PROJECT UDAY<br />
(Urban Water Supply and Environmental Improvement in <strong>Madhya</strong> <strong>Pradesh</strong>)<br />
Quarterly Progress Report (QR-07)<br />
June 2007<br />
Urban Administration & Development Department (UADD)<br />
2.1.3 Targeted Disbursement Schedule and Monitoring<br />
A cumulative total expenditure, to 30 th June 2007, amounts to Rs.5,931 lakh, which equates to<br />
5.26% <strong>of</strong> the overall approved fund <strong>of</strong> Rs.112,750 lakh (US$ 275 million). Referring to Figure 2.2,<br />
this shows a shortfall <strong>of</strong> 55.3%, according to the targeted expenditure <strong>of</strong> Rs.13,274 lakhs, which<br />
highlights that the upward trend <strong>of</strong> improved expenditure over the preceding quarter (47.7%<br />
shortfall) has not continued, with comparatively poor returns being made throughout the March to<br />
June 2007 reported period. The shortfall <strong>of</strong> the actual expenditure to that <strong>of</strong> the targeted would be<br />
explained by the following factors:<br />
• awaiting release <strong>of</strong> pending invoices remaining in the pipeline;<br />
• continued slippage in the anticipated start <strong>of</strong> contracts;<br />
• poor competitive bidding process to date giving rise to marked slippage; and<br />
• modification to the overall pattern <strong>of</strong> mobilization and deployment <strong>of</strong> consultant and support<br />
staff.<br />
2.2 Disbursements and Financial Statements<br />
2.2.1 ADB Cumulative Disbursements<br />
A cumulative The cumulative record <strong>of</strong> all previous ADB disbursements, inclusive <strong>of</strong> the reported<br />
quarter April to June 2007 against UWSEIP claims, is according to the financial statement given in<br />
Table 2.4, which gives a total <strong>of</strong> US$ equivalent <strong>of</strong> disbursements <strong>of</strong> US$6.176m to date.<br />
2.2.2 Financial Statements<br />
As per ADB guidelines, a financial statement <strong>of</strong> accounts is given in Appendix-E, for the UWSEIP<br />
MP Urban <strong>Project</strong> separately for the period ending 30 th June 2007, for the following:<br />
• Sources and applications <strong>of</strong> funds, for a closing balance <strong>of</strong> Rs.408.41 lakhs, refer to<br />
Table E-1; and<br />
• Withdrawal <strong>of</strong> loan proceeds totals Rs.250,300,439 and US$461,368, amounting to<br />
US$6.176m equivalent, refer to Table E-2.<br />
File: Qt 07 Jun 2007 Text Rev (00).doc<br />