Moore’s Example<br />
Start with EDD schedule<br />
Job Time Done Due Tardy<br />
2 2 2 6 0<br />
5 5 7 8 0<br />
3 3 10 9 1<br />
4 4 14 11 3<br />
1 6 20 18 2<br />
Job 3 is first late job.<br />
Job 5 is longest of jobs 2,5,3.<br />
Moore’s Example<br />
Job Time Done Due Tardy<br />
2 2 2 6 0<br />
3 3 5 9 0<br />
4 4 9 11 0<br />
1 6 15 18 0<br />
5 5 20 8 12<br />
Average Flow = 51 / 5 = 10.2<br />
Average tardiness = 12 / 5 = 2.4<br />
Number tardy = 1<br />
Max. Tardy =12<br />