DGBR MONTHLY NEWS LETTER<br />
1. This News Letter covers the period from 01 Mar 2011 to 31 Mar 2011. The information<br />
given is of informative nature and cannot be quoted as an authority.<br />
DG’s SECRETARIAT<br />
2. (a) Visit to Chennai. DGBR visited Chennai wef 28 Feb 2011 to 01 Mar 2011 and<br />
attended seminar on „New Materials in Road Construction for Stabilized Pavements‟ at IIT<br />
Chennai.<br />
(b) Visit to Project Sewak and NH-53 (Pushpak) . DGBR visited Project Sewak<br />
and NH-53 of Project Pushpak wef 02 Mar 2011 to 05 Mar 2011. The highlights of the<br />
visit are as under :-<br />
(i) The DGBR inspected progress of ongoing works on the<br />
following road sectors:-<br />
(aa) NH-53, HH-39, Inspection of Limakong Br, Moreh-Thingphai-New-<br />
Samtal Road and Moreh fencing wks.<br />
(ii)<br />
The DGBR called on the following dignitaries:-<br />
(aa) Shri Nikhil Kumar, HE The Governor of Nagaland.<br />
(ab) Shri Neiphiu Rio, Hon‟ble Chief Minister, Nagaland.<br />
(ac) Maj Gen M George, VSM, Offg GOC 3 Corps.<br />
(ad) Maj DS Hudda, AVSM,VSM, GOC 57 Mtn Div.<br />
(iii)<br />
The DGBR also interacted informally with all ranks at all locations.<br />
(c) Visit to Guwahati. DGBR visited Guwahati on 11 Mar 2011 and attended DPC<br />
for promotion to the grade of Administrative Officer in BRO for the vacancy<br />
year 2010-2011.<br />
(d) Visit to Project Sampark. DGBR visited Project Sampark wef 16 Mar to 18<br />
Mar 2011. The highlights of the visit are as under :-<br />
(i) The DGBR inspected progress of ongoing works on the following road<br />
sectors :-<br />
(aa) Four laning wks of NHAI, Basoli Br, Rajouri-Tain Br,<br />
Reasi-Katra Road & Domel-Katra road.<br />
(ii) The DGBR called on the following dignitaries :<br />
(aa)<br />
(ab)<br />
(ac)<br />
Lt Gen KT Parniak, UYSM, YSM, GOC-in-C, Northern Command.<br />
Lt Gen JP Nehra, AVSM, GOC 16 Corps.<br />
Maj Gen AK Chaturvedi, CE, Northern Command.<br />
(iii) The DGBR also interacted informally with all ranks at HQ CE (P)<br />
Sampark.
PERSONNEL DIRECTORATE<br />
Assumption of Appointment<br />
3. The following offrs have assumed the appointments as shown against each during the<br />
month of Mar 2011 :-<br />
(a)<br />
Chief Engineer<br />
(i) IC-41915F Brig - CE (P) Vartak<br />
Rohit Kapoor (01 Mar 2011)<br />
(ii) IC-41994F Brig - CE (P) Sewak<br />
Arun Joshi (08 Mar 2011)<br />
(b)<br />
Commander Task Force<br />
(i) IC-52073F Col - Commander 32 TF<br />
Rajesh Karel (28 Feb 2011)<br />
(II) GO-002167H EE (C) - Offg Commander 760 TF<br />
Steevan Prakash Kolipey (11 Mar 2011)<br />
Promotions<br />
4. Promotion from Sudpdt E&M-I to AE (E&M):-<br />
(a) GS-156960A, MOHANAN KR<br />
(b)<br />
(c)<br />
(d)<br />
(e)<br />
GS-158514X, RANJIT SINGH<br />
GS-158515A, PARVEEN SINGH GURM<br />
GS-160791F, KAILASH NARAYAN<br />
GS-160792K, RANAJAY SARKAR<br />
5. Promotion from AE (E&M) to AEE (E&M):-<br />
(a)<br />
(b)<br />
(c)<br />
GO-3456K, SANJAY SABLE<br />
GO-3459X, CHITRA NAND GUPTA<br />
GO-3475P, SURINDER KUMAR
6. Promotion from AE (Civ ) to AEE (Civ):-<br />
(a) GO-3153P, JAGDISH SINGH<br />
(b) GO-3154X, JALANDER PRASAD SAHU<br />
(c) GO-3155A, KEWAL SINGH SALARIA<br />
(d) GO-3156H, SHASHI BHUSHAN JOSHI<br />
(e) GO-3157L, BIPIN CHANDRA OLI<br />
(f) GO-3158N, YS GULERIA<br />
(g) GO-3159W, YOGENBER SINGH NEGI<br />
(h) GO-3160L, MURARI PRASAD<br />
(j) GO-3162W, BRAHMA DASS BISHT<br />
(k) GO-3177Y, NETRAPAL SINGH<br />
(l) GO-3178F, ASHWANI KUMAR SHARMA<br />
(m) GO-3231F, UDAIYAR E<br />
(n) GO-3232K, TULSI RAM JATAV<br />
(o) GO-3233M, RAM DHARI RAM<br />
(p) GO-3234P,DILIP KUMAR KHATIK<br />
(q) GO-3235X, DINESH BABU K<br />
(r) GO-3236A, KASHMIRI LAL<br />
(s) GO-3238L, RAJ KUMAR<br />
(t) GO-3239N, RAM PRAKASH UDAY<br />
(u) GO-3241L, PREM NARAYAN<br />
(v) GO-3242N, GIRISH CHAND<br />
(x) GO-3243W, SATYANARAYAN RAM<br />
(y) GO-3257W, R KARTHIKEYAN PILLAI<br />
(z) GO-3259F, SATYA PRAKASH SHARMA<br />
(aa) GO-3260W, APPUKUTTAN AP<br />
(ab) GO-3261Y, AK MEHRA<br />
(ac) GO-3262F, KKR BABU<br />
(ad) GO-3263K, DS DHILLON<br />
(ae) GO-3265P, S CHANDRA SEKARAN<br />
(af) GO-3332P,DESRAJ BHARDWAJ<br />
(ag) GO-3333X, GAJRAJ SINGH<br />
(ah) GO-3334X, KP KRISHNAN KUTTY<br />
(aj) GO-3337N, VIPIN KUMAR<br />
(ak) GO-3342Y, K GURUSWAMY<br />
(ak) GO-3357F, A THOMAS EDISON<br />
(al) GO-3358K, SHRIPAL SINGH<br />
(am) GO-3360F, VR MURALEEDHARAN NAIR<br />
(an) GO-3361K, SASIDHARAN CG<br />
(ao) GO-3370L, SATENDER KUMAR<br />
(ap) GO-3400X, T VARAPRASADAM<br />
(aq) GO-3411K, SANT RAM YADAV<br />
(ar) GO-3420L, RADHIKA RAMAN SINGH<br />
(as) GO-3421N, ANIL KUMAR BISHNOI<br />
(at) GO-3422W, HAKAM SINGH<br />
(au) GO-3424F, T BOOPATHI
Postings : GREF Officers<br />
7. Following posting orders of various cadres of GREF Offrs have been issued:-<br />
(a) SE (Civ) FS - 02<br />
(b) EE (Civ) - 15<br />
(c) AEE (Civ) - 66<br />
(d) AE (Civ) - 13<br />
(e) EE (E&M) - 05<br />
(f) AEE (E&M) - 09<br />
(g) AE (E&M) - 07<br />
(h) JD (Admn) - 03<br />
(j) SAO - 05<br />
(k) AO - 05<br />
(l) AAO - 03<br />
(m) MO-II (ADHOC) - 04<br />
Wastage Data of GREF Officers<br />
8. (a) Superannuation<br />
Ser GO No Rank Name Project/TF/Unit Date of<br />
Retirement<br />
(i) GO-3361K AE (CIV) SASIDHARAN CG 1441 BCC/(P) VTK 31.03.2011<br />
(b)<br />
Resignation<br />
Ser GO No Rank Name Project/TF/Unit Date of Resignation<br />
(i) GO-3883A MO-II MUKESH SHARMA 45 BRTF/ (P)<br />
CTK<br />
With IMMEDIATE<br />
EFFECT/21.03.2011<br />
(ii) GO-3650Y AEE<br />
(CIV)<br />
VIKRAM SINGH<br />
MEENA<br />
151 FCPL/68<br />
RCC/(P) DPK<br />
WITH IMMEDIATE<br />
EFFECT<br />
(c)<br />
Voluntary Retirement<br />
Ser GO No Rank Name Project/TF/Unit Date of Retirement<br />
(i) GO-3635K AE (CIV) R SIKAMANI 361 RMPL/57 01.03.2011 (VR)<br />
RCC/13 TF/(P) SPK<br />
(II) GO-1450K CE (CIV) Dr. AR TIWARI HQ DGBR 29 MAR 2011<br />
COMPULSORY<br />
RETIREMENT<br />
Wastage Data of GREF Subordinates<br />
9. Wastage data of GREF subordinates for the month is as under:-<br />
(a) Voluntary Retirement - 26<br />
(b) Superannuation - 17<br />
(c) Death Cases - 17<br />
(d) Resignation/Discharge/Removal - 35<br />
from Service/Permanent Absorption<br />
Total - 95
Loans and Advances<br />
10. Govt sanction received towards loans and advances during the month are as under :-<br />
Courses<br />
(a) Motor Cycle/Scooter Advance : Rs. 90,000/-<br />
11. Following courses have been conducted:-<br />
Ser Name of<br />
Course<br />
Institution<br />
(a) SKT GREF Centre,<br />
Pune<br />
Works Achievement<br />
Vacancy Vacancy<br />
Period<br />
Allotted Utilised<br />
30 28 14-03-2011 TO 02-04-2011<br />
TECHNICAL PLANNING DIRECTORATE<br />
12. Achievement of works up to Mar 2011 is as under:-<br />
Ser<br />
Name<br />
of<br />
work<br />
(a) Fmn<br />
(b) Sur<br />
A/U<br />
Eqvt Cl-<br />
9 Km<br />
Eqvt Cl-<br />
9 Km<br />
Annual Works Plan RE 2010-11 Achievement up to 31 Mar 2011 Re<br />
ma<br />
rks<br />
GS Agency Total GS Agency Total<br />
1408.61 948.96 2357.57 1241.51 675.36 1916.87<br />
2008.35 2417.33 4425.68 1261.65 1310.95 2572.60<br />
(c) Rsur Cl-9 Km 2646.46 71.88 2718.34 2148.38 146.26 2294.64<br />
(d) Pmt<br />
Wrks<br />
Rs in<br />
Lakh<br />
83411.92 132263.25 215675.17 70230.73 103431.79 173662.52<br />
(e) Mjr Pmt<br />
Brg<br />
Mtr 2552.25 2236.02 4788.27 1467.20 1534.69 3056.89<br />
13. SIGNING OF MoU<br />
TECHNICAL ADMINISTRATION DIRECTORATE<br />
(a) MoU between BRO and M/s BPCL for Procurement of Primary Oils and Bitumen<br />
products by BRO Projects for the year 2011-2012 was signed on 31 Mar 2011 by Lt Gen S<br />
Ravi Shankar, VSM, DGBR and Mr. P Anandasundaresan, General Manager (Sales)<br />
I & C, BPCL.<br />
(b) MoU between BRO and M/s HPCL for Procurement of Primary Oils and Bitumen<br />
products by BRO Projects for the year 2011-2012 was signed on 31 Mar 2011 by Lt Gen S<br />
Ravi Shankar, VSM, DGBR and Mr. R S Rao, Executive Director, (Direct Sales), HCPL<br />
14. TPC FOR LUBRICANTS AND GREASES 2011-2012<br />
(a) Contract for procurement of lubs and greases for the year 2011-12 has been concluded<br />
with M/S HPCL for a total qty of approx 937 KL of lubs and greases amounting to Rs 11.53 Cr.<br />
(b) Acceptance Tender Note No 52805/TPC/DGBR/91/E3Q (FOL) dated 31 Mar 2011 has<br />
been issued.
15. Details of ISG/RSG issued during 01 Mar 2011 to 31 Mar 2011<br />
Ser ISG/RSG Veh/eqpt/Plant Date of<br />
Review<br />
(a) RSG Gen set 30 KVA fitted with Ruston<br />
3YDA/4YDA Eng & Kir Alternator SRA-40<br />
16 Mar 2011<br />
16. Supply Order placed for Cat ‘A’ Spares<br />
Ser<br />
(a)<br />
(b)<br />
(c)<br />
(d)<br />
(e)<br />
(f)<br />
(g)<br />
(h)<br />
(j)<br />
(k)<br />
(l)<br />
(m)<br />
(n)<br />
(o)<br />
Supply Order<br />
No. and Date<br />
SO-1223 dated<br />
16 Mar 2011<br />
SO-1224 dated<br />
16 Mar 2011<br />
SO-1225 dated<br />
16 Mar 2011<br />
SO-1226 dated<br />
16 Mar 2011<br />
SO-1227 dated<br />
17 Mar 2011<br />
SO-1228 dated<br />
24 Mar 2011<br />
SO-1229 dated<br />
24 Mar 2011<br />
SO-1230 dated<br />
24 Mar 2011<br />
SO-1231 dated<br />
30 Mar 2011<br />
AT-1232 dated<br />
30 Mar 2011<br />
AT-1233 dated<br />
30 Mar 2011<br />
AT-1234 dated<br />
30 Mar 2011<br />
SO-1235 dated<br />
31 Mar 2011<br />
AT-1236 dated<br />
31 Mar 2011<br />
Items/Eqpts<br />
Amount<br />
(In Rs.)<br />
Sector<br />
JCB Excavator 3DX 3,11,457.00 Both Sector<br />
JCB Excavator 3DX 11,89,024.00 Both Sector<br />
JCB Excavator 3DX 11,25,588.00 Both Sector<br />
JCB Excavator 3DX 15,68,475.00 Both Sector<br />
TATA 207 & 407 34,14,294.00 Both Sector<br />
TAT A Hitachi 16,56,309.00 Both Sector<br />
TAT A Hitachi 10,64,968.00 Both Sector<br />
TAT A Hitachi 6,21,559.00 Both Sector<br />
Stone Crusher Sisco 13,26,432.00 Both Sector<br />
Eng Assy HA-694 &<br />
4R-1040<br />
16,81,875.00 Both Sector<br />
JCB Hyd Excavator 7- 25,15,552.00 Both Sector<br />
8<br />
Escort TVRR HD 85 13,86,074.00 Both Sector<br />
BEML BS 6D 105 & 3,64,15,118.00 Both Sector<br />
BS 6D 125 Eng Spare<br />
Snow Cutter Rolba 1,67,695.00 WSD<br />
User Trials in Progress<br />
17. User trials of following equipments are in progress at various Projects:-<br />
S/No Firm Subject Remarks<br />
(a) M/s BEML Snow Cutter<br />
BS-42<br />
(b)<br />
M/s Dhama Apparel<br />
Innovation Pvt Ltd<br />
Jacket, Scarf<br />
and shoe<br />
Eqpt again desp to (P) Beacon on 16 Feb 2011 for<br />
NCNC trials. Presently engine not bearing load as<br />
intimated vide Bcn FAX No. Q-8093/E4 EME dt<br />
25/3/11.<br />
Final report from (P) Shivalik received, but Final<br />
report from (P) Himank has not yet been received.<br />
Reminder sent on 16/03/11.
S/No Firm Subject Remarks<br />
(c)<br />
M/s Metalite<br />
International Pvt Ltd<br />
Oko puncture<br />
free tyre<br />
Sealant<br />
(d) M/s TVS Motor Ltd TVS Star<br />
Sports & TVS<br />
Apache RTR<br />
Final trial report from (P) Chetak has been recd.<br />
Final trial report from (P) Himank and Shivalik<br />
awaited. Reminder sent on 09 Feb 2011.<br />
Monthly trial report recd from (P) Chetak, Deepak<br />
and (P) Vartak has not yet submitted reminder sent<br />
on 30/3/11.<br />
DESIGN AND SPECIFICATION DIRECTORATE<br />
18. Following Seminars / Workshops were held during the month:-<br />
Ser Name of<br />
Seminar/<br />
Workshop<br />
(a) International<br />
programme for<br />
training cum field<br />
workshop on land<br />
slides<br />
(b) International<br />
seminar on<br />
national road<br />
development<br />
strategies and road<br />
safety on improved<br />
highways<br />
Duration Organised<br />
By<br />
Venue<br />
Officers Attended<br />
03 days NIDM Gangtok a) Brig RAJIV SAWHNEY,<br />
CE (P) Swastik<br />
06 days School of<br />
Planning<br />
and<br />
Architecture<br />
New<br />
Delhi<br />
b) Col Rakshvir, Dir (Wks),<br />
(P) Swastik<br />
c) Shri KP Purushotaman, SE<br />
(Civ) FS, (P) Swastik<br />
d) Shri Manv Prasad, SE (Civ),<br />
(P) Swastik<br />
e) Lt Col MP Singh, (P) Swastik<br />
f) Maj Chetan Kumar, (P)<br />
Swastik<br />
g) Shri Pankaj Sarswat, EE (Civ)<br />
(P) Swastik<br />
h) Shri SK Choubey EE (Civ)<br />
SG, (P) Swastik<br />
j) Shri Ajit Kumar, EE (civ), (P)<br />
Swastik<br />
k) Shri RA Khural, EE (Civ), (P)<br />
Swastik<br />
l) Shri VK Saini, AEE (Civ), (P)<br />
Swastik<br />
m) Shri Rajeev Chandra, AEE<br />
(Civ), (P) Swastik<br />
(n) Shri JP Sahu, AE (Civ), (P)<br />
Swastik<br />
a) Shri SK Doon, SE (Civ) FS,<br />
(P) Vartak<br />
b) Shri KV Nagaraja Kumar, EE<br />
(Civ) SG, (P) Arunank
Ser Name of Seminar/<br />
Workshop<br />
(c) Three days<br />
workshop on<br />
noting & drafting<br />
for section officers/<br />
dealing assistants<br />
(d) Workshop on<br />
“Design<br />
consideration in<br />
road safety”<br />
Duration Organised<br />
By<br />
03 days Institute of<br />
Secretariat<br />
Training &<br />
Managemen<br />
t<br />
01 days Indian road<br />
Congress<br />
Venue<br />
New<br />
Delhi<br />
New<br />
Delhi<br />
Officers Attended<br />
a) Shri Yad Ram Balotia,<br />
Assistants, RTI Cell (Pers Dte)<br />
b) Shri P. Sathiamoorthy,<br />
Assistants, Pers Coord<br />
c) Shri Mukhtiar Singh,<br />
Assistants, TP Dte<br />
a) Shri BB Lal, CE, DDG (D&S),<br />
HQ DGBR.<br />
b) Shri KKY Mahindrakar, VSM,<br />
CE, DDG (WP), HQ DGBR<br />
c) Shri PKH Singh, SE (Civ) FS,<br />
HQ DGBR<br />
(d) Shri DK Purwar, EE (Civ) SG,<br />
B&T Dte, HQ DGBR<br />
BRIDGING AND TUNNELING DTE<br />
19. Major Permanent Bridges: Project wise targets for the year 2010-11 and<br />
achievements up to Mar 2011 are as under:-<br />
Ser Project Target (m) Achvt (m)<br />
(a) Arunank 335.02 198.27<br />
(b) Beacon 335.62 180.55<br />
(c) Chetak 171.35 120.25<br />
(d) Dantak 199.12 52.63<br />
(e) Deepak 172.58 67.63<br />
(f) Himank 142.50 50.24<br />
(g) Hirak 131.84 110.18<br />
(h) Pushpak 158.11 52.37<br />
(j) Rohtang 100.00 77.22<br />
(k) Sampark 584.42 373.51<br />
(l) Setuk 113.26 18.83<br />
(m) Sewak 181.03 152.20<br />
(n) Shivalik 692.63 344.72<br />
(o) Swastik 150.00 164.25<br />
(p) Udayak 900.94 788.30<br />
(q) Vartak 289.05 219.43<br />
(r) Vijayak 130.80 86.31<br />
Total 4788.27 3056.89
PROGRESS OF ROHTANG TUNNEL<br />
20. The physical progress of Rohtang Tunnel works in Mtrs up to 31 Mar 2011 is given<br />
below:-<br />
Scope (m) Progress (m)<br />
8,802.00 685.18<br />
21. Completion of Bridges<br />
31 Nos of major permanent bridges were completed during 2010-11.<br />
WORKS PROJECT DIRECTORATE<br />
22. Following AEs / RAEs have been sanctioned during the month:-<br />
Project<br />
Nos of AEs<br />
sanctioned<br />
Nos of RAEs<br />
sanctioned<br />
Nos of Go-Ahead<br />
Sanctioned<br />
Beacon 24 - -<br />
Sampark 31 - 5<br />
Deepak 4 - -<br />
Shivalik 26 1 -<br />
Himank 8 - -<br />
Vijayak - - -<br />
Chetak 14 2 -<br />
Hirak - - -<br />
Pushpak 7 - -<br />
Dantak 3 2 -<br />
Sewak 5 - -<br />
Udayak 12 - 2<br />
Swastik 5 - 1<br />
Vartak 8 1 1<br />
Arunank 8 - -<br />
Rohtang<br />
1 1 -<br />
Tunnel<br />
Setuk 1 - 1<br />
Total 157 7 10
OBITUARY<br />
23 We regret to inform the death of the following Officers/Pers and CPLs during the month<br />
of Mar 2011 and convey our heart felt sympathies to the bereaved families:-<br />
Ser GO/GS No. Trade Name Unit/TF/Project Date of<br />
death<br />
GREF OFFICERS<br />
(a) GO-3126L AAO PRAFULLA<br />
MECH<br />
GREF PERSONNEL/ARMY PERS<br />
518 SS&TC/48<br />
BRTF/(P) UDK<br />
06.03.2011<br />
(a) GS-166937A Mason NARSINGH PAL 203 PWP/14 TF/VTK 04.03.2011<br />
(b) GS- PNR SMT<br />
WBW/SPK 10.03.2011<br />
188609M<br />
BALWINDER<br />
KAUR<br />
(c) GS-191230N OEM PANKAJ<br />
183 FCP/761<br />
11.03.2011<br />
CHHETRY TF/SVLK<br />
(d) GS-164057L MTD1 GHARU RAM 503 SS & TC/13 15.03.2011<br />
SHARMA TF/SPK<br />
(e) GS- MTD II TK ROY 477 RMPL/755 18.03.2011<br />
163410M<br />
TF/STK<br />
(f) GS-169756A PNR SAMBASIVAN K 1634 PC/25 TF/SWK 19.03.2011<br />
(g) GS-166845N OEM-2 KANHAYA 346 SPL/23 TF/ARK 21.03.2011<br />
PRASAD<br />
(h) GS- OEM-2 ROBI RAM 680 IE(SC)/753 22.03.2011<br />
165847M<br />
BORO<br />
TF/HMK<br />
(j) GS-187622K PNR SURESH KUMAR 1620 PC/753 TF/HMK 22.03.2011<br />
(k) GS-190870L OEM SANJAY KUMAR 332 SPL/753 TF/HMK 22.03.2011<br />
(l) GS-154284X PTR SHIV KUMAR 1071 FW/49 TF/CTK 28.03.2011<br />
(m) GS-154905L LHNT M ISRALE 21 BRTF/SVLK 28.03.2011<br />
(o) GS-173569Y PNR BALESHAR 1642 PC/15 TF/SWK 30.03.2011<br />
BAITHA<br />
(p)<br />
CPL C/No.11302 CPL NOOR ISLAM 60 RCC/19 TF/DTK 06.03.2011<br />
s<br />
(a) C/No298/74 CPL MALIK HANSDA 94 RCC/46 TF/STK 12.03.2011<br />
5<br />
(b) C/No.26567 CPL MURARI KUWAR 402 RMP/36<br />
14.03.2011<br />
TF/SVLK<br />
(c) C/No.7517 CPL BENGIA 85 RCC/756 TF/ARK 17.03.2011<br />
(d) C/No.5126 CPL TADAK PAKWA 128 RCC/23 TF/ARK 19.03.2011<br />
(e) C/No.34327 CPL SHAM BAHADUR 123 RCC/21<br />
TF/SVLK<br />
29.03.2011<br />
* * * * *
DGBR MONTHLY NEWS LETTER<br />
MAR 2011