters are<br />

covered, some algae problems have been experienced. However, there does<br />

not appear to be fly or snail problems typically associated with trickling filters.<br />

Effluent kom the biofilters is pumped to the solids contact tank by three (2<br />

duty; 1 standby) 60 hp Flygt pumps located in the main pumpstation. The<br />

biofilter underflow pumps are equipped with VFD's. The solids contact tank is<br />

equipped with Wyss rubber sheath diffusers manufactured by Parkson.<br />

Aeration air is supplied by two (1 duty; 1 standby) 50 hp Aerzen positive<br />

displacement blowers. Mixed liquor in the solids contact tank appears to have<br />

good sludge settling properties, with SVI's generally between 65 and 75 mL/g.<br />

Mixed liquor from the solids contact tank flow by gravity to two 29 m<br />

diameter secondary clarifiers. The clarifiers are equipped with double sided<br />

inboard emuent launders and "Tow-Bro" rapid sludge removal mechanisms<br />

manufactured by Envirex. Return biological solids (RBS) are pumped from<br />

the secondary clarifiers to the solids contact tank by thee (2 duty; 1 standby)<br />

30 hp Flygt pumps located in the main pumpstation.<br />

3.2.5 Emnent Disposal<br />

The plant is equipped for effluent disinfection and dechlorination using<br />

gaseous chlorine and sulphur dioxide. However, these facilities are not<br />

currently in use as the City has an exemption h m effluent chlorination.<br />

Effluent from the plant discharges to the Fraser River through a 900m diameter<br />

outfall pipe.<br />

3.2.6 Sludge <strong>Treatment</strong><br />

Approximately 2.5 L/s of waste secondary sludge is continuously bled off the<br />

RBS line and returned to the inlet of the primary sedimentation tanks for cothickening<br />

with the primary sludge. The waste primary and secondary sludge<br />

mixture is pumped to two mesophilic anaerobic digesters for stabilization. The<br />

two digesters are operated in series, one as a primary and the other as a<br />

secondary digester. Both digesters are equipped with floating covers. Digester<br />

heating is provided by 2 (1 duty; 1 standby) low pressure boilers. Digester gas<br />

is also used to power a 250 hp cogeneration unit manufactured by Caterpillar.<br />

The primary digester is reseeded every 2 weeks using sludge from the


Section 3.0 -Audit of Existing Facilities<br />

secondary digester. Sodium percarbonate is added to the digesters for<br />

hydrogen sulphide and odour control.<br />

The digested sludge is dewatered on belt filter presses manufactured by<br />

Envirex. Each press has a 2 rn wide gravity section, and a 1 m wide pressure<br />

section. The presses are operated for 7 h/4 4 to 5 &week. Percol757 polymer<br />

and a potato starch based product (Raifix) are used as coagulants. The presses<br />

produce a sludge cake with a dry weight solids content of approximately 22<br />

percent.<br />

3.3 Operations Staff<br />

The <strong>Blackburn</strong> and Lansdowne Road WWTPs are operated by a full time sta!T<br />

of eight persons consisting of one Class IV chief operator, a laboratory<br />

technician, 2 Class I1 operators, and 4 Class I operators. The operating staff<br />

are all based at the Lansdowne Road facility, where most of their duties are<br />

carried out. One operator spends 1 hld, 7 dweek to do a daily inspection at the<br />

<strong>Blackburn</strong> WWTP, and 4 hours once monthly to do the effluent composite<br />

sampling and preventive maintenance. Other City tradespeople (millwright,<br />

electrician, instrument technician) are called to the plants on an "as required"<br />

basis.<br />

3.4 Conclusion<br />

The existing Lansdowne Road WWTP was designed for an ADWF of 44.5<br />

Mud and a PWWF of 115 Mud. The plant is currently treating<br />

approximately 30 MU& or 67 percent of its design flow and load, and does not<br />

appear to have any unit processes in either the liquid or sludge treatment<br />

streams that are close to capacity and may serve as a "bottleneck" if flows to<br />

the plant were increased by a modest amount. The current dry weather flows<br />

and loads h m the Blackbum catchment represent less than 2 percent of the<br />

design capacity of the Lansdowne Road WWTP. The current wet weather<br />

flows (i.e. prior to implementation of the VI mitigation measures) represent<br />

less than 5 percent of the hydraulic capacity of the Lansdowne Road WWTP.<br />

Even with the expected increase in flows and loads from Blackbum sewage<br />

collection area as a result of increasing the serviced population to 5,000, these<br />

flows and loads represent less than 4 percent of the design capacity of the<br />

Lansdowne Road WWTP.


SECTION 2<br />

I/I MITIGATION MEASURES


SECTION 2.0<br />

III MITIGATION MEASURES<br />

2.1 INTRODUCTION<br />

Snowmelt and rainfall that enters a sanitary sewer during wet weather periods can be<br />

categorized as either inflow or infiltration. Inflows are due to direct connections of<br />

rainfall and/or snowmelt and contribute to rapid flow increases, whereas infiltration is<br />

due to indirect sources and produces delayed flows and extended flow increases.<br />

Therefore, inflows are critical for short high intensity as well as for long duration<br />

storms; infiltration would be critical for Iong duration events. Since prolonged wet<br />

weather, due to winter thaws and spring raidthaw conditions, is quite normal in the<br />

BIackbum area, both inflow and infiltration (III) contribute significantly to the<br />

overloading of sanitary sewers.<br />

Excessive H places significant peak flow demands on the sanitary sewer system.<br />

Retrofit measures such as upgrading capacity of pipes, pumpstations, and treatment<br />

facilities can substantially increase the cost of providing sewer service. On the other<br />

hand, realizing the significance of yI and impIementing a program of L'l reduction can<br />

extend the life of facilities by deferring the need to upgrade hydraulic capacity.<br />

Controlling excessive amounts of VI is the single largest demand-side management<br />

issue for any wastewater collection system. Therefore, a planned yI investigation and<br />

analysis methodology can be adopted to: detect and identify these It1 sources on a site<br />

specific basis; quantify their comparative impacts; find appropriate mitigative<br />

measures on a prioritized basis; and implement policies that promotes the reduction of<br />

excessive UI.<br />

A Mica1 I/I mitigation work plan methodology recognizes that:<br />

Within the sewer network, major VI sources can be 'leaky' manholes, poor pipe<br />

joints, poor senice connections, and failed pipes.<br />

High ground water table during wet weather periods can create high hydraulic<br />

heads, which result in continuous UI through the defective components of the<br />

sewer network.<br />

A significant portion of UI is often generated within private property.<br />

Since a major source of the UI can be generated on individual lots, the potential<br />

costbenefits of implementing I/l reduction measures on private property should be<br />

part of the solution.


Section 2.0 - III Mitigation Measures<br />

The I/I control program should incorporate ongoing performance monitoring by<br />

collecting additional performance data to monitor the cost effectiveness of the<br />

various rehabilitation techniques.<br />

It is important to control both the "on-lot" UI and "on-street" I/I by developing a<br />

public information/participation component into the IT management strategy. Control<br />

of "on lot" V1 has significant merit as it is a 'source control' at the top end which<br />

eliminates entry into the sewer network. However, it can be hught with the often<br />

challenging need to get the homeowner's buy-in. This would need a review of the<br />

service connection and lot grading practiceshy-laws applicable to existing lots as well<br />

as future developments.<br />

The City commissioned Stantec Consulting Ltd. to complete a study on Vl in the<br />

<strong>Blackburn</strong> sewage collection area Ad present conclusions and recommendations. The<br />

final report was submitted June, 1999. Attached as Appendix A are the conclusions of<br />

this report. In short, the Stantec Consulting report recommended that the most cost<br />

effective approach to the VI problem was to implement a rehabilitation program for<br />

manholes and the collection pipework.<br />

Based on the Stantec Consulting report recommendations, the City plans to implement<br />

during the operating year of 1999 a manhole rehabilitation program and attempt to<br />

reduce by the end of 2000, PWWF by nearly 50 percent. Over the following 5 to 10<br />

years, the VI reduction program would be ongoing.<br />

2.2 IA REDUCTION PLAN<br />

2.2.1 Inflow Reduction<br />

The manhole rehabilitation work, set out by Stantec Consulting Ltd., has been<br />

predicted to reduce the volume of inflow by 2,170 m3/d. Tnis brings the peak wet<br />

weather flow (PWWF) down from 4,500 m3/d to 2,330 m3/d. However, this still<br />

exceeds the limits of the discharge permit. Tberefore, Wher reduction of Ill is<br />

required to meet design and permit requirements.<br />

2.2.2 Infiltration Reduction<br />

Population<br />

Currently, the population for the Blackbum sewerage area is estimated to be 1,800. A<br />

population growth rate of approximately 4.2 percent is assumed for the area and based<br />

on this growth rate the population in 25 years will be 5,000. See Table 2.1.


Section 2.0 - UI Mitigation Measures<br />

Sanitary Design Flow<br />

Using a sanitary design flow value of 350 L/cap/d and contributing population of<br />

1,800, the current average dry weather flow (ADWF) can be calculated as 630 m3/d.<br />

The design allowable PWWF can then be determined at 2 x ADWF as 1,260 m3/d.<br />

Using this calculation, the discharge permit limit of 1,375 m3/d at the Blackbum<br />

WWTP would be exceeded in the year 2002 assuming apopulation of 2,035.<br />

Projected PWWF<br />

Projected PWWFs are calculated on the basis of the PWWF volume recorded during<br />

the March 25,1999 period. As discussed above, the manhole rehabilitation program is<br />

predicted to reduce the inflow portion of M, decreasing the PWWF kom 4,500 m3/d to<br />

2,330 m3/d. In order to reduce this flow to the PWWF permit allowable requirements,<br />

infiltration will have to be reduced. The infiltration portion of UI is calculated as:<br />

Infiltration (1999), m3/d = P W -Inflow - Design PWWF (1999)<br />

- 4,500-2,170- 1,260<br />

- 1,070<br />

The reduction of infiltration could be accomplished by rehabilitating pipes, pipe joints,<br />

manholes, and service connections over a 5 or 10 year implementation period.<br />

5 Year Rehabilitation Plan<br />

The 5-year plan investigates the reduction of 1,070 m3/d over a 5 year period. This<br />

equates to a reduction of approximately 215 m31dly assuming a PWWF (2004) of<br />

1,545 m3/d. Table 2.1 lists PWWF reductions over a 5 year period.<br />

10 Yar Rehabilitation Plan<br />

Much like the 5 year plan, the 10 year plan investigates the reduction of 1,070 m3/d<br />

over a 10 year period. This equates to a reduction of approximately 105 m3/ay,<br />

assuming a PWWF (2009) of 1,895m3/d. Table 2.1 lists PWWF reductions over a 10<br />

year period.<br />

Figure 2.1 compares the projected PWWF to the design P IW over a 25 year period.<br />

2.3 REHABILITATION COST ESTIMATES<br />

As described previously, the volume of inflow is estimated as 2,170 m3/d and the<br />

volume of infiltration as 1,070 m3/d. The ratio of inflow to total VI is 67 percent; and<br />

for infiliration 33 percent.


Section 2.0 - UI Mitigation Measures<br />

Infiltration can enter a sewer system through deficiencies or cracks in 3 categories of<br />

the sewer line: connections, in-street pipes including joints, and manholes. Infiltration<br />

that can be expected to result from each of the 3 categories is calculated on a mmdiameter-m<br />

basis. Other assumptions involved in the proportioning of infiltration<br />

amongst pipes, manholes, and connections is the lower construction standards of<br />

connection installment (45 percent), and the 7 mt10 m split of municipaVprivate<br />

connection length.<br />

Table 2.2a calculates that of the 33 percent of III that is infiltration, approximately 21<br />

percent is from pipes, 3 percent from manholes, 4 percent from municipal connections,<br />

and 5 percent from private connections.<br />

Table 2.2b and Table 2.2~ calculate the percent infiltration reduction required from<br />

pipes including joints, manholes, and connections in order to reach the required yearly<br />

reduction as previously described in Table 2.1. The amount of physicaf rehabilitation<br />

is based on the assumption that grouting a section of pipe will only reduce its<br />

contribution to infiltration by a maximum of 75 percent. Therefore, the percent of<br />

rehabilitation must be higher in order to achieve the required percent of infiltration<br />

reduction. For example, during the first year (2000) of the 5 year plan, about 6 percent<br />

of the infiltration in pipes must be reduced. This means that approximately 8 percent<br />

ofpipes must be grouted to achieve the required reductions in infiltration.<br />

Table 2.3a and Table 2.3b estimates the cost of rehabilitation based on the grouting of<br />

each sewer element. The cost of grouting is assumed as follows:<br />

Pipes, $/m<br />

Manholes, $/unit<br />

Connections, $/m<br />

The total cost for the 5 year and 10 year rehabilitation plans are $1,580,000 and<br />

$1,120,000 respectively. The Net Present Value (NPV) is calculatd in Table 2.4.<br />

Based on an annual discount rate of 6 percent, the NPV for the 5 and 10 year plans are<br />

$1,319,000 and 5815,000 respectively.<br />

The 10 year plan requires less work to be done as it is based on the percentage of flow<br />

reduction each year to the previous year. Therefore, the overall capital cost is<br />

$460,000 less than the 5 year plan. However, it should be noted, that by committing<br />

to a 10 year plan, the City of Prince George is not meeting the 2 x ADWF criteria for<br />

the Blackbum sewerage area for an additional 5 years. This makes the 5 year plan a<br />

flow based benefit plan, and the 10 year plan a cost based benefit plan.


APPENDIX E<br />

FLOW CALCULATIONS FOR SEWER UPGRADES


.<br />

Date: 23 December 1999<br />

File: 1174-01-01<br />

Reid Crowther & Partners Ltd.<br />

Consulting Engineers<br />

300, 41 70 Still Creek Drive<br />

Burnaby, British Columbia<br />

V5C 6C6<br />

Attention:<br />

Mr. Andv North. P.Ena.<br />

Dear Andy,<br />

AS recently requested by Les Nemeth. P.Eng.. please find attached our flow calculatio'n - ,<br />

,<br />

...<br />

spreadsheet showing the capacity of the existing sanitary sewer mains from the ~e~ional , ' -<br />

. .<br />

Correctional Centre to tlie discharge into the 600mm diameter City trunk sanitary . .<br />

. .<br />

. . . .<br />

sewermain on Taylor Drive. -<br />

. .<br />

. ........<br />

. .<br />

. . .. -<br />

,-<br />

..<br />

The estimated future peak PU~P~IOW<br />

rate.from the Mackus Road sewage lift station is -<br />

.....<br />

..- .<br />

50 Lls (0.05 mals). The section :of existing 200mm diameter sewer main from the I' ~ .,<br />

. ~<br />

discharge point of the 200mm diameter syphon, at MH KL23a to the intersection'of the ......<br />

525 mm diameter main at Birch Street, will need to be upgradbd,to a 300mm diameter . . ,<br />

pipe at a-minimum. grade of 0.3% to handle the futire pumped peak flows'of ':

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!