liquidated damages were irrecoverable as <strong>the</strong> completion date could not be identified as<br />
time had become “at large”.<br />
However, Jackson J in Multiplex Constructions (UK) Ltd v Honeywell Control Systems Ltd (No.<br />
2). 22 did not accept that Gaymark represented English law <strong>and</strong> instead considered that a<br />
notice must be provided. The case of City Inn Ltd v Shepherd Construction Ltd. 23 adopted<br />
<strong>the</strong> same approach, although in <strong>the</strong> third <strong>and</strong> final judgment <strong>the</strong> Judge accepted that <strong>the</strong><br />
right had been waived by <strong>the</strong> employer because <strong>the</strong> lack of notice had not been initially<br />
relied upon by <strong>the</strong> architect.<br />
Finally, <strong>the</strong> contractor may be able to rely upon <strong>the</strong> equitable principles of waiver <strong>and</strong>/or<br />
estoppel. It may be that <strong>the</strong> contractor does not serve a formal notice because, by words<br />
or conduct, <strong>the</strong> employer or indeed <strong>the</strong> project manager represents that <strong>the</strong>y will not rely<br />
upon <strong>the</strong> strict eight week notice period. The contractor would also need to show that<br />
<strong>the</strong> contractor relied upon that representation <strong>and</strong> that it would now be inequitable to<br />
allow <strong>the</strong> employer to act inconsistently with <strong>the</strong> representation made by <strong>the</strong> employer<br />
or project manager. In addition, this approach could be fur<strong>the</strong>r supported by core clause<br />
10.1 which requires <strong>the</strong> parties to act “in a spirit of mutual trust <strong>and</strong> co-operation”.<br />
Clause 63 provides that changes to <strong>the</strong> price as a result of <strong>the</strong> compensation event are<br />
assessed by reference to <strong>the</strong> actual Defined Cost of <strong>the</strong> work already done, forecast<br />
Defined Cost of <strong>the</strong> work to be done, <strong>and</strong> any resulting fees. 24 It is <strong>the</strong> project manager<br />
that assesses compensation events. In <strong>the</strong> event of a disagreement, <strong>the</strong>n disputes may<br />
be referred to an adjudicator.<br />
FIDIC<br />
FIDIC is <strong>the</strong> Federation International Des Ingenieurs-Conseils. It is an association of<br />
national associations of engineers, which formed in 1913. Its headquarters are in<br />
Switzerl<strong>and</strong>.<br />
The first edition of <strong>the</strong> FIDIC form was produced from <strong>the</strong> ICE st<strong>and</strong>ard form, <strong>and</strong> so was<br />
virtually <strong>the</strong> same. The 4 th edition of <strong>the</strong> “Red Book” has been widely used around <strong>the</strong><br />
world for major projects. Many public works department contracts are based on it, for<br />
example <strong>the</strong> Malaysian Public Works Department contracts PWD203.<br />
22 Multiplex Constructions (UK) Ltd v Honeywell<br />
Control Systems Ltd (No 2) [2007] EWHC 447<br />
(TCC), [2007] BLR 195.<br />
23 City Inn Ltd v Shepherd Construction Ltd<br />
2002 SLT 781, [2001] SCLR 961, Outer Hse, Ct of<br />
Sess; <strong>the</strong>n appealed to <strong>the</strong> Inner Hse (successful<br />
on <strong>the</strong> point that failure to use <strong>the</strong> procedures<br />
of clause 13.8 was not itself a breach of<br />
contract, so <strong>the</strong> clause could not be treated as<br />
imposing a penalty), [2003] BLR 468.<br />
24 Clause 52.1 sets out <strong>the</strong> meaning of<br />
Defined Cost<br />
It cannot now be said that <strong>the</strong>re is much similarity between ICE <strong>and</strong> FIDIC. Both <strong>the</strong> ICE<br />
<strong>and</strong> FIDIC have developed by way of revision, <strong>and</strong> <strong>the</strong>n <strong>the</strong> issue by FIDIC of a suit of<br />
contracts:<br />
• Conditions of Contract for Construction Building <strong>and</strong> Engineering Works<br />
Designed by <strong>the</strong> Employer (Red Book);<br />
• Conditions of Contract for Plant <strong>and</strong> Design Build for Electrical <strong>and</strong><br />
Mechanical Plant <strong>and</strong> for Building <strong>and</strong> Engineering works designed by <strong>the</strong><br />
Contractor (Yellow Book);<br />
• Conditions of Contract for EPC/Turnkey Projects (Silver Book); <strong>and</strong><br />
• Short Form of Contract (Green Book).<br />
18