PROJECT UDAY<br />
(Urban Water Supply and Environmental Improvement in <strong>Madhya</strong> <strong>Pradesh</strong>)<br />
Quarterly Progress Report (QR-07)<br />
June 2007<br />
Urban Administration & Development Department (UADD)<br />
Package no. IND/WS/07 Construction <strong>of</strong> 132 kV/33 kV sub-station & HT Line<br />
Name <strong>of</strong> Contractor: M/s Asiatic Traders, Indore<br />
Cost <strong>of</strong> Contract:<br />
Rs. 2538.85 lakh<br />
Date <strong>of</strong> Award: 16.11.2006<br />
Time <strong>of</strong> completion: 24 months<br />
Works includes:<br />
Construction <strong>of</strong> 132 kv/33kv electric sub-station & HT line<br />
About 75% Design / Drawings approved. Leveling work <strong>of</strong><br />
ground for 132 kv as well as 33 kv sub-stations has almost<br />
been completed.<br />
Package no. IND/WS/10 Design, Construction, commissioning O&M <strong>of</strong> 363 MLD<br />
output capacity water treatment plant near village Bhaklai<br />
Name <strong>of</strong> Contractor: M/s Enviro Control Associates Pvt. Ltd., Surat<br />
Cost <strong>of</strong> Contract:<br />
Rs. 3971.00 lakh<br />
Date <strong>of</strong> Award: 03.02.2007<br />
Time <strong>of</strong> completion: 21 months<br />
Works includes:<br />
Construction <strong>of</strong> 363 MLD WTP along with connected works<br />
Work Plan, General Layout Plan & Process Design<br />
submitted by the contractor firm have been approved by the<br />
PIU/DSC. Excavation work <strong>of</strong> clarifloculors has almost been<br />
completed. Construction <strong>of</strong> <strong>of</strong>fice building is under progress.<br />
Package no. IND/WS/16 Construction <strong>of</strong> Overhead Storage Reservoirs<br />
Name <strong>of</strong> Contractor: M/s Gondwana Engineers Pvt. Ltd., Nagpur<br />
Cost <strong>of</strong> Contract:<br />
Rs. 891.00 lakh<br />
Date <strong>of</strong> Award: 13.11.06<br />
Time <strong>of</strong> completion: 15 months<br />
Works includes:<br />
7 Overhead reservoirs each <strong>of</strong> 3000 KL capacity at the<br />
following locations in the city, Staging:<br />
Sl. no. 1 to 5 - 20 meters<br />
Sl. no. 6 - 15 meters<br />
Sl. no. 7 - 10 meters<br />
1. Sangam Nagar: Staging completed, Beam’s work <strong>of</strong><br />
bottom slab under progress;<br />
2. MIG Colony: Construction up to 18m height <strong>of</strong><br />
columns above ground level has<br />
been completed;<br />
3. Zinsi Hat Maidan: Foundation work in progress;<br />
columns up to ground level bracing<br />
completed.<br />
4. Dravid Nagar: Foundation work completed along<br />
with ground level bracing.<br />
5. Urdu School: Foundation work in progress.<br />
Columns up to ground level bracing<br />
completed.<br />
6. M.Y. Hospital: Foundation work in progress.<br />
Columns up to ground level bracing<br />
completed.<br />
7. Vidur Nagar: Staging completed.<br />
File: Qt 07 Jun 2007 Text Rev (00).doc<br />
23