Moore’s Example<br />

Start with EDD schedule<br />

Job Time Done Due Tardy<br />

2 2 2 6 0<br />

5 5 7 8 0<br />

3 3 10 9 1<br />

4 4 14 11 3<br />

1 6 20 18 2<br />

Job 3 is first late job.<br />

Job 5 is longest of jobs 2,5,3.<br />

Moore’s Example<br />

Job Time Done Due Tardy<br />

2 2 2 6 0<br />

3 3 5 9 0<br />

4 4 9 11 0<br />

1 6 15 18 0<br />

5 5 20 8 12<br />

Average Flow = 51 / 5 = 10.2<br />

Average tardiness = 12 / 5 = 2.4<br />

Number tardy = 1<br />

Max. Tardy =12<br />