Capital Project Reconciliation Report - East Aurora Union Free School

Capital Project Reconciliation Report - East Aurora Union Free School

Capital Project Reconciliation Report - East Aurora Union Free School

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

$24 Million <strong>Capital</strong> <strong>Project</strong> Status<br />

and<br />

<strong>Reconciliation</strong> <strong>Report</strong><br />

Board of Education Meeting<br />

Wednesday, October 27, 2010<br />

Paul Blowers, <strong>School</strong> Business Manager


History<br />

<br />

<br />

<br />

<br />

March 10, 2005 – Contract for architectural services<br />

for pre-referendum services<br />

July 12, 2005 – Resolution designating the <strong>School</strong><br />

District as Lead Agency for additions, alterations<br />

and the acquisition of land.<br />

January 10, 2007 – Public Hearing on the proposed<br />

<strong>Capital</strong> <strong>Project</strong><br />

January 30, 2007 – Public vote on the proposed<br />

$24,000,000 <strong>Capital</strong> Improvement <strong>Project</strong>.


Phase I – High <strong>School</strong> and Parkdale<br />

Purpose of Building<br />

<br />

<br />

To consolidate the <strong>East</strong> <strong>Aurora</strong> <strong>Union</strong> <strong>Free</strong> <strong>School</strong><br />

District elementary students in one location by<br />

doubling the amount of available classroom space;<br />

and by updating existing classroom and noninstructional<br />

space. Features include a new<br />

Gymnasium, Media Center and Multi-Media<br />

Common Area.<br />

Improve Baseball and Softball fields and Tennis<br />

Courts; Reconstruct Industrial Arts Area; Renovate<br />

Special Education Rooms and Relocate Buildings<br />

and Grounds Office.


<strong>Project</strong> Cost<br />

Parkdale Total: $13.6 Million<br />

High <strong>School</strong> Total: $2.5 Million


Construction Start<br />

Overall – April 10, 2008<br />

Phase 1A: Addition – April 10, 2008<br />

Phase 1B: Classroom Renovation –<br />

February 23, 2009<br />

Phase 1C: Foodservice Renovation – June<br />

25, 2009<br />

Phase 1D: High <strong>School</strong> Renovation – June<br />

25, 2008


Completion Date<br />

Overall – September 1, 2009<br />

Phase 1A: Addition – February 23, 2009<br />

Phase 1B: Classroom Renovation – June 29,<br />

2009<br />

Phase 1C: Foodservice Renovation –<br />

September 1, 2009<br />

Phase 1D: High <strong>School</strong> Renovation –<br />

September 1, 2008


Percent Occupied<br />

Overall – 100 Percent<br />

Phase 1A: Addition – 100 Percent<br />

Phase 1B: Classroom Renovation – 100<br />

Percent<br />

Phase 1C: Foodservice Renovation – 100<br />

Percent<br />

Phase 1D: High <strong>School</strong> Renovation – 100<br />

Percent


Each phase of this multi-phase project was<br />

completed ahead of schedule and under<br />

budget. This allowed the <strong>School</strong> District to<br />

accelerate their move-in schedule, thus<br />

creating useful swing space for the second<br />

phase of the project. The new facilities have<br />

become a cornerstone of the school district.


Phase II – Main Street<br />

Purpose of Building<br />

To update the majority of the facilities and the<br />

site at the <strong>East</strong> <strong>Aurora</strong> <strong>Union</strong> <strong>Free</strong> <strong>School</strong><br />

District Middle <strong>School</strong>. Highlights included a<br />

complete renovation of the pool with a focus<br />

on safety (new lighting and drainage) and a<br />

complete facelift in four classroom wings.


<strong>Project</strong> Costs<br />

Main Street Middle <strong>School</strong> - $7.9 Million


Construction Start<br />

Overall – March 1, 2009<br />

Phase 2A: Natatorium – March 1, 2009<br />

Phase 2B: 2 nd and 3 rd Floor A Wing,<br />

Cafeteria and Site – June 26, 2009<br />

Phase 2C: 3 rd Floor B and C Wing –<br />

September 1, 2009


Completion Date<br />

Overall – December 28, 2009<br />

Phase 2A: Natatorium – November 1, 2009<br />

Phase 2B: 2 nd and 3 rd Floor A Wing,<br />

Cafeteria and Site – September 1, 2009<br />

Phase 2C: 3 rd Floor B and C Wing –<br />

December 28, 2009


Percent Occupied<br />

Overall – 100 Percent<br />

Phase 2A: Natatorium – 100 Percent<br />

Phase 2B: 2 nd and 3 rd Floor A Wing,<br />

Cafeteria and Site – 100 Percent<br />

Phase 2C: 3 rd Floor B and C Wing – 100<br />

Percent


A large majority of the construction value for<br />

the Phase was put in place over one<br />

summer. The site work, cafeteria and two<br />

classroom wings were completed by the start<br />

of school in 2009. In addition, the<br />

appearance of the Site and Pool were greatly<br />

improved.


Revenues<br />

Total <strong>Project</strong> Revenues<br />

$24,000,000<br />

Revenue Sources:<br />

<strong>Capital</strong> Reserve<br />

EXCEL<br />

Proceeds of Serial Bonds<br />

TOTAL<br />

$2,500,000<br />

652,136<br />

20,847,864<br />

$24,000,000


Total Budget<br />

Expenses and Encumbrances<br />

to Date<br />

Architect<br />

Construction Management<br />

Construction Costs<br />

Land Acquisition<br />

Legal Services<br />

Furniture and Equipment<br />

Utilities<br />

Various Contractual<br />

Total Expenses and Encumbrances<br />

Available Funds as of Oct. 27, 2010<br />

Total <strong>Project</strong> Expenses<br />

Amount<br />

$1,788,400<br />

1,450,000<br />

19,319,800<br />

310,000<br />

84,400<br />

450,400<br />

53,000<br />

389,600<br />

$23,845,000<br />

155,000<br />

$24,000.000<br />

Percent<br />

of<br />

<strong>Project</strong><br />

7.5%<br />

6.0%<br />

80.5%<br />

1.3%<br />

0.4%<br />

1.9%<br />

0.2%<br />

1.6%<br />

99.4%<br />

0.6%<br />

100%


Retainage Held as of October 27, 2010<br />

Contractor<br />

Concept Construction<br />

Pepe Construction<br />

Alpha Masonry<br />

Amount<br />

Held<br />

$32,866<br />

58,275<br />

10,000<br />

Subcontractor Issue –<br />

Department of Labor<br />

Closeout Issue – Late<br />

Paperwork<br />

Closeout Issue<br />

Reason<br />

Total<br />

$101,141


Furniture and Equipment Needs<br />

General Classroom $44,900<br />

Student Desks (225), Student Chairs (275), Kidney Tables (4),<br />

Chairs (28), Multi-configuration table, Chairs (12), White Boards<br />

(10), Rolling room divider<br />

Science Labs $10,800<br />

Interactive White Boards (2), Carts, Microscope Camera,<br />

Stereoscope, Hotplates, Drying Rack, Goggles, Various Lab<br />

Equipment<br />

*Note: All numbers are rounded estimates


Furniture and Equipment Needs<br />

Physical Education $10,300<br />

<br />

Paint Locker Rooms, Pool Divider, Soccer Nets<br />

Technology Room $2500<br />

Air Cleaners (5)<br />

Library $800<br />

Reading Chairs (6)


Furniture and Equipment Needs<br />

Music Department $9,800<br />

Chairs with desk arms (6), stools (25), Instrument<br />

Lockers (3), Mobile storage rack, Percussion<br />

workstation, Music Notation Board, Conductor’s<br />

System<br />

Multi-purpose Room $1,350<br />

<br />

Large Screen, Room Darkening Shades


Furniture and Equipment Needs<br />

Miscellaneous $5,400<br />

<br />

Teacher Desks (4), Teacher Chairs (8), Office Chairs, Divider<br />

Curtains for Nurses Office, 6 person conference table, chairs<br />

(6)<br />

Other <strong>Project</strong>s<br />

<br />

<br />

<br />

<br />

TOTAL: $85,850<br />

(waiting for pricing)<br />

Replace blinds in all classrooms<br />

Remodel ping-pong room<br />

Remove wall to library classroom<br />

Build permanent wall between science and music room


Final Steps<br />

Purchase remaining furniture and equipment<br />

by December, 2010<br />

Complete and submit Final Cost <strong>Report</strong>s by<br />

March, 2011


Questions and Answers