Summary Progress Report PDF 37 KB - Meetings, agendas, and ...
Summary Progress Report PDF 37 KB - Meetings, agendas, and ...
Summary Progress Report PDF 37 KB - Meetings, agendas, and ...
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
Project W2R<br />
Staffordshire <strong>and</strong> Stoke on Trent Joint Waste Management Board<br />
5 th April 2012<br />
<strong>Summary</strong> <strong>Progress</strong> <strong>Report</strong><br />
<strong>Report</strong> of Contract Managers for W2R<br />
Agenda Item<br />
Project W2R remains on schedule <strong>and</strong> budget <strong>and</strong> has continued to make significant<br />
progress since the last meeting of the Joint Waste Management Board.<br />
At the last meeting, overall ground stabilisation <strong>and</strong> some foundation works had been<br />
completed, the waste bunker pit has been fully excavated <strong>and</strong> the base lined.<br />
Substantial progress has been made on the construction of the waste bunker walls.<br />
Significant above ground works can therefore now be seen on the site. Concreting of<br />
the bunker <strong>and</strong> associated structures has now been completed to 20M above ground<br />
level. This is the highest significant concrete within the structure. The main frame for<br />
the accommodation block has been completed, with “first fix” of some internal works<br />
to be started shortly. Foundation works <strong>and</strong> structures to enable installation of some<br />
of the main internal components have been completed. It is expected that the main<br />
process contractor CNIM will take over the lead in the project in May as the works<br />
move away from civil engineering to process engineering <strong>and</strong> installation.<br />
The principal process sub contractor (CNIM) has made good progress on the<br />
procurement of the plant <strong>and</strong> equipment for the facility <strong>and</strong> orders have been placed<br />
for the majority of major items. Works have started on the fabrication of the main<br />
boiler components <strong>and</strong> other major process items.<br />
Key elements of the Project are:<br />
• Veolia were selected as Contractor for W2R <strong>and</strong> contracts were signed on 29<br />
July 2010<br />
• SCC Planning Permission was granted for the Veolia Application in February<br />
2011. The Judicial Review (JR) Period expired on 18 May with no<br />
applications for JR made.<br />
• Road works to improve the A5/ Vicarage Road Junction were completed on 9<br />
May 2011.<br />
• Site works commenced in June 2011.<br />
• Veolia submitted their Application for an Environmental Permit to the<br />
Environment Agency in June 2011.<br />
• A draft Permit has now been issued by the EA. Veolia have responded with<br />
their comments – there are no major issues.<br />
• The opportunity to develop Combined Heat <strong>and</strong> Power (CHP) at Featherstone<br />
Prison is being actively pursued. Initial discussions are now being held in<br />
regard to supplying CHP to the i54 site.<br />
As a reminder to all Board members the project is described below:<br />
Location<br />
Four Ashes Industrial Estate, South Staffordshire
L<strong>and</strong><br />
4 Hectares of brown field development l<strong>and</strong> acquired by<br />
Staffordshire County Council in December 2007<br />
Planning Planning Approved by SCC 29 April 2009<br />
Planning Permission for Veolia design February 2011<br />
Technology Energy from Waste (EfW)<br />
Size 300,000 tonnes per annum<br />
Waste Residual Waste only after kerbside recycling (55%)<br />
Source Staffordshire 106,132 -141,510 tonnes per year<br />
Warwickshire 29,723 - 39,630 tonnes per year<br />
Walsall<br />
46,687 - 62,250 tonnes per year<br />
S<strong>and</strong>well<br />
42,458 - 56,610 tonnes per year<br />
Total<br />
225 -300,000 tonnes<br />
Commercial 0-75,000 tonnes<br />
Transfer<br />
New Transfer Station to serve Tamworth at Lower House<br />
Farm, Warwickshire<br />
A project timeline is set out below:<br />
Event Date Comment<br />
Provisional Preferred Tenderer announced as<br />
Veolia<br />
June 2010<br />
No challenges to the<br />
procurement process<br />
Veolia appointed June 2010<br />
Contract <strong>and</strong> Financial Close 29 July 2010<br />
Veolia submits new planning application August 2010<br />
Planning Permission determination.<br />
Planning Notice<br />
Judicial Review Challenge Period<br />
3 February 2011<br />
18 February 2011<br />
18 Feb – 18 May<br />
2011<br />
Unanimously passed<br />
No Challenges<br />
received<br />
Preliminary site preparation works February 2011 Completed<br />
SCC completed works on A5 junction 9 May 2011<br />
Start of works on site 14 June 2011<br />
Environmental Permit application made June 2011<br />
Commissioning<br />
Summer/Autumn<br />
2013<br />
Services Commencement December 2013
Initial Expiry Date 31 March 2039<br />
Extension Expiry Date<br />
4 years from the<br />
Initial Expiry Date<br />
Veolia’s Planning Application <strong>and</strong> Consents<br />
Veolia continue to work with the Planning Authority <strong>and</strong> have finalised all outst<strong>and</strong>ing<br />
issues regarding the Planning Permission <strong>and</strong> S106 agreement. Veolia have made<br />
applications for some minor amendments to the building <strong>and</strong> a S73 application to<br />
allow the incorporation of some engineering improvements. These have both been<br />
approved by the Planning Authority. A further S73 application is under discussion<br />
with the Planning Authority regarding the air cooling system.<br />
Veolia have completed <strong>and</strong> submitted an application to the Environment Agency for<br />
an Environmental Permit (EP) for the facility. A draft version of the Permit has now<br />
been issued by the EA for comment by the Contractor. Veolia have reported no major<br />
issues with the draft <strong>and</strong> have responded to the EA accordingly. It is hoped that the<br />
full Permit can be issued in the next few weeks.<br />
Communications<br />
Details of the project can now be found on<br />
http://www.veoliaenvironmentalservices.co.uk/Staffordshire<br />
This now includes some photographs of the construction process to date.<br />
Local residents continue to be provided with information updates on a regular basis<br />
by Veolia. The W2R team will continue to be consulted by Veolia regarding public<br />
communications <strong>and</strong> information.<br />
The Community Liaison Group has now met several times to discuss any matters<br />
that may arise from Veolia’s construction <strong>and</strong> operating activities at the W2R Site.<br />
This group has a number of local County, District <strong>and</strong> Parish Council members, local<br />
residents <strong>and</strong> business representatives. The latest Liaison group was held on 22 nd<br />
March. Chaired by Cllr Cope (South Staffs DC) the representatives were given a site<br />
visit <strong>and</strong> viewed the construction works from the 20m level. It was noted that no<br />
significant issues were raised by the group <strong>and</strong> that no complaints had been received<br />
from local residents.<br />
A special traffic liaison committee has been established to look at traffic calming <strong>and</strong><br />
other issues has now reported <strong>and</strong> a variety of improvements to the local road<br />
network, mainly consisting of speed <strong>and</strong> weight restrictions with some limited road<br />
upgrading is to be implemented. These works will be undertaken during the summer<br />
months 2012. It was reported at the liaison group that local residents were very<br />
pleased with the increased safety <strong>and</strong> speed of use at the A5/VicarageRoad junction.<br />
It was noted that the traffic trough Calf heath was now significantly reduced.<br />
A new information leaflet has been circulated to local resident by Veolia.
The Veolia Environmental Trust will soon be announcing a donation to a local Parish<br />
Council of £5225 for improvement to one of their Jubilee paths.<br />
Over the last 12 months the trust has made the following donations:<br />
Codsall Village Hall - £9026 to improve heating etc<br />
Trinity Methodist Church Codsall - £20,000 improvements to the church<br />
The Washl<strong>and</strong>s in Burton on Trent - £9351 for planting at the washl<strong>and</strong>s<br />
Health <strong>and</strong> Safety<br />
There have now been 163,000 hours of work on the site without a lost time incident.<br />
Along with CNIM Clugston Veolia have made a pledge to make a donation to six<br />
local schools linked to non loss of man hours due to accident. Each time they reach<br />
100,000 man hours on site without accident a school will receive £1000.<br />
The first school – St Pauls CE First School in Coven has already been visited <strong>and</strong> will<br />
be receiving their donation after Easter.<br />
Each school will be shown a presentation about site safety, asked to produce a<br />
poster <strong>and</strong> there will be prizes given to the best. The school will receive a donation<br />
of £1000 (£500 from Veolia £500 from CNIM Clugston) to use for an environmental<br />
project within the school.<br />
The second school is St Mary <strong>and</strong> St Chad CE First School in Brewood. They will be<br />
receiving a visit from Veolia after Easter.<br />
The other schools are:<br />
St Mary’s Catholic Primary School Brewood<br />
Brewood C.E. Middle School Brewood<br />
St Dominic’s High School for Girls Brewood<br />
Havergal CE Primary School Shareshill<br />
Inter Authority Agreement (IAA) <strong>and</strong> Contract Management Board<br />
The Contract Management Board met on 31 January <strong>and</strong> included <strong>and</strong> was held on<br />
site. No significant issues were raised by the Board members. The excellent progress<br />
of the Project to date was noted.<br />
Local Employment<br />
Both Veolia <strong>and</strong> Clugston Construction are committed to using subcontractor <strong>and</strong><br />
direct labour from the local area. Veolia have promised to keep SCC updated on the<br />
appointment of West Midl<strong>and</strong>s based subcontractors to the Project <strong>and</strong> have made a<br />
website available for any contractors wishing to become suppliers:<br />
www.staffsprocurent@veolia.co.uk<br />
Clugston have stated that they are actively trying to recruit local construction labour<br />
in order to reduce their on site costs (Clugston are based in Scunthorpe). The<br />
Construction activities currently employ about 130 staff, most of whom are<br />
subcontract labour, <strong>and</strong> will employ up to 250 workers during the build period. 83% of<br />
the workers <strong>and</strong> subcontractors come from within a 30 radius of the site.
Other Items<br />
The joint procurement with Warwickshire County Council for the Design/ Build of<br />
Lower House Farm Transfer Station <strong>and</strong> Household Waste Recycling Centre has<br />
been completed. A contractor has been appointed <strong>and</strong> the contract has now<br />
commenced. A contractor for its operation <strong>and</strong> waste haulage to W2R (Biffa) has<br />
also been appointed.<br />
A meeting of the Lower House Farm project Board was held on 26 th March. <strong>Progress</strong><br />
was reported as a little behind schedule but this was being caught up in the next few<br />
weeks. Otherwise construction is progressing well at to budget. Some minor planning<br />
amendments have been submitted to WCC planning. It is not anticipated that these<br />
will be problematic.<br />
<strong>Report</strong> Author:<br />
Ian Benson (ian.benson@satffordshire.gov.uk)<br />
Staffordshire County Council<br />
01785 276550