28.12.2014 Views

Government of Madhya Pradesh - Project Uday

Government of Madhya Pradesh - Project Uday

Government of Madhya Pradesh - Project Uday

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

PROJECT UDAY<br />

(Urban Water Supply and Environmental Improvement in <strong>Madhya</strong> <strong>Pradesh</strong>)<br />

Quarterly Progress Report (QR-07)<br />

June 2007<br />

Urban Administration & Development Department (UADD)<br />

Package no. IND/WS/07 Construction <strong>of</strong> 132 kV/33 kV sub-station & HT Line<br />

Name <strong>of</strong> Contractor: M/s Asiatic Traders, Indore<br />

Cost <strong>of</strong> Contract:<br />

Rs. 2538.85 lakh<br />

Date <strong>of</strong> Award: 16.11.2006<br />

Time <strong>of</strong> completion: 24 months<br />

Works includes:<br />

Construction <strong>of</strong> 132 kv/33kv electric sub-station & HT line<br />

About 75% Design / Drawings approved. Leveling work <strong>of</strong><br />

ground for 132 kv as well as 33 kv sub-stations has almost<br />

been completed.<br />

Package no. IND/WS/10 Design, Construction, commissioning O&M <strong>of</strong> 363 MLD<br />

output capacity water treatment plant near village Bhaklai<br />

Name <strong>of</strong> Contractor: M/s Enviro Control Associates Pvt. Ltd., Surat<br />

Cost <strong>of</strong> Contract:<br />

Rs. 3971.00 lakh<br />

Date <strong>of</strong> Award: 03.02.2007<br />

Time <strong>of</strong> completion: 21 months<br />

Works includes:<br />

Construction <strong>of</strong> 363 MLD WTP along with connected works<br />

Work Plan, General Layout Plan & Process Design<br />

submitted by the contractor firm have been approved by the<br />

PIU/DSC. Excavation work <strong>of</strong> clarifloculors has almost been<br />

completed. Construction <strong>of</strong> <strong>of</strong>fice building is under progress.<br />

Package no. IND/WS/16 Construction <strong>of</strong> Overhead Storage Reservoirs<br />

Name <strong>of</strong> Contractor: M/s Gondwana Engineers Pvt. Ltd., Nagpur<br />

Cost <strong>of</strong> Contract:<br />

Rs. 891.00 lakh<br />

Date <strong>of</strong> Award: 13.11.06<br />

Time <strong>of</strong> completion: 15 months<br />

Works includes:<br />

7 Overhead reservoirs each <strong>of</strong> 3000 KL capacity at the<br />

following locations in the city, Staging:<br />

Sl. no. 1 to 5 - 20 meters<br />

Sl. no. 6 - 15 meters<br />

Sl. no. 7 - 10 meters<br />

1. Sangam Nagar: Staging completed, Beam’s work <strong>of</strong><br />

bottom slab under progress;<br />

2. MIG Colony: Construction up to 18m height <strong>of</strong><br />

columns above ground level has<br />

been completed;<br />

3. Zinsi Hat Maidan: Foundation work in progress;<br />

columns up to ground level bracing<br />

completed.<br />

4. Dravid Nagar: Foundation work completed along<br />

with ground level bracing.<br />

5. Urdu School: Foundation work in progress.<br />

Columns up to ground level bracing<br />

completed.<br />

6. M.Y. Hospital: Foundation work in progress.<br />

Columns up to ground level bracing<br />

completed.<br />

7. Vidur Nagar: Staging completed.<br />

File: Qt 07 Jun 2007 Text Rev (00).doc<br />

23

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!