Question 12<br />
State in the correct sequence the first FIVE<br />
tests that would need to be undertaken on an<br />
A1 ring circuit during an initial verification<br />
GN3 Page 29 2.7.4<br />
1. Continuity of protective conductors<br />
2. Continuity of ring final circuit conductors<br />
3. Insulation resistance<br />
4. Polarity<br />
5. Impedance Zs