10 APM <strong>Introductory</strong> <strong>Certificate</strong> in <strong>Project</strong> Management – Exam <strong>paper</strong><br />
50. The role of a leader includes:<br />
a. effectively managing risks.<br />
b. selecting the project team.<br />
c. coaching and mentoring project staff.<br />
d. producing accurate project reports.<br />
51. The primary purpose of a gate review is to decide:<br />
a. whether the project manager and team are per<strong>for</strong>ming well.<br />
b. if the project is on schedule and within budget.<br />
c. if stakeholders are satisfied.<br />
d. whether to continue with the project.<br />
52. The primary purpose of the post-project review is to:<br />
a. find out who was responsible <strong>for</strong> problems on the project and why.<br />
b. find out whether the business benefits were achieved and why.<br />
c. find out who per<strong>for</strong>med well on the project in order to support future resource<br />
allocations.<br />
d. identify lessons learned to enable continuous improvement.<br />
53. The project manager’s prime responsibility is to:<br />
a. deliver the benefits.<br />
b. define the requirements.<br />
c. sign off the business case.<br />
d. implement the project plan.<br />
54. Which one of the following best describes the purpose of a project’s business case<br />
a. A statement of what the project will deliver in terms of products/deliverables and<br />
satisfaction.<br />
b. The reasons why the project sponsor wants their project to proceed.<br />
c. A statement on how the project fits into the long-term aims of the project sponsor.<br />
d. Provides justification <strong>for</strong> undertaking the project, in terms of evaluating the benefits, cost<br />
and risks.<br />
55. What is the term given to the senior management team that set the strategic direction <strong>for</strong> a<br />
project<br />
a. <strong>Project</strong> management office.<br />
b. Change control board.<br />
c. <strong>Project</strong> steering group.<br />
d. Programme director.