A: <strong>The</strong> bores for the CPS electric lines on the West Frontage Road have been eliminated,<br />

and the electric lines at these locations will be installed by open cut trenching. This<br />

revision is included in <strong>Addendum</strong> No. 3. <strong>The</strong> AT&T bores are to be directional bores, not<br />

conventional bores. HDPE casings are to be used for these bores.<br />

15. Q: Are bore casings for CPS and AT&T to be grouted after conduit installation<br />

A: See answer to question 14 above for CPS bores. Bore casings for AT&T will only<br />

require grouting <strong>of</strong> the casing ends.<br />

16. Q: On the IT and Time Warner duct banks on the utility layout sheets, it appears that<br />

they are going on the same course as AT&T, but there are no pay items for boring.<br />

A: <strong>The</strong> IT and Time Warner ducts are not at the same location as the AT&T duct bank.<br />

No boring is anticipated to install these ducts.<br />

17. Q: Who is furnishing the IT conduit and manholes<br />

A: <strong>The</strong> contractor will furnish all materials for the IT lines.<br />

18: Q: Sheet 2 <strong>of</strong> 2 <strong>of</strong> <strong>Addendum</strong> No. 2 says there is an updated 025 Bid Form, but it was not<br />

included in the addendum. Is there an updated bid form that should have been issued or<br />

will it be issued with <strong>Addendum</strong> No. 3.<br />

A: Form 025 was inadvertently omitted from <strong>Addendum</strong> No. 2. It will be included in<br />

<strong>Addendum</strong> No. 3.<br />

19. Q: <strong>The</strong>re are a couple <strong>of</strong> discrepancies between forms 020 and 025. Form 025 has a total<br />

for SAWS Reclaimed Water but there is not a spot for it on form 020. Form 025 has<br />

subtotals for 2 chilled water alternates, but there is only one spot on form 020 for<br />

chilled water alternate. Can form 020 be updated<br />

A: An updated form 020 will be included in <strong>Addendum</strong> No. 3.<br />

20. Q: <strong>The</strong> SAWS Long Lead Time spec that is included in <strong>Addendum</strong> No. 2 and on sheet 953<br />

<strong>of</strong> the plans requires that submittal data be submitted with the bid. Form 010 does not<br />

list these submittals in the list <strong>of</strong> forms that need to be submitted with the bid. Do these<br />

submittals need to be submitted with the bid, and if so, can you provide additional<br />

clarification on exactly what should be submitted so that we can make sure that all <strong>of</strong><br />

our suppliers are providing the correct information<br />

A: Additional clarification <strong>of</strong> what should be submitted with the bid pertaining to the<br />

SAWS Long Lead Time will be included in <strong>Addendum</strong> No. 3.