Capital Projects<br />

Cost<br />

Budget/<br />

Forecast<br />

(millions)<br />

Schedule<br />

Plan/Forecast<br />

Begin Complete<br />

Environmental Environmental<br />

Complete<br />

Design<br />

Complete<br />

Construction<br />

Rail and Station Projects:<br />

Rail-Highway Grade Crossing Safety Enhancement $94.4 Jan-08 Oct-08 Sep-08 Dec-11<br />

Project R $94.4 Jan-08 Oct-08 Sep-08 Dec-11<br />

San Clemente Beach Trail Safety Enhancements $6.0 Sep-10 Jul-11 Apr-12 Jun-13<br />

Project R $6.0 Sep-10 Jul-11 Jun-12 Sep-13<br />

Metrolink Service Expansion Program $134.0 May-07 Apr-08 Mar-09 Jun-12<br />

$134.0 May-07 Apr-08 Mar-09 Sep-12<br />

Anaheim Rapid Connection TBD Jan-09 Oct-14 TBD TBD<br />

Project S TBD Jan-09 Nov-14 May-14 Aug-18<br />

Santa Ana/Garden Grove Fixed Guideway TBD Aug-09 Mar-12 TBD TBD<br />

Project S $252.0 Aug-09 Apr-13 Nov-15 Jul-18<br />

Anaheim Regional Transportation Intermodal Center $227.4 Apr-09 Feb-11 Feb-12 Nov-14<br />

Project R & T $227.4 Apr-09 Feb-12 May-12 Nov-14