19.02.2015 Views

guidelines for designers / builders and heat installers - Bord Gais ...

guidelines for designers / builders and heat installers - Bord Gais ...

guidelines for designers / builders and heat installers - Bord Gais ...

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

gas pipework installations <strong>for</strong> residential properties<br />

<strong>guidelines</strong> <strong>for</strong> <strong>designers</strong> /<br />

<strong>builders</strong> <strong>and</strong> <strong>heat</strong><br />

<strong>installers</strong><br />

2


Contents <strong>and</strong> general<br />

in<strong>for</strong>mation<br />

It is a legal requirement under The Energy<br />

(miscellaneous provisions) Act 2006 that all<br />

“domestic gas works” must be under taken <strong>and</strong><br />

certified by a registered gas installer (RGI) who is<br />

registered with the RGII (Register Gas Installers<br />

of Irel<strong>and</strong>). This guide prepared by <strong>Bord</strong> Gáis is<br />

intended to assist <strong>installers</strong> but is not to be used<br />

as an alternative to the most up to date edition of<br />

I.S.813.<br />

Contents Page 2<br />

The Meter box Page 3<br />

Safety <strong>for</strong> the home<br />

owner<br />

Safety, certificate &<br />

getting connected<br />

Important notice to all <strong>installers</strong> Page 35<br />

Steps to admitting gas to<br />

new home Page 36<br />

Commissioning the installation Page 37<br />

Declaration of Con<strong>for</strong>mance Page 39<br />

The Irish St<strong>and</strong>ards &<br />

Contact Details Page 40<br />

Natural gas pipework<br />

Gas installation pipework Page 4<br />

Pipe materials & sizing Page 5<br />

Jointing of pipes Page 8<br />

Pipework protection Page 9<br />

Pipework from the Meter to<br />

the building<br />

Extended pipework runs Page 11<br />

Installation pipework beneath<br />

footpaths Page 12<br />

Installation pipework beneath<br />

roads & l<strong>and</strong>scaped areas Page 12<br />

Polyethylene pipework Page 13<br />

Pipework within the building<br />

Pipes laid in floors Page 15<br />

Vertical pipe runs Page 18<br />

Dry lined walls Page 19<br />

Timber framed walls Page 20<br />

Internal pipework ducts Page 23<br />

Supports & fixings Page 24<br />

Natural gas <strong>and</strong> electrical<br />

considerations<br />

Gas meters & electrical elements Page 25<br />

Electrical cross bonding Page 26<br />

Appliance connections<br />

Cookers / hobs <strong>and</strong> ovens Page 28<br />

Natural Gas Fires Page 29<br />

Central <strong>heat</strong>ing boilers Page 30<br />

Lamps Page 30<br />

External appliances Page 31<br />

Permitted flue termination<br />

points & ventilation<br />

requirements<br />

Flue termination <strong>guidelines</strong> Page 32<br />

Ventilation requirements Page 33<br />

2


The meter box<br />

Meters<br />

Normally meters are fitted in purpose designed cabinets external<br />

to the building, (<strong>for</strong> further details see Booklet 1 of this guide).<br />

The meter location should be agreed with <strong>Bord</strong> Gáis in advance of<br />

construction commencing.<br />

Only in certain circumstances may meters be fitted inside the<br />

dwelling <strong>and</strong> in such instances care should be taken to ensure<br />

that the location is well ventilated accessible <strong>and</strong> protected from<br />

possible impact.<br />

Please go to pages 35 to 39 <strong>for</strong> details on certification of<br />

installation <strong>and</strong> arranging <strong>for</strong> a Natural Gas connection.<br />

Recessed meter box<br />

Figure 1:<br />

Gas meter box be<strong>for</strong>e <strong>and</strong><br />

after meter being fitted<br />

Figurer 2:<br />

Typical detail of pipe through Cavity Wall<br />

Insulation<br />

Recessed<br />

Meter Box<br />

DPC<br />

Pipe clip<br />

Concrete floor slab<br />

All pipe joints must<br />

be outside the sleeve<br />

Ground Leve<br />

Sleeve<br />

25mm min.<br />

Piping in concrete<br />

must be protected<br />

from corrosion with<br />

wrap or PVC coating<br />

Polystyrene<br />

insulation<br />

Foundation<br />

3


Natural Gas pipework<br />

Gas installation pipework<br />

This section of the <strong>Bord</strong> Gáis Technical Manual Booklet<br />

2 refers to gas installation pipework in a traditional<br />

domestic building. This guide has been prepared to<br />

reflect the requirements of I.S. 813:2002 ‘Domestic<br />

Gas Installations <strong>and</strong> I.S. EN 1775 1998.<br />

For <strong>guidelines</strong> to installing Natural Gas to multioccupancy<br />

dwellings i.e. apartments, please refer to<br />

Booklet 3.<br />

Any person installing natural gas must be a registered<br />

gas installer <strong>and</strong> do so in accordance with I.S. 813<br />

‘Domestic Gas Installations’. This guide prepared by<br />

<strong>Bord</strong> Gáis is intended to assist <strong>installers</strong> but is not to be<br />

used as an alternative to the most up to date edition of<br />

I.S.813.<br />

Where gas pipework may be confused with other<br />

pipework, it must be colour coded bright yellow<br />

(Yellow ochre - 08 C 35), indelibly marked along its<br />

entire length with the word “GAS”/Marking tape.<br />

General<br />

Gas pipework is installed in a dwelling in order to<br />

convey gas in a safe manner from the point where<br />

delivery is made by <strong>Bord</strong> Gáis (usually at the meter)<br />

to connect to the various appliances, which may be<br />

installed inside or outside the dwelling.<br />

In designing <strong>and</strong> installing domestic pipework every<br />

ef<strong>for</strong>t should be made to ensure that it <strong>for</strong>ms a<br />

robust, serviceable element constructed within the<br />

dwelling <strong>and</strong> will continue to be serviceable <strong>and</strong><br />

safe <strong>for</strong> a period not less than the expected life of<br />

other services within the building.<br />

Typical appliances which could be provided <strong>for</strong><br />

when installing pipework, include:<br />

• Central Heating Boiler<br />

• Water Heater<br />

• Cooker/Oven/Hob<br />

• Tumble Dryer<br />

• Barbeque<br />

• Living Flame Fire<br />

• Decorative Lighting<br />

4


Pipe materials<br />

Piping materials should be selected by considering<br />

mechanical strength, appearance, corrosion potential<br />

<strong>and</strong> cost. Copper tubing is normally used <strong>for</strong> residential<br />

gas installation piping. Corrosion protected steel<br />

should be considered in external locations where<br />

impact damage is a risk.<br />

Table 1:<br />

Suitable materials <strong>for</strong> external <strong>and</strong> internal installation pipework<br />

Material<br />

Rigid Copper Tubing<br />

Soft Copper Tubing<br />

C.S.S.T<br />

Mild Steel Pipe (coated)<br />

Polyethylene Pipe<br />

Location<br />

Internal / External<br />

External / Below ground only<br />

Specifications<br />

BS 2871 Table 4 or Equivalent<br />

BS 2871 Table 4 or Equivalent<br />

BS 7838<br />

BS 1387 table 5 or Equivalent<br />

EN 1555<br />

Note Polyethlene Pipe may not be brought within<br />

any dwelling. If brought above ground, polyethylene<br />

pipework must be protected against uv light, impact<br />

<strong>and</strong> sources of <strong>heat</strong>. (See figure 11).<br />

Be Aware !<br />

Polyethylene (PE) pipe has an extremely low<br />

melting point. Take care when soldering near PE<br />

pipe.<br />

Pipe Sizing<br />

Pipework <strong>for</strong> domestic installations should be sized<br />

to meet the maximum combined flow rate <strong>for</strong> all the<br />

appliances installed.<br />

Be Aware !<br />

The maximum pressure loss between the meter<br />

outlet <strong>and</strong> any appliance should not exceed 1<br />

mbar (with all appliances in normal use).<br />

If the maximum consumption of<br />

all appliances is greater than 6m 3 /hr, then a<br />

larger meter than the st<strong>and</strong>ard domestic meter is<br />

required. Please contact <strong>Bord</strong> Gáis.<br />

Remember<br />

• Keep elbows <strong>and</strong> tees to a minimum.<br />

• Each elbow or branch connection is equivalent to<br />

about 0.5m of straight pipe.<br />

• Use machine or spring <strong>for</strong>med bends wherever<br />

possible.<br />

Tables 2 & 3:<br />

Typical appliance consumption <strong>and</strong> conversion factors<br />

Typical appliance Consumptions<br />

Conversion Factors<br />

Domestic Boiler<br />

Cooker<br />

Dryer<br />

Gas Fire<br />

2.00m 3 /hr approx<br />

1.00m 3 /hr approx<br />

0.50m 3 /hr approx<br />

0.75m 3 /hr approx<br />

1.00m 3 Nat. Gas = 11kW approx<br />

1.00m 3 Nat. Gas = 37,500 Btu/hr approx<br />

1kW = 3,412 Btu/hr<br />

5


Table 4:<br />

Pipe sizing <strong>for</strong> copper tubing source: I.S.813: 2002<br />

length<br />

m<br />

Tube Diameter mm - Copper<br />

6 8 10 12 15 22 28<br />

m 3 /h Heat m 3 /h Heat m 3 /h Heat m 3 /h Heat m 3 /h Heat m 3 /h Heat m 3 /h Heat<br />

input input input input input input input<br />

kW kW kW kW kW kW kW<br />

3 0.13 1.5 0.57 6.6 1.11 12.9 1.65 19.1 3.2 37 9.6 111 19.8 230<br />

6 0.07 0.8 0.29 3.3 0.69 8.0 1.10 12.8 2.1 24 6.4 74 13.2 153<br />

9 0.04 0.5 0.19 2.2 0.56 6.5 0.94 10.8 1.7 19 5.1 59 10.3 120<br />

12 0.03 0.4 0.14 1.7 0.52 6.1 0.90 10.5 1.4 17 4.3 50 8.8 102<br />

15 0.03 0.3 0.11 1.3 0.43 5.0 0.76 8.8 1.2 14 3.7 43 7.7 89<br />

20 0.02 0.2 0.08 0.9 0.32 3.8 0.57 6.6 1.0 12 3.2 37 6.5 75<br />

25 0.02 0.2 0.07 0.8 0.26 3.0 0.45 5.2 1.0 12 2.8 32 5.7 66<br />

30 0.01 0.1 0.06 0.6 0.21 2.5 0.37 4.3 1.0 11 2.5 29 5.2 60<br />

40 0.01 0.1 0.03 0.4 0.16 1.9 0.29 3.3 0.7 8 2.1 24 4.3 50<br />

Note: 1mBar = 10 N/m 2 = 0.1kPa<br />

Effective capacity of a copper tube installation with 1.0<br />

mbar difference between the ends <strong>for</strong> a gas of relative<br />

density 0.6 (air = 1)<br />

Table 5:<br />

Pipe sizing <strong>for</strong> mild steel source: I.S.813: 2002<br />

length<br />

m<br />

Tube Diameter mm - Mild Steel<br />

(Natural Gas)<br />

6 8 10 12 15 22 28<br />

m 3 /h Heat m 3 /h Heat m 3 /h Heat m 3 /h Heat m 3 /h Heat m 3 /h Heat m 3 /h Heat<br />

input input input input input input input<br />

kW kW kW kW kW kW kW<br />

3 0.32 3.7 0.88 10.2 2.31 26.8 1.65 19.1 4.7 55 14.3 166 29.7 345<br />

6 0.15 1.8 0.58 6.8 1.54 17.9 1.10 12.8 3.2 37 9.6 112. 20.3 235<br />

9 0.10 1.1 0.54 6.3 1.21 14.0 0.94 10.8 2.5 29 7.9 92 16.2 188<br />

12 0.08 0.9 0.40 4.6 1.02 11.9 0.90 10.5 2.2 26 6.7 78 13.8 160<br />

15 0.06 0.6 0.32 3.7 0.89 10.3 0.76 8.8 1.9 22 5.9 68 12.3 142<br />

20 0.04 0.5 0.24 2.8 0.77 8.9 0.57 6.6 1.7 19 5.0 57 10.6 122<br />

25 0.03 0.4 0.19 2.2 0.76 8.8 0.45 5.2 1.5 18 4.4 51 9.2 106<br />

30 0.03 0.3 0.15 1.8 0.63 7.3 0.37 4.3 1.4 17 3.9 45 8.3 97<br />

40 0.02 0.2 0.12 1.4 0.47 5.5 0.29 3.3 1.3 15 3.3 39 7.0 82<br />

Note: 1mBar = 10 N/m 2 = 0.1kPa<br />

Effective capacity of a steel pipe installation with 1.0<br />

mbar difference between the ends <strong>for</strong> a gas of relative<br />

density 0.6 (air = 1)<br />

6


Table 6:<br />

Pipe sizing <strong>for</strong> polyethylene pipe source: I.S.813: 2002<br />

length<br />

m<br />

Tube Diameter mm - Polyethylene<br />

(Natural Gas)<br />

25 mm 32 mm 63 mm<br />

Heat m 3 /h Heat m 3 /h Heat m 3 /h<br />

input input input<br />

kW kW kW<br />

3 97.1 8.4 189.9 16.4 1144.9 98.7<br />

6 65.0 5.6 127.6 11.0 774.9 66.8<br />

9 51.4 4.4 100.9 8.7 616.0 53.1<br />

12 43.4 3.7 85.5 7.4 523.2 45.1<br />

15 38.0 3.3 75.1 6.5 460.6 39.7<br />

18 34.2 2.9 67.5 5.8 415.1 35.8<br />

21 31.8 2.7 61.7 5.3 380.1 32.8<br />

24 30.6 2.6 57.1 4.9 352.2 30.4<br />

Note: 1mBar = 10 N/m 2 = 0.1kPa<br />

Discharge in a straight horizontal polyethylene pipe<br />

with 1.0 mbar difference between the ends, <strong>for</strong> gas of<br />

relative density 0.6 (air = 1)<br />

Note:<br />

1. The above tables refer to Natural Gas only.<br />

Should an installation be on a temporary<br />

supply from an LPG tank, awaiting<br />

connection of Natural Gas, the above<br />

tables must be adhered to.<br />

2. For further details in relation to pipe sizing,<br />

please consult the CIBSE Guide Section C4<br />

7


Jointing of pipes<br />

Solder Joints<br />

Flux should be used sparingly <strong>and</strong> only applied to the<br />

spigot part of the joint.<br />

The joint should not be over<strong>heat</strong>ed.<br />

Residual flux should be wiped from joints after being<br />

made.<br />

It is known that fluxed, unsoldered joints may satisfy<br />

the soundness test, there<strong>for</strong>e, finished joints should<br />

always be visually examined to confirm that the solder<br />

has run.<br />

When making screwed joints, all threads should be<br />

clean <strong>and</strong> undamaged.<br />

The preferred method of jointing is to use the correct<br />

PTFE tape complying with either. BS 4375 or BS 6974.<br />

Be Aware !<br />

• White lead based paste is not allowed<br />

• Hemp can only be used with paste complying<br />

with BS 6956.<br />

Sources of ignition<br />

When making solder joints extreme care should be<br />

taken when using a blow lamp or power tool in the<br />

vicinity of combustible materials. Adequate protection<br />

must be used when working near timber components<br />

<strong>and</strong> bitumised products <strong>and</strong> polyethylene pipework.<br />

Figure 3:<br />

Correct protection of back-ground material when<br />

coldering copper<br />

Hemp should only be used on threaded joints in<br />

conjunction with thread sealing paste.<br />

If <strong>for</strong> any reason paste is being used then it must<br />

comply with BS 6956.<br />

Liquid detergent should never be used when leak<br />

testing, it can cause rapid corrosion of copper.<br />

Mechanical Joints<br />

The use of union joints, compression fittings or<br />

screwed joints is ONLY acceptable where they will<br />

be readily accessible to allow correct tightening <strong>for</strong><br />

a sound joint. They should not be used in concealed<br />

locations eg. ducts, underfloor, etc.<br />

Copper Tube<br />

Tube ends should be cut square <strong>and</strong> any burrs, internal<br />

or external, removed. Tube lengths should be checked<br />

<strong>and</strong> cleared of any <strong>for</strong>eign matter be<strong>for</strong>e use.<br />

Be Aware !<br />

Breather membrane in the cavity of timber<br />

framed houses or the styrofoam insulation in<br />

the cavity of block / brick dwellings is particularly<br />

vulnerable <strong>and</strong> once ignited can spread quickly<br />

within the cavity. Rectification could involve<br />

complete dismantling of the wall with serious<br />

cost implications <strong>for</strong> the installer.<br />

Screwed Joints<br />

When making screwed joints, all threads should be<br />

clean <strong>and</strong> undamaged.<br />

Hemp should only be used on threaded joints in<br />

conjunction with thread sealing compounds.<br />

When jointing paste is used, it must comply with<br />

B.S. 6956 <strong>and</strong> should only be applied to the external<br />

thread. Excess paste should be wiped away on<br />

completion of the joint. Specially compounded jointing<br />

pastes must be used <strong>for</strong> Natural Gas - white lead based<br />

pastes are not acceptable.<br />

8


Pipework protection<br />

Mechanical<br />

Protection against physical damage <strong>and</strong> corrosion must<br />

be provided where circumstances dictate. Copper tube<br />

should only be considered where mechanical damage<br />

is unlikely or where it will be enclosed in a mechanically<br />

strong protective cover.<br />

Corrosion<br />

Steel pipes run externally or in damp areas will require<br />

protection against corrosion. Copper tube will not<br />

normally require corrosion protection when run<br />

externally. When supporting pipework externally on a<br />

horizontal / vertical surface the support brackets must<br />

ensure that the pipework remains clear of the surface.<br />

Any metallic pipework run underground, embedded<br />

in a solid floor / wall or in any other corrosive location<br />

should be protected against corrosion by one of the<br />

methods shown below.<br />

Fire<br />

Pipework material, jointing methods <strong>and</strong> locations<br />

should be chosen in order to minimise the risk of a fire<br />

in the building causing a pipework failure which might<br />

add to the extent of the fire.<br />

Protective Wrapping<br />

Tape wrapping is normally used at joints or on short<br />

lengths. Any tape wrapping applied should extend at<br />

least 25mm beyond the surface of the material likely<br />

to cause corrosion. All surfaces should be clean <strong>and</strong><br />

dry be<strong>for</strong>e the tape protection is applied. An overlap of<br />

50% is required to provide a layer of double thickness.<br />

Be Aware !<br />

Bends <strong>and</strong> joints on factory coated pipe should<br />

be further protected by wrapping with a suitable<br />

plastic tape.<br />

Figure 4:<br />

Methods of pipe protection<br />

Place the pipe in a non-corrodible sleeve or duct (vent<br />

to ventilated area)<br />

Pipe with a factory bonded coating of PVC<br />

Pipe wrapped with corrosion resistant tape<br />

9


Protection<br />

Sleeves<br />

Pipes passing through external, load bearing <strong>and</strong> cavity<br />

walls should take the shortest route <strong>and</strong> be sleeved<br />

through the cavity.<br />

The purpose of a sleeve is to:<br />

• Prevent access gas entering a vulnerable space<br />

(e.g. cavity wall) in the event leakage.<br />

• To protect the gas installation pipe against<br />

corrosion.<br />

• To protect the gas installation pipe from damage<br />

by normal building movement.<br />

• To accommodate normal expansion <strong>and</strong><br />

contraction of the pipework.<br />

Sleeve Material<br />

Sleeves should be made of a material capable of<br />

containing gas. Suitable materials include polyethylene,<br />

PVC, steel <strong>and</strong> copper. The selection of the sleeve<br />

material should reflect the need <strong>for</strong> mechanical<br />

strength corrosion resistance <strong>and</strong> / or fire retardance<br />

where required.<br />

Size of Sleeve<br />

The sleeve should be of a diameter that provides a<br />

loose fit to the pipe allowing normal pipe expansion /<br />

contraction.<br />

Be Aware !<br />

Pipes / sleeves of dissimilar metal (steel to copper)<br />

should not contact at ANY point.<br />

Sealing of Sleeves<br />

Sleeves should always be sealed to the surrounding<br />

structure with a suitable building material (e.g. mastic,<br />

mortar, etc.).<br />

When gas pipes enter through an outside wall, the gap<br />

between the pipe <strong>and</strong> the sleeve should be sealed to<br />

the pipe at the inner end of the sleeve only with a<br />

flexible, fire resisting compound. (See figure 29, page<br />

26).<br />

Sleeves through internal walls should be sealed to the<br />

pipe at entrance <strong>and</strong> exit. (See detail below).<br />

Be Aware !<br />

Pipework within a sleeve should not be jointed.<br />

Figure 5:<br />

Details of pipe sleeve through cavity wall<br />

Insulation<br />

Grout<br />

Any joint must be<br />

outside the sleeve<br />

Sleeve<br />

10


Pipework from the meter to the building.<br />

Provision of customer isolation valves<br />

on extended pipework runs:<br />

Figure 6:<br />

Locating isolating values<br />

<strong>for</strong> terraced houses<br />

Hse 1<br />

Hse 2<br />

Hse 3<br />

Wall<br />

Hse 4<br />

Meter Box or<br />

Cabinet<br />

Meter Box<br />

Figure 7:<br />

Locating isolating values<br />

<strong>for</strong> duplex units<br />

Upper Duplex Unit<br />

(See page 22)<br />

Ground Floor Unit<br />

Figure 8:<br />

Locating isolating<br />

values in apartments<br />

6 Meter Cabinet<br />

External Riser<br />

Internal Rising Duct<br />

Note:<br />

Regardless of the route<br />

taken by installation<br />

pipework from meter<br />

to each dwelling, the<br />

pipework must be fitted<br />

with a customer isolation<br />

valve as soon as the pipe<br />

enters the dwelling that<br />

it is supplying.<br />

Meter<br />

Manifold<br />

Meter<br />

Manifold<br />

Ground Level<br />

See booklet 3<br />

pages 17 <strong>and</strong> 18.<br />

Naturally Ventilated Basement<br />

11


Installation pipework from the meter<br />

Pipework should be protected against<br />

corrosion preferably by using pipes with<br />

a factory applied PVC coating. Where<br />

copper pipes are run externally exposed<br />

to the elements but supported clear of<br />

other surfaces, corrosion protection is not<br />

normally necessary. Consult page 9 <strong>for</strong><br />

further considerations.<br />

Pipework should not be installed under<br />

the foundations of a building nor in the<br />

ground under the base of a wall footing<br />

or foundation.<br />

Be Aware !<br />

All underground pipework should be pressure tested be<strong>for</strong>e<br />

initial wrapping or covering takes place.<br />

Installation pipework under concrete paths, (pedestrian traffic only),<br />

should have:<br />

• Minimum cover of 25mm between sleeve / wrapping <strong>and</strong><br />

concrete finish, (see figure 9 below).<br />

• Pipework must be placed in sleeve or have protective wrapping.<br />

Figure 9:<br />

Meter on adjacent wall<br />

(pipework beneath footpath)<br />

Meter Box<br />

Protective cover<br />

25mm<br />

cover min.<br />

Footpath<br />

Buried pipework in open soil, lawns, or under gravel paths, areas<br />

which can be accessed by vehicle should have:<br />

• Minimum trench depth of 375mm.<br />

• Minimum s<strong>and</strong> or fine fill surround required in trench of<br />

150mm.<br />

• When area can be accessed by vehicle (under tarmac,<br />

cobblestone, etc.), the pipework must also have a protective<br />

sleeve, (see figure 10 above).<br />

Figure 10:<br />

Meter on adjacent wall<br />

(pipework beneath soft<br />

ground or vehicular traffic)<br />

Meter Box<br />

375 mm<br />

min. cover<br />

Protective<br />

sleeve<br />

12


Polyethylene pipework<br />

Polyethylene (PE) Gas installation piping -<br />

Underground<br />

PE piping can be used <strong>for</strong> underground supply of gas<br />

to a premises <strong>and</strong> is a convenient alternative to metallic<br />

pipes when used externally.<br />

External buried PE pipework shall be constructed as<br />

follows:<br />

• Mechanical fittings in accordance with I.S. 265<br />

can be used on buried PE pipework.<br />

• Any metallic joints must be wrapped with a<br />

minimum of two layers.<br />

• PE pipework must be tested to ensure it is gas<br />

tight be<strong>for</strong>e being covered.<br />

• Pipework in soil should be bedded in s<strong>and</strong> or fine<br />

filling to a depth of 150mm above <strong>and</strong> below the<br />

pipe. The minimum depth of cover of the pipe<br />

required is 375mm.<br />

Any installer engaging in<br />

• Welding<br />

• Electrofusion<br />

• Pipework insertion by mole or horizontal drilling<br />

in compliance with I.S. 265 should be suitably trained<br />

<strong>and</strong> certified (GDF1 or equivalent).<br />

Be Aware !<br />

PE pipework should not be laid above 375mm<br />

dept of cover regardless of cover material.<br />

• Pipework, which may be subject to vehicular<br />

loading eg. under cobble lock driveway, should<br />

be, in addition to the minimum depth of cover<br />

of 375mm, enclosed in a protective sleeve.<br />

Be Aware !<br />

• Polyethylene pipe is not allowed within a<br />

building.<br />

For correct method of entry into building above<br />

ground level, see figure 11 below.<br />

For correct method of entry into building below<br />

ground level, see figure 12 over-leaf.<br />

Figure 11:<br />

Polyethylene-metal transition<br />

(supply entering building<br />

above ground level)<br />

GRP cover<br />

fixed to wall<br />

Above ground<br />

fitting<br />

Capillary<br />

soldered elbow<br />

Suitably sized<br />

copper pipe<br />

GRP sleeve<br />

GRP sleeve bend<br />

GRP sleeve<br />

bend<br />

Note:<br />

PE from<br />

meter<br />

Both GRP sleeve <strong>and</strong> GRP cover<br />

must be used on this section.<br />

13


Figure 12:<br />

Polyethylene-Metal transition (supply<br />

entering building below ground)<br />

External Leaf<br />

375mm minimum<br />

dept of cover<br />

PVC coated copper<br />

Anti-shear sleeve<br />

300mm min.<br />

PE<br />

from<br />

meter<br />

PE pipe<br />

Polyethylene / Metal<br />

transition fitting (Two<br />

layers of protective<br />

wrapping required)<br />

Figure 13:<br />

Below-ground transition fitting with anti-shear sleeve<br />

Below-Ground transition<br />

fitting<br />

Below-Ground transition fitting with<br />

Anti-shear sleeve.<br />

Note:<br />

The polyethylene-metal transition must be suitable<br />

<strong>for</strong> below ground applications, always consult the<br />

supplier.<br />

The anti-shear sleeve must be fitted at all times<br />

when placing transition beneath the ground.<br />

14


Pipes laid in floors<br />

Where the piping is to be laid on a solid floor slab, the<br />

finished floor screed must allow 25mm minimum cover<br />

over the installed pipe.<br />

Figure 14:<br />

Pipe run on solid floor slab<br />

Floor covering<br />

Screed<br />

25 mm<br />

minimum<br />

Solid or screeded floors<br />

Pipework laid in solid floors should be:<br />

• Tested <strong>for</strong> soundness be<strong>for</strong>e any<br />

protective coating or cover is applied.<br />

• Protected against corrosion e.g. factory bonded<br />

PVC. see fig 15<br />

• Adequately embedded by at least 25mm below<br />

the final floor finish.<br />

• Sleeved <strong>and</strong> taken the shortest practicable route<br />

when passing vertically through a solid floor. see<br />

fig 16.<br />

Floor slab<br />

Figure 15:<br />

Pipe with factory bonded PVC<br />

Be Aware !<br />

Compression fittings, screwed joints shall<br />

not be used on internal buried metallic<br />

pipework.<br />

All joints should be kept to a minimum<br />

Figure 16:<br />

Sleeving pipework vertically<br />

through floors<br />

Fire resistant<br />

mastic<br />

Sleeve<br />

Fire resistant<br />

mastic<br />

15


Pipes laid in floors<br />

Suspended floors<br />

Prior to running pipework below suspended<br />

floors, a visual inspection should be carried<br />

out to note the position of any electrical<br />

cables, junction boxes <strong>and</strong> ancillary<br />

equipment, in order to safely route the gas<br />

pipes.<br />

Figure 17:<br />

Compression fittings.<br />

Be Aware !<br />

Compression fittings can not be used when pipes are<br />

placed beneath / within floors or in inaccessible positions.<br />

Where pipes are installed between joists, they<br />

should be correctly supported in accordance<br />

with the following table:<br />

Table 7:<br />

Support distances <strong>for</strong> horizontal runs of<br />

pipe in suspended floors.<br />

Material Normal size (mm) Interval Horisontal Run (m)<br />

Copper Up to 15 1.2<br />

22 1.8<br />

28 1.8<br />

Mild Steel Up to 15 2<br />

20 2.5<br />

25 2.5<br />

Where pipes are laid across joists fitted with floor<br />

boards or flooring grade chipboard, the pipe should<br />

be located in purpose made notches or circular holes<br />

drilled through the joists.<br />

Figure 18:<br />

Notching or providing holes in joists<br />

Max. D/7<br />

Min. S/14<br />

Max. S/4<br />

Timber Joist<br />

Depth (D)<br />

Span (S)<br />

Support wall<br />

Support wall<br />

Max. Diameter d = D/4<br />

Min. S/14<br />

Max S/4<br />

Depth (D)<br />

C L C<br />

Support<br />

wall<br />

Min. distance between hole centres - 3d<br />

Span (S)<br />

Support wall<br />

16


Pipes laid in floors<br />

Timber floors<br />

Notches should not be made in joists of less than<br />

100mm depth. The depth of any notch should be<br />

sufficient to accommodate fully the pipe or fittings, but<br />

should not exceed 15% (approximately one seventh)<br />

of the joist depth. The notch should be located not<br />

further than one quarter of the span from an end<br />

support; it should be U-shaped when possible <strong>and</strong><br />

no wider than necessary to accommodate the pipes.<br />

Notches should not extend across the joint between<br />

the floor boards.<br />

Be Aware !<br />

Care should be taken when re-fixing floor boards<br />

to prevent damage to the pipes by nails or<br />

screws.<br />

Location of under floor pipes should be marked on<br />

floor boards using pencil / marker or rotary stamp.<br />

Figure 19:<br />

Marking areas where pipes are laid<br />

Laying pipes<br />

Care should be taken to prevent the ingress of dirt <strong>and</strong><br />

water etc. into the pipes. The bore should be examined<br />

be<strong>for</strong>e installation <strong>and</strong> the open ends temporarily<br />

sealed or plugged prior to running the pipes through<br />

dirty areas, <strong>for</strong> example, below floor boards, (see detail<br />

below)<br />

Figure 20:<br />

Preventing the ingress of dirt / water within feeding<br />

pipework though concealed spaces<br />

17


Vertical pipe runs<br />

Particular care is required to ensure that pipes hidden<br />

in walls do not become a risk due to accidental<br />

damage or structural damage due to building<br />

settlement. The ingress of gas into voids or cavities<br />

must be avoided.<br />

Protection<br />

Where pipework is to be chased into a solid wall, it is<br />

of particular importance that high quality corrosion<br />

protection is applied, preferably factory bonded PVC.<br />

This is to ensure that high levels of moisture within the<br />

wall do not have any detrimental corrosive effect on<br />

the pipework.<br />

Vertical Pipe Runs (Only)<br />

It is not acceptable <strong>for</strong> pipework to be run horizontally<br />

or at any angle other than vertically in a wall chase.<br />

Figure 21:<br />

Permitted direction of wall chase (vertical only)<br />

Pipes in solid walls<br />

Vertical pipes should be placed in ducts on the wall<br />

surface with convenient access. If this is not practical,<br />

the pipework may be chased into the wall provided<br />

that the depth of the chase does not exceed one third<br />

of the depth of the block or brick. In this situation, the<br />

pipe should be protected against corrosion.<br />

Be Aware !<br />

Such chasing is unlikely to be achieved in walls<br />

constructed of ‘hollow’ blocks.<br />

18


Gas pipework behind Dry lined walls<br />

The installation pipework within dry lined walls should<br />

be run within purpose designed channels providing<br />

adequate protection, ie. metal protection where<br />

required.<br />

Where it is not possible to do this, then it is acceptable<br />

to run the pipe on the wall surface behind the dry<br />

lining provided that the pipe is:<br />

Be Aware !<br />

Compression/mechanical fittings can not be<br />

used when pipes are placed behind plasterboard<br />

or in inaccessible positions.<br />

• Securely fixed <strong>and</strong> supported.<br />

• Joints are kept to an absolute minimum.<br />

• The pipe is protected against corrosion.<br />

• The pipe is protected against mechanical damage,<br />

(see details below).<br />

Figure 22:<br />

Details of pipework behind dry lining<br />

PVC Coated Copper<br />

Protective 18 swg steel cover<br />

Pipe in wall behind dry lining<br />

PVC Coated Copper<br />

Protective 18 swg steel cover<br />

Pipe in channel behind dry lining<br />

19


Timber framed walls<br />

The following issues need to be addressed when<br />

considering running gas pipework within the walls of<br />

timber framed construction:<br />

• Possible interference with or weakening of<br />

structure members of the house frame.<br />

• Possibility of inadvertent damage to pipework<br />

when using plasterboard or other fixings to the<br />

inner timber leaf.<br />

• Possibility, in the event of a gas escape that:<br />

• a dangerous accumulation could occur or<br />

• the gas might migrate into the<br />

outer cavity, be<strong>for</strong>e the escaping gas is<br />

smelled by the occupant.<br />

• Possibility that natural movement of the structure<br />

could damage the pipe.<br />

One of the following options, chosen at design stage,<br />

can be used to ensure the avoidance of the possibilities<br />

listed above.<br />

Option 1<br />

Run pipework (* rigid or flexible) in floor slab <strong>and</strong> exit<br />

from the floor to the appliance in front of the finished<br />

plasterboard face of the wall - see figure 23 below.<br />

Be Aware !<br />

*Compression joints are not permitted in slab.<br />

Option 1A<br />

Run pipework as above but exit from the floor into a<br />

separately constructed channel to exit at the appliance.<br />

This channel must not allow gas to move into the<br />

timber frame or cavity. Termination must be in front of<br />

the finished plasterboard face of the wall.<br />

Option 2<br />

All pipework to be run on exposed internal wall<br />

surface or in plastic ducting on wall surface or within<br />

cupboards.<br />

Figure 23:<br />

Appliance connection in front of timber leaf<br />

Plasterboard<br />

Recessed Gas Meter Box<br />

Concrete floor slab<br />

External<br />

Brick / Block Leaf<br />

25mm min.<br />

Piping in concrete<br />

protected from<br />

corrosion with wrap<br />

or PVC coating<br />

Sleeve<br />

Ground level<br />

Polystyrene insulation<br />

Copper joint must be<br />

outside sleeve<br />

20


Timber Framed Walls<br />

Option 3<br />

Run pipework in timber frame walls using continuous<br />

plastic coated soft copper or stainless steel - see<br />

figure 24. If copper is used, a protective metal cover<br />

must be placed in front of the pipework.<br />

Timber framed construction of the inner wall requires<br />

particular consideration when it is proposed to run<br />

gas installation pipework within it. This should only<br />

be considered as a last resort, prefered options are<br />

described on the previous page.<br />

Where there is no other option, gas installation<br />

pipework may be laid within the timber frame<br />

construction provided the following is adhered to:<br />

• Any gas pipe run should be kept to a minimum<br />

<strong>and</strong> run vertically within purpose designed<br />

channels.<br />

• Channels should be fitted with insulation <strong>and</strong><br />

covered with the vapour barrier <strong>and</strong> plasterboard<br />

to the same st<strong>and</strong>ard as the rest of the wall.<br />

• Gas pipes should be adequately supported on the<br />

studs.<br />

• Pipe joints should be kept to an absolute<br />

minimum.<br />

• Compression fittings must not be used.<br />

• Studs should not be notched. Holes in studs<br />

<strong>and</strong> holes <strong>and</strong> notches in horizontal timber /<br />

membranes should be kept as small as possible.<br />

• Pipes should be coated copper or steel to avoid<br />

corrosion.<br />

• Where copper pipes are used, they should be<br />

enclosed within a 18 swg steel sheet or equivalent<br />

metal plate. (See figure 24). Alternatively,<br />

mild steel pipes may be used without further<br />

mechanical protection. But full corrosion<br />

protection is required.<br />

• Provision should be made <strong>for</strong> the pipe to<br />

accommodate any normal movement of the<br />

building.<br />

• Where the gas supply point is to be positioned on<br />

a separating (party) wall, the pipe should rise in<br />

front of the finished plasterboard face.<br />

Be Aware !<br />

• Pipes must not be laid within separating<br />

(party) walls dividing individual dwellings.<br />

21


Figure 24:<br />

Full storey height riser in timber framed walls<br />

Full storey height riser<br />

Continuous PVC<br />

Coated Copper<br />

No mechanical<br />

fittings permitted<br />

100 mm<br />

Metal cover<br />

A<br />

A<br />

Section A-A<br />

Figure 25:<br />

Appliance connection point to the front of timber<br />

framed walls<br />

Appliance connection-point riser<br />

PVC Coated<br />

Copper<br />

Appliance<br />

connection point<br />

Additional noggins<br />

required <strong>for</strong> support<br />

100 mm<br />

A<br />

A<br />

22


Internal pipework ducts<br />

For Apartment Installation Guidelines:<br />

Please consult Booklet 3<br />

For installation of Gas within Duplex<br />

units:<br />

Please use external risers as per page 11 of<br />

Booklet 3. If an external riser can not be<br />

facilitated, it is recommended that an internal<br />

“filled” duct is used (as per page 16, Booklet 3).<br />

Figure 26:<br />

Internal ventilated duct<br />

Internal<br />

ventilated<br />

duct<br />

PVC coated copper<br />

or steel pipework<br />

Fire resistant<br />

material<br />

Gas pipes should not be fitted in lift shafts or protected<br />

shafts or in any space where gas could migrate in<br />

openings to those shafts.<br />

Building services shafts containing compressed air,<br />

steam or air conditioning ducts should not be used as<br />

a route <strong>for</strong> gas pipes.<br />

For further details on the interaction of natural gas<br />

pipework <strong>and</strong> other services, please consult Booklet 3<br />

of this guide, page 20.<br />

Vertical or horizontal purpose-laid ducts, containing<br />

pipework, should be ventilated at the top <strong>and</strong> bottom<br />

with an open grille (see fig 26). These vents to the duct<br />

must have a free area of 5,000mm2 or 1/500th the<br />

cross sectional area of the duct, which ever is greater.<br />

The purpose of the vents is to ensure that any escape<br />

of gas can transmit to a non-hazardous area <strong>and</strong> be<br />

detected by smell.<br />

23


Pipe Supports <strong>and</strong> fixings<br />

Figure 27:<br />

Support of pipework to prevent corrosion caused by<br />

contact with aggressive surfaces<br />

All pipework should be adequately supported to<br />

prevent the pipework from coming into contact<br />

with surfaces that are likely to cause corrosion (e.g.<br />

concrete, masonry, plaster). Supports made from<br />

plastic are generally acceptable.<br />

Be Aware !<br />

Ferrous materials e.g. screws <strong>and</strong> support brackets<br />

shall not be in contact with copper piping.<br />

Table 8:<br />

Supporting pipework (Horizontally <strong>and</strong> vertically)<br />

Pipe Support Distance<br />

Material Normal size Interval <strong>for</strong> vertical run Interval <strong>for</strong> horizontal run<br />

(mm) (m) (m)<br />

Copper Up to 15 2.0 1.2<br />

22 2.5 1.8<br />

28 2.5 1.8<br />

35 3.0 2.5<br />

42 3.0 2.5<br />

54 3.0 2.7<br />

Mild steel Up to 15 2.5 2.0<br />

20 3.0 2.5<br />

25 3.0 2.5<br />

32 3.0 2.7<br />

40 3.5 3.0<br />

50 3.5 3.0<br />

24


Gas meters <strong>and</strong> electrical elements.<br />

Pipework should not be installed closer than 150mm to<br />

an electricity meter. When this is not possible, a nonconductive<br />

shield should be placed between the pipe<br />

<strong>and</strong> the electrical equipment providing the required<br />

separation distance.<br />

Gas meters shall not be located above or below nor<br />

closer than 400mm to an electrical distribution board.<br />

Pipework should be installed at least 25mm away from<br />

the electricity supply, distribution cables. Otherwise<br />

an appropriate electrical insulation material should<br />

be wrapped around the pipe to prevent arcing. Gas<br />

pipework should always be separated by a minimum of<br />

10mm from other metal piped services.<br />

Note:<br />

Subject to approval from electricity supplier.<br />

Figure 28:<br />

Installation in relation to electrical meters etc.<br />

Electricity meter<br />

150mm Min.<br />

Non-conductive partition<br />

150mm<br />

min.<br />

Electricity meter<br />

25


Electrical cross bonding of supply<br />

pipework<br />

For meters installed in external meter boxes, the<br />

bonding connection should be as near as practicable<br />

to the point of entry. Bonding wires should not be<br />

connected in the meter box.<br />

Figure 29:<br />

External Meter (Cross bonding)<br />

Bond<br />

Connection to<br />

earth must be<br />

outside meter<br />

box<br />

Pipework<br />

from meter<br />

Temperature<br />

resistant mastic<br />

Grout<br />

Figure 30:<br />

Internal Meter (Cross bonding)<br />

500 mm<br />

Max<br />

Bonding<br />

Connection<br />

In the case where the meters are installed inside the<br />

building, the bond should be located within 500mm of<br />

the meter outlet pipe.<br />

26


Electrical Cross Bonding at boiler<br />

The current edition of I.S.813: 2002 refers to some<br />

requirements, which can be found in current editions<br />

of the E.T.C.I. wiring regulations including the necessity<br />

to cross bond all ‘extraneous metal work including gas<br />

supply, water <strong>and</strong> central <strong>heat</strong>ing pipes’.<br />

Figure 31:<br />

Cross bonding<br />

arrangement near<br />

boiler<br />

Wall Mounted<br />

Gas Boiler<br />

Gas Supply C.W. H.W.<br />

Be Aware !<br />

Installers on sites should check with the<br />

building contractor that the electrician is<br />

completing all bonding work <strong>and</strong> the existence<br />

of an electrical completion certificate must<br />

be confirmed by the installer be<strong>for</strong>e issuing<br />

a Declaration of Con<strong>for</strong>mance <strong>for</strong> the gas<br />

installation (see pg 39). If the contractor on<br />

site does not confirm this, then a copy of the<br />

notice (shown below) should be affixed to the<br />

boiler be<strong>for</strong>e issue of a con<strong>for</strong>mity declaration to<br />

I.S.813: 2002.<br />

Example of Safety Notice<br />

Electrical safety - equipotential (cross) Bonding<br />

Some types of electrical installations are fitted with<br />

equipotenial bonding, which is the connection of<br />

the internal gas <strong>and</strong> water pipes to the electrical<br />

installation’s earth terminal. In particular those<br />

installations with Protective Multiple Earthing<br />

(P.M.E) should, <strong>for</strong> safety reasons, be fitted with<br />

equipotential bonding.<br />

*For in<strong>for</strong>mation contact your Electricity Supplier<br />

In the Gas Safety Installation St<strong>and</strong>ard I.S.813: 2002<br />

there is the safety in<strong>for</strong>mation that any person who<br />

carries out installation pipe work should in<strong>for</strong>m the<br />

user that electrical bonding must be checked (& if<br />

necessary rectified) by a competent person*, in any<br />

dwelling where electrical equipotential bonding may<br />

be necessary.<br />

Be Aware !<br />

Risk of Electrical shock if Working on<br />

Existing Pipework<br />

A temporary continuity bond must be used when<br />

carrying out any work on the pipework or fittings<br />

which will break electrical continuity through them.<br />

27


Appliance Connections<br />

It is necessary to provide an appliance valve within 1<br />

metre of each appliance supplied. Depending on the<br />

appliance the preferred valving methods are shown<br />

below.<br />

Be Aware !<br />

Plug type valves (gas cocks) are not permitted.<br />

Cookers<br />

Figure 32:<br />

Cooker flexible pipe connected to self-closing<br />

bayonet valve.<br />

Yellow indicates<br />

suitability <strong>for</strong><br />

Nat. Gas<br />

Hobs <strong>and</strong> ovens<br />

Figure 33:<br />

A valve may be fitted in adjacent cupboards to the left or<br />

right of the oven / hob.<br />

28


Fires<br />

Figure 34:<br />

Valve near <strong>builders</strong> opening<br />

Recessed valve located in chimney breast<br />

When installed, turn on <strong>and</strong> refit cover<br />

disk <strong>and</strong> plate<br />

Figure 35:<br />

Recessed valve - detail<br />

Ball valve with casing<br />

flush to wall surface<br />

8mm wrapped<br />

copper - 1m<br />

max. run<br />

10mm wrapped<br />

copper - 3m max. run<br />

Flush fitting ball valve <strong>for</strong> concealed gas installations<br />

All pipework to be<br />

PVC coated copper<br />

Be Aware !<br />

If not fitting the<br />

fire as st<strong>and</strong>ard:<br />

1. Do not connect<br />

or leave live gas<br />

pipework to the<br />

<strong>builders</strong> opening.<br />

or<br />

2. Turn off micropoint<br />

<strong>and</strong> cap off<br />

the downstream<br />

side of the valve.<br />

29


Central <strong>heat</strong>ing boilers <strong>and</strong> water<br />

<strong>heat</strong>ers<br />

Positioning the boiler<br />

A room sealed boiler, may be located within any room<br />

of the dwelling. If located in bathroom / shower, in<br />

an enclosed compartment or understairs, additional<br />

requirements must be adhered to. (I.S.813: 2002).<br />

Additional requirements are needed if placing a boiler<br />

beneath stairs.<br />

Be Aware !<br />

Open flue boilers are permitted in a small<br />

number of locations.<br />

See I.S.813: 2002.<br />

Lamps<br />

Figure 37:<br />

Location <strong>for</strong> valve <strong>for</strong> street lamp / garden lamp<br />

Figure 36:<br />

Boiler Valve<br />

These appliances<br />

are normally<br />

fitted with valve<br />

when supplied.<br />

Wall Mounted<br />

Gas Boiler<br />

Gas valve on supply to boiler<br />

30


External pipework<br />

External Appliances<br />

Where appliances such as barbecues, patio <strong>heat</strong>ers,<br />

<strong>and</strong> gas lights etc. are installed remote from the<br />

dwelling <strong>and</strong> the pipes are run underground,<br />

consideration should be given to installing an<br />

additional isolation valve on the supply pipe at<br />

an accessible position either internally or externally as<br />

close as possible to where the pipe exits the dwelling.<br />

The valve should be labelled showing “GAS OFF”<br />

position.<br />

Please consult figure 38 below <strong>and</strong> page 12 <strong>for</strong> pipe<br />

run requirements.<br />

Figure 38:<br />

External pipework detail<br />

House wall<br />

Barbecue<br />

Outside<br />

gas valve<br />

375 mm min.<br />

depth below grass<br />

<strong>and</strong> driveway<br />

Plastic wrapped soft<br />

copper tube<br />

150 mm s<strong>and</strong>/fine fill<br />

40 mm min. depth<br />

under concrete slabs<br />

25 mm min. depth<br />

buried in concrete<br />

Figures 39 / 40:<br />

Isolation valve <strong>and</strong> Barbecue point detail<br />

Isolation Valve<br />

Demountable connection (flexible) with integral valve.<br />

31


Permitted Flue terminal locations<br />

Flue termination<br />

<strong>guidelines</strong><br />

Irish st<strong>and</strong>ards always<br />

take precedence over<br />

manufacturers instructions,<br />

unless manufacturers<br />

instructions call <strong>for</strong><br />

additional or more strict<br />

requirements.<br />

Guttering<br />

Figure 41:<br />

Permitted locations<br />

<strong>for</strong> flue terminations<br />

Car ports shall have two<br />

open unobstructed sides<br />

All dimensions in mm<br />

Typical width 100 / 125 mm.<br />

Boiler flue<br />

termination<br />

32<br />

Sample power<br />

Flue termination


Ventilation requirements <strong>for</strong><br />

appliances<br />

All appliances require combustion air.<br />

Room-sealed appliances are provided with an air<br />

supply from outside air through a sealed pipe to the<br />

appliance, with products of combustion expelled<br />

through the flue. This, more often than not, is provided<br />

by a concentric flue arrangement.<br />

Figure 42:<br />

Recommended venting detail<br />

Be Aware !<br />

Vents must not be adjustable or capable of being<br />

closed.<br />

Be Aware !<br />

The amount of free area from the airbrick<br />

<strong>and</strong> airspace grill should be sought from<br />

manufacturer be<strong>for</strong>e fitting.<br />

Airbrick<br />

Airspace grill<br />

Sizing of vents<br />

When sizing vents the critical dimension is the amount<br />

of free area required. Physical dimensions of a vent<br />

are not of concern, but the amount of free area that<br />

is available so that air may pass through it is critical.<br />

(Note table on page 34, specific requirements <strong>for</strong> one<br />

of each type of appliance within a room).<br />

If an extraction fan, or cooker hood with an extractor<br />

fan, is fitted in the room containing an open appliance,<br />

or in a connected space to this room, the size of the<br />

vent required should be increased by 500mm2 <strong>for</strong> each<br />

30 litre per second maximum extraction fan rate.<br />

The manufacturer should have a stamp on their<br />

products showing total free area. When two or more<br />

open appliances are installed in the same compartment<br />

or space, whether or not they are supplied as a<br />

combined unit, the aggregate input rating should be<br />

used <strong>for</strong> sizing the vents.<br />

33


Table 10:<br />

Appliance ventilation requirements<br />

Appliance type <strong>and</strong> input<br />

Minimum ventilation opening<br />

(free area) required<br />

Decorative fuel effect fires 10,000mm 2<br />

Open-Flued appliance < 7kW 3,500mm 2<br />

Open-Flued appliance > 7kW <strong>and</strong> < 14kW 6,500mm 2<br />

Open-Flued appliance > 14kW <strong>and</strong> < 70kW<br />

450mm 2 per kW<br />

Fixed space <strong>heat</strong>er<br />

Permanent openings of a minimum of<br />

(e.g. flueless fire - see Case Study 9) 12,000mm 2<br />

The total ventilation required shall be equally<br />

divided between high <strong>and</strong> low level openings<br />

on the same wall, separated by a minimum<br />

distance of 1,600mm.<br />

Maximum input rate 4.2 kW<br />

(See note 2)<br />

Note 1: Rooms built in accordance with<br />

the 1997 Building Regulations TDG’s have<br />

a minimum of 6,500mm2 ventilation, or in<br />

excess of 12,000mm2 when a room contains<br />

a chimney. To allow this ventilation to count<br />

towards the minimum opening required,<br />

it must be permanently fixed in the open<br />

position.<br />

Note 2: As combustion products from this<br />

appliance are released directly into the room,<br />

additional provisions may be needed to avoid<br />

condensation <strong>and</strong> ensure satisfactory air<br />

quality. Advice should be sought from the<br />

manufacturer of the specific appliance if not<br />

included in the manufacturers instructions.<br />

Alternative vents<br />

Vents may be incorporated in window frames (Curtains<br />

must not restrict air flow) <strong>and</strong> in doors in order to<br />

satisfy the air requirement of gas appliances. The free<br />

air requirement must be stated by the manufacturer.<br />

Openings must not be adjustable or capable of being<br />

closed.<br />

34


Safety <strong>for</strong> the Home Owner<br />

Safety, certification & getting connected<br />

Important notice to all <strong>installers</strong><br />

Under current legislation <strong>Bord</strong> Gáis must be assured<br />

that an installation is safe <strong>and</strong> complies with Irish<br />

St<strong>and</strong>ard 813(I.S 813) Domestic Gas installations<br />

be<strong>for</strong>e gas can be supplied to the dwelling.<br />

It is a legal requirement under The Energy<br />

(miscellaneous provisions) Act 2006 that all “domestic<br />

gas works” must be under taken <strong>and</strong> certified by a<br />

registered gas installer (RGI) who is registered with the<br />

RGII (Register Gas Installers of Irel<strong>and</strong>)<br />

The Declaration of Con<strong>for</strong>mance Certificate ,which<br />

must be signed by the RGI carrying out the work, is a<br />

declaration by the RGI that the gas work is safe. That it<br />

has been carried out in accordance with <strong>and</strong> con<strong>for</strong>ms<br />

to the National st<strong>and</strong>ard <strong>for</strong> Domestic Gas Installations<br />

I.S.813.<br />

Only a declaration of con<strong>for</strong>mance certificate obtained<br />

from the Register of Gas Installers of Irel<strong>and</strong> (RGII) <strong>and</strong><br />

completed <strong>and</strong> signed by a RGI is acceptable <strong>for</strong> this<br />

purpose.<br />

Be Aware !<br />

If the steps outlined are not followed, in the<br />

interest of safety, the gas will not be supplied<br />

by <strong>Bord</strong> Gáis.<br />

See below.<br />

Important Notice<br />

A Registered gas Installer is only permitted to certify his / her own work or that of a registered Trainee<br />

work under supervision.<br />

The Public Listing of Registered Gas Installers is available at:<br />

www.rgii.ie<br />

35


Domestic gas installation safety<br />

In<strong>for</strong>mation <strong>for</strong> Registered Gas Installers (RGI) requiring<br />

a new meter fit.<br />

New Housing Projects<br />

A Registered Gas Installer must<br />

• Complete the entire gas installation<br />

• Issue a declaration of con<strong>for</strong>mance (post<br />

construction section)<br />

• Leave properly completed gas supplier/network<br />

operator copy on site with part one (post<br />

construction section) completed<br />

When the meter is fitted the RGI must<br />

• Connect to the gas installation<br />

• Purge installation in accordance with I.S.813<br />

• Commission appliances/installation in accordance<br />

with manufacturers requirements<br />

• Purge installation in accordance with I.S.813<br />

• Commission appliances/installation in accordance<br />

with manufacturers requirements<br />

• Complete post construction section (part 1) of<br />

declaration of con<strong>for</strong>mance<br />

• Complete part 2 of the declaration of<br />

con<strong>for</strong>mance<br />

• Issue customer with a copy of the declaration of<br />

con<strong>for</strong>mance<br />

• Return green copy to RGII within 10 days of<br />

meter fit<br />

Be Aware !<br />

Any person installing gas must be a Registered<br />

Gas Installer to do so in accordance with I.S<br />

813 “Domestic Gas Installations”<br />

• Complete part 2 of the declaration of<br />

con<strong>for</strong>mance<br />

• Issue customer copy of declaration of<br />

con<strong>for</strong>mance<br />

• Return green copy to RGII within 10 days of issue<br />

One off existing/new housing<br />

The <strong>Bord</strong> Gáis procedure <strong>for</strong> this type of installation<br />

allows <strong>for</strong> gas meters to be fitted pre-construction. If a<br />

registered gas installer requires a meter to be fitted in<br />

such circumstances then.<br />

A Registered Gas Installer must<br />

• Issue a declaration of con<strong>for</strong>mance (pre<br />

construction section)<br />

• Leave properly completed gas supplier/network<br />

operator copy on site with part one (pre<br />

construction section) completed<br />

When the meter is fitted the RGI must<br />

• Complete the installation in accordance with I.S.<br />

813<br />

• Connect to the gas meter installation (when ready<br />

<strong>for</strong> commissioning)<br />

36


Commissioning of natural gas<br />

installations<br />

Conducting a Soundness Test<br />

Be<strong>for</strong>e a declaration of con<strong>for</strong>mance is issued the<br />

R.G.I.I installer must carry out a soundness test to<br />

ensure there are no leaks in the piped system.<br />

The soundness test is carried out as follows:<br />

• All work must be carried out by a Registered Gas<br />

Installer.<br />

• Use only a pressure gauge / manometer with<br />

clearly marked 0.1 mbar gradations.<br />

• Shut off all appliance valves.<br />

• Pressurise installation with air to 100mbar (on<br />

gauge).<br />

• Wait <strong>for</strong> 5 minutes to ensure temperature<br />

stabilisation.<br />

• Check gauge / manometer <strong>and</strong> record exact<br />

marking.<br />

• After 5 minutes, check again.<br />

• If pressure has dropped at all from noted mark,<br />

the installation can not be regarded as sound<br />

<strong>and</strong> shall not be commissioned until the escape is<br />

repaired <strong>and</strong> the installation re-tested.<br />

Pressure test connection at meter outlet<br />

• If pressure remains stable, then installation can be<br />

deemed sound.<br />

• Any component <strong>for</strong>ming part of the installation,<br />

which was excluded from the pipework test,<br />

shall be reconnected, gas introduced into the<br />

installation <strong>and</strong> purging carried out. These<br />

connections <strong>and</strong> components shall then be tested<br />

<strong>for</strong> soundness using either a leak detection fluid<br />

or a gas detector.<br />

Be Aware !<br />

Installers must be registered<br />

see I.S.813: 2002<br />

37<br />

Carrying out the soundness text.


Commissioning of natural gas<br />

installations<br />

Purging the installation<br />

Every installation must be cleared (purged) of air or air<br />

/ gas mixture whenever a gas supply is made available<br />

<strong>for</strong> the first time or when an existing system has been<br />

shutdown <strong>and</strong> is being recommissioned.<br />

Why is it necessary?<br />

A gas / air mixture in the meter or pipework is<br />

potentially explosive <strong>and</strong> it is necessary there<strong>for</strong>e to<br />

ensure that the installation <strong>and</strong> appliances are left with<br />

only a 100% natural gas concentration.<br />

Whilst an appliance may initially light <strong>and</strong> burn<br />

correctly, if there is a pocket of air in the internal<br />

installation, the appliance flame will extinguish as the<br />

air reaches the appliance burner.<br />

Be Aware !<br />

It is a legal requirement under The Energy<br />

(miscellaneous provisions) Act 2006 that all<br />

“domestic gas works” must be under taken <strong>and</strong><br />

certified by a registered gas installer (RGI) who is<br />

registered with the RGII (Register Gas Installers of<br />

Irel<strong>and</strong>.<br />

Purging Method<br />

• All work must be carried out by Registered Gas<br />

Installers<br />

• Purging of a new installation should not be<br />

undertaken without completion of a satisfactory<br />

soundness test.<br />

• Purging from air to gas should be supervised by a<br />

Registered Gas Installer<br />

• Ensure the dwelling is well ventilated.<br />

• Ensure there are no naked lights or sources of<br />

ignition.<br />

• Select a purge point furthest away from the meter<br />

<strong>and</strong> in a well ventilated area.<br />

• If it is necessary to purge from a point in a<br />

confined area then the purge should be piped to<br />

atmosphere.<br />

• For most domestic installations one burner on the<br />

cooker hob is an ideal purge point.<br />

• When a full flow of gas is verified, <strong>for</strong> example,<br />

by a stable burner flame, other appliances in the<br />

dwelling should then be purged.<br />

• Commission appliances.<br />

38


Declaration of Con<strong>for</strong>mance<br />

All elements of the declaration must be completed <strong>and</strong><br />

signed <strong>for</strong> <strong>and</strong> the copies distributed as instructed in<br />

the document.<br />

The completed top copy (white copy) should be given<br />

to, or left <strong>for</strong>, the householder. The Green copy sent to<br />

the RGII. The <strong>Bord</strong> Gáis meter fitter collects <strong>and</strong> verifies<br />

the second (yellow) copy. If you are not present, please<br />

leave in meter box or attached to boiler.<br />

<strong>Bord</strong> Gáis will not supply gas unless a valid, properly<br />

completed con<strong>for</strong>mance declaration is submitted <strong>for</strong><br />

verification in one of the ways described. See page 35<br />

/ 36.<br />

The installer should retain the remaining copy in a<br />

secure place, as it may be of use in the future should<br />

any difficulties arise as to the safety or acceptability of<br />

the installation.<br />

Be Aware !<br />

Only registered <strong>installers</strong> may issue a<br />

con<strong>for</strong>mance declaration.<br />

Sample declaration <strong>for</strong>m<br />

Figure 35: Certificate: Declaration of<br />

Con<strong>for</strong>mance<br />

<br />

<br />

<br />

<br />

<br />

S<br />

<br />

CERT<br />

1<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

Form G01(S) Version 1<br />

<br />

<br />

<br />

39


For gas mains <strong>and</strong> services<br />

<strong>Bord</strong> Gáis install all gas mains <strong>and</strong> services in<br />

accordance with the latest edition of the following<br />

Irish St<strong>and</strong>ards:<br />

I.S. 329 “Code of Practice <strong>for</strong> Gas Distribution<br />

Mains”<br />

&<br />

I.S. 265 “Installation of Gas Service Pipes”.<br />

For downstream of the meter<br />

Irish St<strong>and</strong>ard I.S.813: 2002 “Domestic Gas<br />

Installations” applies to installations downstream of<br />

the meter.<br />

This St<strong>and</strong>ard is the code of practice <strong>for</strong> Natural Gas<br />

installation requirements downstream of the point<br />

of delivery <strong>and</strong> includes the requirements <strong>for</strong> meters,<br />

appliances <strong>and</strong> associated pipework in single<br />

<strong>and</strong> multiple occupancy dwellings.<br />

All of the above st<strong>and</strong>ards can be obtained from<br />

the NSAI (National St<strong>and</strong>ards Authority of Irel<strong>and</strong>).<br />

Telephone (01) 8073878.<br />

or<br />

www.st<strong>and</strong>ards.ie<br />

RGII contact in<strong>for</strong>mation<br />

List of registered Gas Installers 01 4997998<br />

Con<strong>for</strong>mance Certificates 01 4997998<br />

Web Site: www.rgii.ie<br />

For your Next Residential Scheme<br />

New Connections 1850 411 511<br />

Construction 1850 411 511<br />

Meter Boxes 1850 411 511<br />

Dial be<strong>for</strong>e you dig 1850 42 77 47<br />

July 2010 Document no: 25697<br />

All rights reserved. No part of this publication may be reproduced, stored in a retrieval system or transmitted in any <strong>for</strong>m or any means,<br />

electronic, mechanical, photocopying, recording or otherwise, without the prior permission of the publishers. In<strong>for</strong>mation correct at time of<br />

printing. The advice above is a guide line only <strong>and</strong> based on the most authoritative in<strong>for</strong>mation available at the date of issue <strong>and</strong> users should<br />

ensure that it is relevant to the specific circumstances in which they seek to apply it. Professional advice should always be sought. Users should<br />

ensure they have up to date in<strong>for</strong>mation. © <strong>Bord</strong> Gáis<br />

40<br />

GSDC 2508/3009d

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!